23rd March 2011
Chooz A dismantling project
International atomic energy agency
DIN - CIDEN 2
SummarySummary
23rd March 2011
1. Presentation of Chooz A project2. The project team3. 2010 results4. 2011 - 2014 : project time plan5. Decontamination of the steam generators6. Dismantling of the vessel
DIN - CIDEN 3
SummarySummary
23rd March 2011
1. Presentation of Chooz A project2. The project team3. 2010 results4. 2011 - 2014 : project time plan5. Decontamination of the steam generators6. Dismantling of the vessel
23rd March 2011 DIN - CIDEN 4
1 Presentation of Chooz A project1 Presentation of Chooz A project
23rd March 2011 DIN - CIDEN 5
First PWR built in France
Specificity : Underground nuclear buildings
Power : 305 MWConstruction from 1962 to 1966
Operating from 1967 to 1991
NPP shut down : 1993
End of fuel disposal : December 1995
Complete dismantling decree : September 2007
1 Presentation of Chooz A project1 Presentation of Chooz A project
HK cavern
HR cavern
23rd March 2011 DIN - CIDEN 6
Subproject 1 : preparatory construction work
Subproject 2 : nuclear auxiliaries dismantling
Subproject 3 : HR dismantling except the vessel
Subproject 4 : HR vessel dismantling
Subproject 5 : sanitation of the buildings
Subproject 6 : rehabilitation of the site
1 Presentation of Chooz A project1 Presentation of Chooz A project
DIN - CIDEN 7
SummarySummary
23rd March 2011
1. Presentation of Chooz A project2. The project team3. 2010 results4. 2011 - 2014 : project time plan5. Decontamination of the steam generators6. Dismantling of the vessel
23rd March 2011 DIN - CIDEN 8
2 The project team (in Lyon)2 The project team (in Lyon)
Estelle GREVINProject managerSébastien ALBERTINI
Work CoordinatorPierre-Emmanuel PONCET
Studies Coordinator
Florence BERRYSupplies coordinator
Catherine BIASELLICost controller
Cyrille TRICARTTime plan
Project team : 6 people + 1 contractor
Sylvain MANDEVILLE (ALTRAN)Time plan and support
23rd March 2011 DIN - CIDEN 9
Team on site : 21 people
2 The project team (in Chooz)2 The project team (in Chooz)
DIN - CIDEN 10
SummarySummary
23rd March 2011
1. Presentation of Chooz A project2. The project team3. 2010 results4. 2011 - 2014 : project time plan5. Decontamination of the steam generators6. Dismantling of the vessel
2003 2004 2005 2006 2007 2008 2009 2010 2011
DIN - CIDEN 23rd March 201111
Complete dismantling decree
Forecasted physical progress : 44,90% Realised physical progress : 43,32%
3 2010 results : physical progress3 2010 results : physical progress
DIN - CIDEN 12
SummarySummary
23rd March 2011
1. Presentation of Chooz A project2. The project team3. 2010 results4. 2011 - 2014 : project time plan5. Decontamination of the steam generators6. Dismantling of the vessel
23rd March 2011 DIN - CIDEN 13
The critical path for the project concerns the activities in the HR cavern :
• Primary circuit dismantling
• Renewal of the water filling circuit of the pool
• Vessel dismantling
2011
Dismantling of the primary circuit : 3 SG decontaminated and the 4th
SG extracted
End of nuclear auxiliaries dismantling in HK cavern, except
the casemates
2011
Dismantling of the primary circuit : 3 SG decontaminated and the 4th
SG extracted
End of nuclear auxiliaries dismantling in HK cavern, except
the casemates
2012
Dismantling of the primary circuit :
- Decontamination of the pressuriser and of the primary
loops
- Disposal of 2 SG to ANDRA in one piece
2012
Dismantling of the primary circuit :
- Decontamination of the pressuriser and of the primary
loops
- Disposal of 2 SG to ANDRA in one piece
2013
- Vessel cover lift and dismantling of the vessel
internals
- Dismantling of the casemates in HK cavern
2013
- Vessel cover lift and dismantling of the vessel
internals
- Dismantling of the casemates in HK cavern
4 2011 - 2014 : project time plan4 2011 - 2014 : project time plan
23rd March 2011 DIN - CIDEN
2011 20122010
HR dismantling except the vessel
14
HR vessel
Studies review
HR vessel : execution studies
Water filling of the pool
Safety report sending
Casemates in HK : contract signature
Safety report
Effluents treatment station
4 2011 - 2014 : project time plan (studies) 4 2011 - 2014 : project time plan (studies)
23rd March 2011 DIN - CIDEN
2011 2012 2013 20142010
HR dismantling except the vessel
HR vessel Internals dismantling
1st SG decontaminated
4 SG outside
Vessel cover lift
B wastes in HR
Dismantling in HK
Casemates in HK
15
HR cavern
HK cavern
Water filling of the pool
HR dismantling except the
er filling of the pool
Internals dismantling
Critical path
4 2011 - 2014 : project time plan (work)4 2011 - 2014 : project time plan (work)
DIN - CIDEN 16
SummarySummary
23rd March 2011
1. Presentation of Chooz A project2. The project team3. 2010 results4. 2011 - 2014 : project time plan5. Decontamination of the steam generators6. Dismantling of the vessel
17 23rd March 2011 DIN - CIDEN
5 SG decontamination process (2011)5 SG decontamination process (2011)
CORD : Chemical Oxidation Reducing DecontaminationAMDA : Automated Mobile Decontamination Appliance
DIN - CIDEN 18
SummarySummary
23rd March 2011
1. Presentation of Chooz A project2. The project team3. 2010 results4. 2011 - 2014 : project time plan5. Decontamination of the steam generators6. Dismantling of the vessel
23rd March 2011 DIN - CIDEN 19
6 Vessel dismantling process (2013)6 Vessel dismantling process (2013)
Lift and treatment of the vessel cover (operations under water)
1. Containment plate 2. Inferior sub plate 3. Biological protection dome
4. Containment casing
Internals treatment (secondary sources, superior internals, operational wastes, inferior internals) - operations under water
23rd March 2011 DIN - CIDEN 20
Insulated vessel handling (operation in the open)
Treatment of the vessel insulation (operation under water)
Vessel dismantling (operation under water)
6 Vessel dismantling process (2013)6 Vessel dismantling process (2013)