CITY OF FORT COLLINS NEW FACILITIES. KEN MANNON, Operations Services Director. CITY PARK POOL REPLACEMENT $ 1.75M - SCD: MAY 2003. COLLINDALE CLUBHOUSE -14,660 SF $2.6 M – SCD: DEC 2002. CSU TRANSIT CENTER – 11 DROP/ PICKUP SITES $2.37M – PHASE I COMPLETED SEPT 2002. - PowerPoint PPT Presentation
Citation preview
CITY OF FORT COLLINS CITY OF FORT COLLINS
NEW FACILITIESNEW FACILITIES
KEN MANNON,KEN MANNON,
Operations Services Director Operations Services Director
CITY PARK POOL REPLACEMENT$ 1.75M - SCD: MAY 2003
COLLINDALE CLUBHOUSE -14,660 SF $2.6 M – SCD: DEC 2002
CSU TRANSIT CENTER – 11 DROP/ PICKUP SITES
$2.37M – PHASE I COMPLETED SEPT 2002
CSU TRANSIT CENTER SITE LAYOUT
EPIC / TWICE THE ICE - 36,400 SF$ 3.93M – SCD: MARCH 2003
FIRE STATION # 14 - 10,800 SF$ 2.4M - SCD: APRIL 2003
FOSSIL CREEK MAINT. BUILDING – 6,550 SF
$ 700K – SCD: MARCH 2003
GARDENS ON SPRING CREEK - 4,000 SF + 10 ACRES GARDENS -$ 2.05M - SCD: SEPT 2003
GARDENS ON SPRING CREEK –
LONG RANGE MASTER PLAN
NEW METER SHOP SITE - 8,500 SF$ 2.03M - SCD: DEC 2003
NEW N S A C - 52,000 SF CONCEPTUAL PHASE: $100,000
YR 2004 FUNDING: $8 M
NIX SITE MAINTENANCE FACILITY - 6,000 SF$ 2.05M - 27.48 AC COMPLETED: JUNE 2002
NIX SITE – FARM HOUSE – 6,500 SF$ 2.4M - SCD: OCT. 2002
SOUTHRIDGE GOLF CART STG – 3,250 SF
$ 200,000 - SCD: EARLY 2003
TRAFFIC OPS BUILDING - 9,300 SF$ 2.17M - SCD: NOV. 2002
UTIL’S WH YD IMPRVMNT SITE – EAST SIDE $ 3.25M - SCD: SUMMER 2003