  • PSQAQP150

    ADVANCE QUALITY PLANNING

  • 2

    INTRODUCTION

    Tell us about yourself

    Your name

    Your job and how long youve been doing it

    Your role in the AQP process

    What you would like to know about AQP?

  • 3

    OBJECTIVES

    1.What is AQP?

    2.Why should we do it?

    3.How do we do it?

  • 4

    FOUNDATION OF AQP: CPCP

    Chrysler Product Creation Process

    Process Design / AQP (SQ Lead) IRE (Approx. timing)

    Product Design (Engineering Lead)

    Sourcing (Purchasing Lead)

  • 5

    FOUNDATION OF AQP: CPCP

  • 6

    FOUNDATION OF AQP: CPCP

  • 7

    AQP

    PSO

    A process that will ensure parts that meet all requirements are delivered on

    time to designated manufacturing

    facilities. AQP/PSO Manual 7th Edition, page 1

    AQP: WHAT IS IT?

  • 8

    AQP: WHAT IS IT?

    AQP focuses on the design/development of the Suppliers manufacturing process to ensure that it is capable of producing parts that meet design requirements at the quoted

    tooling capacity

    Customer requirements / CPCP timing

    AQP Meetings

    VP Build

    Trial Runs (SRE)

    Process Sign-Off / PV Testing

    PPAP

    PVP Build

    Corrective Actions

    Lessons Learned

    Depicting product quality planning as a cycle illustrates the never-ending pursuit of continual improvement that can only be achieved by taking the experience in one program and applying that acquired knowledge to the next program. APQP & Control Plan Manual, 2nd Edition, page 1

  • 9

    AQP: WHY DO IT?

    Minimize / reduce late changes to the part and process

    Reduce / eliminate quality spills at all stages of production

    Reduce / eliminate warranty

    Increase customer satisfaction

    In short, to eliminate waste and save money!

  • 10

    WHAT IS NEEDED: INPUTS

    What do we need before we can begin AQP?

    Sourced part or module (Supplier must be known)

    Source package

    CPCP Program Timing

    Design Model

    Engineering specifications

    Engineering Change Notices (CNs), if applicable

    Lessons Learned from previous programs

  • 11

    AQP: HOW DO WE DO IT?

    Milestone

    Pre-Volume Production

    (PVP)

    Volume Readiness Phase

    Job 1 Offline

    Launch Phase

    Commercial Launch

    PSO On-Site Visit &Production

    Demonstration Run

    PSO Result

    Submit final PSW/PPAP

    Complete PPAP requirements & submit Dimensional

    PSW/PPAP

    Complete corrective actions; reschedule On-Site Visit / PDR

    as necessary

    5 (Z)1-4 (N)

    End & Forever

    Requirements

    Lessons Learned

    A B C

    5 + PVT (A)

    D

  • 12

    Source Evaluation

    New Supplier (Also new management/

    organization structure)

    New Location

    New Process,

    Commodity or

    Technology

    New Product

    or Project

    Has Not Shipped

    Product for More

    Than 24 Months

    Events

    On-Site Source Evaluation

  • 13

    Source Evaluation

    1. Review list of possible

    suppliers.

    2. Analyze Fiat and

    Chrysler suppliers with

    existing ratings or

    evaluations.

    3. Screen supplier pre-

    evaluation data.

    4. Determine strategic

    suppliers needing

    evaluations.

    1. Clarify scope of tasks

    related to product, site,

    technology and supplier

    performance data.

    2. Prepare decision

    making

    recommendation and

    obtain management

    approval for task.

    1. Form the cross

    functional team.

    2. Hold kickoff meeting

    and assign roles and

    responsibilities.

    3. Preliminary

    discussion of supplier

    pre-evaluation

    package.

    4. Schedule on-site visit

    and confirm trip

    details.

    1. Perform on-site

    evaluation.

    2. Inspect facility.

    3. Collate and coordinate

    analysis results and

    scoring.

    4. Conduct closing

    meeting with supplier

    with verbal feedback of

    major observations.

    5. Resolve/clarify

    discrepancies.

    1. Finalize summary

    report and defined

    criteria.

    2. Calculate evaluation

    pass/fail rating and

    identify any risk

    factors.

    3. Report to approved

    managers.

    4. Upload information to

    GPSIS.

    1. Complete gap analysis

    form if supplier can be

    considered for

    business.

    2. Assign supplier target

    dates on action items.

    3. Track progress to gap

    close and follow-up

    meetings.

    4. Notify approved

    managers of completed

    status.

    5. Re-load updated SE

    form in GPSIS.

    Identification Task

    Clarification

    Visit

    Preparation

    On-Site

    Visit

    Results

    and

    Reporting

    Closure

  • SOURCE EVALUATION

    Check if Fiat has a PSA (Potential Supplier Assessment)

    If so, use PSA result

    Pre-Evaluation form sent to Supplier for completion

    Buyer sends Request form to SQ Commodity Manager

    SQ Commodity Manager determines the SQE to lead the

    Source Evaluation

    SQE assembles team SQE, Engineering are mandatory

    Purchasing, Supply recommended but may delegate

    14

    General Navigation

    The tabs on this tool are arranged by function.

    Tan tabs are general information and Cover Sheet

    Green tabs are for the area-specific questions and data input

    Dark Blue tabs are for reporting

    Light Blue tabs are reference material

    Supplier Source Evaluation Toolkit

    Instructions for using this tool appear below

    Note: Macros must be enabled for this tool to work properly.

  • SOURCE EVALUATION

    Team reviews Pre-Evaluation information

    Team holds on-site review at the Supplier with the SE tool

    Gap analysis completed with action items and target dates

    for unacceptable items

    SE result determines if Supplier can be sourced or not

    15

    Date:

    Zip / Postal Code

    DUNS Code

    eMail/Nic:

    eMail/Nic:

    Commodity Code

    N

    N

    N

    Total Management

    N Expiration Date: Name and Local #

    Mailing Executive

    Position

    Supplier Profile

    Small Business Y/N

    Woman Owned Y/N

    Sheltered Workshop Y/NForeign Ownership

    Name

    Main Contact

    Minority Classification

    E-mail Address

    Country

    Percentage

    HR/Safety

    Union Representation Y/N

    Union Information

    Number of Employees at facility?

    Dedicated to the Product Line

    Name

    Country

    Buyer Name

    Plant Manager

    Head of Sales

    Quality Manager

    Supplier Contacts

    CEO / President

    City, State

    [email protected]

    Country

    Jim Buyer

    City, ST 12345

    Materials Management

    Phone #

    Account Rep

    Address (Assessed Location) Address

    Comm name DC4321Commodity Name

    Author Name email

    123456789

    AddressAddress 2

    Hourly

    Supplier Source Evaluation ToolkitSnameCity, ST

    SnameSupplier Name

    After Hours Contact

    Traffic Manager

  • SOURCE EVALUATION

    16

    Score each question (or N/A)

    0, 15, or 30 pts possible

    Click on question number to go directly to

    applicable workbook

    section

  • Summary tab shows results for each section, plus an

    overall percentage score

    Overall percentage score determines if Supplier can

    be sourced

    SEs for commodities with safety characteristics

    require a higher score

    Individual items that are RED still require corrective

    actions!

    17 17

    SOURCE EVALUATION

  • 18

    SCORING

    60-80% >80% 90%

  • 19

    INITIAL RISK EVALUATION (IRE)

    What is the IRE?

    An assessment of the inherent risks in a new or

    modified part

    Determines Chrysler involvement with the AQP

    and PSO for the new or

    modified part

    Required to be completed within 14 business days of

    the part appearing in CQMS

    AQP: SupplierPSO: Supplier

    Initial Risk Evaluation

    AQP: SupplierPSO: Chrysler

    AQP: ChryslerPSO: Chrysler

    LOW MEDIUM HIGH

  • 20

    IRE RISK DRIVERS

    Are there issues preventing Production Tools Complete by the required date?

    Expectation: Review the planned Tooling Kickoff (TKO) and Production Tools Complete (PTC) dates. PTC is required by Verification of Process (VP).

    Guidelines: Tooling completion affects numerous AQP deliverables, such as PV Testing, Process Sign-Off, PPAP, etc. Late tooling should equate to a higher risk level;

    completion after Pre Volume Production (PVP) should be an automatic High risk.

    Will PPAP be completed by the required date? Expectation: Review the planned PPAP date. PPAP completion is required by PVP.

    Guidelines: Late PPAP may equate to a higher risk level. Late engineering changes that push PPAP beyond PVP or Job 1 should be re-evaluated to determine if the risk

    level of the part should increase. As soon as it is known that PPAP will be after PVP,

    follow the "PPAP Submission Delay - Escalation" process in the Book of Knowledge .

    Is the design complete? Expectation: Part design / CAD should be complete and attached as part of the

    original Source Package.

    Guidelines: If the Supplier submitted an RFQ to an incomplete or non-existent design, there is increased risk to the program. TKO without a complete design also represents

    a High risk to the program.

  • 21

    IRE RISK DRIVERS

    Has historical design stability (e.g., high CN activity) been considered?

    Expectation: Review Lessons Learned from previous programs (both from the Supplier and on similarly-designed parts) for CN activity. Were engineering changes minimal and minor in scope?

    Guidelines: A high incidence of CNs on the part, or one or more major part redesigns, should reflect a higher risk level.

    What is the customer impact if the part fails? (Safety, Appearance, functionality, etc.)

    Expectation: Determine the potential customer impact if the part fails. Would it cause injury, result in vehicle breakdown, or negatively impact customer perception?

    Guidelines: Parts with a high degree of customer interface should have correspondingly higher risk levels. Examples include Safety components, parts that could result in a "walk-home" condition, or parts in high-visibility areas with Appearance requirements.

    What is the level of process technology (e.g., established, widespread, innovative)?

    Expectation: Review the proposed manufacturing process.

    Guidelines: Processes that are using technologies new to the Supplier, Chrysler, or the industry may require a higher risk level.

  • 22

    IRE RISK DRIVERS

    Is this a new manufacturing location? Expectation: Manufacturing locations new to Chrysler require a Source Evaluation performed with

    an acceptable score. Ensure open issues from Source Evaluation have been closed. If the Supplier received an unacceptable rating, were the proper overrides obtained?

    Guidelines: New Suppliers to Chrysler represent a higher risk to the program. Lack of an acceptable Source Evaluation for a new Supplier should be an automatic High risk.

    Have there been historical quality problems with similar parts? Expectation: Review the quality history (Nonconformance Tickets, yardholds/PRIs, warranty issues

    and field actions) of the part in question (if applicable) or parts with a similar design. Review the Master PFMEA for this commodity to ensure these issues have been addressed. Have there been repeat issues?

    Guidelines: A high incidence of NCTs, a high c's/1000 rating, or ANY PRIs or field actions on similar parts represents a higher risk. Repeat issues or lack of corrective actions in the Master PFMEA also indicate a higher program risk.

    What is the Supplier's Supplier Quality Bid List score? Expectation: The Supplier should be "green" per the Supplier Quality Bid List (SQBL). Their overall

    score includes AQP/NCT, 3CPR (Level 1 and Level 2 incidences; reference ), yardholds, Forever Requirement Violations (reference ), ISO/TS-16949 Certification, and New Business Hold (NBH; reference ). "Yellow" or "Red" scores on the SQBL require a written override from a SQ Director for the Supplier to receive business.

    Guidelines: A Supplier with a "yellow" or "red" SQBL score indicates potential additional risk to the program.

  • 23

    IRE RISK DRIVERS

    What is the Supplier's Warranty history? Expectation: Review the Supplier's warranty history with the Customer Satisfaction

    Team (CST). Are they meeting their targets? Have they had any recent warranty spikes

    or field actions?

    Guidelines: If the Supplier's warranty has been increasing, or if they have had a field action recently, it may indicate additional risk.

    What is the Supplier's ability to successfully conduct AQP activities?

    Expectation: Assess the Tier 1 Supplier's ability to manage AQP / APQP activities. Review PSO Element 1, requirements 1.2 through 1.2.4 ("Supply Base Management");

    the Tier 1 should have all requirements met. Review if the Supplier location has

    required multiple PSO visits in the past before receiving approval.

    Guidelines: A lack of sub-tier Supplier management processes indicates high program risk, as does a history of failing to meet deliverable due dates. Multiple PSO visits in the

    past can also indicate poor AQP management.

  • 24

    IRE RISK LEVELS

    High Risk (H) Chrysler SQE leads the AQP

    Chrysler SQE leads the PSO

    Medium Risk (M) Supplier leads the AQP

    Chrysler SQE leads the PSO

    Low Risk (L) Supplier leads the AQP

    Supplier leads the PSO

  • 25

    DESIGNATING THE IRE IN CQMS

    Use the Part Information tab in CQMS Select Part Risk

    Review and acknowledge

    the IRE risk drivers!

  • 26

    To Enter Initial Risk Evaluation for One or More Parts:

    1. Click the Part Information tab. Then, click the Part Risk link.

    2. Logon to CQMS with your TID and user password.

    3. Enter valid Chrysler Supplier Quality Deck Code

    Note: SQE Deck Code is populated by default, where applicable. Select Clear to enter a new value.

    4. Check the box for Unassigned Risk

    5. To limit the results, enter a value for one or more Optional filters.

    6. Click Find.

    7. Click the radio button(s) for the parts where you want to apply a single Initial Risk value.

    8. Select a risk value from the Initial Risk drop down.

    Note: Do not make a separate selection for Current risk. The initial risk value will automatically populate to Current risk when updated.

    9. Check the box to Acknowledge Risk Drivers

    10.Click Update.

    To Enter Initial Risk Evaluation for a Single Part:

    1.Logon to CQMS with your TID and user password.

    2.Click Part Information tab. Then, click the Part Risk link.

    3.Type the full Chrysler part number in the Part Number field.

    4.Check the box for Unassigned Risk

    5.Click Find.

    6.Click the radio button for the Supplier Code where you want to apply Initial Risk.

    7.Select a risk value from the Initial Risk drop down.

    Note: Do not make a separate selection for Current risk. The initial risk value will automatically populate to Current risk when updated.

    8.Check the box to Acknowledge Risk Drivers

    9.Click Update.

    DESIGNATING THE IRE IN CQMS

  • 27

    To Change Current Part Risk for a Single Part:

    1. Logon to CQMS with your TID and user password.

    2. Click Part Information tab. Then, click the Part Risk link.

    3. Type the full Chrysler part number in the Part Number field.

    4. De-select the check box for Unassigned Risk

    5. Click Find.

    6. Click the radio button for the Supplier Code where you want to change Current Risk.

    Note: Current Risk can only be changed once the Initial Risk has been captured. Do not select rows where the Current risk value is the same as the new risk value.

    7. Select a risk value from the Current Risk drop down.

    Note: Do not make a separate selection for Initial risk. The initial risk value cannot be changed once it is captured. If you attempt to enter a value for Initial risk, you will receive an error message.

    8. Click Update.

    To Change Current Part Risk for One or More Parts:

    1. Logon to CQMS with your TID and user password.

    2. Click the Part Information tab. Then, click the Part Risk link.

    3. Enter valid Chrysler Supplier Quality Deck Code

    Note: SQE Deck Code is populated by default, where applicable. Select Clear to enter a new value.

    4. De-select the check box for Unassigned Risk

    5. To limit the results, enter a value for one or more Optional filters.

    DESIGNATING THE IRE IN CQMS

  • 28

    QUALITY PLANNING / AQP MEETINGS

    What are AQP Meetings?

    Regular reviews of the program status

    A way to ensure progress of CPCP milestone deliverables

    Ensures communication between AQP team members

    1. AQP Kick-off Meeting2. Hold regular AQP

    Meetings and track status

    with Executive Summary,Timing Chart

  • 29

    WHEN / WHERE ARE AQP MEETINGS HELD?

    Required for all programs following the AQP process

    All components with a High IRE

    Recommended for Medium and Low IRE programs, although the Supplier may also

    use the APQP process (see the AIAGs Advanced Product Quality Planning and

    Control Plan Manual, 2nd Edition)

    Regular, frequent schedule Recommended weekly

    No mandatory location If possible, it is strongly recommend that

    some meetings are held at the Tier 1

    manufacturing location, critical Tier 2 or

    lower Suppliers, and at the Chrysler

    manufacturing facility

  • 30

    WHOS IN CHARGE?

    The Chrysler SQE leads the AQP Meetings for High IRE programs

    The Supplier leads their own AQP/APQP Meetings for Medium and Low IRE programs

    The Chrysler SQE can require

    AQP Meetings for any program

    on an as needed basis

  • 31

    THE AQP KICK-OFF MEETING

    Should occur as soon as the part is sourced and given an IRE in CQMS Early involvement by Supplier Quality and the Supplier is critical

    Should include all AQP Team members

    Chrysler Supplier Quality Engineer

    Chrysler Product Engineer

    Supplier Personnel

    Core Team

    Chrysler SQ Manager / Vehicle Lead

    Chrysler Buyer Chrysler Supply Other Chrysler

    Personnel as needed

    Sub-Tier Suppliers as needed

    Extended Team

  • 32

    Review the IRE Gain additional team input

    Review issues/risk drivers that gave the highest risk

    Establish team roles and responsibilities (including responsibilities between Tier 1 and Directed/Consigned

    Suppliers)

    THE AQP KICK-OFF MEETING AGENDA

    Directed Tier II

    Part PO Tier I

    Tool PO Chrysler

    AQP/PSO Resp. Chrysler

    Release/Logistics Tier I

    Receiving Location Tier I

    NCT Issued to: Tier I

    eCIMS Issued to: Tier II

    Consigned Tier II

    Part PO Chrysler

    Tool PO Chrysler

    AQP/PSO Resp. Chrysler

    Release/Logistics Chrysler

    Receiving Location Tier I

    NCT Issued to: Tier II

    eCIMS Issued to: Tier II

    Standard Tier II

    Part PO Tier I

    Tool PO Tier I

    AQP/PSO Resp. Tier I

    Release/Logistics Tier I

    Receiving Location Tier I

    NCT Issued to: Tier I

    eCIMS Issued to: Tier I

  • 33

    THE AQP KICK-OFF MEETING AGENDA

    Determine AQP meeting frequency How often, at what location, attendance expectations, etc.

    Confirm core AQP Team members Chrysler SQE

    Chrysler Engineer

    Supplier Personnel (Quality and Program Management, at a minimum)

    Review the source package Ensure requirements are accurate

    Engineering specifications

    Prototype build requirements

    Review volume assumptions (e.g., shift pattern agreement with P.O. volumes)

    Get an early idea of SRE/PSO cycle time & line speed requirements

    Identify potential capacity issues up-front

  • 34

    Establish and review program timing / major CPCP milestones Prototype (VP, PVP) and Launch (Job 1) build dates and Material

    Required Dates (MRD)

    Dates for deliverables (including, but not limited to):

    THE AQP KICK-OFF MEETING AGENDA

    PFMEA Acceptance

    Production Tools Complete

    Equipment, Fixtures, Facilities, and Gages Complete

    Gage R&R

    Supplier Readiness Evaluation (SRE)

    Dimensional Capability

    Part I/S Draft & Final Complete

    Pre-PSO Meeting

    PSO On-Site Visit

    PSO Complete

    IMDS Submitted

    PV Testing Start / Complete

    PPAP submission

    When initial program timing is developed, deliverables for milestones that are

    already past due shall be included for completion. These deliverables shall be

    distributed into appropriate, future milestones as determined by the AQP Team.

  • 35

    THE AQP KICK-OFF MEETING AGENDA

    Establish AQP/Process Sign-Off (PSO)

    expectations Maintenance of AQP forms and

    documents

    SRE/PDR part run quantities

    Extended Run PSO?

    Etc.

    Confirm manufacturing location

  • 36

    GENERAL AQP MEETINGS

    Agenda should include:

    Program timing and major milestones If timing slips, an appropriate Risk Mitigation Plan shall be developed and

    implemented to manage the risk

    CPCP timing and deliverables for the current and next milestone Late deliverables also require an appropriate Recovery Plan

    Open issues Prototype quality issues (NCTs, eCIMS, etc.)

    Current or proposed Engineering Changes, IAAs

    Sub-tier Supplier status

    Etc.

  • 37

    Sometimes broken up into two types: High-level AQP and Working-level AQP

    High-level Agenda based on Milestones / Timing

    Focus on process-readiness vs. product design

    Team provides brief updates on status

    Working-level Agenda targets specific deliverables

    Team members do the work during these meetings (i.e., develop PFMEA, Part Inspection Standard, Control Plan, etc.)

    GENERAL AQP MEETINGS

  • 38

    AQP MEETING FORMS AND DOCUMENTS

    AQP Timing Chart

    Supplier must maintain and update for each AQP meeting

    Tracks progress towards completion of all PSO elements, plus key Supplier Quality deliverables and AQP tasks (IRE, PPAP, etc.)

    Details item status and customer responsible lead

    Required for all programs following AQP (and all Fiat parts managed by Chrysler)

    SUPPLIER:

    SUPPLIER CODE: MY/VEHICLE FAMILY:

    PART NUMBER(S):

    REVISION:

    PART NAME(S): REVISION DATE:

    AQP MEETING DATE:

    PART RISK (H/M/L): AQP MEETING LOCATION:

    VP

    PVP

    Job 1

    BEGIN

    P LAN ACT P LAN ACT

    SQE -

    SQE 1

    SQE -

    ENG -

    SQE -

    SQE -

    SQE -

    SQE -

    Confirm composition and commitment of Core

    AQP Team Members

    CU

    ST

    OM

    ER

    LE

    AD

    PSO

    Element

    END

    Build

    NameMRDBuild Date

    Month-DateMonth-DateMonth-Date Month-Date

    SUPPLIER

    RESPONSIBLE

    # of

    Veh

    AQP ACTIVITIES

    eCIMS / Lessons Learned Reviewed

    If status is 1, 2, or 3 (Red

    or Yellow), you must

    provide a Risk Mitigation

    PlanEnter 1-5

    Advance Quality Planning

    Month-Date Month-DateMonth-Date

    ADVANCE QUALITY PLANNING (AQP)

    TIMING CHART

    Month-Date Month-DateMonth-DateMonth-Date STATUS

    # of

    Days

    YEAR

    Month-Date

    #NUM!FIAT PROGRAM

    REVIEW STATUS#NUM!

    CHRYSLER AQP

    STATUS

    RISK MITIGTION PLAN

    YEAR

    Month-Date

    Initial Risk Evaluation (IRE)

    Source Package Review

    KEY MATERIAL/BUILD DATES

    Verify deliverables timing to CPCP timing

    Prior PSO Review (similar products)

    Volume, ramp-up curve, and product mix verified

    and capable - CPV, P.O, SP

    Program & Style

    Approval

    EF EFEF

    Step 2 Style

    Freeze

    Step 3 Tooling

    Kickoff

    EF

    Verification of Process

    VP EF

    Pre Volume Production

    PVP EF

    Job 1 Offline

    EF

    Commercial Launch

    EF

    Step 5 Prod. Designs

    Complete

    0

    0

    0

  • VP

    PVP

    Job 1

    BEGIN

    P LAN ACT P LAN ACT

    SQE -

    SQE 1

    SQE -

    ENG -

    SQE -

    SQE -

    SQE -

    SQE -

    SQE -

    PTS -

    ENG -

    ENG -

    ENG -

    SQE -

    ENG -

    ENG 3

    ENG 4

    SQE -

    Review CNs and IAAs (including associated Risk)

    TAG Review (Chrysler-purchased tooling only)

    Confirm composition and commitment of Core

    AQP Team Members

    Part Development Plan Complete

    Status of Open Issues from Technical Review Risk

    Assessment (FIAT parts only)

    Supplier Quality Risk Assessment (SQRA)

    CU

    ST

    OM

    ER

    LE

    AD

    PSO

    Element

    END

    Build

    NameMRDBuild Date

    Production Tooling Complete (PTC)

    SUPPLIER

    RESPONSIBLE

    # of

    Veh

    AQP ACTIVITIES

    eCIMS / Lessons Learned Reviewed

    Advance Quality Planning

    Design FMEA

    Test Sample Sizes and Frequencies

    # of

    Days

    Design Review - Customer Perception targets

    Initial Risk Evaluation (IRE)

    Source Package Review

    Confirm Supplier PPAP Self-Certification status

    KEY MATERIAL/BUILD DATES

    Verify deliverables timing to CPCP timing

    Prior PSO Review (similar products)

    Volume, ramp-up curve, and product mix verified

    and capable - CPV, P.O, SP

    39

    AQP TIMING CHART

    1. Item or activity title Key AQP tasks and SQ

    deliverables (IRE, Production Tools Complete, IMDS, PPAP)

    All PSO Elements

    2. Tracks Supplier responsibility for each item, with begin/end dates

    3. Key build/MRD dates

    4. Details Chrysler lead for each item

    1

    2

    3

    4

  • If status is 1, 2, or 3 (Red

    or Yellow), you must

    provide a Risk Mitigation

    PlanEnter 1-5

    STATUS RISK MITIGTION PLAN

    Commercial

    40

    AQP TIMING CHART

    5 6

    5. Indicate the status of the task.

    6. Brief description of the risk mitigation plan (or reference to a more detailed action plan)

    Score Chrysler Definition

    1

    Not present / not started and: Very late to required milestone and will cause other required deliverables to be late to their required milestone/vehicle launch Risk Mitigation Plan does not exist Extremely High Risk to milestone/vehicle launch (certain to cause delay in milestone/vehicle launch)

    2

    Incomplete and: Late to required milestone and may cause other deliverables to be late to their required milestone/vehicle launch Risk Mitigation Plan exists but is not acceptable or requires unrealistic timing to meet milestone High Risk to milestone/vehicle launch (may cause delay in milestone/vehicle launch)

    3

    Incomplete and: Late to required milestone Risk Mitigation Plan exists and is acceptable Low Risk to milestone/vehicle launch

    4 Incomplete and: Progressing according to required milestone timing No Risk to milestone/vehicle launch

    5 Complete and approved

  • 41

    AQP TIMING CHART

    7. Use this section to track progress of each item towards completion Shows suggested AQP start and finish CPCP milestones (solid black line)

    Shows current progress (gold dotted line; manually adjusted)

    Use solid red line to show current date (manually adjusted)

    Details required deliverable dates (black diamonds)

    Month-Date Month-Date Month-DateMonth-DateMonth-Date

    YEAR

    Month-Date Month-DateMonth-Date Month-DateMonth-Date Month-DateMonth-Date

    YEAR

    Month-Date

    High risk; PO + 8 wks

    All Other

    Program &

    Style

    Approval

    EF EFEF

    Step 2

    Style

    Freeze

    Step 3

    Tooling

    Kickoff

    EF

    Verification of

    Process

    VP EF

    Pre Volume

    Production

    PVP EF

    Job 1

    Offline

    EF

    Commercial

    Launch

    EF

    Step 5 Prod.

    Designs

    Complete

    7

  • 10 AQP Activities [Specific] Follow the instructions listed below: Used in FIAT

    Program Review?

    Initial Risk Evaluation (IRE) The SQE performs the Initial Risk Evaluation and determines the part risk to be High, Medium, or Low. No

    Advance Quality Planning PSO Element 1. Includes overall program timing, Supply Base Management, Problem Solving, and most

    supporting processes. Verify timing for tooling, fixtures, gages, testing requirements, and sub-components.

    Regularly review and update timing plans, as needed. Review risk assessments for sub-components. Ensure

    the Tier 1 Supplier has a process for tracking Sub-Tier Supplier quality and delivery, and that poor-performing

    suppliers have been replaced or are receiving commensurate additional attention during the development

    phase. Review the Tier 1 Supplier's plan for PSO on sub-components, and verify back-up plans exist for Sub-

    Tier Suppliers with a high risk for supply issues.

    Yes

    Confirm composition and commitment of Core AQP

    Team Members

    Verify the core AQP Team members: Supplier Quality, Engineering, Plant Quality Center (for Part I/S), and key

    Suppler team members (Quality, Program Management/Engineering). Identify non-core AQP Team members

    that may need to provide input, such as Purchasing, Logistics/Supply, Supplier Sales Representative, etc.

    Complete, and keep up-to-date, a contact list with all AQP Team members, their phone numbers, and email

    addresses.

    Yes

    Source Package Review At the AQP Kick-Off Meeting, review the completed Source Package, noting key information and program

    deliverables. Ensure engineering specifications and Quality and Supply requirements are understood by the

    Supplier.

    No

    Volume, ramp-up curve, and product mix verified and

    capable - CPV, P.O, SP

    Review program volume requirements, planned product mix, and planned launch ramp-up curve. Ensure the

    Supplier understands the requirements. Support the Buyer in timely Purchase Order issuance, and ensure the

    quoted Daily Tooling Capacity is sufficient to meet Chrysler's needs.

    Yes

    eCIMS / Lessons Learned Reviewed Review quality spills from previous and similar products/processes. Use the eCIMS system, NCT system, and

    completed 8-steps. Ensure issues are accounted for when developing Design and Process FMEAs. Verify that

    issues resulting in past yardholds, PRIs, or Field Actions are adequately error-proofed or completely designed

    out of the part in the new process.

    Yes

    Prior PSO Review (similar products) Review Process Sign-Off (or PCPA, for Fiat parts) results from previous programs, both on similar product and

    from the same Supplier. Account for issues that may have resulted in lack of PSO approval so that do not

    reoccur, and make sure all open issues have been closed.

    Yes

    Verify deliverables timing to CPCP timing Ensure the AQP Team has the most current CPCP timing, including all milestones. Verify that Supplier

    promise dates for all deliverables are consistent with CPCP timing and are not late. Reference the "Supplier

    Quality Deliverables Timing" form on the AQP/PSO website.

    Yes

    Status of Open Issues from Technical Review Risk

    Assessment (FIAT parts only)

    Applicable for FIAT parts only. Review the status of open issues created from the Risk Assessment during the

    Technical Review (part of the FIAT Sourcing process). Verify progress and ensure it is consistent with what

    was planned.

    Yes

    Supplier Quality Risk Assessment (SQRA) Review the status and issues from the Supplier Quality Risk Assessment (SQRA) with the Product Team

    SQE. Ensure the AQP Executive Summary form is kept updated after each AQP Meeting with potential launch

    risks and Risk Mitigation plans.

    No

    Part Number, Description, and Change Level PSO Element 2. Verify that the Supplier has the latest Technical Documentation, including the design model,

    GD&T, access to the latest Chrysler Engineering Standards, access to color/gloss/graining masters, etc.

    Review GD&T to ensure datums are adequately defined and special characteristics are identified. Verify CNs

    allow sufficient time for tool modifications, testing, etc.; propose V2 timing for CNs that may create a risk to

    launch. Note: Planning to run the PSO at an unapproved revision level (i.e., a future CN) results in a maximum

    score of "3" for this item.

    Yes

    AQP TIMING CHART

    42

    Sample of task directions:

  • AQP TIMING CHART

    43

    Scoring Examples:

    Task

    Production Tooling

    Complete (PTC)

    Process FMEA

    Issue

    Late design release means the Supplier will not have

    production tools ready by VP. They plan to build parts with

    prototype tooling, using production intent materials and

    gages. Tools will be available in time to provide parts for

    PSO and the Pre-series build. (Suggested score = 3)

    In a review of the PFMEA, the SQE discovers that the

    Supplier has not implemented error/mistake-proofing on

    several safety-related items. In addition, an overall audit

    using the Supplier PFMEA Audit form returns a red result. (Suggested score = 1 or 2, depending on when this

    is discovered)

  • 44

    AQP MEETING FORMS AND DOCUMENTS

    AQP Open Issues

    Open Issues must be created and maintained throughout the program

    SQE has responsibility to maintain, but can delegate to the Supplier

    Key Points:

    1. ONE Individual as responsible for an item

    2. Dates: when the issue was opened, target for completion, and actual

    completion or closed

    3. Priority or risk level (recommended)

    4. Updates and comments

    AQP Open Issues are considered quality records

    Kept for life of the program, plus one year

    Who retains them? (SQE)

  • 45

    PART INSPECTION STANDARD (PART I/S)

    Provides clear communication and agreement between the Chrysler Manufacturing Plant, Engineering, Supplier Quality and the Supplier in regards to: Characteristics on the design model

    which the Chrysler Manufacturing Plant considers to be most important

    The measurement method, sample size, and frequency with which the Supplier checks those characteristics

    DRAWING/SKETCH

    SUPPLIERCHRYSLERDATEREVISION / DESCRIPTION

    FINALPART NO: PART NAME/DESC:

    SUPPLIER NAME: MANUFACTURING LOCATION:SUPPLIER CODE:

    PART INSPECTION STANDARD VEHICLE MY / FAMILY: DATE:

    DRAFT

    ENG QLTY MGR

    REV.

    # ENGPLANT QC SQE

    INITIAL SIGN-OFF / APPROVALDATETITLE SIGNATURENAME

    Engineer - Chrysler

    Plant QC Eng. - Chrysler

    SQE - Chrysler

    DRAWING NO. / REVISION LEVEL:

    Engineering - Supplier

    Quality Mgr. - Supplier

  • 46

    PART I/S

    SUPPLIER CODE: SUPPLIER NAME: MANUFACTURING LOCATION:

    FINAL

    PART INSPECTION STANDARD VEHICLE MY / FAMILY: DATE:

    DRAFT

    PART NO: PART NAME/DESC:

    INITIAL SIGN-OFF / APPROVALTITLE DATENAME SIGNATURE

    Plant QC Eng. - Chrysler

    SQE - Chrysler

    Engineer - Chrysler

    Quality Mgr. - Supplier

    Engineering - Supplier

    ITEM

    #REMARKS / INSPECTION METHODFREQ.

    SAMPLE

    SIZE

    MEAS.

    METHOD

    SPECIFICATION /

    TOLERANCE

    CHARACTERISTIC /

    INSPECTION POINT

    DRAWING NO. / REVISION LEVEL:

    Provides the Chrysler Manufacturing Plant a tool to more quickly identify a problem and responsibility when a quality issue occurs

    Gives the AQP team an opportunity to identify potential problems/conflicts between individual part requirements and Chrysler Build Objectives before the prototype build phase.

  • 47

    PART I/S TEAM

    Team Members (minimum):

    Chrysler:

    Supplier Quality Engineer

    Engineer

    Plant Quality Center Engineer

    Supplier:

    Quality Manager

    Engineering / Program Manager

    Additional team members may be added, as needed. Examples

    include the Chrysler Dimensional Engineer, Design Office, TAG

    representative, etc.

  • 48

    PART I/S RASIC

    Sup

    plier

    Sup

    plier Q

    uality

    Sys

    tem

    & C

    ompo

    nent

    Eng

    inee

    ring

    Man

    ufac

    turin

    g Qua

    lity (P

    lant

    )

    Veh

    icle E

    nginee

    ring

    Des

    ign

    Office

    Selection of Parts C CS C RA C

    Confirm Assembly vs Part Datum Scheme Alignment1

    R/S C C/R A

    Selection of Critical Dimensions1

    R/S C C/R A

    Sample Size and Frequency determination R A C C

    Measurement Method of Critical Dimensions R S A C

    Selection of Appearance Specs/Characteristics1

    R/S C C/R A C S

    Boundary Sample Creation and Review/Sign-off R S C A S S

    Selection of Functional Specs/Characteristics1

    R/S C C/R A

    Completion of Part I/S form R S CA

    Retention of Completed Part I/S RA I I I I I

    Responsible - Those who do the work to achieve the task. There is typically one role with a participation type of Responsible

    Accountable - Final Approving Authority

    Support - Resources allocated to Responsible

    Informed - Those who are kept up-to-date on progress, often only on completion of the task or deliverable; and with whom there is just one way

    Consulted -Those whose opinions are sought; and with whom there is two-way communication

    NOTES

    1: Dependant upon which party is design-responsible

  • 49

    HOW IS THE PART I/S DONE?

    Chrysler Product Creation Process (CPCP)

    FINAL DRAFT CREATION

    PART INSPECTION STANDARD

    IRE FPSC PSO & PPAP

  • 50

    Part I/S Creation Phase

    HOW IS THE PART I/S DONE?

    Scope of the program is defined (parts identified, critical characteristics identified, etc.)

    Document is created

    Identify Parts

    & Provide

    Information

    Team Review Revise &

    Sign Create

    Part I/S

  • 51

    Use of the Part I/S Draft to check parts for the VP and PVP pilot builds

    Follows the same basic flow for each build:

    Part I/S Draft Phase

    Implement &

    Collect Data Team Review

    Revise &

    Resubmit

    Build

    Event

    HOW IS THE PART I/S DONE?

  • 52

    Part I/S is finalized for Job 1 and continuing volume production

    The Part I/S remains a living document and can be revised as needed

    Part I/S Final Phase

    The Part I/S does not replace either the Control Plan or FPSC

    at any program stage.

    HOW IS THE PART I/S DONE?

  • 53

    PART I/S AND OTHER DOCUMENTS

    The Part I/S should be developed alongside other quality documents, especially the PFMEA, Control Plan, and

    FPSC plan The Part I/S does NOT replace or supersede any other quality

    documents!

    Characteristics included on the Part I/S should also be included on the Control Plan for the part

    The Part I/S should be updated at the same time as other quality documents (e.g., for CNs, FRs, etc.)

  • PART I/S AND OTHER DOCUMENTS

    54

    FPSC: Safe Launch; checks/inspections over and above Control Plan

    Control Plan: Controls (w/ frequency, sample size) for

    entire process

    Part I/S: Ties controls for the final product characteristics

    with visual representation (GD&T) and allows for

    measurement scheme agreement with the Chrysler

    Manufacturing Plant

  • PART I/S AND OTHER DOCUMENTS

    Question: If were instituting 100% inspection for VP (or other pilot build), with a gradual lessening of frequency as

    we move into production, should the Part I/S reflect this? No. The Part I/S is a tool to communicate how the Supplier will check

    parts in production. As such, it should reflect the production control

    plan inspection frequencies and sample sizes. If the team is requiring

    100% inspection for a pilot build, this should be reflected on the FPSC

    plan, NOT Part I/S. Per the RASIC on slide 8, SQ has the final

    approving authority on sample sizes and frequencies.

    55

  • PART I/S FLAG IN CQMS

    56

  • PFMEA ACCEPTANCE

    57

    Part Inspection

    Standard (Part I/S)PFMEA Acceptance

    What is significant PFMEA Acceptance?

    An audit or assessment of the Suppliers Process FMEA

    Applicable for any part that also requires a Part I/S All parts with a High IRE and those parts selected by the Assembly Plant

    Required to be completed 14 weeks prior to VP

  • PFMEA ACCEPTANCE

    58

    Supplier Quality Engineer (SQE) Supplier 3rd Party

    Audit Result?

    Identify Significant PFMEA Acceptance parts (Notify

    Supplier)

    End

    3rd Party Review required?

    Review PFMEA using "Supplier PFMEA Audit Summary" form

    Review PFMEA using "Supplier PFMEA Audit Summary" form

    Forward PFMEA to SQE

    Forward PFMEA to 3P (copy SQE)

    YES

    Audit Result?

    Make corrections to PFMEA (work with Chrysler SQE)

    Enter Actual Date in CQMSGREEN

    NO

    Make corrections to PFMEA (work with 3P)

    REDRED

    YELLOW

    YELLOW

    Dispute ProcessIf Supplier and/or SQE disagrees with 3P assessment:1. Submit PFMEA to Sr. Manager - SQ Operations2. Sr. Manager - SQ Operations reviews PFMEA3. If result matches 3P, 3P assessment stands and process is

    followed as normal4. If result differs, Audit Result changes and process follows

    the new result flow for 3P

    Audit Result?

    GREEN

    RED

    YELLOW

    GREEN

    SQE determines if audit will be done by

    themselves or 3rd Party

    Auditor uses the Supplier PFMEA Audit Summary form

    If not green, Supplier makes corrections and

    resubmits per the

    flowchart

  • PFMEA ACCEPTANCE

    Criteria for using a 3rd Party Auditor include (but is not

    limited to):

    Suppliers who are "Red" in the Quality Bid List system

    Suppliers who are on New Business Hold

    Suppliers on the Top Problem Supplier Locations list

    Parts from Suppliers that have been involved with / responsible for recent yardholds, Product Related Issues (PRIs), or Field Actions

    The SQE makes the final decision for whether or not a Supplier must

    use a 3rd Party auditor for this process

    59

  • PFMEA ACCEPTANCE

    60

    Dispute Process

    If the Supplier and/or SQE disagrees with the 3rd Party assessment:

    1. Submit the PFMEA to the Sr. Manager - SQ Operations

    2. The Sr. Manager - SQ Operations reviews the PFMEA with Supplier PFMEA Audit Summary form

    3. If the result matches the 3rd Party, the assessment stands and process

    is followed as normal

    4. If the result differs, the Audit Result is changed and the process

    follows the process flow for the new result

  • PFMEA ACCEPTANCE

    61

    Supplier Process FMEA: Audit Summary (based on Fourth Edition FMEA Manual)

    MY/Program

    Name of Component(s), Sub-System(s) or System(s):

    Part Number(s):

    Responsible Supplier:

    Responsible Chrysler Supplier Quality Engineer:

    Name of Auditor:

    Date Reviewed:

    Date of PFMEA audited (Later of Original or Rev. Level):

    Rating Detail Criteria

    Header: "Yes" if all answers in section 1 are "Yes."

    Non-Header sections (2 through 13): Count # of sections 2-13 "No" and # "E/I."

    Header "Yes" overall and no more than

    three sections "E/I" overall = "Green"

    Neither "Green" nor "Red" criteria met =

    "Yellow"

    Six or more non-Header sections "No"

    overall = "Red"

    1 Header Yes E/I No N/A Auditor Comments

    1a Name of Vehicle(s)/Program(s) included? - -

    1b Model Year of Program(s) included? - -

    1c Name of Supplier included? - -

    1d Part Number and Description included? - -

    1e Core Team includes (at a minimum): Chrysler: Supplier Quality Engineer and

    design-responsible Engineer. Supplier: Quality Engineer and Plant Mfg.

    Engineer? Names and titles or area of responsibility are included? Note: Phone

    #'s recommended, but not mandatory for this audit.

    - -

    1f Key Date shown is PPDC date or P.O. issuance + 60 days, whichever is later (for

    new vehicle programs), or does not exceed PPAP date (for programs already in

    production )? Note: Contact Chrysler SQE, if required.

    - -

    1g FMEA Date (Orig.) is shown? - -

    1h FMEA "(Rev.)" date within past 60 days? Note: "N/A" if "(Orig.)" date is within 60

    days.- -

    Additonal Comments (not to impact audit results): - - - -

    If all answers "Yes," check "Yes." If one or more "No," check "No." - -

    Result

    "No"___ "E/I"___

    Overall Rating (place an "X" in the appropriate box)

    Note 1: "E/I" = only minor "E"xceptions or requirement "I"nconsistently applied (approx. 25% or less) and correction still required.

    Note 2: Do not allow a "No" answer to one question (e.g., Detection ranking too low) result in a "No" answer to another related question (e.g.,

    lack of "Recommended Actions" or "Action Results"). Evaluate each question based only on their own merits.

    Note: If PFMEA is done by process vs. part, a separate header sheet listing the various programs, parts, etc. for each element in Section 1 is acceptable.

    If you dont know if something has been done, answer , No then follow up later.

    Ask how? and when? vs. yes/no questions when assessing certain questions, (i.e., Did the Design-responsible Engineer provide input on Effects?).

    Be sure to read and understand the Notes to help ensure consistency.

  • Additional Comments on the PFMEA

    PFMEAs shall incorporate lessons learned from past programs or similar parts, internal and external nonconformance data related to

    the parts, and customer (Chrysler) inputs, as outlined in the Supplier

    PFMEA Audit Summary.

    For the parts requiring PFMEA Acceptance in the Chrysler Quality Management System (CQMS), the SQE and Supplier shall jointly

    audit the PFMEA no later than (14) weeks prior to VP SOF. In

    addition, the result of the PFMEA audit shall be "Green" before the

    Actual Date is entered in CQMS.

    All PFMEAs, regardless of the risk level, shall be rated "Green" per the "Supplier PFMEA Audit Summary" form as part of PSO

    requirements.

    Please refer the PFMEA Acceptance process standard in the Book of Knowledge for more details.

    62

  • The responsible SQE is expected to provide following support:

    Ensure the Supplier provides the PFMEA and supporting documents within 2 weeks of email notification. Do not rework the documents beforehand.

    If the 3rd party audit obtains a "Red result, the Supplier is required to contract one of the 3rd Party Auditors and start coaching and audits within

    (2) weeks. The Supplier works with the 3rd Party Auditor until a "Green"

    result is achieved. The supplier may be issued a Forever Requirement Violation (FRV) as Failure to

    follow/respond to Chrysler requirements or requests if they refuse to seek coaching within (2) weeks of receiving a Red audit result.

    If the supplier needs to dispute the audit result, the Supplier and/or SQE shall submit the PFMEA audit form as originally completed by the auditor

    and an explanation for the dispute to the PFMEA Auditor Facilitator, Stanley

    Zhou ([email protected]).

    Please refer to the PFMEA 3rd Party Audits and Coaching process

    standard in the Book of Knowledge for more details.

    3rd Party PFMEA Audits

  • 64

    FIRST PRODUCTION SHIPMENT CERTIFICATION

    What is FPSC?

    Safe Launch activities

    Audit / inspection above and beyond standard

    process controls

    Records retained by the Supplier; may be

    requested by Chrysler

    personnel at any time

  • 65

    FPSC BASICS

    FPSC includes all Special Characteristics Product characteristics or manufacturing process parameters which can

    affect safety or compliance with regulations, fit, function, performance or

    subsequent processing of a product

    Also includes any additional characteristics selected by the AQP and/or PSO Team (Chrysler or Supplier)

    Key characteristics

    Safety characteristics

    Emissions characteristics

    Torque requirements

    SPC points

    Others deemed critical by the Supplier or Chrysler

    S

  • 66

    FPSC BY PROGRAM

    NEW PROGRAMS

    Begins with first shipment for VP build

    Duration is until Job 1 + 90 days has passed (minimum)

    Plan, results for VP, and effectiveness of the FPSC

    reviewed during the Pre-PSO

    Meeting

    MODIFIED PROGRAMS / FR

    CHANGES / RESOURCING

    Begins with first shipment to a Chrysler (or Chrysler-designated)

    facility

    Duration is until 1st shipment + 90 days has passed (minimum)

    Plan reviewed during PSO

    The Chrysler AQP Team is final approver of the FPSC duration. Deviations from the minimum are to be approved in writing by the Chrysler AQP Team.

  • 67

    OTHER FPSC INFORMATION

    The Supplier is responsible for ensuring that FPSC (or

    equivalent) activities are implemented through the Supply

    Chain (Tier 2 and lower). The duration of FPSC (or

    equivalent) at sub-tier suppliers shall match that of the Tier

    1 Supplier's FPSC.

    FPSC is not a replacement for the Part I/S or Control Plan,

    nor is the Part I/S or Control Plan a replacement for FPSC.

    FPSC is intended to be an additional level of inspections or

    audits to protect the Chrysler (or Chrysler-designated)

    manufacturing facility during the pilot and launch phases.

  • PART QUALIFICATION PROCESS

    68

    Plant validation of BIW/QAF (Interior & Exterior Quality

    Assurance Fixtures)

    components (internal and

    external suppliers) to fulfill the

    customer requirements,

    Quality standards, Build

    Objectives (EBO) and Design

    intent. Validation includes

    Dimensional control.

    Plant Metrology Center lead; SQE supports the plant by

    ensuring Supplier submits

    parts and data when required

    and corrective actions are

    completed

    75% of Tolerance

    75%-100% of Tolerance

    Over 100% of Tolerance

  • PART QUALIFICATION PROCESS

    69

    Supplier submits part data from 5 parts and

    transfer to Plant

    Mark up two parts with measured

    data to bring to plant

    Meet with Plant to review parts and data

    Supplier Creates new

    PDCA if required

    Supplier incorporates Changes in

    Manufacturing Process if req.

    If part has Red data supplier should submit PDCA and sub-tier data

    Supplier (Internal & External) Requirements for Part Submission (preferred two Weeks prior to MRD) for each build phase

    Plan Do Check Act (PDCA)/Quick Kaizen required for any red points

    More loops should be repeated as corrective action timing permits

    Parts and Data need to be characterized :

    Part made from Soft Tool / Hard Tool

    Tools are on Home Line / Temp Line

    Special Means were /were not

    Gage R&R Roadmap of Part

  • PART QUALIFICATION PROCESS

    70

    Vehicle Development Phase Mass Production

    Continuous Loops

    Additional loops will be required within each build phase (S1A, S1B etc.) according to:

    Part achievement of Dimensional Compliance Engineering changes Part availability (Pilot Build Phase) Measurement schedule Process changes (e.g. soft to hard tools)

    Must have knowledge of part production process hard tools/soft tools , maturity of supplier process

    Parts shall be dimensionally correct for S1 / VP Parts shall meet PP/PPK per Appendix B of the AQP/PSO

    Manual at S2 / PVP (min 30 pc sample) Parts shall meet CP/CPK of 1.33 at V1 and later (min 30 pc

    Sample)

    NOTE: Supplier should build in small batches for each burst build in the pilot phase to accommodate continuous improvement plans

    NOTE: Submission due date - preferred 2 weeks prior to MRD First submission for each Pilot Phase must be complete before A Phase framing

    NOTE: Request 2 additional parts for each pilot phase to accommodate submission requirement NOTE: Supplier Must submit for each of the 3 Pilot Phase (if applicable)

    S1/VP S2/PVP V1

    S1A - Framing S2A - Framing Loop 1

  • PART QUALIFICATION PROCESS

    71

    PART AVG. WEIGHT SUBMISSION DATE:

    SUBMISSION: BUILD: PHASE:

    FIRST PRODUCTION SHIPMENT CERTIFICATION (FPSC) S1 / VP Phase A

    PART QUALIFICATION S2 / PVP Phase B

    PART INSPECTION STANDARD (PART I/S) V1 / Job 1 Other

    INITIAL PROCESS STUDY Post-V1 / Post-Job 1

    OTHER

    PROCESS:

    TOOLING ASSEMBLY SPECIAL MEANS

    COMMENTS:

    Chrysler SQE/ASME Phone ( )

    Chrysler Plant QE Phone ( )

    Chrysler Engineer Phone ( )

    Plant Mgr. (Supplier) Phone ( )

    Quality Mgr. (Supplier) Phone ( )

    Data Prepared by: Phone ( )

    Special Means Not Required Date: Home Line Complete Date: Production Tooling Complete Date:

    Email

    Email

    Email

    Email

    Email

    Email

    CharacteristicChar #

    PROTOTYPE PRODUCTION TEMP LINE HOME LINE

    PART NUMBER

    SUPPLIER CODE

    SUPPLIER NAME

    M eisterbock R/Y/GCP3 CPK

    3 Gage R&R

    Acc?ACC/REJ

    Free

    State FitQAF

    Variable /

    Attribute

    Dim.

    Correct?1P P

    2 P PK2

    YES NO

    MEASUREMENT RESULTS SUMMARYSpecification /

    To leranceClassif.

    MFG. LOCATIONPART DESCRIPTION

    MY/VEHICLE

    3 Parts shall meet CP/CPK of 1.33 at V1 and later

    2 Parts shall meet PP/PPK per Appendix B of the AQP/PSO Manual at S2 / PVP

    NOTES:1 Parts shall be dimensionally correct for S1 / VP

    Supplier Completes Part Data Submission form- Requirement of Submission prior to MRD

    Metrology Center will notify supplier of Disposition Green = Dimensionally Correct (< 75% of Tolerance) Yellow Dimensionally Correct (>75% and < 100% of

    Tolerance) Red = Dimensionally incorrect - Quick Kaizen/PDCA

    needed with data submission Metrology Center will notify supplier of Part Validation

    Meeting Green Part = Metrology Center will notify supplier of next

    build phase submission and give approval for next batch build

    Red Part = Suppliers corrective action will determine next submission (PDCA needed documenting plan)

  • PART QUALIFICATION PROCESS

    72

    Supplier Submits GD&T or PIS (Part Inspection Standard - if available) - Requirement of Submission

    Part I/S is used only if the part is required to have one based on Part I/S criteria Part I/S is NOT automatically required for parts undergoing the Part Qualification

    Process!

  • PART QUALIFICATION PROCESS

    73

  • PART QUALIFICATION PROCESS

    74

    Dimensional Compliance Team: -Product Release Engineer

    -Have the released model/GD&T up to date -Ensure CN is complete to document dimensional revisions

    -Supplier Quality Engineer (SQE) External Suppliers -Assist Metrology Center Rep by communicating requirements to the supply base -Assist supplier with Quick Kaizen/PDCA

    -Advance Stamping Manufacturing Engineer (ASME) Internal Suppliers -Assist Metrology Center Rep by communicating requirements to the supply base -Assist supplier with Quick Kaizen/PDCA

    -Metrology Center Representative -Maintains Master Part Approval Schedule -Schedules part disposition Team Meetings -Schedules part submissions

    -Supplier Representative (Internal & External) -Timely part submissions with appropriate forms -When part is red, develops Quick Kaizen/PDCA

  • PART QUALIFICATION PROCESS

    75

    After 1 Day late Escalates to SQ Manager/Metrology Manager

    After 3 Days Escalates to Plant Manager , Director, and Plant

    Metrology Center Manager Level

    After 5 Days Escalates to VP level, Manufacturing , P & SQ,

    Engineering

    Escalation Process:

  • PART DATA SUBMISSION FORM

    76

    Data Sheet

  • 77

    PART DATA SUBMISSION FORM

    PART AVG. WEIGHT SUBMISSION DATE:

    SUBMISSION: BUILD: PHASE:

    FIRST PRODUCTION SHIPMENT CERTIFICATION (FPSC) S1 / VP Phase A

    PART QUALIFICATION S2 / PVP Phase B

    PART INSPECTION STANDARD (PART I/S) V1 / Job 1 Other

    INITIAL PROCESS STUDY Post-V1 / Post-Job 1

    OTHER

    PROCESS:

    TOOLING ASSEMBLY SPECIAL MEANS

    COMMENTS:

    Chrysler SQE/ASME Phone ( )

    Chrysler Plant QE Phone ( )

    Chrysler Engineer Phone ( )

    Plant Mgr. (Supplier) Phone ( )

    Quality Mgr. (Supplier) Phone ( )

    Data Prepared by: Phone ( )

    Email

    Email

    Email

    Email

    Email

    Email

    3 Parts shall meet CP/CPK of 1.33 at V1 and later

    2 Parts shall meet PP/PPK per Appendix B of the AQP/PSO Manual at S2 / PVP

    NOTES:1 Parts shall be dimensionally correct for S1 / VP

    PROTOTYPE PRODUCTION

    Classif.

    Home Line Complete Date: Production Tooling Complete Date:

    Variable /

    Attribute

    Dim.

    Correct?1P P

    2Char # P PK2

    YES NOTEMP LINE HOME LINE

    M eisterbock R/Y/GCP3 CPK

    3 Gage R&R

    Acc?

    Special Means Not Required Date:

    Build Use?Free

    State FitQAF

    MEASUREMENT RESULTS SUMMARYSpecification /

    To leranceCharacteristic

    MFG. LOCATIONPART DESCRIPTION

    MY/VEHICLE

    PART NUMBER

    SUPPLIER CODE

    SUPPLIER NAME

    Results sheet

    Form used to

    submit data for: FPSC Part Qualification Part I/S Initial Process

    Study

    Information

    carried over from

    data sheet

  • WHAT IS CRAFTSMANSHIP? INFLUENCES AND CONCEPTS

    CRAFTSMANSHIP REVIEWS

  • 8 CRAFTSMANSHIP INFLUENCES

    Design: tolerance stackup, mating parts have different form (Eng)

    AAR: colour, gloss, grain (PDO)

    Appearance Standards: AS-10169, objective standard which must be met for conformance (Supplier)

    Supplier Process: no spec, boundary samples required, flow lines, sink marks, squeezeout, etc. (Supplier, SQ)

    HMI: human-machine interface, tactile feel of buttons and controls, sounds made while functioning, efforts to press buttons, etc. (All)

    Chrysler Assembly Process: internal practices, mallet scuff marks, ISD, missing/loose/shy, etc. (Mfg)

    Nonconforming Parts: (Supplier, SQ)

    Cleanliness: smudge marks, dirt, dust, etc.(All)

    What else?

  • Interior vs Exterior Craftsmanship Philosophies

    within Chrysler

    Both follow the same principles

    Interior managed by dedicated Interior Quality and Craftsmanship department, interior SQE is part of team

    Exterior historically managed by SQ and started later in product development phase, craftsmanship reviews

    held during S2 timeframe

  • Exterior Craftsmanship Reviews Main areas of

    Concentration

    Appearance Standards: AS-10169, objective standard which must be met for conformance (Supplier)

    Supplier Process: no spec, boundary samples required, flow lines, sink marks, squeezeout, etc. (Supplier, SQ)

    Nonconforming Parts: dimensional issues, improper materials used, (Supplier, SQ)

  • CRAFTSMANSHIP FOLLOW UP

    Document results of review on PIS

    Schedule follow up visits

    Maintain craftsmanship PDCA

    Ask for boundary samples during supplier visits to gauge current production

    Maintain good communication between advance and current SQ post-review

  • 83

    PROCESS SIGN-OFF

    What is PSO?

    Verification that the AQP activities have

    been successfully

    completed

    A review of the Suppliers process, from beginning to end

    Production Validation Phase

    Verification of Process (VP)

    Supplier Readiness Evaluation (SRE)

    First Production Shipment Certification

    (FPSC)

    PV Testing

    Pre-PSO Meeting

    PSO On-Site Visit &

    Production Demonstration Run

    PSO Result

    Complete PPAP requirements & submit Dimensional

    PSW/PPAP

    Complete corrective actions; reschedule On-Site Visit / PDR

    as necessary

    5 (Z)1-4 (N)

    5 + PVT (A)

    Supplier

    Quality RiskAssessment

    (SQRA)

    PartQualification

    Process

    (Assembly Plant Lead)

  • 84

    PROCESS SIGN-OFF: BRIEF SUMMARY

    FOUR BASIC ACTIVITIES TO PSO:

    1.Trial Runs / Supplier Readiness Evaluation (SRE) Readiness for the PSO On-Site Visit

    Yields parts for PV Testing

    2.Pre-PSO Meeting Document review

    Evaluate SRE results

    Schedule PSO On-Site Visit

  • 85

    PROCESS SIGN-OFF: BRIEF SUMMARY

    3. PSO On-Site Visit Review of Suppliers process and facilities

    Production Demonstration Run

    Initial Process Study

    4. PV Testing Functional testing, et. al.

    Select component & system PV (Production Validation) level testing required by VP: Only that testing required to ensure the components

    function as intended, and which have been agreed

    upon between the supplier and the Chrysler Product

    Engineer at Production Design Clean-up (PDC), and

    documented in the Design Verification Plan and

    Report (DVP&R).

    Concurrent with other PSO activities

  • 86

    MORE INFORMATION

    For full information and training on the

    Process Sign-Off, please sign up for

    PSQPSO200 in TEDS

  • 87

    PPAP

    PSO Z APPROVAL

    Supplier can submit the dimensional PSW

    SQE can enter the dimensional PPAP into CQMS

    Receive partial tool payment (at the discretion of purchasing)

    Still needs an IAA to ship parts

    PSO A APPROVAL

    Supplier can submit the full PSW

    SQE can enter full PPAP into CQMS

    Receive full tooling payment

    Can ship parts normally

  • 88

    Supplier sends the PSW to the Chrysler SQE Must copy the Supplier Quality Group mailbox ([email protected])

    SQE reviews the PSW for proper information

    Verifies correct part number, CN, IMDS

    number present, etc.

    SQE enters PPAP dates & disposition into CQMS

    Supplier enters PPAP dates & disposition into

    CQMS

    Medium & High risk parts Low risk parts

    PPAP

  • 89

    CQMS - PPAP Submission

    Enter a Chrysler part number, click Find. Check box indicates row(s) to update. Enter dates as

    MM/DD/YYYY or use the calendar icon. The Disposition is required with Actual Dates.

  • 90

    CQMS - PPAP Mass Update

    Select an Update Element: Blank Promise Dates, Promise Due Next 30 Days, Not

    Approved or All. Enter a CN or enter a Supplier Code and CN Model Year. Click Find.

    Optionally enter a Commodity Code or a Deck Code (with Supplier Code and CN Model

    Year) for additional filters.

  • 91

    CQMS - PPAP Mass Update

    Check box indicates row(s) to update. Enter dates as MM/DD/YYYY or use the calendar

    icon. The Disposition is required with Actual Dates.

  • 92

    LESSONS LEARNED

    Ensure lessons learned from the current program are carried

    forward into new programs

    Corrective actions for issues documented in FMEAs, Control

    Plans, etc. and added to the quality

    documents of other, similar products

    Hold a Things Gone Right / Things Gone Wrong review meeting (30-60 days post launch)

    Document TGR/TGW and retain in an accessible location

    Review prior to beginning new programs

    Review AQP meeting minutes and open issues from previous programs

    Keep the Master PFMEA updated as issues occur

  • 93

    FOREVER REQUIREMENTS

    1. Proactively communicate with Chrysler. Know when to raise the red flag.

    2. Request approval from Chrysler prior to implementing any anticipated process changes.

    3. Request approval from Chrysler prior to implementing any internal or Sub-Tier manufacturing location changes.

    4. Watch for sub-tier Supplier issues and tell Chrysler about them.

    5. Notify Chrysler of potential supply / capacity issues

    AQP/PSO 7th Edition Manual, Appendix E

  • 94

    FOREVER REQUIREMENTS

    Changes to the process post-PSO require submission to Chrysler via the

    Forever Requirements system

    The Tier 1 Supplier is responsible to ensure all of their sub-tier Suppliers

    follow the Forever Requirements

    Submissions to Chrysler always come from the Tier 1, regardless of what level of sub-

    tier is making the change

    Full information and training on the Forever Requirements can be found in

    MQCFRR200, available through TEDS

  • AQP TIMING CHART

    Group Activity AQP Timing Chart scoring

  • 96

    SQ DELIVERABLES & TIMING

    Shaded deliverables require promise and actual date entries into, or are managed through, the Chrysler Quality

    Management System (CQMS)

    SQ Deliverable Chrysler Product Creation Process (CPCP) Milestone

    Initial Risk Evaluation (IRE) Complete N/A (Source Identified in CQMS + 2 weeks)

    Part I/S Parts Identified 22 weeks prior to VP Start of Frame

    PFMEA Accepted [PFMEA] 14 weeks prior to VP Start of Frame

    Part Inspection Standard (draft) [Part I/S (d)] 10 weeks prior to VP Start of Frame

    Component-level Production Validation (PV) Testing Complete VP - Verification of Process Build

    Equipment, Fixtures, Facilities, and Gages Complete VP - Verification of Process Build

    First Production Shipment Certification (FPSC) Start VP - Verification of Process Build

    Gage R&R Complete [Gage R&R] VP - Verification of Process Build

    IMDS Submitted VP - Verification of Process Build

    Production Tooling Complete [PTC] VP - Verification of Process Build

    Station Cycle Time / FTC Compliant VP - Verification of Process Build

    Supplier Quality Risk Assessment (SQRA) VP, PVP, & Job 1 Offline

    Dimensional Capability Complete [Dim Cap] PVP - Pre-Volume Production (Pre-Series)

    Error / Mistake Proofing Implemented PVP - Pre-Volume Production (Pre-Series)

    Key Personnel Hiring/Training Complete PVP - Pre-Volume Production (Pre-Series)

    Production Demonstration Run (PDR) Complete [PDR] PVP - Pre-Volume Production (Pre-Series)

    Production Validation (PV) Testing Complete [PVT] PVP - Pre-Volume Production (Pre-Series)

    PPAP Complete [PPAP] PVP - Pre-Volume Production (Pre-Series)

    Part Inspection Standard (final) [Part I/S (f)] Job 1 Offline

  • 97

    ADDITIONAL TRAINING

    Register through TEDS

    Process Sign-Off PSQPSO200

    Forever Requirements / Resourcing MQCFRR100

    Chrysler Quality Management System MQCQMS100

    Advanced PFMEA DQIFMA210

    Nonconformance Tracking System MQCNCT100

    eCIMS DQCZRO100

    Warranty Management MQCSWM100

    3 Legged 5 Why MQCTLW100

    Part Inspection Standard PSQPIS100

  • 98

    ADDITIONAL TRAINING

    Training CDs available

    DQIFMA201 - PFMEA

    DQISPC350 - Statistical Process Control

    DQIPCA300 - Process Capability Analysis

    DQIMPT300 - Error Mistake Proofing

    DQICPD400 - Control Plan Development

    DQIFMA275 - Design FMEA

    Contacts:

    Sheri De Hesselle [email protected] 722-1370

    Paula Mack [email protected] 722-1370

  • 99

    QUESTIONS?

    Please visit the AQP/PSO website for electronic versions of the following:

    The AQP/PSO 7th Edition Manual

    AQP Executive Summary and Open Issues forms (including the PTLR)

    AQP Timing Chart

    PSO forms

    FPSC form

    Part I/S form

    Appearance Approval form and instructions

    Supplier PFMEA Audit Summary

    Supplier Quality Deliverables Timing Requirements

    Part Data Submission form

    https://gsp.extra.chrysler.com/qlty/pso/index.html

    Suppliers can access through the Chrysler Portal Reference section of COVISINT

  • BACKUP

    Special Notes for Chrysler SQEs

    Managing parts for FIAT

    100

  • Chrysler SQEs Managing Fiat Parts

    101

    Macro phases legend

    Approach / Style / initiative Approval / Sourcing

    Technical / Technological Development

    Industrialization

    Production Ramp Up

    Production Tracking (6 months minimum) / Supplier Containment / Continuos Improvement

    6 months 9 - 10 months 1 m

    16 - 17 months

    Card 0

    CSE

    Product

    Card

    Recommendation

    IRE

    AQP TC

    1 m

    DaP = OK to Ship

    PSO = Process Sign-Off (w/ PDR)

    IRE = Initial Risk Evaluation

    PS = Pre Series

    CSE = Chrysler Source Evaluation

    TFU = Tooling Follow Up

    VP = Process Verification

    AQP TC = AQP Timing Chart Review

    SRE = Supplier Readiness Eval.

    FPSC = First Prod. Shipment Cert.

    Main Deliverables

    Main Milestones

    SQ Tools

    Supplier Tooling Sign Off

    5 - 6 months

    VP PS

    2 m

    SRE

    DaP Commercial

    Launch

    2 m

    Job1

    PSO

    TFU

    - Start -

    >

    Final CAD Mathematics (Step 5) Article Card Final Drawings Availability Codep

    .

    Samples - Selfqualification

    /PPAP (SQ)

    - Integrative tests

    (E&D)

    - Plant Approval

    (Plant)

    Qualification

    Informative System VDDP

    AQP TC FPSC

    Pre-PSO

  • Fiat Sourcing Process

    The Chrysler SQE

    is required to

    support the Fiat

    Sourcing Process

    in the same

    manner as Fiat

    SQEs

    102

    Opening of the Sourcing Agenda

    Extraction to the Roll Out

    PACKAGES creation

    Input Check

    Key Stakeholders Meeting

    PRE-RFQ

    Input Check

    RFQ dispatch

    Quotation analysis

    Technical review

    Target setting

    Negotiation

    Recommendation

    Process steps

    requiring SQE

    involvement

  • 103

    Used when the Input check finds a gap in the data needed to proceed in the sourcing process

    The KSM is a meeting among all those with key responsibilities in the development of major items,

    time and strategy management

    Its goal is to ensure that all the quotations received after the RFQ are comparable and

    compliant to the requirements

    Key Stakeholders Meeting (KSM)

  • 104

    PRE RFQ - Supplier Preliminary Data

    Profile

    The SPDP is a survey where we ask a potential supplier to provide all the general information

    regarding its organizational size and structure

    Applies to new suppliers, not yet present in our data base

    Equivalent to the Supplier Pre-Evaluation form in the Source Evaluation process

  • 105

    PRE RFQ - Quality Bid List

    All the suppliers involved in the sourcing process shall be included in the Quality Bid List. If they

    are not, the SQE must complete a Business Case

    The suitable suppliers will receive the RFQ from the buyer

    An approved Business Case is requested for every new supplier, containing data about its

    Quality System, benchmarks for similar parts and

    the PSA (Chrysler personnel will use the CSE)

  • Chrysler Source Evaluation

    106

    SCORING

    Potential Supplier Assessment

    Source Evaluation Tool

    60-80% >80% 90% 80% 90%

  • 107

    PRE RFQ - Quality Bid List

    80 + = green (ok to bid)

    60-79 = yellow (need SQ Sr. Manager or Commodity Managers (Chrysler) approval to bid)

    Below 60 = red (need SQ Directors approval to bid)

  • 108

    PRE RFQ - Quality Statement of

    Requirements

    Goals of the QSR:

    Inform the supplier about Fiat quality requirements, including those special requirements linked to the part

    construction technology and/or the specific supplier

    Obtain from the supplier all the information related to its Quality system, its standards, its future behaviors

    Have the supplier commitment to project feasibility, as required on the Product Card (Scheda Prodotto).

    The supplier shall fulfill and submit the form together with the quotation, being ready for clarifications during

    the Technical Review

  • 109

    Technical Review

    Attendees

    Purchasing: Lead Buyer, SQE, TAG,

    E&D,

    Logistics: SCD

    Technologies: (mandatory only in case of Stampings)

    Quality Risk Assessment for all potential suppliers strong and weak points, improvement recommendations to be agreed upon before

    sourcing

  • 110

    Technical Review procedure regarding the

    SQE

    The SQE receives the Quality SOR from the supplier and prepares related questions prior to the meeting, then verifies the agreement

    Any partial agreement from the supplier to our Quality SOR must be discussed and could result in the suppliers exclusion from the subsequent stages

    Neither the buyer nor the SQE may accept any technical deviation from the requirements (e.g. Reliability targets, metrics like ICP and TOC, Customer profile) without the approval of the model Vehicle line Team/Platform

    When the RASI chart is required, the SQE takes care that the document is properly shared.

    Any deviation in the Technical documentation, with all the underlying risks, must be accepted under the approval of the MR only, with the updated documentation itself

  • Quality Risk Assessment

    111

    QUALITY RISK ASSESSMENT

    Supplier Name: Supplier Code:

    Part Number: Part Description:

    Project:

    Supplier Quality Engineer: Commodity (C;E;M;P):

    Buyer: Co-design? (Y/N):

    Design Engineer:

    ASSESSMENT CATEGORY

    ISSUE (OBLIGATORY FOR CONDITIONAL

    RATING) RATING

    ASSESSMENT

    #

    1. New Process, Technology and/or Capacity

    A = Approved; C = Conditional;

    NS = Not Sourceable.

    2. Supplying Location

    A = Approved; C = Conditional;

    NS = Not Sourceable

    3. Facilities/Equipment

    A = Approved; C = Conditional;

    NS = Not Sourceable

    4. New Design Responsibility

    A = Approved; C = Conditional;

    NS = Not Sourceable

    5. Quality History

    A = Approved; C = Conditional;

    NS = Not Sourceable

    6.

    Key Characteristics Mgt. (Important, Critical, Safety/Report & Legal)

    A = Approved; C = Conditional;

    NS = Not Sourceable.

    7. Quality Targets (PPM, IPTV, Quality Tracking ICP/TOC)

    A = Approved; C = Conditional;

    NS = Not Sourceable

    8. Timing Concerns

    A = Approved; C = Conditional;

    NS = Not Sourceable

    9. Program Management

    A = Approved; C = Conditional;

    NS = Not Sourceable

    10. Other (SQE)

    A = Approved; C = Conditional;

    NS = Not Sourceable

    11. Other (TAG)

    A = Approved; C = Conditional;

    NS = Not Sourceable

    ASSESSMENT PARTICIPANTS:

    DATE: SQE (Surname & Signature) TAG (Surname & Signature)

    DATE: Buyer (Surname & Signature) Design Engineer (Surname & Signature)

    Supplier Project Responsible Name & Signature (Obligatory for Conditional Rating) NOTE: If one of more Assessment Categories are rated Not Sourceable, the whole Risk Assessment is

    considered NOT SOURCEABLE.

    New process, technology, tools, capacity: not present; new tools capacity increase/new tooling new process to the plant extremely fast production acceleration new technology to company new technology to the industry

    Supplying location current supplier current supplier-new location new supplier to the division out of region supplier with more than 2 years new to region new to industry out of region supplier first year imported

    Facilities/Equipment

    existing facility new addition/rearrangement to existing building new building new plant

    New Design Responsibilities

    carryover design customer is design responsible source is design & production responsible contract house is design responsible

    Quality History few past problems; good response minor problems; poor responses company requires multiple Qualificazioni submissions high PPM or Bills with weight 90 no data-new source high Warranty or bid list Field Major Disruptions Top Q supplier

    Key Characteristics Mgt. (Important, Critical, Safety/Report & Legal)

    used to manage key characteristics good for important characteristics, not used to S/R characteristics not used to manage key characteristics

    Quality Targets (PPM, R/100, Quality Tracking ICP/TOC)

    It means how are the Supplier performances with respect to the targets

    Timing Concerns

    no timing concerns late release/source to plan PPAP/Qualificazioni late but before Material Required Date Full approval after start of saleable vehicles

    Program management

    past successful launches Advanced IP new source; unknown APQP program mgt ability launch problems/Launch Major Disruptions or Launch IP limited program management team capacity issues with past programs

  • Initial Risk Evaluation (IRE)

    The IRE shall be completed within 1 month of the sourcing Recommendation Report the equivalent Monitoring Level to Fiat at this time, using the

    following chart:

    Document the part risk level from the IRE on the AQP Timing Chart; the IRE will NOT be added in CQMS

    112

    SUPPLIER:

    SUPPLIER CODE:

    PART NUMBER(S):

    PART NAME(S):

    PART RISK (H/M/L):

    #NUM!FIAT PROGRAM

    REVIEW STATUS#NUM!

    CHRYSLER AQP

    STATUS

    ADVANCE QUALITY PLANNING (AQP)

    TIMING CHART

    IRE Result Monitoring Level

    High Total

    Medium

    LowPartial

  • Advance Quality Planning (AQP)

    The AQP Kick-Off Meeting shall be held within 1 month of the sourcing Recommendation. Complete the first revision of the AQP Timing Chart, including a status

    for each applicable task.

    Report the Fiat Program Review Status to Fiat for entry into the VDDP system

    113

    #NUM!FIAT PROGRAM

    REVIEW STATUS#NUM!

    CHRYSLER AQP

    STATUS

    ADVANCE QUALITY PLANNING (AQP)

    TIMING CHART

  • Advance Quality Planning (AQP)

    General Notes:

    Update the AQP Timing Chart after each AQP Meeting is held.

    The Fiat Program Review Status will need to be reported to Fiat once more following the Supplier Tooling Sign-Off milestone, approximately 6

    months before VP

    The First Production Shipment Certification (FPSC) process is followed as normal, beginning at VP

    The Chrysler SQE shall support the Fiat Assembly Plant for the Benestare process

    The Part Inspection Standard process is not applicable and not required for Fiat parts. Completion of a Part I/S is at the discretion of

    the Chrysler SQE (Fiat Assembly Plants do not currently follow the

    Part I/S process).

    114

  • Using the AQP Timing Chart form

    115 115

    RISK MITIGTION PLAN

    If status is 1, 2, or 3 (Red

    or Yellow), you must

    provide a Risk Mitigation

    PlanEnter 1-5

    STATUS

    Commercial

    Score Chrysler Definition FIAT Definition

    1Incomplete/non-existant; no recovery plan in place and

    High Risk to launch Job Stopper

    2Incomplete w/ inadequate recovery plan in place or

    High Risk to launch Job Stopper risk

    3Incomplete w/ recovery plan in place or minor issues

    and Low risk to launch 2nd Level Issue

    4Incomplete but progressing according to plan w/ no or

    very minor issues Planned Activity according to Project

    5 Complete and approved Implemented Activity

  • 116

    #NUM!FIAT PROGRAM

    REVIEW STATUS#NUM!

    CHRYSLER AQP

    STATUS

    ADVANCE QUALITY PLANNING (AQP)

    TIMING CHART

    Includes only the 29 tasks shown below

    Tasks used in calculating the FIAT Program Review status:

    Review CNs and IAAs (including associated Risk)

    TAG Review (Chrysler-purchased tooling only)

    Confirm composition and commitment of Core

    AQP Team Members

    Design Model Status review

    eCIMS / Lessons Learned Reviewed

    Status of Open Issues from Technical Review Risk

    Assessment (FIAT parts only)

    Part Number, Description, and Change Level

    Production Tooling Complete (PTC)

    Advance Quality Planning

    Design FMEA

    Design Review - Customer Perception targets

    Verify deliverables timing to CPCP timing

    Volume, ramp-up curve, and product mix verified

    and capable - CPV, P.O, SP

    Prior PSO Review (similar products)

    Error and Mistake Proofing

    Production Validation Testing Complete

    Control Plan and Process Monitoring

    Operating Instructions

    Special Characteristics Identified and FPSC

    Gage and Test Equipment Evaluation

    Incoming & Outgoing Material Certification Plan

    Test Sample Sizes and Frequencies

    Parts Packaging and Shipment Specifications

    Process Flow Diagram & Mfg. Floor Plan

    Production Demonstration Run

    Process FMEA

    Part Delivery Plan Review (for VP, PVP, V1, etc.)

    Part Qualification Process (PQP)

    Confirm Supplier PPAP Self-Certification status

    Use this task to track Fiat Benestare and matchability

    Non-Chrysler Suppliers will not have this; for Fiat parts, verify the Suppliers testing

    facilities have been appropriately certified.

    Use this task to track Fiat Self-Qualification and Integrative

    testing

    Using the AQP Timing Chart form

  • 117

    It is strongly recommended that Chrysler personnel tracking Fiat parts

    monitor and track the status of all tasks, not just the tasks used in

    calculating the Program Review result. A small number of tasks remain

    N/A, however.

    Tasks on the AQP Timing Chart that are Not Applicable when managing Fiat Parts:

    Part Development Plan Complete

    Supplier Quality Risk Assessment (SQRA)

    Layered Process Audit

    Part Inspection Standard

    Please be aware: the Chrysler AQP Status and the Fiat

    Program Review status may be different!

    Only N/A for Fiat parts from Non-Chrysler

    Suppliers!

    Using the AQP Timing Chart form