Technical Data Sheet issue 02/Oct.11 Cicobond ® EP Slow Set Epoxy Bonding Agent Powerful Protection Description Cicobond ® EP is two component solvent free epoxy bonding agent. Cicobond ® EP has long setting time that allows different repair activities to take place during bonding coating setting time, like anchoring, steel reinforcement and shuttering works. Cicobond ® EP also obtains high bonding strength to concrete, which makes it essential part of any successful structural repair. Uses As a bonding agent for structural repair specially R.C elements upgrading. For bonding old and new concrete. Advantages Provides excellent bonding to concrete. Could be coated over dry and damp surfaces. Provides excellent water resistance. Ideal for hot and tropical climates. Safe when used in closed spaces, as it is solvent free. Provides superior freeze/thaw resistance. Obtains high mechanical characteristics. Packaging 5 and 20 kg set Shelf life & Storage 12 months storage life if stored in its original unopened containers under shaded place in a temperature from 5 o C to 40 o C. Properties Appearance Light green thick liquid Solid content, % 100 Open time hrs@ 25 o C 9±15 min Initial hardness 36 hours Full cure 7 days Compressive strength (BS 6319 Part 2) 52±2 N/mm 2 Tensile strength (BS 6319 Part 7) 19±1 N/mm 2 Flexural Strength (BS 6319 Part 3) 34±1 N/mm 2 Slant Shear strength (BS 6319 Part 4) 26±1 N/mm 2 Coverage, m 2 /kg 4 Application Instructions Surface preparation Concrete substrates All Concrete Substrates should be sound, clean, and free from oil and grease. Any loose or weak concrete should be removed using hand tools or light mechanical tools (heavy tools are not recommended). It’s recommended to wash the concrete contact surfaces with plenty of water 24 hours before applying Cicobond ® EP. For upgrading concrete structural elements, it’s recommended to roughen the surface to add more mechanical bonding key. Steel substrates All steel surfaces should be blasted or abraded carefully using sandblasting, any mechanical abrasives, or hard steel brush to remove rust. Mixing Stir the base only separately. The entire contents of the smaller can (hardener) could be poured into the base container and the materials should be mixed for at least one minute by mechanical mixer using a slow or medium speed mixing drill. Insufficient mixing may lead to color variation. Application Apply the mixed Cicobond ® EP on the prepared substrate using soft hair brush, making sure that the Cicobond ® EP is tacky when the new concrete, screed or repair mortar is placed. If the overlay time is finished, another coat of Cicobond ® EP must be coated. Cicobond ® EP is applicable to be coated on both dry and damp surfaces. In hot climate, it’s important to check the open time first before applying Cicobond ® EP, because the high temperature of the substrate will reduce the open time of the material obviously. We recommend spraying the concrete surface by water just before coating to help reducing the substrate temperature.

Cicobond EP

  • Upload
    mud444

  • View
    43

  • Download
    5

Embed Size (px)

DESCRIPTION

CIC prouduct

Citation preview

  • CicofloorFS-50 Technical Data Sheet Solvent Free Epoxy Floor Coating issue 02/Oct.11

    CicobondEP

    Slow Set Epoxy Bonding Agent

    Powerful Protection

    Description

    CicobondEP is two component solvent free

    epoxy bonding agent.

    CicobondEP has long setting time that allows

    different repair activities to take place during

    bonding coating setting time, like anchoring, steel

    reinforcement and shuttering works.

    CicobondEP also obtains high bonding strength

    to concrete, which makes it essential part of any

    successful structural repair.

    Uses

    As a bonding agent for structural repair

    specially R.C elements upgrading.

    For bonding old and new concrete.

    Advantages

    Provides excellent bonding to concrete.

    Could be coated over dry and damp surfaces.

    Provides excellent water resistance.

    Ideal for hot and tropical climates.

    Safe when used in closed spaces, as it is

    solvent free.

    Provides superior freeze/thaw resistance.

    Obtains high mechanical characteristics.

    Packaging

    5 and 20 kg set

    Shelf life & Storage

    12 months storage life if stored in its original

    unopened containers under shaded place in a

    temperature from 5oC to 40oC.

    Properties Appearance Light green thick liquid

    Solid content, % 100

    Open time hrs@ 25oC 915 min

    Initial hardness 36 hours

    Full cure 7 days

    Compressive strength (BS 6319 Part 2) 522 N/mm2

    Tensile strength (BS 6319 Part 7) 191 N/mm2

    Flexural Strength (BS 6319 Part 3) 341 N/mm2

    Slant Shear strength (BS 6319 Part 4) 261 N/mm2

    Coverage, m2

    /kg 4

    Application Instructions

    Surface preparation

    Concrete substrates

    All Concrete Substrates should be sound, clean,

    and free from oil and grease. Any loose or weak

    concrete should be removed using hand tools or

    light mechanical tools (heavy tools are not

    recommended). Its recommended to wash the

    concrete contact surfaces with plenty of water 24

    hours before applying CicobondEP.

    For upgrading concrete structural elements, its

    recommended to roughen the surface to add more

    mechanical bonding key.

    Steel substrates

    All steel surfaces should be blasted or abraded

    carefully using sandblasting, any mechanical

    abrasives, or hard steel brush to remove rust.

    Mixing

    Stir the base only separately. The entire contents

    of the smaller can (hardener) could be poured into

    the base container and the materials should be

    mixed for at least one minute by mechanical mixer

    using a slow or medium speed mixing drill.

    Insufficient mixing may lead to color variation.

    Application Apply the mixed Cicobond

    EP on the prepared

    substrate using soft hair brush, making sure that

    the CicobondEP is tacky when the new concrete,

    screed or repair mortar is placed. If the overlay

    time is finished, another coat of CicobondEP

    must be coated.

    CicobondEP is applicable to be coated on both

    dry and damp surfaces.

    In hot climate, its important to check the open time

    first before applying CicobondEP, because the

    high temperature of the substrate will reduce the

    open time of the material obviously. We

    recommend spraying the concrete surface by

    water just before coating to help reducing the

    substrate temperature.

  • CicofloorFS-50

    Warranty CIC products are guaranteed against defective materials and manufacture and sold subject to CIC's standard terms and conditions of sale. Whilst CIC endeavors to ensure that any advice, information or recommendation given is correct, the company can not accept any liability either directly or indirectly arising from the use of its products, since the company has no control over the application of its products. Information contained in this document is given on the best current knowledge. CIC's policy is one of continuous improvement and the company reserves the right to change the company products without prior notice.

    Head Office: Jeddah Towers Building, Sharafiyah P.O Box 7232, Jeddah 21462

    Tel. 653-2152 Fax 651-9230

    Riyadh 01-493 9213 Fax: 01-492 1743 Makkah 02-548 2280 Fax: 02-545 5431 Dammam 03-865 1349 Fax: 03-865 6410 Madina 04-839 0424 Fax: 04-834 2091

    www.cictg.com

    Aal Taher Group

    CicobondEP

    Cleaning

    Clean all tools and application equipment with

    Cicosolvent immediately after use.

    Hardened and/or cured material can only be

    removed mechanically, or by hand tools.

    Precautions

    Health and Safety

    All safety stuff should be worn during application

    like safety goggles and rubber gloves, to avoid any

    harmful accidents.

    If CicobondEP is splashed accidentally to the

    skin, it must be washed off with water and soap at

    once.

    If it was splashed to the eyes or nose, they must

    be rinsed with plenty amount of clean warm water

    and seek medical attention immediately.

    Technical Support

    CIC provides on-site assistance, as well as

    consulting services on projects when requested.

    Technical data sheets on other CIC products and

    guidance on their use are available on request

    For more details, please review our

    Technical Guide for Cementitious Repair