180
CITY OF ORILLIA WASTEWATER SYSTEM MASTER PLAN UPDATE JANUARY 2013

CITY OF ORILLIA WASTEWATER SYSTEM MASTER PLAN UPDATE · wastewater system and evaluated alternative methods for rectifying those problems. In the 2012 Master Plan Update, population

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

CITY OF ORILLIA

WASTEWATER SYSTEM MASTER PLAN UPDATE

JANUARY 2013

ii

EXPLANATORY NOTE

The City of Orillia 2012 Wastewater System Master Plan Update (2012 Master Plan Update) provides an

update of the City of Orillia 2004 Wastewater System Master Plan (Original Document). The 2012

Master Plan Update is a stand-alone document, however, it is not a replacement for the Original

Document.

Under the same headings, the 2012 Master Plan Update summarizes the discussion in the Original

Document. It also provides an update of the works carried out since the period covered by the Original

Document. As well, it includes revised projections, additional public consultation, and additional works

not included in the Original Document.

For a comprehensive review of the process followed in the development of the Master Plan, refer to the

Original Document. The 2012 Master Plan Update provides complete details of the process followed to

complete the revisions.

iii

EXECUTIVE SUMMARY

The 2012 Master Plan Update re-establishes the framework set out in the Original Document and

specifically identifies the wastewater system requirements to service City re-urbanization and

development of approximately 550 hectares of land in West Orillia. This framework was originally

established through a process that identified the constraints and problems associated with the existing

wastewater system and evaluated alternative methods for rectifying those problems. In the 2012 Master

Plan Update, population and wastewater flow projections have been revised and updated to reflect recent

development, and the capabilities of the existing system have been updated to include recent upgrades to

January 2012. A revised Schedule of Works listing the annual major works that are recommended over

the next 20 years has also been developed, including timelines and costs.

The recommended wastewater system expansion works include:

Expansion of the existing Wastewater Treatment Centre Capacity

The works do not include smaller, collector sewers to service individual residences, businesses and

industries – planning for these smaller systems will be the responsibility of the developers.

The recommended works also include:

Improvements to existing Sewage Pumping Stations; and

Other programs to improve monitoring, system efficiency and reliability.

These efficiency procedures could potentially reduce the scope of future works, in particular ultimate

treatment and sewage pumping station capacity.

Planning for the Original Document followed the Municipal Engineers Association Class Environmental

Assessment process and thereby satisfied the first two phases, including Phase 1 and 2 requirements with

respect to public and agency notification and involvement. This means that all works identified in the

Original Document, with the exception of major expansions of the existing Wastewater Treatment Centre,

could proceed to implementation without further public or agency notification.

Public and agency consultation for the revised works outlined in the 2012 Master Plan Update consisted

of an advertisement announcing Public Comment Invited, and a Notice of Completion of the process with

a brief summary of the revisions to the originally proposed works. This is in accordance with the

requirements of Ontario Environmental Assessment Act as outlined in the Municipal Engineers

Association Class Environmental Assessment, October 2000, as amended 2007.

The Master Plan and subsequent updates should be reviewed and updated again every five years to ensure

that the documentation continues to accurately reflect planned works and thereby avoid having to begin

the entire process again.

The updated Schedule of Works is presented overleaf. This Schedule of Works has been developed on the

assumption of wastewater flow projections within MOE-recommended per capita flows.

Cla

ss E

A

Sched

ule

20

122

013

20

142

015

20

162

017

20

182

019

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28

20

29

20

30

20

31

20

32

20

33

To

ta

l

11.1

.1A

$2

65

$2

65

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$17

,03

0

11.1

.2A

$50

$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$2

,050

11.1

.3A

$18

$15

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$4

,03

3

11.1

.4A

$3

75

$3

30

$4

00

$4

00

$4

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$7,0

05

11.1

.5A

$15

0$15

0

11.1

.6A

$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$4

00

11.1

.7B

$50

0$50

0$1,

00

0

11.1

.8B

$1,

00

0$1,

00

0$2

,00

0

11.1

.9A

+$6

00

$4

00

$1,

00

0$1,

00

0$3

,00

0

11.1

.10

A+

$50

0$50

0$50

0$1,

50

0

11.1

.11

A+

$3

50

$3

50

11.1

.12

$3

0$3

0$3

0$3

0$12

0

11.1

.13

C$1,

00

0$5,0

00

$5,0

00

$4

,00

0$15

,00

0

11.1

.14

C$0

$1,

70

8$5,6

10$7,2

95

$6

,44

5$2

,04

5$2

,475

$2

,44

5$1,

79

5$2

,44

5$2

,44

5$1,

475

$1,

94

5$1,

94

5$1,

94

5$1,

44

5$1,

475

$1,

44

5$1,

44

5$1,

44

5$1,

44

5$1,

475

$1,

44

5$53

,63

8

Inch S

ew

age P

um

pin

g S

tation a

nd

Forc

em

ain

Vic

toria P

oin

t A

rea S

erv

icin

g

CN

R T

runk S

ew

er

Upgra

des /

Rero

uting

Changes to J

ohn S

treet S

ew

age

Pum

pin

g S

tation D

rain

age A

rea

TO

TA

L O

F W

OR

K A

NN

UA

LL

Y

Waste

wate

r S

yste

m M

aste

r Pla

n

Updating

Realig

nm

ent of

Old

Huro

nia

Road

Sew

er

alo

ng L

aclie

Str

eet

TA

BL

E 1

1-1

Waste

wate

r C

olle

ction S

yste

m

Rehabilita

tion

Inflow

and Infiltra

tion P

rogra

m

WW

TC

Im

pro

vem

ents

and

Optim

ization

TW

EN

TY

YEA

R F

OR

EC

AS

T (

in T

HO

US

AN

DS

of

$)

Pro

ject

Sta

ndby P

ow

er

for

Sew

age

Pum

pin

g S

tations

WW

TC

Tert

iary

Tre

atm

ent U

pgra

de

Sew

age P

um

pin

g S

tation

Impro

vem

ents

WW

TC

Expansio

n a

nd

Environm

enta

l A

ssessm

ent (N

ot

required u

ntil beyond 2

042)

Wa

ste

wa

ter

Sys

tem

Ma

ste

r P

lan

Sc

he

du

le o

f W

ork

s

Public

Education P

rogra

m

v

CONTENTS

EXPLANATORY NOTE...……………………………………………………………………………….ii

EXECUTIVE SUMMARY………………………………………………………………………………iii

PHASE 1 – PROBLEM IDENTIFICATION

1.0 BACKGROUND INFORMATION……………………………………………………………..2

1.1 Location of the Undertaking……………………………….…………..………………….2

1.2 Existing Wastewater System…………………….………..………….……………………2

1.3 Purpose of the Master Plan…………………………………..………………..……………2

1.4 Relevant Reports and Studies…………….………………………………….…………….3

2.0 SUMMARY OF MASTER PLANNING PROCESS…………………………………………...4

3.0 EXISTING CONDITIONS…..…………………………………………………………………..5

3.1 Physical Environment……………………..…………………………...………………….5

3.2 Socio-Economic Environment…………………………...…………..……………………5

3.3 Receiving Water…………………………………..…………………………...……………6

3.4 Existing Wastewater System…………….…………………………………..…………….7

3.4.1 General……………………………………………………………...…………….7

3.4.2 Sanitary Sewers……………………………………………………..…………….7

3.4.3 Sewage Pumping Stations…………………………………………..…………….8

3.4.4 Wastewater Treatment Centre…………………………………………………...20

4.0 FUTURE CONDITIONS……………………………………………………………………….24

4.1 Population Growth……………………………………………………………………….24

4.2 Industrial/Commercial/Institutional (ICI) Growth………………………………………27

4.3 Wastewater Flow Projections………………………………………………..……………27

4.4 Predicted WWTC Effluent Requirements………………………………….…………….32

4.5 Predicted Future Biosolids Management Requirements …………………………….…..32

5.0 PROBLEM IDENTIFICATION……………………………………………………………….34

5.1 General…………………………………………………………………………………...34

5.2 Infiltration and Inflow……………………………………………………………………36

5.3 Condition and Age of Existing Sewers…………………………………………………..37

5.4 Capacities of Existing Trunk Sewers………………………………………………….....38

5.5 Capacities of Existing Sewage Pumping Stations…………………………….…………38

5.6 Capacity of Existing Wastewater Treatment Centre…………………………..…………38

5.7 Quantity and Quality of Septage Received at the WWTC………………………………39

5.8 Biosolids Management…………………………………………………………………..40

5.9 Operational Issues with the Unit Processes and Operations at the WWTC……………..40

5.10 Treated Effluent Discharge Quality Standards…………………………..……………….41

vi

PHASE 2 – ALTERNATIVE SOLUTIONS

6.0 ALTERNATIVE SOLUTIONS………………………………………………………………...43

6.1 General Alternative Solutions……………………………………………………………43

6.2 Alternative Solutions for Wastewater Collection………………………………………..43

6.3 Alternative Solutions for Wastewater Treatment………………………………………..43

6.4 Alternative Solutions for Biosolids Management……….……………………….………45

6.5 Alternative Solutions for Effluent Disposal………………...……………………………45

7.0 ASSESSMENT OF THE ALTERNATIVES…………………………………………………..47

7.1 Assessment of General Alternatives…………………………………………………..…47

7.2 Assessment of Collection System Alternatives………………………………………….47

7.3 Assessment of Treatment System Alternatives…………………………………………..47

7.4 Assessment of Biosolids Management Alternatives…….……………………….………48

7.5 Assessment of Effluent Disposal Alternatives……………...……………………………48

8.0 SELECTION OF PREFERRED ALTERNATIVES………………………………………….49

9.0 PUBLIC AND REVIEW AGENCY COMMENTS…………………………………………...52

10.0 GENERAL SUMMARY AND REQUIREMENTS………………………...……………..…..53

10.1 Proposed Service Area…………….…………………………………………………..…53

10.2 Proposed Wastewater Collection System………….…………………………………….53

10.3 Proposed Wastewater Treatment System………….……………………………………..53

10.4 Property Requirements…………………………………..……………………….………53

10.5 Environmental Impacts……………………………………..……………………………53

10.6 Environmental Assessment Categories of Proposed Projects……………………………54

11.0 RECOMMENDATIONS……………………………………………………………………..…55

11.1 General…………………….…….…………………………………………………..…55

11.1.1 Wastewater Collection System Rehabilitation…………….……….………….55

11.1.2 Inflow and Infiltration Program………………………………..…..…….…….55

11.1.3 WWTC Improvements and Optimization………………………..……...…….55

11.1.4 Sewage Pumping Station Improvements……………………….……………..56

11.1.5 Standby Power for Sewage Pumping Stations………………….……………..56

11.1.6 Public Awareness Program on Sewage Discharge….….……………………..56

11.1.7 Inch Sewage Pumping Station and Forcemain………………………………..56

11.1.8 Victoria Point Area Servicing….…………….………………………………..57

11.1.9 CNR Trunk Sewer Upgrades and Rerouting….……………………..………..57

11.1.10 Changes to John Street Sewage Pumping Station Drainage Area….…..……..57

11.1.11 Realignment of Old Huronia Road Sewer Along Laclie Street…………...…..57

11.1.12 Wastewater System Master Plan Updating…………………….……………..57

11.1.13 WWTC Tertiary Treatment Upgrade….……..………………………………..58

11.1.14 WWTC Expansion and Environmental Assessment….……..………………..58

11.2 Proposed Schedule of Works and Costs………….…………………….……………....58

REFERENCES…………………………………………………………………………………………...61

vii

Figures

1-1 - Key Plan………………………………………………………………………Follows Pg 2

1-2 - Major Development Areas……………………………………………………Follows Pg 2

3-1 - Overall Service Area……………………………………………………….…Follows Pg 5

4-1 - Population Growth 2012-2042………………………………………………...…………24

5-1 - Metered vs Pumped vs Treated vs Population 1992-2011……………………………….34

5-2 - Sanitary Drainage Areas…………...………………………..……………….…Follows Pg 36

5-3 - Sewer Replacement over 20 Years…………………………………….……Follows Pg 38

5-4 - Projected Wastewater Flows 2012-2042……………………...……………..…………….39

10-1 - Proposed Future Wastewater System Expansion……………………………Follows Pg 53

11-1 - Schedule of Works – Twenty Year Forecast………………………………….…………59

Tables

3-1 - Phosphorus Loading and Concentration in WWTC Effluent Over the Last 5 Years..........6

4-1 - Projected Annual Population Growth……………………………………………………26

4-2 - Projected Annual Industrial Growth…………………………….………...……………..…28

4-3 - Projected Annual Commercial Growth………………………………………………..…29

4-4 - Projected Annual Institutional Growth……………………….………...………………..…30

4-5 - Projected Annual Average Wastewater Flows………………….……...………………..…31

5-2 - Sewer Replacement Over Next 20 Years………...……………………......................……37

11-1 - Schedule of Works……………………………………………………………………….60

APPENDICES

A - Terms of Reference for Wastewater System Master Plan 2012 Update

B - Sewage Pumping Station Information

C - Inventory of Development Update – Industrial, Commercial & Institutional

D - City of Orillia, Report to Council April 9,2003

Water and Sewage Design Flows

E - HYDRA Sanitary Sewage Collection System Computer Model Analysis

F - MOE Policy on Septic Systems

G - Public Consultation Documentation for 2012 Master Plan Update

viii

LIST OF ABBREVIATIONS

ADF Average Daily Flow

AOC Area of Concern

BOD5 5-day biochemical oxygen demand

CCTV Closed Circuit Television

CNR Canadian National Railway

DAF Dissolved Air Flotation

EA Environmental Assessment

ECA Environmental Compliance Approval

ESR Environmental Study Report

ha hectares

ICI Industrial / Commercial / Institutional

IJC International Joint Commission

MCC Motor Control Centre

MEA Municipal Engineers Association

MH Maintenance Hole

MISA Municipal and Industrial Strategy for Abatement

MOE Ministry of the Environment

NMS Nutrient Management Strategy

OCI Overall Condition Index

OMAFRA Ontario Ministry of Agriculture, Food and Rural Affairs

PLC Programmable Logic Controller

PWQO Provincial Water Quality Objective

RAP Remedial Action Plan

RF Radio Frequency

ix

SCADA Supervisory Control and Data Acquisition

SPS Sewage Pumping Station

SS Suspended Solids

TAN Total Ammonia Nitrogen

TDH Total Dynamic Head

TP Total Phosphorus

TSS Total Suspended Solids

UV Ultraviolet

WAS Waste Activated Sludge

WFP Water Filtration Plant

WWTC Wastewater Treatment Centre

PHASE 1: PROBLEM IDENTIFICATION

Page 2

1.0 BACKGROUND INFORMATION

1.1 LOCATION OF THE UNDERTAKING

The City of Orillia is located approximately 35 km northeast of Barrie via Highway No. 11, on

the shores of Lake Simcoe and Lake Couchiching, as shown on Figure 1-1.

In general terms, the service area included in the Original Document is defined by the existing

municipal boundary, including West Orillia (See Section 3.1). However, in the process of

developing the Original Document, adequate consideration was also given to the possibility of

servicing adjacent municipalities.

1.2 EXISTING WASTEWATER SYSTEM

The existing wastewater system in the City of Orillia consists of 163 km of sanitary sewer, 20

sanitary sewage pumping stations, 10.3 km of sanitary forcemain, 2187 maintenance holes, a

septage receiving facility, and a 27,300 m3/d capacity (average day) Wastewater Treatment

Centre (WWTC).

All components of the wastewater system are owned, operated and maintained by the City of

Orillia.

1.3 PURPOSE OF THE MASTER PLAN

The purpose of the Original Document was to establish a framework to specifically identify the

wastewater infrastructure requirements to service: City re-urbanization, the Victoria Point area,

development of approximately 550 hectares of land in West Orillia, the Inch Development Area

and some land area in Severn Township (See Figure 1-2). In order to achieve this objective, it

was necessary to: clearly identify the constraints and problems associated with the existing

wastewater system, evaluate alternative methods of rectifying these problems, and recommend,

cost, phase and schedule major works for future budgeting and implementation.

The purpose of the 2012 Master Plan Update is to summarize the progress made since the

Original Document was prepared and to revise the projections and recommended works to reflect

current information and new legislation and regulations.

Planning for the Original Document followed the Municipal Engineers Association (MEA) Class

Environmental Assessment (EA) process, satisfying the first two phases of the requirements of

the Ontario Environmental Assessment Act as outlined in the MEA Municipal Class

Environmental Assessment, June 2000 to plan, design and implement the future components of

the Scheduled Works. The Municipal Class EA process provides for the planning and

implementation of projects which, while subject to the Environmental Assessment Act, do not

warrant an individual EA.

Planning for the 2012 Master Plan Update followed the same process. The Municipal Class

Environmental Assessment was amended in 2007, with none of the updates changing the

planning requirements that were undertaken for the Original Document.

H:\E - Environmental Services\E01 - Sanitary Sewers\E01 MAS\WWMP 2012\Drawings\12WWMP1-1.dwg

Jan 30, 2013 - 11:46am

TITLE:

PUBLIC WORKS DEPARTMENT

CITY of ORILLIA

THE CORPORATION OF THE

JAN. 22, 2013

JAN. 22, 2013

JC

WH

12WWMP1-1.DWG

Not to Scale

PLOTTED:

DATE:

APPROVED BY:

CHECKED BY:

DRAWN BY:

DESIGN BY:

ACAD FILE:

FIGURE:

N

S

W E

Location Map

Orillia

Tobermory

Wiarton

Port Elgin

Owen

Sound

Meaford

Thornbury

Collingwood

Wasaga

Beach

Midland

Orangeville

Shelburne

Mount

Forest

Newmarket

Parry Sound

Bracebridge

Gravenhurst

Barrie

Orillia

Penetanguishene

Lake Simcoe

Georgian Bay

Nottawasaga Bay

Wastewater Master Plan

City of Orillia

Figure 1.1

1.1

JC

PT

W

e

s

t

S

t

r

e

e

t

N

o

r

t

h

D

r

i

v

e

N

o

r

t

h

F

r

o

n

t

S

t

r

e

e

t

C

o

l

b

o

r

n

e

S

t

r

e

e

t

W

e

s

t

C

o

l

d

w

a

t

e

r

S

t

r

e

e

t

F

i

t

t

o

n

s

R

o

a

d

E

a

s

t

Ath

erley R

oad

Hig

hway 1

2

H

ighw

ay 11

J

a

m

e

s

S

t

r

e

e

t

E

a

s

t

W

e

s

t

S

t

r

e

e

t

S

o

u

t

h

C

o

l

b

o

r

n

e

M

e

m

o

r

i

a

l

A

v

e

n

u

e

M

u

r

p

h

y

R

o

a

d

U

h

t

h

o

f

f

L

i

n

e

S

k

y

l

i

n

e

H

ig

h

w

a

y 1

1

M

i

s

s

i

s

s

a

g

a

S

t

r

e

e

t

W

e

s

t

K

i

n

g

S

t

r

e

e

t

N

o

r

t

h

S

t

r

e

e

t

E

a

s

t

G

o

l

d

i

e

D

r

Q

u

e

e

n

S

t

E

Lake Couchiching

M

a

t

c

h

e

d

a

s

h

S

t

S

Tudhope

Park

B

o

r

l

a

n

d

S

t

r

e

e

t

P

r

o

g

r

e

s

s

D

r

i

v

e

B

y

-p

a

s

s

Lake Simcoe

R

o

a

d

D

r

i

v

e

C

o

u

c

h

i

c

h

i

n

g

P

n

t

P

a

r

k

S

t

r

e

e

t

B

r

a

n

t

S

t

r

e

e

t

B

a

y

v

i

e

w

P

a

r

k

w

a

y

M

i

s

s

i

s

s

a

g

a

S

t

r

e

e

t

E

a

s

t

West

R

id

g

e

B

o

u

l

e

v

a

r

d

M

o

n

a

r

c

h

D

r

i

v

e

J

u

l

i

a

C

rescent

A

r

t

h

u

r

S

t

r

e

e

t

W

o

o

d

s

i

d

e

D

r

i

v

e

G

i

l

l

S

t

r

e

e

t

J

a

r

v

i

s

S

t

r

e

e

t

S

t

r

e

e

t

E

a

s

t

E

a

s

t

F

o

r

e

s

t

A

v

e

n

u

e

E

a

s

t

S

t

r

e

e

t

B

r

a

n

t

S

t

r

e

e

t

E

a

s

t

W

e

s

t

M

e

m

o

r

i

a

l

A

v

e

n

u

e

M

a

t

c

h

e

d

a

s

h

S

t

r

e

e

t

N

o

r

t

h

L

a

c

l

i

e

S

t

r

e

e

t

Laclie

Street

P

e

t

e

r

S

t

r

e

e

t

N

o

r

t

h

H

i

l

d

a

S

t

r

e

e

t

O

x

f

o

r

d

S

t

r

e

e

t

H

u

g

h

e

s

R

o

a

d

O

l

d

B

a

r

r

i

e

R

d

E

S

t

o

n

e

R

i

d

g

e

B

l

v

d

H

a

r

v

i

e

S

e

t

t

l

e

m

e

n

t

R

d

University A

ve

J

a

m

e

s

S

t

W

B

a

r

r

i

e

R

d

M

ississaga S

t W

V

i

c

t

o

r

i

a

C

r

L

i

n

e

1

5

N

W

o

o

d

l

a

n

d

D

r

W

e

s

t

m

o

u

n

t

Cold

wate

r R

oad

B

a

r

r

i

e

R

d

F

i

t

t

o

n

s

R

o

a

d

W

e

s

t

Legend

Township of Severn

Township of Oro-Medonte

H

i

g

h

w

a

y

1

1

Areas Requiring Extension

of Municipal Service

Ward Boundaries

Orillia City Limits

Ward 1

Ward 2

Ward 3

Ward 4

H:\E - Environmental Services\E01 - Sanitary Sewers\E01 MAS\WWMP 2012\Drawings\12WWMP1-2.dwg

Jan 30, 2013 - 11:47am

TITLE:

PUBLIC WORKS DEPARTMENT

CITY of ORILLIA

THE CORPORATION OF THE

JAN. 22, 2013

JAN. 22, 2013

JC

WH

12WWMP1-2.DWG

450m

1:45000

SCALE

PLOTTED:

DATE:

APPROVED BY:

CHECKED BY:

DRAWN BY:

DESIGN BY:

ACAD FILE:

FIGURE:

N

S

W E

0 450 900m

Major Development Areas

Wastewater Master Plan

City of Orillia

Figure 1.2

1.2

WH

PT

Page 3

In accordance with the Class EA process, projects are categorized according to their magnitude

and potential effect(s) on the environment. Schedule A/A+ projects, such as upgrading a

wastewater collection system or existing sewage treatment facility within an approved

development plan, are pre-approved and may proceed to implementation without following the

full Class EA process. Schedule B projects, such as extending a wastewater collection system

beyond an approved development plan, and generally include improvements and minor

expansions to existing facilities, require a screening process, involving mandatory contact with

directly affected public and relevant review agencies, to ensure that their concerns, if any, are

addressed (referred to as Phase 2 in the Class EA process). Schedule C projects, such as

constructing a new sewage treatment plant or expanding an existing sewage treatment plant

beyond its rated capacity, should follow the full planning and documentation procedures

specified in the Class EA document including preparation of an Environmental Study Report

(ESR) to be filed for review by public and review agencies.

The Original Document identified an EA category for each of the projects recommended in its

Schedule of Works. Any individual or agency who felt that there were significant environmental

concerns associated with any of the recommended projects, which would be better handled

through the next Class EA category, or by an Individual EA rather than a Class EA, had the

opportunity to request a Part II Order by writing to the Minister of the Environment.

Since the procedures outlined in the Original Document satisfied the first two phases of the Class

EA process and no Part II Orders were requested, the proponent (the City of Orillia) was free to

proceed with the design and construction of all Schedule A/A+ and B projects. For Schedule C

projects, the proponent is still required to fulfill the additional requirements of Phases 3, 4 and 5

of the Class EA process, including preparation of an ESR, evaluation of alternative design

concepts for a preferred solution, site specific environmental issues, and additional public

consultation and notification.

Similarly, the City is free to proceed with all revised Schedule A/A+ and B projects as outlined

in the 2012 Master Plan Update, and must fulfill additional requirements for revised Schedule C

projects, having completed the EA procedures required to update the Master Plan.

More detailed information on the Class EA and Master Plan processes can be found in Section

2.2 of the Original Document.

1.4 RELEVANT REPORTS AND STUDIES

A list of various reports and documentation which contain additional information relevant to this

Master Plan Update can be found in the References at the end of this report.

Page 4

2.0 SUMMARY OF MASTER PLANNING PROCESS

Due to pressure for growth in the City, particularly in West Orillia, the City prepared a

Wastewater System Master Plan in 2004 to define the framework for future City development

and expenditures. The Master Planning procedure followed the first two phases of the five phase

Class EA process.

In Section 2 of the Original Document, a comprehensive summary of the five phase Class EA

process and Master Planning procedure, the public consultation process followed and review

agency participation is provided.

The 2012 Master Plan Update reflects the deletion of works from the Schedule of Works that

have been completed since the Original Document was filed, as well as refinements of

recommended works due to revised (lower) population and flow projections and additional

works arising primarily as a result of new Provincial legislation and regulations. In short, the

revisions are of a relatively minor nature that do not warrant an extensive re-consultation

process. Therefore, public consultation consisted of inviting public comment and notification of

review agencies by letter and publication in a local newspaper of a Revised Notice of

Completion of the Wastewater System Master Plan (which also summarized the proposed works,

notified who to contact with questions and comments, and outlined Part II Order procedures). A

copy of the letter to review agencies and Revised Notice of Completion is included in Appendix

A.

Page 5

3.0 EXISTING CONDITIONS

3.1 PHYSICAL ENVIRONMENT

The proposed Orillia service area and layout of the existing sewage collection system are shown

in Figure 3-1. The service area corresponds to the City of Orillia municipal boundary, including

West Orillia.

The City of Orillia extends on either side of Highway 11, at the intersection with Highway 12

(Coldwater Road), approximately 35 km northeast of Barrie. The present service area is

approximately 2,656 hectares and is bounded on the northwest by the Township of Severn, on

the southwest by the Township of Oro-Medonte, on the northeast by Lake Couchiching and on

the southeast by Lake Simcoe. The Township of Ramara is located east of Orillia, across the two

lakes.

Current wastewater flows generated from industries, commercial developments and institutions

represent approximately 43% of the total flows in the City, and are ultimately expected to

account for almost 50% of the total wastewater flows. Therefore the need to accommodate

industrial development is an important element of the Master Planning process.

The 2006 and 2011 Census identified residential population in Orillia of 30,259 and 30,586

respectively. There are currently 12,980 residences, 106 industries, 395 commercial

establishments, and 38 institutions (e.g. schools, hospitals, libraries, and nursing/retirement

homes).

The existing Wastewater Treatment Centre (WWTC) is located in the City of Orillia on a site

bordered by Kitchener Street to the south, Highway 12 to the north and West Street South to the

east. The plant location is shown on Figure 3-1 and is in an industrial area, adjacent to the City's

waste diversion site. Open space and some commercial establishments surround the industrial

area. The closest residential area is several hundred metres away from the WWTC. Hence, the

plant does not infringe upon the required site buffer zone, nor is likely to in the event of an

expansion.

3.2 SOCIO-ECONOMIC ENVIRONMENT

The demographic characteristics of Orillia as summarized in the Original Document were those

of a generally older population than that of Simcoe County, Ontario and Canada as a whole.

Overall, this reflects the character of Orillia as a quiet, but active urban centre, with a wide range

of professional, community, cultural, recreational and tourism activities and all amenities

associated with a small urban centre.

The 2011 Census indicates that Orillia’s population grew from in 27,846 in1996 to 29,121 in

2001 to 30,259 in 2006 to 30,586 in 2011. The Census indicates that Orillia’s population

continues to fit an older age profile, with a median age of 45 compared with 42 in Simcoe

County, 40 in Ontario, and 41 in Canada as a whole.

The economic characteristics of Orillia as summarized in the Original Document were those of

an economy largely oriented towards the service, trade and manufacturing sectors. The 2006

W

e

s

t

S

t

r

e

e

t

N

o

r

t

h

D

r

i

v

e

N

o

r

t

h

F

r

o

n

t

S

t

r

e

e

t

C

o

l

b

o

r

n

e

S

t

r

e

e

t

W

e

s

t

C

o

l

d

w

a

t

e

r

S

t

r

e

e

t

F

i

t

t

o

n

s

R

o

a

d

E

a

s

t

Ath

erley R

oad

Hig

hway 1

2

H

ighw

ay 11

J

a

m

e

s

S

t

r

e

e

t

E

a

s

t

W

e

s

t

S

t

r

e

e

t

S

o

u

t

h

C

o

l

b

o

r

n

e

M

e

m

o

r

i

a

l

A

v

e

n

u

e

M

u

r

p

h

y

R

o

a

d

U

h

t

h

o

f

f

L

i

n

e

S

k

y

l

i

n

e

H

ig

h

w

a

y 1

1

M

i

s

s

i

s

s

a

g

a

S

t

r

e

e

t

W

e

s

t

K

i

n

g

S

t

r

e

e

t

N

o

r

t

h

S

t

r

e

e

t

E

a

s

t

G

o

l

d

i

e

D

r

Q

u

e

e

n

S

t

E

Lake Couchiching

M

a

t

c

h

e

d

a

s

h

S

t

S

Tudhope

Park

B

o

r

l

a

n

d

S

t

r

e

e

t

P

r

o

g

r

e

s

s

D

r

i

v

e

B

y

-p

a

s

s

Lake Simcoe

R

o

a

d

D

r

i

v

e

C

o

u

c

h

i

c

h

i

n

g

P

n

t

P

a

r

k

S

t

r

e

e

t

B

r

a

n

t

S

t

r

e

e

t

B

a

y

v

i

e

w

P

a

r

k

w

a

y

M

i

s

s

i

s

s

a

g

a

S

t

r

e

e

t

E

a

s

t

West

R

id

g

e

B

o

u

l

e

v

a

r

d

M

o

n

a

r

c

h

D

r

i

v

e

J

u

l

i

a

C

rescent

A

r

t

h

u

r

S

t

r

e

e

t

W

o

o

d

s

i

d

e

D

r

i

v

e

G

i

l

l

S

t

r

e

e

t

J

a

r

v

i

s

S

t

r

e

e

t

S

t

r

e

e

t

E

a

s

t

E

a

s

t

F

o

r

e

s

t

A

v

e

n

u

e

E

a

s

t

S

t

r

e

e

t

B

r

a

n

t

S

t

r

e

e

t

E

a

s

t

W

e

s

t

M

e

m

o

r

i

a

l

A

v

e

n

u

e

M

a

t

c

h

e

d

a

s

h

S

t

r

e

e

t

N

o

r

t

h

L

a

c

l

i

e

S

t

r

e

e

t

Laclie

Street

P

e

t

e

r

S

t

r

e

e

t

N

o

r

t

h

H

i

l

d

a

S

t

r

e

e

t

O

x

f

o

r

d

S

t

r

e

e

t

H

u

g

h

e

s

R

o

a

d

O

l

d

B

a

r

r

i

e

R

d

E

S

t

o

n

e

R

i

d

g

e

B

l

v

d

H

a

r

v

i

e

S

e

t

t

l

e

m

e

n

t

R

d

University A

ve

J

a

m

e

s

S

t

W

B

a

r

r

i

e

R

d

M

ississaga S

t W

V

i

c

t

o

r

i

a

C

r

L

i

n

e

1

5

N

W

o

o

d

l

a

n

d

D

r

19

22

23

9

20

5

8

17

16

2

1

11

10

14

4

3

7

18

12

13

P

P

P

W

e

s

t

m

o

u

n

t

Cold

wate

r R

oad

B

a

r

r

i

e

R

d

F

i

t

t

o

n

s

R

o

a

d

W

e

s

t

Legend

Sanitary Pumping Station (City)

Sanitary Pumping Station (Private)

12

Existing Sanitary Collection System

P

Township of Severn

Township of Oro-Medonte

Wastewater Treatment Centre

Orillia City Limits

P

P

P

P

P

P

H:\E - Environmental Services\E01 - Sanitary Sewers\E01 MAS\WWMP 2012\Drawings\12WWMP3-1.dwg

Jan 30, 2013 - 11:29am

TITLE

PUBLIC WORKS DEPARTMENT

CITY of ORILLIA

THE CORPORATION OF THE

JAN. 22, 2013

JAN. 22, 2013

JC

WH

12WWMP3-1.DWG

450m

1:45000

SCALE

PLOTTED:

DATE:

APPROVED BY:

CHECKED BY:

DRAWN BY:

DESIGN BY:

ACAD FILE:

FIGURE:

N

S

W E

0 450 900m

Overall Service Area and

Existing Wastewater

Collection System

Wastewater Master Plan

City of Orillia

Figure 3.1

3.1

JC

PT

P

P

P

P

P

P

Page 6

Census indicates that these characteristics have changed slightly with an increase in the

business/finance/ administration sector and a decrease in the manufacturing sector.

3.3 RECEIVING WATER

The Orillia Wastewater Treatment Centre (WWTC) discharges to Lake Simcoe via Ben’s Ditch

which, through Lake Couchiching and the Severn River, ultimately feeds Severn Sound and the

Midland Harbour.

The Original Document anticipated that the MOE would require more stringent effluent

conditions in the future. Since that time, Lake Simcoe has been the focus of extensive

environmental management strategies concerned with the control and reduction of nutrient

levels. Due to the implementation of the Lake Simcoe Protection Plan (2009) and the Phosphorus

Reduction Strategy for the Lake Simcoe Watershed (2010), the Orillia WWTC will be required

to meet more stringent phosphorus limits of 0.1 mg/L and 996 kg/yr as of June 2015. An

Environmental Compliance Approval has been issued to the City by the Ministry of the

Environment (MOE) in June 2012 to reflect these more stringent effluent total phosphorus (TP)

limits. Total loading and average concentration of phosphorus in WWTC effluent to Lake

Simcoe over the last 5 years are presented in Table 3-5.

TABLE 3-1 PHOSPHORUS LOADING AND CONCENTRATION

IN WWTC EFFLUENT OVER THE LAST 5 YEARS

Year Average Concentration

(mg/L)

Total Loading

(kg)

2007 0.23 1350

2008 0.16 1048

2009 0.19 1349

2010 0.11 593

2011 0.08 498

In addition, the MOE has indicated that although no effluent total ammonia nitrogen (TAN)

limits would be required at this time; effluent TAN objectives will be included in the ECA for

the upgraded facility. A computer model of the Orillia WWTC was developed to assess the

ability of the existing facility to meet the design effluent TAN objectives of 13 mg/L in the

"summer" and 17 mg/L in the "winter". Based on the results of the modeling, no expansion to the

existing bioreactor or secondary clarifier tankage is required to meet the effluent TAN objectives

for flows up to the ECA rated capacity of 27,300 m3/d. Therefore, the process modification is

required only for phosphorus reduction in the WWTC effluent.

In the Original Document, parameters set out by the MOE for effluent “plume” widths, beyond

which residual chlorine concentrations must be reduced to 0.002 mg/L. Since that time, the

WWTC has been upgraded with an ultraviolet (UV) effluent disinfection facility. This replaced

the previous disinfection process using chlorine gas and satisfies the residual chlorine parameters

set out by the MOE and Environment Canada.

Page 7

Historical parameters measured for secondary treatment plant performance, i.e. 5-day

biochemical oxygen demand (BOD5) and suspended solids (SS), are not likely to be a concern

since nitrification (ammonia oxidation) and enhanced phosphorus treatment will also result in

more efficient removal of these parameters. Effluent compliance will likely be in the order of 10-

15 mg/L BOD5 and 15 mg/L SS, as is the requirement under the current Environmental

Compliance Approval.

It should also be noted that Severn Sound, into which the effluent from Orillia's WWTC is

ultimately carried, is one of 17 Areas of Concern (AOC's) in Canada (there are an additional 26

AOC's in the United States) which have been identified by the International Joint Commission

(IJC) as areas where provincial water quality objectives have been exceeded. Of the 43 original

areas of concern in Canada and the United States, only one has been delisted. The Severn Sound

AOC is located in south eastern Georgian Bay and covers an area of approximately 1,000 km2. A

Remedial Action Plan (RAP) was developed to identify and control sources of pollution and

report on the clean-up. However, if provincial requirements with respect to nutrient levels in

Lake Simcoe are not exceeded, then the loadings from wastewater treatment centres discharging

to Lake Simcoe is considered to be acceptable by the IJC.

3.4 EXISTING WASTEWATER SYSTEM

3.4.1 General

Due to the topology of the area, the City’s wastewater collection system is a complex network of

gravity sewers serviced by 20 sanitary sewage pump stations and 17 trunk sewers (defined in this

document as sewers having a diameter of 350 mm or more). All wastewater flows to the James

Street Pumping Station, from where it is pumped to the grit tank inlet of the WWTC.

3.4.2 Sanitary Sewers

Construction of the City’s wastewater collection system commenced in 1909 and by 1911 was

comprised of approximately 13 km of sewer pipe. In subsequent years the length of the system

increased as follows:

1928 - 24 km 1980 - 105 km

1949 - 40 km 1988 - 115 km

1960 - 57 km 1995 - 126 km

1970 - 77 km 2003 - 139 km

2011 - 163 km

The estimated replacement cost of the sewers is $69 million. The trunk sewer collection system

is comprised of the following trunk sewers (pipes with a diameter of 350 mm or more):

Barrie Rd/Jameson St/Birch St to Lexington St

Birch St@Lexington Ave/Westmount Dr S/Rose St/Memorial Ave to James St West

CNR/Queen St E/Matchedash St S to James St East

Fittons Rd East and West to CNR

Fittons Rd West to SPS #18

Front St S/Poughkeepsie St/Gill St to James St East

Page 8

Gill St to James St East

James St East to James St West

King St/Front St S to CNR

Grenville Ave/Lakeview Ave/Barrie Rd/Lexington Ave to Birch St

Powley St/Wyandotte St/Barrie Rd/West Street South to James St West

Progress Drive/Memorial Avenue to James St West

West Ridge Blvd to Stone Ridge Blvd

West Street South to James St West

Woodside Dr/Walker Ave to Barrie Rd

As well as two new trunk sewers added in West Orillia:

Stone Ridge Blvd to West Ridge Blvd.

University Ave from West Orillia Sports Complex to Stone Ridge Blvd.

Canadian National Railway (CNR) Trunk

The CNR Sanitary Trunk Sewer is 3445 m long consisting of 625 m of 525 mm diameter, 2559

m of 600 mm diameter, 185 m of 750 mm diameter, and 76 m of 825 mm diameter pipes. It runs

down the eastern side of the City of Orillia mostly along an old CNR right-of-way.

Information on condition assessment of the sewer system is given in section 5.3.

3.4.3 Sewage Pumping Stations

The City of Orillia sanitary sewer system consists of 20 sanitary sewage pumping stations (SPS)

located as shown on Figure 3-1, and about 10.3 km of sewage forcemain. These stations have

pump design flows from as low as 5 m3/d to over 100,000 m

3/d and are estimated to have a

replacement value of $22 to $27 million. In addition, there are abandoned SPS on Hughes Road

(No. 6) and Cedarmere Road (SPS No. 21), and a stormwater pumping station on James Street

East (No. 15).

At present, the sewage pumping stations at Bayview Parkway (No. 2), Fittons Road West (No.

18), James Street SPS (No. 1), and Champlain Industrial Park (No. 23) are provided with standby

power. In addition, the stations at Couchiching Point Road (No. 5), Bridget Drive/Maple Drive

(No. 13), and Shannon Street (No. 11) are capable of being powered by a portable generator.

In 2005 the City completed a Sewage Pumping Stations Rehabilitation Status Report: an

evaluation of the condition of all of its sewage pumping stations. Each pumping station was

assessed based on Ministry of the Environment and Ten States Standards criteria for new

facilities, with an emphasis physical qualities in order to address concerns with aging equipment,

high power costs, and increased maintenance requirements. The Status Report ranked the

pumping stations in order of priority for rehabilitation / replacement and suggested that one SPS

project be completed per year.

The capacities and service areas of the SPS are included in Appendix C of the Original

Document and are summarized as follows:

Page 9

SPS No. 1 – James Street West

The James Street West SPS receives flow from the entire city. It discharges directly to the

WWTC via twin 600 mm diameter force mains that are 784 m long. It has four electric pumps

two channel grinding units and a standby diesel generator. Several upgrades have been

completed at the James Street West SPS since the Original Document:

In 2005 the existing mechanical bar screening equipment and grinder were replaced

with two new channel grinding units. This upgrade was identified in the Original

Document to address downstream problems associated with rags and other extraneous

matter escaping the screens. This project included: modification of the concrete and

floor grating, installation of hoists for removing the units from the channel for service

and repair, and instrumentation and control linked to the existing SCADA system.

In 2006 a 90 m3/hr septage and hauled sewage receiving station was constructed at

the James Street West SPS. This upgrade was identified in the Original Document to

eliminate problems associated with receiving septage at the WWTC. This system has

a peak flow capacity of 90 m3/hour and discharges to the pumping station inlet

channel through a 250 mm outlet pipe, equipped with a knife gate valve. A second

250 mm knife gate valve and blind flanged pipe was provided for connection to a

future equalization tank. Electronic monitoring and control through a PLC is

connected to the existing SCADA at the Wastewater Treatment Centre via Ethernet.

In 2009 a new standby diesel generator was installed to provide emergency power for

the entire James Street West SPS. Removal of the existing diesel standby engine for

pump #2 was also completed. The Original Document identified this upgrade as

necessary to avoid problems that may occur during a prolonged power outage.

SPS No. 2 – Bayview Parkway

The Bayview Parkway SPS was built in 1957 and upgraded in 1973 with two Fairbanks Morse

variable speed centrifugal pumps. Additional upgrades have been completed to this SPS as

follows:

In 2006 the SPS pumps were replaced with new;

In 2008 the standby generator and electrical controls were replaced.

The drainage basin is in the southeast portion of the city and consists of the following:

Service Area ~ 32 ha

331 residential units

4.0 ha of commercial and institutional facilities

This SPS also receives sewage flows from two SPS to the south (No. 16 & No. 17) and one SPS

to the east (No. 8) whose service areas are not included in the above breakdown. The area

serviced is low lying terrain, susceptible to flooding during spring runoff and storm periods

resulting in higher than normal peak flow to the SPS. Therefore, a 1140 m3 flow equalization

chamber was constructed in 1987, and regular bypass events have been eliminated at this station

since that time.

Page 10

Flow design calculations and field measurements:

Average design flow 10.7 L/s

Peak design flow 34.3 L/s

(including flow from three contributing SPS: No. 8, 16, & 17)

Number of pumps 2

Rated capacity of each pump 57.5 L/s at 21. 9 m total dynamic head (TDH)

Maximum two-pump capacity 66 L/s

Force main size 200 mm

Flo-tote data (Jul 19 – Aug 4, 2004) 17.1 L/s (Max. Flow)

Hydra model (2012 update) 31.4 L/s (Max. Flow)

Flow measurements and calculations indicate that the present pumping capacity and equalization

storage are adequate to maintain average and peak flows. Field flow measurements suggest that,

under peak flow conditions, this SPS operates at approximately 26% of its rated capacity.

Updated Hydra model results take into consideration some inflow and infiltration, and suggest

that peak flow conditions may be closer to 48% of the SPS rated capacity. Previous extensive

flow monitoring indicated that the majority of peak flow can be attributed to storm water inflow.

SPS No. 3 – Couchiching Park

The Couchiching Park SPS was built in 1930 and upgraded with two new Flygt CP3101MT

pumps installed in 1980. The drainage basin is in the vicinity of the Water Filtration Plant (WFP)

and consists of the following:

Service Area ~ 11.5 ha

61 residential units

0.8 ha institutional facility (Birchmere Retirement Home – 78 units)

Flow design calculations and field measurements:

Average design flow 1.2 L/s

Peak design flow 4.3 L/s

Number of pumps 2

Rated capacity of each pump 15.8 L/s at 4.6 m TDH

Forcemain size 200 mm

2004 Drawdown test Pump 1 – 10.8 L/s

Pump 2 – 15.6 L/s

Flo-tote data No data

Hydra model (2012 update) 2.9 L/s (Max. Flow)

This SPS is operating at approximately:

27% of the rated capacity (15.8 L/s) based on the peak design flow (4.3 L/s)

18% of the rated capacity (15.8 L/s) based on 2012 Hydra model results (2.9 L/s)

Note that the Water Filtration Plant discharges an estimated 450 m3/d of backwash water directly

into the CNR trunk sewer. Both the WFP and SPS No. 3 discharge into maintenance hole no. 47

on the CNR trunk sewer.

Page 11

SPS No. 4 – Elgin Street at Scott Street

The Elgin Street SPS was built prior to 1966 and upgraded with two new ABS pumps

installed in 2003. The drainage basin consists of the following:

Service Area ~ 9.9 ha

89 residential units

Flow design calculations and field measurements:

Average design flow 1.3 L/s

Peak design flow 4.5 L/s

Number of pumps 2

Rated capacity of each pump 34.1 L/s at 6.1 and 7.6 m TDH

Force main size 150 mm

2004 Drawdown test: Pump 1 – 13.5 L/s

Pump 2 – 16.2 L/s

Flo-tote data (Jun 28 – Oct 1, 2001) 5.8 L/s (Max. Flow)

Hydra model (2012 Update) 3.7 L/s (Max. Flow)

This SPS is operating at approximately:

13% of the rated capacity (34.1 L/s) based on the peak design flow (4.5 L/s)

17% of the rated capacity (34.1 L/s) based on 2001 Flo-tote data (5.8 L/s)

11% of the rated capacity (34.1 L/s) based on 2012 Hydra model results (3.7 L/s)

SPS No. 5 – Couchiching Point (Atherley Road East)

The original Couchiching Point SPS was built in 1966 and was a Smith & Loveless dry well/wet

well station with two model 4B3 pumps. This station was replaced in 2007 with a new Flygt

submersible station with two model NP3127 pumps, new above ground electrical/control

cabinet, radio communication capability with the WWTC, and receptacle for portable generator

connection.

The drainage basin is located at the most easterly area of the city and is comprised of the

following:

Service Area ~ 42.4 ha

259 residential units

1.9 ha of commercial facilities

Flow design calculations and field measurements:

Average design flow 11.1 L/s

Peak design flow 31.4 L/s

Number of pumps 2

Rated capacity of each pump 38.9 L/s at

Force main size 250 mm

Flo-tote data (Jun 2 – Aug 3, 2002) 17.9 L/s (Max. Flow)

Hydra model (2012 Update) 12.4 L/s (Max. Flow)

This SPS is operating at approximately:

81% of the rated capacity (38.9 L/s) based on the peak design flow (31.4 L/s)

Page 12

46% of the rated capacity (38.9 L/s) based on the Flo-tote data (17.9 L/s)

32% of the rated capacity (38.9 L/s) based on 2012 Hydra model results (12.4 L/s)

Previous extensive flow monitoring indicated nominal storm inflow and higher than expected

infiltration flow.

SPS No. 6 – Hughes Road

The Hughes Road SPS has been abandoned by the City and, therefore, has not been considered

further in this report.

SPS No. 7 – Laclie Street at Neywash Street (Royal Oak)

The Laclie Street SPS was built in 1962 and the one submersible pump was replaced with a Flygt

C3085MT pump installed in 1982. The drainage basin is comprised of the following:

Service Area ~ 0.6 ha

5 residential units

0.4 ha of commercial facilities

Flow design calculations and field measurements:

Average design flow 0.2 L/s

Peak design flow 0.5 L/s

Number of Pumps 1

Rated capacity of pump 8.1 L/s at 7.6 m TDH

Forcemain size 100 mm

2004 Drawdown test: Pump 1 - 12.8 L/s

Hydra model (2012 Update) 0.5 L/s (Max. Flow)

This SPS is operating at approximately:

6% of the rated capacity (8.1 L/s) based on the peak design flow (0.5 L/s)

6% of the rated capacity (8.1 L/s) based on 2012 Hydra model results (0.5 L/s)

SPS No. 8 – Tudhope Park

The Tudhope Park SPS was built in 1969 and the original pumps were replaced with two new

Flygt C3102HT pumps installed in 1991. This SPS was initially installed to service a seasonal

trailer park located within Tudhope park. Currently, it is used seasonally with a drainage basin

comprised of the following:

Service Area ~ 12.0 ha

Beach washroom facility

Flow design calculations and field measurements:

Average design flow 2.0 L/s

Peak design flow 5.1 L/s

Number of Pumps 2

Rated capacity of each pump 14.2 L/s at 16.0 m TDH

Forcemain size 100mm

2004 Drawdown test Pump 1 – 2.8 L/s

Page 13

Pump 2 – 4.6 L/s

Flo-tote data No data

Hydra model (2012 Update) 0.6 L/s (Max. Flow)

This SPS is operating at approximately:

36% of the rated capacity (14.2 L/s) based on the peak design flow (5.1 L/s)

4% of the rated capacity (14.2 L/s) based on 2012 Hydra model results (0.6 L/s)

SPS No. 9 – Commerce Road (at Kubota)

The Commerce Road SPS was built in 1974 and is a Smith & Loveless dry well/wet well station

with two model 4B2A pumps. In 2005, a system failure with the pumps resulted in sewage

flowing into the dry well, destroying the electrical system. As a result, a new motor control

centre was installed above ground.

The drainage basin is a small industrial area located in the northeast corner of the intersection of

West Street North and Highway 11 and is comprised of the following:

Service Area ~ 20.0 ha

1 residential unit

0.4 ha of commercial

19.4 ha of industrial

Flow design calculations and field measurements:

Average design flow 3.3 L/s

Peak design flow 10.6 L/s

Number of Pumps 2

Rated capacity of each pump 36.1 L/s at 21.9 TDH

Forcemain size 150 mm

2004 Drawdown test: Pump 1 – 33.2 L/s

Pump 2 – 38.4 L/s

Flo-tote data (Jun 2 – Aug 3, 2002) No data

Hydra model (2012 Update) 4.3 L/s (Max. Flow)

This SPS is operating at approximately:

29% of the rated capacity (36.1 L/s) based on the peak design flow (10.6 L/s)

12% of the rated capacity (36.1 L/s) based on 2012 Hydra model results (4.3 L/s)

SPS No. 10 – Victoria Crescent (at Lankin Bridge)

The Victoria Crescent SPS was built in 1970 and the original pumps were replaced with two new

ABS submersible pumps installed in 1995. The drainage basin is comprised of the following:

Service Area ~ 9.2 ha

151 residential units

Flow design calculations and field measurements:

Average design flow 1.9 L/s

Peak design flow 7.0 L/s

Number of Pumps 2

Page 14

Rated capacity of each pump 11.4 L/s at 10.8 m TDH

Forcemain size 150 mm

2004 Drawdown test: Pump 1 – 14.0 L/s

Pump 2 – 14.3 L/s

Flo-tote data (Jun 28 – Oct 27, 2001) 9.5 L/s (Max. Flow)

Hydra model (2012 Update) 5.1 L/s (Max. Flow)

This SPS is operating at approximately:

61% of the rated capacity (11.4 L/s) based on the peak design flow (7.0 L/s)

83% of the rated capacity (11.4 L/s) based on the Flo-tote data (9.5 L/s)

45% of the rated capacity (11.4 L/s) based on 2012 Hydra model results (5.1 L/s)

SPS No. 11 – West Street South at Shannon Street

The original West Street South SPS was built in 1966 and was a Smith & Loveless dry well / wet

well station with two model 4B2 pumps. In 2004 the station was converted to a submersible

station with two Flygt NP3085MT pumps, new above ground electrical/control cabinet, radio

communication capability with the WWTC, and receptacle for portable generator connection.

The drainage basin is located at the south end of West Street across from Shannon Street and is

comprised of the following:

Service Area ~ 28.2 ha

276 residential units (includes 144 mobile homes)

11.1 ha of Kitchener Park

Flow design calculations and field measurements:

Average design flow: 4.2 L/s

Peak design flow: 14.6 L/s

Number of Pumps 2

Rated capacity of each pump 22.9 L/s at 5.92 m TDH

Forcemain size 150 mm

Flo-tote data (Jun 28 – Nov 2, 2001) 14.8 L/s (Max. Flow)

Hydra model (2012 Update) 5.1 L/s

This SPS is operating at approximately:

64% of the rated capacity (22.9 L/s) based on the peak design flow (14.6 L/s)

65% of the rated capacity (22.9 L/s) based on the Flo-tote data (14.8 L/s)

22% of the rated capacity (22.9 L/s) based on 2012 Hydra model results (5.1 L/s)

SPS No. 12 – Fittons Road East

The Fittons Road East SPS was built in 1969 and is a Smith & Loveless dry well / wet well

station with two model 4B3 pumps. The drainage basin is located in the northeastern section of

the City and is comprised of the following:

Service Are ~ 12.9 ha

56 residential units

Flow design calculations and field measurements:

Page 15

Average design flow 1.1 L/s

Peak design flow 3.6 L/s

Number of Pumps 2

Rated capacity of each pump 15.8 L/s at 14.3 m TDH

Forcemain size 100 mm

2004 Drawdown test: Pump 1 – 19.2 L/s

Pump 2 – 23.9 L/s

Hydra model (2012 Update) 2.5 L/s (Max. Flow)

This SPS is operating at approximately:

23% of the rated capacity (15.8 L/s) based on the peak design flow (3.6 L/s)

16% of the rated capacity (15.8 L/s) based on 2012 Hydra model results (2.5 L/s)

SPS No. 13 – Maple Drive at Bridget Drive

The Bridget-Maple SPS was built in 1969 and was a Smith & Loveless dry well / wet well

station with two model 4C2 pumps. In 2009 the station was converted to a submersible station

with two Flygt NP3153HT pumps, new above ground electrical/control cabinet, and receptacle

for portable generator connection.

This is the most northern SPS in the City and the drainage basin is comprised of the following:

Service Area ~ 31.24 ha

118 residential units

2.1 ha of industrial

Flow design calculations and field measurements:

Average design flow 3.2 L/s

Peak design flow 8.0 L/s

Number of Pumps 2

Rated capacity of each pump 35.1 L/s at 16.3 m TDH

Forcemain size 200 mm

Hydra model (2012 Update) 4.8 L/s (Max. Flow)

This SPS is operating at approximately:

23% of the rated capacity (35.1 L/s) based on the peak design flow (8.0 L/s)

14% of the rated capacity (35.1 L/s) based on 2012 Hydra model results (4.8 L/s)

SPS No. 14 – Forest Avenue North

The Forest Avenue North SPS was built in 1969 and is a Smith & Loveless dry well / wet well

station with two model 4B2A pumps. The drainage basin is located at the north end of Forest

Avenue at Lake Couchiching and is comprised of the following:

Service Area ~ 2.7 ha

19 residential units

Flow design calculations and field measurements:

Average design flow 0.3 L/s

Peak design flow 1.1 L/s

Page 16

Number of Pumps 2

Rated capacity of each pump 14.2 L/s at 11.7 m TDH

Forcemain size 100 mm

2004 Drawdown test: Pump 1 – 16.8 L/s

Pump 2 – 22.1 L/s

Hydra model (2012 Update) 0.6 L/s (Max. Flow)

This SPS is operating at approximately:

8% of the rated capacity (14.2 L/s) based on the peak design flow (1.1 L/s)

4% of the rated capacity (14.2 L/s) based on 2012 Hydra model results (0.6 L/s)

Pumping Station No. 15 – James Street East

This pumping station is used strictly for stormwater flow and has, therefore, not been considered

further in this report.

SPS No. 16 – Forest Avenue South

The Forest Avenue South SPS was built in 1970 and the original pumps were replaced with two

Flygt CP3102MT pumps installed in 1987. The drainage basin is located on Forest Avenue

South, pumps into Bayview Parkway SPS drainage area, and is comprised of the following:

Service Area ~ 19.3 ha

183 residential units

Flow design calculations and field measurements:

Average design flow 2.9 L/s

Peak design flow 10.5 L/s

Number of Pumps 2

Rated capacity of each pump 18.9 L/s at 7.0 m TDH

Forcemain size 100 mm

2004 Drawdown test Pump 1 – 21.3 L/s

Pump 2 – 11.6 L/s

Hydra model (2012 Update) 8.5 L/s

This SPS is operating at approximately:

56% of the rated capacity (18.9 L/s) based on the peak design flow (10.5 L/s)

45% of the rated capacity (18.9 L/s) based on 2012 Hydra model results (8.5 L/s)

SPS No. 17 – Collins Drive at MacIssac Drive

The Collins Drive SPS was built in 1975 with two Flygt CP3082MT pumps and one of these

pumps was replaced in 2004. The drainage basin is located in the most easterly area of the City

and is comprised of the following:

Service Area ~ 2.0 ha

17 residential units

Flow design calculations and field measurements:

Average design flow 0.2 L/s

Page 17

Peak design flow 0.8 L/s

Number of Pumps 2

Rated capacity of each pump 6.3 L/s at 3.6 m TDH

Forcemain size 100 mm

2004 Drawdown test Pump 1 – 10.8 L/s

Pump 2 – out for service

Hydra model (2012 Update) 0.7 L/s

This SPS is operating at approximately:

13% of the rated capacity (6.3 L/s) based on the peak design flow (0.8 L/s)

11% of the rated capacity (6.3 L/s) based on 2012 Hydra model results (0.7 L/s)

SPS No. 18 – Fittons Road West

The Fittons Road West SPS was built in 1975 and is equipped with three vertically mounted

centrifugal pumps with variable speed drives. In 2012 this SPS was upgraded with a new

SCADA-enabled PLC control panel, three new variable frequency drives, reactors and motors,

ultrasonic level monitoring, and Radio Frequency communication with the WWTC.

The drainage basin is located in the northwest section of the City and is comprised of the

following:

Service Area ~ 83.2 ha

777 residential units

9.1 ha of commercial facilities

Flow design calculations and field measurements:

Average design flow 12.0 L/s

Peak design flow 37.9 L/s

Number of Pumps 3

Rated capacity for one pump 61.7 L/s at 29.0 m TDH

Rated capacity for two pumps 98.4 L/s at 32.3 m TDH

Rated capacity for all three pumps 109.8 L/s at 34.3 m TDH

Forcemain size 300 mm

Flo-tote data (Jul 9 – Aug 6, 2003) 33.2 L/s (Max. Flow)

Hydra model (2012 Update) 28.7 L/s (Max. Flow)

This SPS is operating at approximately:

39% of the rated capacity (98.4 L/s) based on the peak design flow (37.9 L/s)

34% of the rated capacity (98.4 L/s) based on the 2003 Flo-tote data (33.2 L/s)

29% of the rated capacity (98.4 L/s) based on 2012 Hydra model results (28.7 L/s)

SPS No. 19 – Westmount Drive North at John Street

The Westmount Drive North SPS was originally built in 1974 and is a Smith & Loveless dry

well / wet well station with two model 804A pumps. In 2013 this station is to be converted to a

submersible station with two Flygt CP3201HT pumps, new above ground electrical/control

cabinet, radio communication capability with the WWTC, and receptacle for portable generator

connection.

Page 18

The drainage basin is the second largest in the City and is comprised of the following:

Service Area ~ 51.7 ha

523 residential units

6.0 ha of commercial and institutional facilities

Flow design calculations and field measurements:

Average design flow 9.3 L/s

Peak design flow 29.1 L/s

Number of pumps 2

Rated capacity of each pump 59.3 L/s at 12.5 m TDH

Forcemain size 200 mm

2004 Drawdown test Pump 1 – 48.6 L/s

Pump 2 – 63.9 L/s

Flo-tote data (Aug 15-Oct 2, 2002) 10.7 L/s (Max Flow)

Hydra model (2012 Update) 23.6 L/s (Max. Flow)

This SPS is operating at approximately:

49% of the rated capacity (59.3 L/s) based on the peak design flow (29.1 L/s)

18% of the rated capacity (59.3 L/s) based on the 2002 Flo-tote data (10.7 L/s)

40% of the rated capacity (59.3 L/s) based on 2012 Hydra model results (23.6 L/s)

SPS No. 20 – Broadview Avenue

The Broadview Avenue SPS was built in 1976 with two Flygt CG-3065 pumps. The drainage

basin is located at the north end of Couchiching Point and is comprised of the following:

Service Area ~2.5 ha

20 residential units

Flow design calculations and field measurements:

Average design flow 0.3 L/s

Peak design flow 1.1 L/s

Number of Pumps 2

Rated capacity of each pump 7.9 L/s at 2.5m TDH

Forcemain size 75 mm

2004 Drawdown test Pump 1 – 8.7 L/s

Pump 2 – 5.2 L/s

Hydra model (2012 Update) 0.7 L/s (Max. Flow)

This SPS is operating at approximately:

14% of the rated capacity (7.9 L/s) based on the peak design flow (1.1 L/s)

9% of the rated capacity (7.9 L/s) based on 2012 Hydra model results (0.7 L/s)

SPS No. 21- Cedarmere Road

The Cedarmere Road SPS has been abandoned by the City and, therefore, has not been

considered further in this report.

Page 19

SPS No. 22 – Westmount Drive South (formerly Ridge Road)

The Westmount Drive South SPS was built in 1995 with two Flygt C2085MT pumps. The

drainage basin is located at the south end of Westmount Drive South and is comprised of the

following:

Service Area ~1.5 ha

2 residential units

Flow design calculations and field measurements:

Average design flow 0.1 L/s

Peak design flow 0.3 L/s

Number of pumps 2

Rated capacity of each pump 3.0 L/s at 7.3 m TDH

Forcemain size 150 mm

2004 Drawdown test Pump 1 – 3.8 L/s

Pump 2 – 6.3 L/s

Hydra model (2012 Update) 0.1 L/s (Max. Flow)

This SPS is operating at approximately:

10% of the rated capacity (3.0 L/s) based on the peak design flow (0.3 L/s)

3% of the rated capacity (3.0 L/s) based on the Hydra model (0.1 L/s)

SPS No. 23 – Champlain Industrial Park

The Champlain Industrial Park temporary SPS was originally built in 1994 and was a

submersible station. In 2010/2011 a permanent Champlain SPS was built to accommodate new

development in West Orillia. This station is a dry well / wet well type pumping station and has

three submersible dry pit installed sewage pumps, a channel grinder unit and by-pass manual bar

screen, and a standby diesel generator. The station discharges to Maintenance Hole 1600 at the

end of Woodside Drive via twin 150 mm and 300 mm force mains that are 500 m long.

The drainage basin is generally bounded by Highway 12 and Bass Lake Side Road to the north,

Old Barrie Road to the south, Highway 11 to the east, and Line 15 North to the west, and is

comprised of:

Service Area ~ 156 ha

2,168 residential units

23.95 ha of commercial facilities

34.75 ha of industrial facilities

59.34 ha of institutional facilities

Flow design calculations and field measurements:

Average design flow 31.6 L/s

Peak design flow 75.4 L/s

Number of pumps 3

Rated capacity for one pump 105.0 L/s at 39 m TDH

Rated capacity for two pumps 210.0 L/s at 39 m TDH

Forcemain size 150 and 300 mm

Hydra model (2012 Update) 33.4 L/s (Max. Flow)

Page 20

This SPS is operating at approximately:

36% of the rated capacity (210.0 L/s) based on the peak design flow (75.4 L/s)

16% of the rated capacity (210.0 L/s) based on the Hydra model (33.4 L/s)

It is proposed to replace the 150 mm force main with a second 300 mm force main to

accommodate ultimate peak flow.

3.4.4 Wastewater Treatment Centre (WWTC)

The Orillia WWTC at its present location was constructed in 1947, designed for a nominal

average daily flow (ADF) of 9,000 m3/d, by the Orillia Water, Light and Power Commission.

The original plant consisted of one coarse bar screen and one Detritor, two primary clarifiers, a

diffused air aeration basin, two final clarifiers, two digesters, and a chlorine disinfection facility.

Over the years the plant was expanded and processes were added, until the current 27,300 m3/d

average day capacity facility was completed. A brief summary of the construction history is as

follows:

In 1963 a substantial expansion of the plant was carried out by the Orillia Water,

Light and Power Commission to increase the nominal ADF capacity to 18,000 m3/d.

This expansion included: an additional bar screen, an additional Detritor, one

additional primary clarifier, one additional final clarifier, and the addition of a

Parshall flume to the chlorination facility.

In 1971 Ontario Water Resources Commission policy prompted addition of

phosphorus removal facilities to the plant consisting of: two 7,000 gal. chemical

storage tanks, two chemical feed pumps and interconnected pipework.

In 1972 alterations were carried out to the digester heating system and the digester

control building consisting of: a new boiler, a gas room, and a heat exchanger.

In 1974 a new primary digester cover was constructed under the supervision of the

Orillia Water, Light and Power Commission.

In 1974 the operation of the WWTC was taken over by the City of Orillia.

In 1975/1976 major alterations were made to the plant's inlet works, administration

building and primary digester. The new inlet works were designed for an ADF of

27,300 m3/d and consisted of the replacement of the bar screens and Detritors, with

two new aerated grit tanks, including an overhead clam, two barminutors, and

blowers for the aerated grit tanks. Additions to the administration building included: a

new MCC panel, a new Hoffman blower for aeration, a new header from the blowers

to the aeration tanks and the installation of a standby 200 KVA diesel generator set in

the basement. New diffusers were installed in the primary digester at this time along

with a new gas compressor.

In 1978/1979 a new floating gasholder cover was provided to the plant's secondary

digester.

Page 21

In 1981 new chlorination facilities designed for 27,300 m3/d ADF were constructed,

replacing the old facilities. The works included: a chlorine contact chamber with

bypass channel, a chlorine building utilizing 1 ton cylinders instead of the old 150 lb

cylinders, new chlorination equipment, and flow measurement over a rectangular weir

for flow recording and chlorine pacing. These works were designed and constructed

such that the main flow of secondary effluent could receive tertiary treatment in the

future, prior to disinfection.

In 1990 the original activated sludge tanks were expanded from four cells to six. The

six cells operate as a single plug flow reactor and aeration is provided by full floor

coverage of tube type pore diffusers.

A summary of work completed since the Original Document is as follows:

Primary clarifiers #1 & #2 failed in 1999 and 1996 respectively. In 2004/2005

clarifier #1 was filled and #2 was converted to an equalization tank for a new

dissolved air flotation (DAF) unit. The DAF unit is designed to a feed flow rate of 88

– 200 m3/d, with a pressurization system designed for a flow rate of 545 m

3/d. Waste

Activated Sludges are redirected to the DAF unit instead of the primary clarifiers,

where they are thickened and pumped to the primary digester. Primary clarifier #3

was retrofitted to a round clarifier 18.3 m diameter after being taken out of service in

the spring of 2003. This retrofit included benching of corners and installation of a

new 18.3 m Cage Drive Scraper Clarifier Mechanism.

In 2005/2006 a project was undertaken to optimize the operation of the dual gas

boiler system at the Wastewater Treatment Centre. This involved troubleshooting the

existing boiler, checking all settings, evaluating performance and determining

SCADA control and monitoring for the system. Flow meters were installed on the gas

train and pressure switch settings optimized.

In 2007/2008 implementation of an ultraviolet disinfection system was initiated to

comply with Environment Canada’s December 2004 Final Notice requiring

implementation of a pollution prevention plan for wastewater systems where chlorine

residual in the effluent exceeded 0.02 mg/L. The UV system was provided with an

operator interface for control and monitoring, and is pace controlled based on contact

chamber weir flow. The system is monitored by the existing PLC in the Chlorine

Building basement and data is transmitted over a new Fibre Optic/Ethernet Cabling

network to the SCADA system located in the Administration Building.

In 2008 two outdated aluminium sulphate chemical feed pumps were replaced with a

new solution feed system featuring two motor driven diaphragm pumps, flow

monitors, and pump interface control module. Also, the secondary digester exterior

was insulated and sealed with protective epoxy paint.

In 2010 the road leading to the plant and parking area were paved, helping to reduce

dust caused from vehicle traffic which may get into equipment and clog filters in air

intakes.

Page 22

In 2010/2011 a new 800kW/1000kVA standby generator was installed on a concrete

pad along the western perimeter of the WWTC property, adjacent to an existing 44

kV hydro transformer substation. This unit was sized to run the entire plant during

power outages and interruptions and is controlled and monitored through the SCADA

system.

The estimated total replacement cost of the WWTC is $62 million. The Orillia WWTC treats an

average annual wastewater flow of 6.5 million cubic metres, and generates approximately 30,000

cubic metres of raw sludge and, assuming approximately 25% volume reduction, 23,000 cubic

metres of anaerobically digested sewage sludge or biosolids annually. The City has established

programs to reduce, reuse and recycle waste, with biosolids recycling forming one component of

that program. Digested liquid biosolids are seasonally applied to agricultural land resulting in

nutrients and organic matter being returned to the soil. When land application cannot be

practised, the liquid is stored in lagoons on-site. The total capacity of the lagoons is

approximately 25,000 m3, however, one of the lagoons is not being used at present because of

suspected leakage, reducing the available capacity by about 36%.

The existing plant utilizes the conventional activated sludge process and the operations consist

of:

Inlet works utilizing two aerated grit tanks and two coarse bar screens;

Primary treatment consisting of three large primary clarifiers #3 , #4 and #5 complete

with sludge collecting and scum skimming equipment (primary sludge is pumped

directly to the anaerobic digesters);

Secondary treatment consisting of a six-cell aeration tank utilizing fine-bubble

diffused air, five secondary clarifiers complete with sludge collecting equipment,

return activated sludge pumping station, waste activated sludge (WAS) dissolved air

flotation thickener (DAF) and equalization tank (from the DAF the thickened WAS is

pumped to the primary digester);

Phosphorus removal by means of dual point chemical (alum) addition;

Effluent disinfection with two banks of UV modules using an actuated weir gate to

control the UV channel levels (flow from the UV system continues to the outfall to

Lake Simcoe);

Sludge treatment by means of anaerobic digestion utilizing a two-stage (primary and

secondary) digester, with floating cover on secondary digester for gas storage, and

dual- fired boilers (excess gas is flared);

Final disposal of digested sludge to agricultural land, with storage available in on-site

sludge lagoons; and

Computerized supervisory control and data acquisition (SCADA) system.

Page 23

Detailed design is currently on-going for WWTC process optimization and tertiary treatment

upgrades. Upgrades will include: new aeration system and blower building, new secondary

effluent pumping equipment, and a new continuous backwash filter system. It is anticipated that

detailed design and tendering of this project will occur in 2013 with completion of construction

in early 2015.

Page 24

4.0 FUTURE CONDITIONS

4.1 POPULATION GROWTH

The current annual growth rate (1.0%) and ultimate population growth projections ( persons) are

lower than the 1.5% growth rate and 17,732 person population growth assumed in the Original

Document. The 2009 Water System Master Plan Update assumed a 1.0% annual population

growth rate. Also, the City’s 2011 Official Plan forecasts growth of approximately 11,000 people

by 2031.

According to Statistics Canada’s Census the 2011 population in Orillia was 30,586 persons. The

most recent population projections for the City call for a total population growth of 11,052

persons based on an annual growth rate of 1.0%. The population is expected to increase by about

35% over the next 30-year period from 30,892 in 2012 to over 41,000 by the year 2042. The

projected population in Orillia from 2012 to 2042 is shown in Figure 4-1 and in Table 4-1.

20,000

25,000

30,000

35,000

40,000

45,000

19

80

19

85

19

90

19

95

20

00

20

05

20

10

20

15

20

20

20

25

20

30

20

35

20

40

20

45

PO

PU

LA

TIO

N

YEAR

Figure 4-1

POPULATION GROWTH2012 to 2042

1.0% Population Growth

Existing Population Growth

Page 25

The majority of the population increase will occur in West Orillia where there remains more than

185 hectares of vacant residential land and more than 75 hectares of vacant industrial land. The

Inch Development Area is another large area with approximately 100 hectares (ha) of land

located in the northwest quadrant of the Highway 11 and Highway 12 interchange. Of the 100 ha

of land, about 67 ha is within the City limit and the remaining 33 ha, known as the Area 3

Development, is located in Severn Township. Both of the areas have land that does not require

servicing: a cemetery (9 ha) and stormwater management facility (11 ha) within the City, and a

golf course (10 ha) in Area 3. Approximately 13 ha of vacant commercial and industrial land and

more than 18 ha of vacant residential land remain in the City portion of the Inch Development

Area. The Area 3 Development will consist of about 163 residential units and 5 hectares of

industrial/commercial land, and is not included in the projections of this 2012 Master Plan

Update.

Page 26

TABLE 4-1 PROJECTED ANNUAL POPULATION GROWTH

YEAR POPULATION GROWTH DOMESTIC POPULATION 1.0%

1981 CANADA CENSUS 23,955

1986 CANADA CENSUS 24,077

1991 CANADA CENSUS 25,925

1996 CANADA CENSUS 27,846

2001 CANADA CENSUS 29,121

2006 CANADA CENSUS 30,259

2011 CANADA CENSUS 30,586

2012 306 306 30,892

2013 309 615 31,201

2014 312 927 31,513

2015 315 1,242 31,828

2016 318 1,560 32,146

2017 321 1,882 32,468

2018 325 2,206 32,792

2019 328 2,534 33,120

2020 331 2,865 33,451

2021 335 3,200 33,786

2022 338 3,538 34,124

2023 341 3,879 34,465

2024 345 4,224 34,810

2025 348 4,572 35,158

2026 352 4,923 35,509

2027 355 5,278 35,864

2028 359 5,637 36,223

2029 362 5,999 36,585

2030 366 6,365 36,951

2031 370 6,735 37,321

2032 373 7,108 37,694

2033 377 7,485 38,071

2034 381 7,866 38,452

2035 385 8,250 38,836

2036 388 8,638 39,224

2037 392 9,031 39,617

2038 396 9,427 40,013

2039 400 9,827 40,413

2040 404 10,231 40,817

2041 408 10,639 41,225

2042 412 11,052 41,638

Page 27

4.2 INDUSTRIAL/COMMERCIAL/INSTITUTIONAL (ICI) GROWTH

Currently the ratio of domestic to ICI (Industrial/Commercial/Institutional) wastewater flow in

Orillia is approximately 1:1. The City anticipates developing/servicing a further 118.99 hectares

of industrial area, 15.57 hectares of commercial area, and 24.23 hectares of institutional area by

the year 2042. Assuming linear growth for industrial development, it is expected to occur at a

rate of approximately 3.97 hectares per year, as shown in Table 4-2. Similarly, commercial

development is also anticipated to occur linearly, at a rate of approximately 0.52 hectares per

year, as shown in Table 4-3. Institutional growth is not linear, with various developments added

into the system at different times. These include Phases 2 and 3 of Lakehead University in 2015

and 2021 respectively, and the Pentecostal Church in about 2016, all shown in Table 4-4.

4.3 WASTEWATER FLOW PROJECTIONS

The average daily wastewater flow received at the Wastewater Treatment Centre in the 5-year

period from 2007 to 2011, inclusive of extraneous flows, was 17,880 m3/d.

The trend has continued to be toward a decrease in per capita and per hectare wastewater flows

since the introduction of the City’s Enviro-Save Program in 1990 and Water Efficiency

Program in 1998. Therefore, for the purpose of this Master Plan Update it is logical to use

actual flows for the existing residences, industries, etc., instead of the rates established in the

MOE Guidelines. The design average day flow rates established in the City of Orillia based on

actual flows are as follows (Copy of Report to the Council Committee No. PD-02-038 on April

14, 2003 in Appendix E):

Domestic - 0.3 m3/c.d

Industrial - 36.0 m3/ha.d

Commercial - 28.0 m3/ha.d

Institutional - 63 m3/d total (Pentecostal Church)

(max day) - 533 m3/d total (Lakehead University)

As in the Original Document, a factor has also been added for re-urbanization of existing

development, equal to 5% of the existing 5-year average flow.

Based on the above design (for growth) and actual (for existing development) flow rates the total

average day flow of 26,457 m3/d for ultimate development is comprised of (see Table 4-5):

16,977 m3/d existing 5-year average

3,315 m3/d future domestic flow

4,284 m3/d future industrial flow

436 m3/d future commercial flow

596 m3/d future institutional flow

849 m3/d allowance for re-urbanization of existing development

An allowance for the Severn Township subdivision adjacent to the proposed Inch subdivision is

not included in the current flow projections because the project does not have a timeline.

Page 28

TABLE 4-2 PROJECTED ANNUAL INDUSTRIAL GROWTH

YEAR AREA INCREASE TOTAL AREA

(ha) INCREASE

2012 0.00 0.00

2013 3.97 3.97

2014 3.97 7.93

2015 3.97 11.90

2016 3.97 15.87

2017 3.97 19.83

2018 3.97 23.80

2019 3.97 27.76

2020 3.97 31.73

2021 3.97 35.70

2022 3.97 39.66

2023 3.97 43.63

2024 3.97 47.60

2025 3.97 51.56

2026 3.97 55.53

2027 3.97 59.50

2028 3.97 63.46

2029 3.97 67.43

2030 3.97 71.39

2031 3.97 75.36

2032 3.97 79.33

2033 3.97 83.29

2034 3.97 87.26

2035 3.97 91.23

2036 3.97 95.19

2037 3.97 99.16

2038 3.97 103.12

2039 3.97 107.09

2040 3.97 111.06

2041 3.97 115.02

2042 3.97 118.99

Page 29

TABLE 4-3 PROJECTED ANNUAL COMMERCIAL GROWTH

YEAR AREA INCREASE TOTAL AREA

(ha) INCREASE

2012 0.00 0.00

2013 0.52 0.52

2014 0.52 1.04

2015 0.52 1.56

2016 0.52 2.08

2017 0.52 2.60

2018 0.52 3.11

2019 0.52 3.63

2020 0.52 4.15

2021 0.52 4.67

2022 0.52 5.19

2023 0.52 5.71

2024 0.52 6.23

2025 0.52 6.75

2026 0.52 7.27

2027 0.52 7.79

2028 0.52 8.30

2029 0.52 8.82

2030 0.52 9.34

2031 0.52 9.86

2032 0.52 10.38

2033 0.52 10.90

2034 0.52 11.42

2035 0.52 11.94

2036 0.52 12.46

2037 0.52 12.98

2038 0.52 13.49

2039 0.52 14.01

2040 0.52 14.53

2041 0.52 15.05

2042 0.52 15.57

Page 30

TABLE 4-4 PROJECTED ANNUAL INSTITUTIONAL GROWTH

YEAR AREA INCREASE TOTAL AREA

(ha) INCREASE

2012 0.00 0.00

2013 0.00 0.00

2014 0.00 0.00

2015 11.41 11.41

2016 1.41 12.82

2017 0.00 12.82

2018 0.00 12.82

2019 0.00 12.82

2020 0.00 12.82

2021 11.41 24.23

2022 0.00 24.23

2023 0.00 24.23

2024 0.00 24.23

2025 0.00 24.23

2026 0.00 24.23

2027 0.00 24.23

2028 0.00 24.23

2029 0.00 24.23

2030 0.00 24.23

2031 0.00 24.23

2032 0.00 24.23

2033 0.00 24.23

2034 0.00 24.23

2035 0.00 24.23

2036 0.00 24.23

2037 0.00 24.23

2038 0.00 24.23

2039 0.00 24.23

2040 0.00 24.23

2041 0.00 24.23

2042 0.00 24.23

Page 31

TABLE 4-5 PROJECTED ANNUAL AVERAGE WASTEWATER FLOW

YEAR CUMULATIVE CUMULATIVE CUMULATIVE CUMULATIVE RE-URBANIZATION TOTAL

DOMESTIC INDUSTRIAL COMMERCIAL INSTITUTIONAL ALLOWANCE AVERAGE

POPULATION AREA AREA AREA 5% OF EXISTING DAY FLOW

INCREASE INCREASE INCREASE INCREASE DEVELOPMENT

x 0.30 m3/c.d x 36.0 m

3/ha.d x 28.0 m

3/ha.d VARIES m

3/d m

3/day

2005 16,454

2006 19,343

2007 15,940

2008 18,062

2009 19,697

2010 15,160

2011 16,024

5 year Average 16,977

2012 92 0 0 0 27 17,096

2013 184 143 15 0 55 17,373

2014 278 286 29 0 82 17,651

2015 373 428 44 267 110 18,197

2016 468 571 58 330 137 18,541

2017 564 714 73 330 164 18,822

2018 662 857 87 330 192 19,104

2019 760 1,000 102 330 219 19,387

2020 860 1,142 116 330 246 19,671

2021 960 1,285 131 596 274 20,223

2022 1,061 1,428 145 596 301 20,509

2023 1,164 1,571 160 596 329 20,796

2024 1,267 1,713 174 596 356 21,084

2025 1,372 1,856 189 596 383 21,373

2026 1,477 1,999 203 596 411 21,663

2027 1,584 2,142 218 596 438 21,954

2028 1,691 2,285 233 596 465 22,247

2029 1,800 2,427 247 596 493 22,540

2030 1,910 2,570 262 596 520 22,835

2031 2,020 2,713 276 596 548 23,130

2032 2,132 2,856 291 596 575 23,427

2033 2,245 2,999 305 596 602 23,725

2034 2,360 3,141 320 596 630 24,023

2035 2,475 3,284 334 596 657 24,323

2036 2,592 3,427 349 596 685 24,625

2037 2,709 3,570 363 596 712 24,927

2038 2,828 3,712 378 596 739 25,231

2039 2,948 3,855 392 596 767 25,535

2040 3,069 3,998 407 596 794 25,841

2041 3,192 4,141 421 596 821 26,148

2042 3,315 4,284 436 596 849 26,457

Page 32

4.4 PREDICTED WWTC EFFLUENT REQUIREMENTS

Based on the existing WWTC effluent criteria, as well as the rationale for criteria established for

the Barrie and Innisfil plant expansions, it is anticipated that future effluent maximum

concentrations for any expansion of capacity of the WWTC will remain as follows:

Bio-chemical Oxygen Demand (BOD5) 15 mg/L (10 mg/L objective)

Suspended Solids (SS) 15 mg/L

Total Phosphorus (TP) 0.1 mg/L and 996 kg per year

It is important to note that there are no specific Provincial Water Quality Objectives (PWQO's)

for BOD5 and SS. However, it is expected that maximum allowable concentrations will be

maintained at current Environmental Compliance Approval (ECA) levels.

The Original Document anticipated that the maximum allowable TP loading would be

maintained at the current Environmental Compliance Approval level, or may even be decreased.

Also, it was expected that any increase in design capacity will have to be accompanied by a

corresponding decrease in TP concentration in order to maintain the required loading per year.

Since that time, the Lake Simcoe Phosphorus Reduction Strategy (2010) has come into effect,

requiring the Orillia WWTC to meet the more stringent phosphorus concentration and total

loading limits above by June 2015. Under long term actions for Sewage Treatment Plants, the

Phosphorus Reduction Strategy recognizes that, given the currently available technology, further

reductions would be costly and difficult. It states that: “The requirement for further incremental

reductions will be re-evaluated in 2015 during the first review of the Strategy.”

The MOE has also indicated that, although the current ECA does not contain any effluent total

ammonia nitrogen (TAN) limits, effluent TAN objectives will be included in the ECA for the

upgraded facility. It is expected that the seasonal TAN objectives will be 13.0 mg/L in the

summer and 17.0 mg/L in the winter.

In the Original Document, it was also anticipated that there would be a restriction on the effluent

residual chlorine concentration in the order of 0.02 mg/L. Since that time the chlorine

disinfection process has been replaced with an ultraviolet disinfection facility which satisfies the

residual chlorine requirements set out by Environment Canada.

4.5 PREDICTED FUTURE BIOSOLIDS MANAGEMENT REQUIREMENTS

The digested biosolids from the WWTC meet all the criteria for disposal by means of application

on agricultural land, during the seasons when the ground is not frozen. The WWTC has six

biosolids storage lagoons for use during the period when land spreading is not permitted. The

projected volume of biosolids is 36,950 m3/yr generated at the rated average daily flow of

27,300 m3/d, which is not anticipated to be reached until after 2042. These projections include

the implementation of the Dissolve Air Flotation (DAF) thickening process for waste activated

sludge (WAS) completed by the City in 2004/2005.

The Ontario Nutrient Management Act, passed in June 2002 (amended January 2010) and its

first set of regulations enacted in September 2003 (O.Reg. 267/03 amended September 2012),

prohibit:

Page 33

Land application of sewage biosolids during the period beginning December 1st of

one year and ending on March 31st of the following year regardless of field or

weather conditions; and

Land application of sewage biosolids on snow covered or frozen soil at any time.

The Original Document anticipated that Orillia’s WWTC would be required to have a biosolids

management plan including provision for at least 180 days of storage, whether on-site or at an

area facility which could accommodate digested biosolids from a number of municipalities.

Development of a long-term biosolids management strategy and implementation plan was

identified as a priority in the Original Document.

Amendments to the General Nutrient Management Regulation (O.Reg. 267/03) in 2009 have

since changed the biosolids management requirements for Orillia’s WWTC:

Preparation of a Nutrient Management Strategy is no longer required;

Generation of biosolids continue to be subject to applicable approval requirements

under the Environmental Protection Act and Ontario Water Resources Act; and

Provision for 240 days of biosolids storage is recommended as a best practice but is

no longer a requirement.

Page 34

5.0 PROBLEM IDENTIFICATION

5.1 GENERAL

The Original Document was initiated to develop a strategy for providing a sustainable

wastewater system for existing and future growth and development areas in Orillia. This

involved an analysis of the limitations and problems associated with the existing system, and

remedial measures to reduce per capita and extraneous flows were discussed.

The main problems for consideration were identified in the Original Document, and remain the

focus of the 2012 Master Plan Update:

Infiltration and inflow

Condition and age of existing sewers

Limited capacities of existing trunk sewers

Limited capacities of existing sewage pumping stations

Limited capacity of the existing Wastewater Treatment Centre (WWTC)

Operational issues with the unit processes at the WWTC

Quantity and quality of Septage received at the WWTC

Future biosolids disposal and management

Treated effluent discharge quality standards

20,000

25,000

30,000

35,000

0

5,000

10,000

15,000

20,000

25,000

19

92

19

93

19

94

19

95

19

96

19

97

19

98

19

99

20

00

20

01

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

PO

PU

LA

TIO

N

FL

OW

in

cu

bic

me

tre

s

YEAR

FIGURE 5-1METERED vs PUMPED vs TREATED vs POPULATION

1992 to 2011

METERED WATER PUMPED WATER TREATED SEWAGE POPULATION

Page 35

The amount of sewage treated at the WWTC annually has typically averaged around 30% more

than the water pumped into the distribution system from the Water Filtration Plant (WFP), as

illustrated in Figure 5-1. This large difference in flows indicates that inflow and infiltration

contribute significant flows within the collection system.

The Original Document identified a number of programs successfully implemented by the City

to reduce wastewater flows. These included the Water Efficiency Program and the Enviro-Save

Program, introduced in 1998 and 1990 respectively. Following its 1989 infiltration/inflow study,

the City commenced the Enviro-Save program: a remedial program including disconnection of

eaves troughs/downspouts, sump pumps, and weeping tiles/foundation drains.

The Ontario Building Code was updated in 1996 to require the installation of ultra-low flush

toilets and other water saving devices in new house construction. As part of the Water

Efficiency Program, the City implemented a Water Fixture Replacement Program that was in

place from 1999 until September 2007 that provided residents with a rebate for replacing:

13 to 20 litre toilets with ultra-low flush toilets (6L)

showerheads with low flow showerheads

faucets with faucet aerators

top-loading washing machines with front-loading washing machines

About 2,075 households participated in the program, with 1,021 toilets replaced, 292

showerheads replaced, 118 faucet aerators installed and 1,383 washing machines replaced. This

has resulted in an estimated reduction of about 6 litres per capita per day.

An Outdoor Water Restriction by-law has been in place since 1992. This was revised in 2008 to

include time allotments and restrict outdoor water use year round.

Water and sewer rates have changed annually since 2003 to better reflect full system costs to

provide services. Sewer use rates have increased significantly, from $0.54 per m3 in 2004 to

$1.17 per m3 in 2012.

Other techniques for reducing water consumption have also been implemented, including:

In-school Education – since 1997 about 7,500 students have been instructed in the

importance of using water wisely.

General Public Information – flyers, bill stuffers, and newspaper advertisements have

been distributed to increase public awareness about water and sewer use, as well as

posting information on the City website

Rain Barrel Program – over 1700 rain barrels have been purchased and are in use

throughout the City

Overall these programs have been successful in reducing water consumption in the City which,

in turn, helps to reduce wastewater flows. There has been a fairly consistent reduction in the

average daily flow per capita treated at the WWTC over the past number of years. However, the

reduction of inflow and infiltration is also an important measure to reduce wastewater flows.

Page 36

In order to assess the capabilities of the existing wastewater collection system, a computer

generated hydraulic model of the system was produced using the Hydra software program. This

model was developed by updating the Hydra model completed for the Original Document, and

analyses the existing system under both current and future flow conditions. A report of the

results of the analysis is included in Appendix C.

5.2 INFILTRATION AND INFLOW

Although at present the WWTC is operating below its capacity, flow measurements over the past

ten years demonstrate that flows to the WWTC have been on average 36% higher than metered

water consumption (excludes WFP backwash flows and flows from the septage receival facility

from flows to the WWTC). Excess inflow and infiltration of water into the sanitary sewer system

reduces system capacity and increases pumping costs, and has the potential to flood basements

and cause manholes to overflow during wet weather. Sanitary sewer overflows can occur

throughout the system at manholes if the sewers lack the capacity to handle flows, or due to tree

roots or other blockages in the sewers. The incidence and frequency of sanitary sewer overflows

can present a public health hazard and can be a threat to receiving water quality.

In the Original Document, a preliminary analysis was presented to determine areas of highest

inflow and infiltration. Pump hour meter records for the City’s sewage pumping stations were

reviewed and compared for dry and wet periods. The areas whose pumping stations experienced

a significant increase in pumping during wet weather were identified as areas with high inflow

and infiltration. The sanitary sewers upstream of the following five sewage pumping stations

were identified as allowing a higher amount of inflow and infiltration: Couchiching Park (SPS

No. 3), Elgin Street at Scott Street (SPS No. 4), Forest Avenue South (SPS No. 16), Collins

Drive at MacIssac Drive (SPS No. 17), and Westmount Drive South (SPS No. 22) (refer to

Figure 5-2).

The Infiltration and Inflow Study (February 2005) identified the central part of the City as

having the most infiltration and inflows, and recommended an integrated approach to deal with

the problem. In October 2005 the Inflow/Infiltration Status Report further prioritized areas to

target for smoke testing, manhole and sewer rehabilitations, CCTV inspections, and flow

monitoring. This report also advocated for a public education program on the benefits of

reducing inflow and infiltration.

The May 2007 report: “Eliminating Inflow/Infiltration Implementation Program” provided an

updated analysis of Flo-tote data, CCTV inspections, storm drainage issues, maintenance hole

inspections, and the sewer replacement program. This report identified four sewage pumping

stations that pump more often than required: Bayview Parkway (SPS No. 2), Couchiching Point

(SPS No. 5), West Street South at Shannon Street (SPS No. 11), and Forest Avenue South (SPS

No. 16). Priority actions were outlined for each sewage pumping station drainage area, a work

plan was proposed for 2007, and an annual program to reduce inflow and infiltration was

recommended. Work completed to date includes:

Inspection of 1551 and rehabilitation of 156 maintenance holes;

Smoke testing of some areas of Franklin Street, Crawford Street, Hida Street, Oxford

Street, Delia Street, Bayview Parkway, and Forest Avenue;

Inspection and rehabilitation of some of the sanitary sewer laterals identified by smoke

testing.

West Street N

orth

Drive N

orth

Front Street

Colborne Street W

est

Coldwater Stre

et

Fittons Road East

Atherley Road

Highway 12H

ighw

ay 11

James Street East

West Street S

outh

Colborne

Memorial A

venue

Murphy Road

Uhthoff Line

SkylineH

ighw

ay 1

1

Mississaga Stre

et West

King Street

North Stre

et East

Goldie Dr

Queen St E

Lake CouchichingM

atchedash

St S

TudhopePark

Borland Street

Progress Drive

By-pass

Lake Simcoe

Road

Drive

Couchiching Pnt

Park Street

Brant Stre

et

Bayview

Parkw

ay

Mississaga Street E

ast

West

Ridge

Boulevard

Monarch Drive

JuliaC

rescent

Arthur S

treet

Woodside

Drive

Gill Street

Jarvis Street

Street E

ast

East

Forest Avenue

East S

treet

Brant Stre

etEast

West

Mem

orial

Avenue

Matchedash

Street N

orthLaclie

Street

Lac

lieS

tree

t

Peter S

treet North

Hilda

Street

Oxford Street

Hughes Road

Old Barrie Rd E

Stone Ridge Blvd

Harvie Settlem

ent Rd

Uni

vers

ity A

ve

James St W

Barrie Rd

Mis

siss

aga

St W

Victoria Cr

Line 15 N

Woodland D

r13

1619

11

21 19

22

23

9

20

58

17

16

2

1

11

10

4

3

13

P

P

P

1825

23

24

22 17

9 26

15

20

4

5

3

2

1

7

12

6

14 8

Westm

ount

Coldwater Road

Barri

e R

d

Fittons Road W

est

Legend

Sanitary Drainage Area Boundary

Sanitary Drainage Area Number

Sanitary Pumping Station (City)

Sanitary Pumping Station (Private)

12

17

Sanitary Sewers

P

Township of Severn

Township of Oro-Medonte

Wastewater Treatment Centre

Orillia City Limits

P

P

P

P

PP

P

3

Sanitary Pumping Station Zone Boundary

14

7

18

12

Pumping Zone Number17

13

9

18

23

19

2211 10

10

16

8

20

5

14

4

7

12

172

H:\E - Environmental Services\E01 - Sanitary Sewers\E01 MAS\WWMP 2012\Drawings\12WWMP5-2.dwgJan 24, 2013 - 11:51am

Sanitary Drainage Areas

TITLE:

PUBLIC WORKS DEPARTMENT

CITY of ORILLIA

THE CORPORATION OF THE

JAN. 24, 2013

JAN. 24, 2013

JC

WH

12WWMP5-2.DWG

450m

1:45000

SCALE

PLOTTED:

DATE:

APPROVED BY:

CHECKED BY:

DRAWN BY:

DESIGN BY:

ACAD FILE:

FIGURE:

N

S

W E

0 450 900m

Wastewater Master PlanCity of Orillia

Figure 5.2

5.2JC

PT

Page 37

5.3 CONDITION AND AGE OF EXISTING SEWERS

Current technology allows for the televising of underground piping to determine its condition.

Closed circuit television (CCTV) inspections of the existing sanitary sewer system have

continued to be completed annually since 1995. To date about 95% of the 163 km collection

system has been inspected. Each section of pipe televised is inspected and given an overall

condition index (OCI) rating. The OCI is a summary of the total frequency of deficiencies in a

section of sanitary pipe (between maintenance holes) with a weighting factor applied to amplify

the deficiencies that are more significant. The weighting factors applied for the various

deficiencies are as follows:

Collapse Light (4) Heavy (8)

Break Light (2) Heavy (4)

Crack Light (1) Heavy (2)

Infiltration Light (4) Heavy (8)

Roots Light (4) Heavy (8)

Ponding Light (1) Heavy (2)

Calcite Light (1) Heavy (2)

Based on the above criteria, the sanitary collection system condition was found to be as follows:

47.4% (77.2 km) in good condition (OCI between 0-25)

34.6% (56.5 km) are new or have been replaced over the past 30 years

1.8% (3.0 km) requires replacement within the next 3 years (OCI >90)

5.2% (8.5 km) requires replacement within the next 10 years (OCI between 45-90)

6.1% (10.0 km) requires replacement within the next 20 years (OCI between 25-45)

4.8% (7.9 km) require CCTV inspection

Figure 5-3 shows the sections of sewer requiring replacement based on the OCI number over the

next 20 years, as summarized in Table 5-2.

TABLE 5-2 SEWER REPLACEMENT OVER THE NEXT 20 YEARS

DIAMETER REPLACEMENT IN METRES

(mm) Within 3 years Within 10 years Within 20 years

200 2,138 4,363 4,355

225 895 736

250 572 1,484 2,671

300 158 589 438

350 75

375 111 347

525 436 173

600 82 365 714

675 32 133

750 229 231

900 99

TOTAL 2,950 8,504 9,972

Page 38

5.4 CAPACITIES OF EXISTING TRUNK SEWERS

Based on the results of the 2012 sanitary sewer computer simulation model runs on the existing

system, the trunk sewers generally appear capable of handling the peak flows generated by the

existing population and some infilling of the existing developed area. However, for future

projected flows, it does appear that trunk sewer capacity will be a problem in some locations,

depending on future development and where the wastewater is discharged into the existing trunk

sewers. A detailed analysis can be found in the 2012 computer model update report in Appendix

G. The Original Document indicated a 2003 study which identified that the CNR trunk sewer

capacity needs to be increased from south of maintenance hole #60 to accommodate future

flows. The 2012 computer model analysis also identified this need – in particular between

maintenance holes #35 and #30. Also identified for needed capacity increase by the computer

model, was a section of the trunk sewer along Fittons Road East between maintenance holes

#1346 and #1344.

5.5 CAPACITIES OF EXISTING SEWAGE PUMP STATIONS

The 2012 Hydra computer model shows that all twenty (20) existing sewage pumping stations

(SPS) are capable of handling peak flows generated by the existing population. However, SPS 10

Victoria Crescent was found to require upgrading to accommodate future flows in the Victoria

Point area.

5.6 CAPACITY OF EXISTING WASTEWATER TREATMENT CENTRE

Based on its most recent Environmental Compliance Approval, the WWTC is currently sized to

accommodate an average day flow of 27,300 m3/d and a process peak flow of 72,700 m

3/d.

Hydraulically, the plant is capable of accepting flows up to 109,000 m3/d, which is the current

peak capacity of the James Street Pumping Station. However, flows in excess of 72,700 m3/d

would by-pass the secondary treatment process units and discharge to Ben’s Ditch following

primary treatment and disinfection.

At present, the plant is operating below its capacity, and within the Environmental Compliance

Approval effluent compliance requirements of BOD5 (biochemical oxygen demand) ≤ 15 mg/L,

TSS (total suspended solids) ≤ 15 mg/L, and TP (total phosphorus) ≤ 0.3 mg/L (less than 2,993

kg/year).

The WWTC was designed to the latest MOE standards and hence it is anticipated that the plant

will continue to perform within its required limits once it reaches capacity. Therefore, the

WWTC has sufficient capacity to accommodate growth to beyond the horizon of this update

report of 2042, as show in Figure 5-4. However, the projected flows and the need for future

capacity expansion will be reviewed when this Master Plan is updated in about 5 years’ time.

The Original Document also noted that, as extraneous flows into the collection system continue

to decline, BOD5, TSS, TP and ammonia concentrations in the raw sewage will increase, and

could conceivably present operational difficulties as the plant nears its hydraulic capacity.

However it was also noted that, in general, the plant is hydraulically and not organically limited

in capacity and can therefore accommodate design flows with higher influent concentrations. In

Lake Couchiching

Lake Simcoe

19

22

23

9

20

58

17

16

2

1

11

10

14

4

3

7

18

12

13

P P

Legend

Sanitary Pumping Station (City)

Sanitary Pumping Station (Private)

12

Sanitary Sewers

P

Township of Severn

Township of Oro-Medonte

P

Wastewater Treatment Centre

Replacement 2013 To 2015 - OCI* > 90

Replacement 2016 To 2022 - OCI* 46 To 90

Replacement 2023 To 2032 - OCI* 25 To 45

Existing High Inflow/Infiltration Area

*OCI - Overall Condition Index

Orillia City Limits

P

P

P

P

PP

P

West Street N

orth

Drive N

orth

Front Street

Colborne Street W

est

Coldwater Stre

et

Fittons Road East

Atherley Road

Highway 12H

ighw

ay 11

James Street East

West Street S

outh

Colborne

Memorial A

venue

Murphy Road

Uhthoff Line Skyline

Hig

hway

11

Mississaga Stre

et West

King Street

North Stre

et East

Goldie Dr

Queen St EM

atchedash

St S

TudhopePark

Borland Street

Progress Drive

By-pass

Road

Drive

Couchiching Pnt

Park Street

Brant Stre

et

Bayview

Parkw

ay

Mississaga Street E

ast

West

Ridge

Boulevard

Monarch Drive

JuliaC

rescent

Arthur S

treet

Woodside

Drive

Gill Street

Jarvis Street

Street E

ast

East

Forest Avenue

East S

treet

Brant Stre

et East

West

Mem

orial

Avenue

Matchedash

Street N

orthLaclie

Street

Lac

lieS

tree

t

Peter S

treet North

Hilda

Street

Oxford Street

Hughes Road

Old Barrie Rd E

Stone Ridge Blvd

Harvie Settlem

ent RdUni

vers

ity A

ve James St W

Barrie Rd

Mis

siss

aga

St W

Victoria Cr

Line 15 N

Woodland D

r

Westm

ount

Coldwater Road

Barri

e R

d

Fittons Road W

est

Hig

hway

11

H:\E - Environmental Services\E01 - Sanitary Sewers\E01 MAS\WWMP 2012\Drawings\12WWMP5-3.dwgJan 24, 2013 - 11:47am

TITLE

PUBLIC WORKS DEPARTMENT

CITY of ORILLIA

THE CORPORATION OF THE

JAN. 24, 2013

JAN. 24, 2013

JC

WH

12WWMP5-3.DWG

450m

1:45000

SCALE

PLOTTED:

DATE:

APPROVED BY:

CHECKED BY:

DRAWN BY:

DESIGN BY:

ACAD FILE:

N

S

W E

0 450 900m

Sewer Replacement OverNext 20 Years

Wastewater Master PlanCity of Orillia

Figure 5.3

5.3JC

PT

Page 39

addition, it was noted that the Municipal and Industrial Strategy for Abatement (MISA) program

requires that industries in Orillia pre-treat their wastewater, thereby reducing industrial

wastewater concentrations discharged to the environment.

0

5,000

10,000

15,000

20,000

25,000

30,000

20

05

20

06

20

07

20

08

20

09

20

10

20

11

5 Y

ea

r A

ve

rag

e

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28

20

29

20

30

20

31

20

32

20

33

20

34

20

35

20

36

20

37

20

38

20

39

20

40

20

41

20

42

DE

SIG

N F

LO

WS

in c

u.m

.

YEAR

Figure 5-4PROJECTED WASTEWATER FLOWS

PROJECTED GROWTH EXISTING WWTC CAPACITY 27,300 cu.m.

5.7 QUANTITY AND QUALITY OF SEPTAGE RECEIVED AT THE WWTC

Septage from sources such as private sewage treatment systems servicing holiday resorts and

camps, portable toilets and recreational vehicles is removed by private haulers using tanker

trucks, and used to be brought to the WWTC for treatment and disposal. It is now brought to the

septage and hauled sewage receiving station located at the James Street West SPS. In 2003 about

11,000 m3 of septage was received at the WWTC, and in 2011 about 20,000 m

3 was received at

the new septage receiving station. The Original Document anticipated an increase in the quantity

of septage received due to the banning of land application of untreated septage by the Ontario

MOE. The quantity of septage received amounts to approximately 0.3% of total wastewater

flows to the WWTC and is not anticipated to have a significant impact on future capacity.

The Original Document also raised concerns with the quality of septage being received. It was

suspected that the presence of rags and other extraneous matter in various components of the

WWTC, associated with certain operational problems, were from the septage received at the

WWTC. The construction of the septage receiving facility at the James Street SPS in 2006 has

addressed these problems. In addition, BOD and TSS concentrations of septage being brought in

were found to be significantly higher than average raw sewage concentrations.

Page 40

5.8 BIOSOLIDS MANAGEMENT

The WWTC continues to have adequate biosolids digestion and storage capacity for the existing

population, but will be stressed when the plant exceeds its rated hydraulic capacity. Odour

complaints about the biosolids storage lagoons continue to be addressed by contract with a

private biosolids hauling company, who haul the biosolids off-site from the lagoons to MOE-

approved locations for land application.

The Ontario Nutrient Management Act restricts land application of biosolids such that:

Land application of sewage biosolids from December 1st

to March 31st is banned; and

Sewage biosolids application where the soil is snow covered or frozen is banned entirely.

The Original Document identified that adequate biosolids storage facilities will be required due

to land application restrictions. It may not be economically feasible for the City to continue to

manage its treated biosolids as it does today, and other sustainable biosolids management

alternatives may have to be investigated in the future.

5.9 OPERATIONAL ISSUES WITH THE UNIT PROCESSES AND OPERATIONS

AT THE WWTC

The Original Document identified several operational issues with the unit processes and

operations at the WWTC. These included issues with: grit removal and screening process,

receiving of hauled sewage at the WWTC, primary treatment equipment, and operation of the

digesters. Several projects have been undertaken to address these issues, and these are outlined in

Section 8.0. Current operational issues at the WWTC have also been identified.

The two manually raked bar screens in the WWTC Primary Building require raking and removal

of debris twice a day. Following weekends, debris has often completely filled the screens and

unscreened sewage bypasses directly to the primary clarifiers. This puts downstream equipment

at risk of damage or failure. Long weekends or high-flow events require operators to be made

available to attend to the manual screens to avoid overflows.

The total capacity of the lagoons is diminishing with time due to settling of solids. In addition,

one of the lagoons is suspected of leakage and is therefore not used. This reduces the available

capacity by about 36%. Cleaning out of the lagoons and rehabilitation of their lining would

restore capacity and lining integrity.

Monitoring and control of most sewage pumping stations is achieved via the SCADA system at

the WWTC and via radio frequency (RF) communication between the pumping stations and

WWTC. However, not all stations are equipped with RF capability or full SCADA capability.

For some stations, monitoring can only be completed by visiting the station on a regular basis.

For other stations, monitoring and control is not as reliable as it should be, and periodic visits to

the station are sometimes necessary.

Page 41

5.10 TREATED EFFLUENT DISCHARGE QUALITY STANDARDS

The WWTC discharges its effluent via Ben's Ditch into the north end of Lake Simcoe which,

through Lake Couchiching and the Severn River, ultimately feeds Severn Sound and the Midland

Harbour. The MOE considers Lake Simcoe to be excessively rich in nutrients. As well, the

Midland Harbour and Severn Sound have been designated by the International Joint Commission

as one of 42 Areas of Concern on the Great Lakes system. Therefore, the Original Document

speculated that the MOE would likely require any expansion in treatment capacity to be

accompanied by an upgrading of the treatment processes, to ensure that the environmental

impacts are mitigated as much as possible.

In particular, the Original Document anticipated that a future expansion of the Orillia WWTC

capacity may require more comprehensive treatment for enhanced phosphorus removal and,

possibly, ammonia and chlorine removal. This was based on the latest approved expansion

proposals for the Innisfil, Barrie, and Midland Water Pollution Control Plants. Since that time

the Lake Simcoe Protection Act has come into effect resulting in new phosphorus compliance

limits for the Orillia WWTC by June 2015. In order to meet this deadline, the City has

undertaken a project to add tertiary treatment to the WWTC.

The Original Document noted that for the time period 1991 to 2003, the annual average

phosphorus concentration in the treated effluent was 0.16 mg/L and the average annual flow was

5,873,435 m3/yr, or a Total Phosphorus (TP) load to Lake Simcoe of 0.94 tonnes per year on

average. For the time period 2004 to 2011, the average annual phosphorus concentration has

remained at 0.16 mg/L and the average annual flow is slightly higher at 6,308,934 m3/yr, giving

an average TP load of 1.01 tonnes per year. Projected wastewater flows have been reduced to

about 27,000 m3/d which translates into a TP load of 1.58 tonnes per year based on an average

phosphorus concentration of 0.16 mg/L. However, the current ECA indicates that the Orillia

WWTC will be required to meet phosphorus limits of 0.1 mg/L and 996 kg/yr as of June 2015.

PHASE 2: ALTERNATIVE SOLUTIONS

Page 43

6.0 ALTERNATIVE SOLUTIONS

The Original Document identified the following alternatives to be considered as possible

solutions to address the wastewater system problems in Orillia:

6.1 GENERAL ALTERNATIVE SOLUTIONS

Do Nothing – Limit Community Growth

Based on existing flows, the WWTC is at approximately 62% capacity and is currently not

expected to reach its capacity in the next 30 years or at ultimate development. However,

wastewater collection system limitations would still require development in Orillia to be

curtailed if the “do nothing” solution was adopted.

6.2 ALTERNATIVE SOLUTIONS FOR WASTEWATER COLLECTION

Identify Zones and Reduce High Inflow and Infiltration. Upgrade/Extend Existing System

to Accommodate Development

This alternative included:

Identifying and reducing areas of high inflow and infiltration to reduce excess flow and

free up capacity in the wastewater collection system to postpone the need for expansion.

Upgrading of the existing system to eliminate bottlenecks and replacement of some major

trunk sewers with larger capacity pipes.

Extension of the collection system to service West Orillia and Victoria Point.

An updated preliminary estimate suggests approximately $18 to $22 million would be required.

Identify Zones and Reduce High Inflow and Infiltration. Provide Independent System for

West Orillia and Victoria Point

This alternative included:

Identifying and reducing areas of high inflow and infiltration to reduce excess flow and

free up capacity in the wastewater collection system to postpone the need for expansion.

Upgrading of the existing system to eliminate bottlenecks and replacement of some major

trunk sewers with larger capacity pipes.

Constructing completely independent wastewater collection systems for West Orillia and

Victoria Point.

An updated preliminary estimate suggests approximately $19 to $23 million would be required.

6.3 ALTERNATIVE SOLUTIONS FOR WASTEWATER TREATMENT

Expand Capacity of Existing Plant

Expansion of the existing plant is likely the most cost effective means of providing additional

treatment capacity. Land acquisition would not be necessary as there is ample land available at

the existing site, located in a non-residential area.

Page 44

The additional volume of effluent associated with an expansion of the existing capacity would

likely require upgrading the treatment capability, and possibly an outfall directly into Lake

Simcoe (or Lake Couchiching) for the expanded plant, rather than to Lake Simcoe via Ben’s

Ditch.

Prior to an expansion of the WWTC, an optimization study should be undertaken to ensure that

the plant is operating at its maximum possible efficiency. In addition, a sludge management

study should be undertaken to identify the best means to treat, store and dispose of sludge

generated at the WWTC.

An updated preliminary estimate suggests approximately $65 to $75 million would be required.

Provide Individual Private Treatment Systems for New Properties

The majority of existing households, industries, and commercial establishments in Orillia are

currently connected to the municipal wastewater collection system. It is very unlikely that

development in Orillia would be permitted based on sanitary servicing by septic systems.

Applications for development approval based on septic systems would be subject to area specific

policy provisions in the City’s Official Plan and Zoning By-Law.

As a general rule, MOE prefers development to occur in areas serviced by communal wastewater

collection and treatment systems. The use of septic systems can lead to contamination of aquifers

and is generally discouraged. Developments serviced by septic systems in conjunction with the

under-utilization of existing municipal systems is not encouraged. Appendix H contains a copy

of the MOE Guidelines on Planning for Sewage and Water Services which documents the

Ministry’s position on development serviced by septic systems.

It is noted that there would be no capital cost to the City for this alternative, as the entire cost

would be borne by the owners.

Provide Independent Communal Treatment Systems for Victoria Point and for West

Orillia Lands

This alternative would involve construction of two new treatment facilities to accommodate

wastewater flows generated from existing and new development in Victoria Point and West

Orillia. Considerable land acquisition and/or easements would be required, and this alternative

would be considerably less cost-effective than expanding the treatment capacity on the existing

site. An updated preliminary estimate suggests approximately $75 to $90 million would be

required.

Provide a New Treatment Facility for the Whole City

This alternative would involve: decommissioning of the current sewage treatment facility,

identifying an appropriate new site, and construction of a new facility to accommodate flows

from all existing and new development. An updated preliminary estimate suggests approximately

$100 to $125 million would be required.

Page 45

Install a New Treatment Facility, Employ a Large Pipeline to Interconnect the Sewage

Systems of Orillia and Neighbouring Municipalities, and Discharge Treated Effluent to a

Large Water Body

This alternative would involve: identifying a site, construction of a new treatment facility to

service Orillia and other municipalities, construction of pumping stations and large dual

transmission pipes, and construction of dual “feeder” mains from Orillia to the transmission

pipes. An updated preliminary estimate suggests that in excess of $0.8 billion would be required.

6.4 ALTERNATIVE SOLUTIONS FOR BIOSOLIDS MANAGEMENT

Continue/Expand Application of Digested Sludge (Biosolids) to Agricultural Land

This alternative would involve:

Identifying new agricultural land for biosolids application;

Improving the storage capacity of the lagoons;

Increasing the digester capacity.

An updated preliminary estimate suggests approximately $3 to $4 million would be required.

Dispose of De-watered Sludge to Waste Diversion Site

This alternative would involve:

Construction of dewatering equipment;

MOE approval to use the City Waste Diversion Site.

An updated preliminary estimate suggests approximately $3 to $4 million would be required.

Thermally Process/Incinerate Sludge

This alternative would involve construction of a modern incinerator. An updated preliminary

estimate suggests approximately $15 to $20 million would be required.

Convert Sludge to Pellets for Use as Soil Conditioner and/or Fuel

This alternative would involve construction of dewatering equipment, furnaces/kilns and

dryer/pelletizer. An updated preliminary estimate suggests approximately $4 to $6 million would

be required.

6.5 ALTERNATIVE SOLUTIONS FOR EFFLUENT DISPOSAL

Partially Utilize Treated Sewage Effluent for Landscape Irrigation

This alternative would involve:

Irrigation of parks, golf courses and playing fields with treated sewage effluent;

Construction of effluent storage lagoons;

Construction of irrigation systems where needed.

An updated preliminary estimate suggests approximately $4 to $6 million would be required.

Page 46

Provide Tertiary and Advanced Treatment Processes to Produce High Quality Effluent

This alternative includes the upgrade to UV disinfection at the WWTC, now complete, as well as

the Tertiary Treatment upgrade project currently underway. Estimated costs to complete the

Tertiary Treatment upgrade project is $15 million.

Detailed descriptions as well as advantages and disadvantages considered for these alternative

solutions can be found in Section 6.0 of the Original Document.

These alternatives have been reviewed and were found to be adequate, therefore no new

alternatives were addressed.

Page 47

7.0 ASSESSMENT OF ALTERNATIVES

Based on public consultation, the Original Document indicated that the preferred alternatives

should accomplish the following goals and objectives:

Further growth within the City of Orillia service area;

No increase in nutrient loading into Lake Simcoe or Lake Couchiching over existing

limits;

Minimize capital, operating, and maintenance costs;

Continue to allow for the simplified management of the wastewater system by a

single operating authority;

Have little, if any, impact on the environment.

An inventory of the environmental effects and socio-economic impacts of each alternative was

used to assess and select the preferred solutions. This inventory is contained in Appendix B of

the Original Document.

7.1 ASSESSMENT OF GENERAL ALTERNATIVES

The Original Document noted that the “Do Nothing” alternative would not meet the expressed

goals and objectives, as the current programs could not be expected to reduce wastewater flows

to the extent required.

7.2 ASSESSMENT OF COLLECTION SYSTEM ALTERNATIVES

Based on analysis completed in earlier sections and computer modelling completed, the Original

Document identified the following wastewater collection system alternative as one that would

satisfy the expressed goals and objectives and therefore warranted further consideration:

Identify Zones and Reduce High Inflow and Infiltration. Upgrade/Extend Existing

System to Accommodate Development

The second collection system alternative was eliminated from consideration. Since that time

work has proceeded to extend the existing system to the West Orillia and Victoria Point areas,

including construction of the new Champlain Sewage Pumping Station in West Orillia.

7.3 ASSESSMENT OF TREATMENT SYSTEM ALTERNATIVES

Based on the foregoing, the Original Document identified that the only wastewater treatment

alternative that warranted further consideration and that would accomplish the expressed goals

and objectives is:

Expand Capacity of Existing Plant

The other four treatment system alternatives were eliminated from further consideration. It is

noted that current wastewater flow projections are not anticipated to reach plant capacity until

beyond the horizon of this update report of 2042.

Page 48

7.4 ASSESSMENT OF BIOSOLIDS MANAGEMENT ALTERNATIVES

Based on analysis completed in earlier sections, the Original Document identified two out of four

biosolids management alternatives that warranted further consideration and that would

accomplish the expressed goals and objectives:

Continue/Expand Application of Digested Sludge (Biosolids) to Agricultural Land

Dispose of De-watered Sludge to Waste Diversion Site

The other two alternatives were eliminated from further consideration for reasons that included:

high capital costs, large public opposition, and ongoing operational costs.

7.5 ASSESSMENT OF EFFLUENT DISPOSAL ALTERNATIVES

The Original Document identified one effluent management alternative that warranted further

consideration and that would accomplish the expressed goals and objectives:

Provide Tertiary and Advanced Treatment Processes to Produce High Quality

Effluent

The other alternative was eliminated from further consideration as minimal use of landscape

irrigation within the City made this alternative unfeasible.

The alternatives warranting further consideration are examined in detail in the next Section.

Page 49

8.0 SELECTION OF PREFERRED ALTERNATIVES

The following alternatives were selected as the preferred solutions in the Original Document:

Wastewater Collection

Identify Zones and Reduce High Inflow and Infiltration. Upgrade/Extend Existing

System to Accommodate Development

Wastewater Treatment

Expand Capacity of Existing Plant

Biosolids Management

Continue/Expand Application of Digested Sludge (Biosolids) to Agricultural

Land

Dispose of De-watered Sludge to Waste Diversion Site

Effluent Disposal

Provide Tertiary and Advanced Treatment Processes to Produce High Quality

Effluent

In general, the preferred alternatives have been or are in the process of being implemented. Due

to slower projected growth rates, expansion of the plant capacity can be deferred significantly.

While the application of biosolids to agricultural land is now more tightly regulated under the

Nutrient Management Act, the practice continues to be permitted. On average about 29,000 m3

of biosolids are applied to MOE approved sites at an annual cost of $265,000.

Since 2004 the following projects have been completed or are underway, and which continue to

provide more information to evaluate the preferred alternatives identified in the Original

Document:

Wastewater Collection System Projects:

CNR Trunk Sewer Upgrades

o Two projects were completed – one in 2004 and one in 2006 – to upgrade a

portion of the CNR trunk sewer from Colborne Street north to Mississaga Street.

Larger diameter pipe was installed in order to accommodate future wastewater

flows.

James Street Sewage Pumping Station Screening System with Grinder, Auger and

Conveyor

o Existing mechanical bar screening equipment and grinder were replaced with two

new channel grinding units, to address downstream problems associated with rags

and other extraneous matter escaping the screens. This project included:

modification of the concrete and floor grating, installation of hoists for removing

Page 50

the units from the channel for service and repair, and instrumentation and control

linked to the existing SCADA system. This project was completed in 2005.

Standby Power for James Street Sewage Pumping Station

o Installation of a new standby diesel generator in 2009 to provide emergency

power for the entire James Street West SPS and avoid problems that may occur

during a prolonged power outage. Removal of the existing diesel standby engine

for pump #2 was also completed.

Rehabilitation of Sewage Pumping Stations

o Champlain SPS #23. A permanent Champlain SPS was built in 2010/2011 to

accommodate new development in West Orillia. This station is a dry well / wet

well type pumping station and has three submersible dry pit installed sewage

pumps, a channel grinder unit and by-pass manual bar screen, and a standby

diesel generator. The station discharges to Maintenance Hole 1600 at the end of

Woodside Drive via twin 150 mm and 300 mm force mains that are 500 m long.

o Bayview Parkway SPS #2. The pumps were replaced with new in 2006 and the

standby generator and electrical controls were replaced in 2008.

o Couchiching Point SPS #5. This station was replaced in 2007 with a new Flygt

submersible station with two model NP3127 pumps, new above ground

electrical/control cabinet, radio communication capability with the WWTC, and

receptacle for portable generator connection.

o Bridget/Maple SPS #13. This station was converted to a submersible station in

2009 with two Flygt NP3153HT pumps, new above ground electrical/control

cabinet, and receptacle for portable generator connection.

o Fittons Road West SPS #18. In 2012 this SPS is being upgraded with a new

SCADA-enabled PLC control panel, three new variable frequency drives, reactors

and motors, ultrasonic level monitoring, and Radio Frequency communication

with the WWTC.

o John Street SPS #19. In 2013 this station is to be converted to a submersible

station with two Flygt CP3201HT pumps, new above ground electrical/control

cabinet, radio communication capability with the WWTC, and receptacle for

portable generator connection.

West Orillia Sewage Servicing

o A Routing Study was completed in 2005 to determine the best possible solution

for servicing new development in West Orillia. A revised Routing Study was

completed in 2008 due to concerns raised during the earlier work, changes in land

availability, and the inclusion of service area to the East of Highway 11.

An Evaluation of Nutrients and Chemical Pollutants in Sanitary Sewer System

Wastewater Treatment Projects:

WWTC Primary Clarifier Upgrades and Waste Activated Sludge (WAS) Thickening

o Primary clarifiers #1 & #2 failed in 1999 and 1996 respectively. In 2004/2005

clarifier #1 was filled and #2 was converted to an equalization tank for a new

dissolved air flotation (DAF) unit. The DAF unit is designed to a feed flow rate of

88 – 200 m3/d, with a pressurization system designed for a flow rate of 545 m

3/d.

Waste Activated Sludges are redirected to the DAF unit instead of the primary

clarifiers, where they are thickened and pumped to the primary digester. Primary

clarifier #3 was retrofitted to a round clarifier 18.3 m diameter after being taken

Page 51

out of service in the spring of 2003. This retrofit included benching of corners and

installation of a new 18.3 m Cage Drive Scraper Clarifier Mechanism.

Septage/Hauled Sewage Receiving Facility at James Street Sewage Pumping Station

o A 90 m3/hr septage and hauled sewage receiving station was constructed at the

James Street West SPS in 2006 to eliminate problems associated with receiving

septage at the WWTC. This system has a peak flow capacity of 90 m3/hour and

discharges to the pumping station inlet channel through a 250 mm outlet pipe,

equipped with a knife gate valve. A second 250 mm knife gate valve and blind

flanged pipe was provided for connection to a future equalization tank. Electronic

monitoring and control through a PLC is connected to the existing SCADA at the

Wastewater Treatment Centre via Ethernet.

WWTC Boiler Control Panel

o A project was undertaken to optimize the operation of the dual gas boiler system

at the Wastewater Treatment Centre in 2005/2006. This involved troubleshooting

the existing boiler, checking all settings, evaluating performance and determining

SCADA control and monitoring for the system. Flow meters were installed on the

gas train and pressure switch settings optimized.

Standby Power and Electrical Upgrades for WWTC

o A new 800kW/1000kVA standby generator was installed on a concrete pad along

the western perimeter of the WWTC property in 2010/2011, adjacent to an

existing 44 kV hydro transformer substation. This unit was sized to run the entire

plant during power outages and interruptions and is controlled and monitored

through the SCADA system.

WWTC Process Optimization and Tertiary Treatment for Nutrient Removal

o A process optimization study has been completed and design is proceeding for a

tertiary treatment upgrade for nutrient removal (phosphorus). The upgrade will

include replacement of the existing aeration blower building and construction of a

secondary effluent pumping station in the old chlorination building. Pre-selection

of major equipment is complete, detailed design is underway and construction is

anticipated to commence in 2013.

UV Disinfection of WWTC Effluent

o Implementation of an ultraviolet disinfection system was initiated in 2007/2008 to

comply with Environment Canada’s December 2004 Final Notice requiring

implementation of a pollution prevention plan for wastewater systems where

chlorine residual in the effluent exceeded 0.02 mg/L. The UV system was

provided with an operator interface for control and monitoring, and is pace

controlled based on contact chamber weir flow. The system is monitored by the

existing PLC in the Chlorine Building basement and data is transmitted over a

new Fibre Optic/Ethernet Cabling network to the SCADA system located in the

Administration Building.

Nutrient Management Strategy for WWTC

o A Nutrient Management Strategy (NMS) was prepared for the Orillia WWTC in

2009 according to the Ontario Ministry of Agriculture, Food, and Rural Affairs

(OMAFRA) NMS report template. It is noted that the NMS report was not

submitted to the Ministry, due to regulation changes that occurred during its

preparation.

Page 52

9.0 PUBLIC AND REVIEW AGENCY COMMENTS An extensive public and review agency consultation process was followed during the preparation of the Original Document, summarized as follows:

Newspaper notification of initiation of the project along with notification by correspondence to the applicable government review agencies, adjoining municipalities and various other organizations in September 2003.

Newspaper notification and correspondence to review agencies in February 2004 regarding the initial Public Information Open House.

Initial Public Information Open House held on February 26, 2004.

Newspaper notification and correspondence to review agencies in September 2004 regarding the second Public Information Open House.

Second Public Information Open House held on September 30, 2004.

Newspaper notification of Notice of Completion of project in December 2004.

Completed questionnaires and responses from the two Open Houses as well as other miscellaneous correspondence received and responded to from concerned review agencies and member of the public

Contained in the Original Document are: a detailed description of the public and review agency consultation process (Section 9.0), and copies of all documentation received and distributed (Appendix I). Public notification for the 2012 Master Plan Update consisted of:

Publication of a “Public Comment Invited” notice in the Orillia Packet and Times on December 22nd, 2011 and January 5th, 2012 and on the City website.

Publication of a “Notice of Completion” in the Orillia Packet and Times on January 31st, 2013 and February 7th, 2013 and on the City website.

Copies of the notices are included in Appendix A along with correspondence distributed and received.

Page 53

10.0 GENERAL SUMMARY AND REQUIREMENTS

10.1 PROPOSED SERVICE AREA

The proposed service area for ultimate development is defined by the existing municipal

boundary, as shown in Figure 3-1. A broad consideration has been given to the possibility of

adjacent communities connecting into the system.

10.2 PROPOSED WASTEWATER COLLECTION SYSTEM

The proposed wastewater collection system expansion over the next 20 years is summarized as

follows:

1. Replace existing trunk sewers with larger pipes at the locations shown on Figure 10-1.

2. Upgrade Victoria Crescent SPS #10 to accommodate future development, as shown on

Figure 10-1.

3. Provide new trunk sewers and pumping stations throughout West Orillia, locations and

sizes to be determined as required by development.

4. Expand the existing wastewater collection system to service the Inch development,

locations and sizes to be determined as required by development.

10.3 PROPOSED WASTEWATER TREATMENT SYSTEM

There are no wastewater treatment system expansions proposed over the next 20 years.

10.4 PROPERTY REQUIREMENTS

The Original Document recommended that developers provide land for utility requirements. It

has been established as routine procedure in all agreements for the developer to provide

easements, right-of-ways and road widenings as required for pumping stations, forcemains, trunk

sewers, etc.

10.5 ENVIRONMENTAL IMPACTS

The various projects will have a measureable positive impact on the environment relative to the

current situation. The environmental benefits of the projects are summarized as follows:

Positive Impacts:

1. Accommodate new and existing development in Orillia.

2. Reduce hydraulic limitations.

3. Positive socio-economic impact on the Orillia population.

W

e

s

t

S

t

r

e

e

t

N

o

r

t

h

D

r

i

v

e

N

o

r

t

h

F

r

o

n

t

S

t

r

e

e

t

C

o

l

b

o

r

n

e

S

t

r

e

e

t

W

e

s

t

C

o

l

d

w

a

t

e

r

S

t

r

e

e

t

F

i

t

t

o

n

s

R

o

a

d

E

a

s

t

Ath

erley R

oad

Hig

hway 1

2

H

ighw

ay 11

J

a

m

e

s

S

t

r

e

e

t

E

a

s

t

W

e

s

t

S

t

r

e

e

t

S

o

u

t

h

C

o

l

b

o

r

n

e

M

e

m

o

r

i

a

l

A

v

e

n

u

e

M

u

r

p

h

y

R

o

a

d

U

h

t

h

o

f

f

L

i

n

e

S

k

y

l

i

n

e

H

ig

h

w

a

y 1

1

M

i

s

s

i

s

s

a

g

a

S

t

r

e

e

t

W

e

s

t

K

i

n

g

S

t

r

e

e

t

N

o

r

t

h

S

t

r

e

e

t

E

a

s

t

G

o

l

d

i

e

D

r

Q

u

e

e

n

S

t

E

Lake Couchiching

M

a

t

c

h

e

d

a

s

h

S

t

S

Tudhope

Park

B

o

r

l

a

n

d

S

t

r

e

e

t

P

r

o

g

r

e

s

s

D

r

i

v

e

B

y

-p

a

s

s

Lake Simcoe

R

o

a

d

D

r

i

v

e

C

o

u

c

h

i

c

h

i

n

g

P

n

t

P

a

r

k

S

t

r

e

e

t

B

r

a

n

t

S

t

r

e

e

t

B

a

y

v

i

e

w

P

a

r

k

w

a

y

M

i

s

s

i

s

s

a

g

a

S

t

r

e

e

t

E

a

s

t

West

R

id

g

e

B

o

u

l

e

v

a

r

d

M

o

n

a

r

c

h

D

r

i

v

e

J

u

l

i

a

C

rescent

A

r

t

h

u

r

S

t

r

e

e

t

W

o

o

d

s

i

d

e

D

r

i

v

e

G

i

l

l

S

t

r

e

e

t

J

a

r

v

i

s

S

t

r

e

e

t

S

t

r

e

e

t

E

a

s

t

E

a

s

t

F

o

r

e

s

t

A

v

e

n

u

e

E

a

s

t

S

t

r

e

e

t

B

r

a

n

t

S

t

r

e

e

t

E

a

s

t

W

e

s

t

M

e

m

o

r

i

a

l

A

v

e

n

u

e

M

a

t

c

h

e

d

a

s

h

S

t

r

e

e

t

N

o

r

t

h

L

a

c

l

i

e

S

t

r

e

e

t

Laclie

Street

P

e

t

e

r

S

t

r

e

e

t

N

o

r

t

h

H

i

l

d

a

S

t

r

e

e

t

O

x

f

o

r

d

S

t

r

e

e

t

H

u

g

h

e

s

R

o

a

d

O

l

d

B

a

r

r

i

e

R

d

E

S

t

o

n

e

R

i

d

g

e

B

l

v

d

H

a

r

v

i

e

S

e

t

t

l

e

m

e

n

t

R

d

University A

ve

J

a

m

e

s

S

t

W

B

a

r

r

i

e

R

d

M

ississaga S

t W

V

i

c

t

o

r

i

a

C

r

L

i

n

e

1

5

N

W

o

o

d

l

a

n

d

D

r

19

22

23

9

20

5

8

17

16

2

1

11

10

14

4

3

7

18

12

13

P

P

W

e

s

t

m

o

u

n

t

Cold

wate

r R

oad

B

a

r

r

i

e

R

d

F

i

t

t

o

n

s

R

o

a

d

W

e

s

t

Legend

Sanitary Pumping Station (City)

Sanitary Pumping Station (Private)

Sanitary Sewers

P

Township of Severn

Township of Oro-Medonte

H

i

g

h

w

a

y

1

1

Future

Employment Area

Inch

Development

Area 3 Development

Severn Township

P

Requires

connection to

existing system.

Preferred routing

to be determined

through further

study

Wastewater Treatment Centre

Requires

connection to

existing system.

Preferred routing

to be determined

through further

study

Requires connection to

existing system.

Preferred routing to be

determined through

further study

Stone Ridge

Residential

Development

Future

Employment

Area

Proposed Area For Extension

Of Existing Service

10

SPS Identified As Requiring Upgrade

to Accommodate Future Flows

12

Requires Upgrade to

Accommodate Future Flow

Orillia City Limits

P

P

P

P

P

P

P

H:\E - Environmental Services\E01 - Sanitary Sewers\E01 MAS\WWMP 2012\Drawings\12WWMP10-1.dwg

Jan 30, 2013 - 11:30am

TITLE:

PUBLIC WORKS DEPARTMENT

CITY of ORILLIA

THE CORPORATION OF THE

JAN. 22, 2013

JAN. 22, 2013

JC

WH

12WWMP10-1.DWG

450m

1:45000

SCALE

PLOTTED:

DATE:

APPROVED BY:

CHECKED BY:

DRAWN BY:

DESIGN BY:

ACAD FILE:

FIGURE:

N

S

W E

0 450 900m

Proposed Future

Wastewater System

Expansion

Wastewater Master Plan

City of Orillia

Figure 10.1

10.1

JC

PT

Page 54

There are also two negative environmental impacts, namely:

Negative Impacts:

1. Create a temporary nuisance during construction.

2. Require property that could otherwise be used for other purposes.

It should be emphasized that the first negative impact would occur temporarily and during

construction only, and will no longer be applicable once the various works are completed.

Overall it is evident that the significant permanent environmental benefits greatly outweigh the

potential temporary nuisance during construction and any loss of land for new facilities.

10.6 ENVIRONMENTAL ASSESSMENT CATEGORIES OF PROPOSED PROJECTS

Planning for the 2012 Master Plan Update followed the Municipal Engineers Association Class

Environmental Assessment (2007) process, and thereby satisfied the Phase 1 and 2 requirements

with respect to public and agency notification and involvement. This means that all works

identified in the 2012 Master Plan Update are categorized as one of the following:

Schedule A/A+ and can now proceed to implementation without further public or agency

notification

Schedule B and require a Notice of Completion for each specific project

Schedule C and would require completion of Phases 3, 4 and 5 as well as additional

public contact and completion of an Environmental Study Report. Only the expansion of

the Wastewater Treatment Centre would be a Schedule C project.

Page 55

11.0 RECOMMENDATIONS

11.1 GENERAL

The following is a detailed description of recommended wastewater collection and treatment

projects, including their rationale, to be carried out by the City over the next 20 years to

accommodate ultimate development. The recommended projects also include programs to reduce

extraneous flows, studies to improve monitoring, efficiency, reliability, etc., and allowances for

major rehabilitation works to preserve the integrity of the existing system.

The recommended projects are an evolution of the works outlined in the Original Document.

Much of the work recommended in that document has now been completed, and has helped

further define requirements for future works.

11.1.1 WASTEWATER COLLECTION SYSTEM REHABILITATION

Continue with an annual program for the maintenance, rehabilitation and reconstruction of

sewers to accommodate wastewater flows. This work will include: spot repairs, replacement and

upsizing (as necessary) of sewers and rehabilitation of manholes. This work is required for

sections identified as having an OCI (Overall Condition Index) of greater than 25, as described in

Section 5.3. Over the next 20 years about 21.4 km of sewers (including trunks) have been

identified to be rehabilitated, which equates to approximately 1.1 km per year.

It is recommended that the wastewater collection system rehabilitation be carried out annually at

a cost of $825,000.

11.1.2 INFLOW AND INFILTRATION PROGRAM

Establish an annual program to complete system improvements to reduce inflow and infiltration

including: maintenance hole rehabilitation, service lateral rehabilitation, and disconnection of

roof leaders and footing drains, as well as to further define problem areas using tools such as

sewage pumping station flows, flo-totes and smoke testing. Flows to the WWTC are typically 30

to 40% higher than metered water consumption on average. Past study has identified areas with

high inflow and infiltration and work should continue to make system improvements in these

areas. Coordination of the inflow and infiltration program with the sanitary sewer rehabilitation

and roads rehabilitation programs should be a priority. This program will postpone the need for a

WWTC expansion and reduce the extent of expansion required.

It is recommended that the inflow and infiltration program be carried out annually at a cost of

$100,000.

11.1.3 WWTC IMPROVEMENTS AND OPTIMIZATION

Periodically, there are specific maintenance, equipment replacement and upgrading requirements

at the WWTC. Current required works include: upgrading to an automated screening system at

the WWTC Primary Building, cleaning out and lining rehabilitation of the lagoons and

upgrading communication and SCADA capabilities of sewage pumping stations that are lacking.

Page 56

In addition, funding should be available for regular plant improvements, including equipment

upgrading/replacement, that are beyond the scope of routine operation and maintenance.

It is recommended that an annual fund of $200,000 be allocated for WWTC improvements.

11.1.4 SEWAGE PUMPING STATION IMPROVEMENTS

The City’s sewage pumping stations require periodic upgrades and design review to ensure

reliability, improve control, remove health and safety hazards. Improvements are required in the

near future at the Broadview Avenue, Forest Avenue North, Fittons Road East and Commerce

Road sewage pumping stations. In addition, a review of design and refurbishment of the

remaining 16 stations will be required over the next 20 years.

The Broadview Avenue work is scheduled for 2013 at a cost of $330,000. It is recommended that

the work for the next three stations be completed in 2014 to 2016 at a cost of $400,000 per year.

It is also recommended to allocate $300,000 per annum starting in 2017 to refurbish one

pumping station annually.

11.1.5 STANDBY POWER FOR SEWAGE PUMPING STATIONS

Standby power for sewage pumping stations during a power outage is essential, as considerable

damage can be caused to residential homes by sewer backups. At present, the sewage pumping

stations at James Street, Bayview Parkway, Fittons Road West and the Champlain Industrial

Park are provided with permanent standby power. The remaining 16 pumping stations also

require access to standby power to assist with pumping during a prolonged power outage.

It is recommended that a portable trailer mounted generator be purchased in 2014 for the sewage

pumping stations without permanent standby power, at a cost of $150,000.

11.1.6 PUBLIC AWARENESS PROGRAM ON SEWAGE DISCHARGE

Establish a program to increase public awareness about the City’s wastewater system, including

such topics as: the City’s Sewage Discharge By-Law, inflow and infiltration, fats, oils and grease

from residential and commercial users, emptying swimming pools, flushing medications and

trash down toilets, and sanitary sewer discharge from industries. This campaign will help to

control the quantity and quality of discharge to the wastewater system and, ultimately, to Lake

Simcoe.

It is recommended that an annual fund of $20,000 be allocated for the public awareness program

on sewage discharge.

11.1.7 INCH SEWAGE PUMPING STATION AND FORCEMAIN

Construction of the Inch Sewage Pumping Station and associated forcemain to service the Inch

Development Area and possibly the adjacent Area 3 Development in Severn Township.

It is recommended that this work be completed in conjunction with development in about

2015/2016 at an estimated cost of $500,000 for each year.

Page 57

11.1.8 VICTORIA POINT AREA SERVICING

Extension of the existing wastewater collection system to service the remaining unserviced

portions of the Victoria Point area. This will include upgrades to the existing trunk sewer on

West Street South, new sewage pumping station and associated forcemain, and new gravity and

pressure sewers.

It is recommended that this work be completed in conjunction with development in about

2017/2018 at an estimated cost of $1,000,000 for each year.

11.1.9 CNR TRUNK SEWER UPGRADES AND REROUTING

Complete upgrades to the southern portion of the CNR trunk sewer to accommodate future

development and consider rerouting the portion of the sewer that passes through lands in the

downtown waterfront area. Necessary upgrades to the southern CNR trunk sewer are in conflict

with potential development plans in the downtown waterfront area. Relocation of the trunk sewer

to within existing road allowances will allow necessary upgrades to proceed.

It is recommended that relocation and upgrading of the southern portion of the CNR trunk sewer

be completed at an estimated cost of $600,000 in 2014, $400,000 in 2015 and $1,000,000 in each

of 2020 and 2021.

11.1.10 CHANGES TO JOHN STREET SEWAGE PUMPING STATION DRAINAGE

AREA

Complete sewer upgrades to allow wastewater from the John Street SPS no. 19 drainage area to

flow by gravity, thereby eliminating the need for this sewage pumping station.

It is recommended that changes to the John Street SPS drainage area be completed in about

2023/2024/2025 at an estimated cost of $500,000 for each year.

11.1.11 REALIGNMENT OF OLD HURONIA ROAD SEWER ALONG LACLIE

STREET

Replacement of the existing sewer that runs along a previous road allowance for Huronia Road

from Laclie Street to Hughes Road with a sewer that runs along Laclie Street to Hughes Road

would free up the land for sale and make a more useful block for redevelopment.

It is recommended that realignment of the old Huronia Road sewer along Laclie Street be

completed in 2019 at an estimated cost of $350,000.

11.1.12 WASTEWATER SYSTEM MASTER PLAN UPDATING

It is necessary for the Wastewater System Master Plan to be reviewed and updated for MOE

approval at least once every 5 years in order to meet the requirements of the Environmental

Assessment Act. It is noted that unless MOE approval is obtained once every five years the

environmental assessment process followed to date, including public and agency review of Phase

Page 58

1 and Phase 2 environmental assessment procedures, may no longer be valid and the City may be

required to start the process again. This could become very costly if a full environmental

assessment process is undertaken when implementing and constructing each of the projects

required or listed in the Schedule of Works.

It is recommended that the Master Plan be reviewed and updated, and MOE approval of its

continued validity be obtained, in 2017, 2022, 2027, and 2032 at an estimated cost of $30,000 in

each of those years.

11.1.13 WWTC TERTIARY TREATMENT UPGRADE

To protect the health of Lake Simcoe reductions of phosphorus inputs to the lake are required.

The City will need to complete the tertiary treatment upgrade at the WWTC by June 2, 2015 to

meet the requirements of the current Environmental Compliance Approval and the Lake Simcoe

Phosphorus Reduction Strategy. This project is in the final stages of design, and tendering is

anticipated to occur in 2013 with construction expected to be undertaken in 2013 to 2015.

It is recommended that the WWTC tertiary treatment upgrade be completed at a cost of $5

million in 2013 and 2014, and $4 million in 2015.

11.1.14 WWTC EXPANSION AND ENVIRONMENTAL ASSESSMENT

The WWTC is currently not projected to require expansion until beyond the horizon of this

update report of 2042. However, this will be reviewed at the next Master Plan update in 5 years’

time. Prior to an expansion the Phase 3 and 4 environmental assessment requirements will need

to be completed including preparation of an Environmental Study Report.

11.2 PROPOSED SCHEDULE OF WORKS AND COSTS

Table 11-1 presents the Schedule of Works and associated costs. All estimated costs are in 2012

dollars. Figure 11-1 on the following page illustrates the forecast costs for the next 20 years.

$0$1

,00

0$2

,00

0$3

,00

0$4

,00

0$5

,00

0$6

,00

0$7

,00

0$8

,00

0$9

,00

0$1

0,0

00

2012

2014

2016

2018

2020

2022

2024

2026

2028

2030

2032

Tho

usa

nd

s o

f $

YearFi

gure

11

-1Sc

he

du

le o

f Wo

rks

-Tw

enty

Yea

r Fo

reca

st

Was

tew

ater

Col

lect

ion

Syst

em R

ehab

ilita

tio

n

Infl

ow a

nd

Infi

ltra

tion

Pro

gram

WW

TC Im

pro

vem

ents

and

Opt

imiz

atio

n

Sew

age

Pum

ping

Sta

tion

Imp

rove

men

ts

Stan

dby

Pow

er f

or S

ewag

e Pu

mp

ing

Stat

ions

Publ

ic E

duca

tion

Pro

gram

Inch

Sew

age

Pum

pin

g St

atio

n an

d Fo

rcem

ain

Vic

tori

a Po

int

Are

a Se

rvic

ing

CN

R T

runk

Sew

er U

pgr

ades

/ R

erou

ting

Cha

nges

to

Joh

n St

reet

Sew

age

Pum

ping

Sta

tion

Dra

inag

e A

rea

Rea

lign

men

t of

Old

Hu

ron

ia R

oad

Sew

er a

lon

g La

clie

Str

eet

Was

tew

ater

Sys

tem

Mas

ter

Plan

Upd

atin

g

WW

TC T

erti

ary

Trea

tmen

t U

pgra

de

Cla

ss E

A

Sched

ule

20

122

013

20

142

015

20

162

017

20

182

019

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28

20

29

20

30

20

31

20

32

20

33

To

ta

l

11.1

.1A

$2

65

$2

65

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$8

25

$17

,03

0

11.1

.2A

$50

$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$10

0$2

,050

11.1

.3A

$18

$15

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$2

00

$4

,03

3

11.1

.4A

$3

75

$3

30

$4

00

$4

00

$4

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$3

00

$7,0

05

11.1

.5A

$15

0$15

0

11.1

.6A

$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$2

0$4

00

11.1

.7B

$50

0$50

0$1,

00

0

11.1

.8B

$1,

00

0$1,

00

0$2

,00

0

11.1

.9A

+$6

00

$4

00

$1,

00

0$1,

00

0$3

,00

0

11.1

.10

A+

$50

0$50

0$50

0$1,

50

0

11.1

.11

A+

$3

50

$3

50

11.1

.12

$3

0$3

0$3

0$3

0$12

0

11.1

.13

C$1,

00

0$5,0

00

$5,0

00

$4

,00

0$15

,00

0

11.1

.14

C$0

$1,

70

8$5,6

10$7,2

95

$6

,44

5$2

,04

5$2

,475

$2

,44

5$1,

79

5$2

,44

5$2

,44

5$1,

475

$1,

94

5$1,

94

5$1,

94

5$1,

44

5$1,

475

$1,

44

5$1,

44

5$1,

44

5$1,

44

5$1,

475

$1,

44

5$53

,63

8

Inch S

ew

age P

um

pin

g S

tation a

nd

Forc

em

ain

Vic

toria P

oin

t A

rea S

erv

icin

g

CN

R T

runk S

ew

er

Upgra

des /

Rero

uting

Changes to J

ohn S

treet S

ew

age

Pum

pin

g S

tation D

rain

age A

rea

TO

TA

L O

F W

OR

K A

NN

UA

LL

Y

Waste

wate

r S

yste

m M

aste

r Pla

n

Updating

Realig

nm

ent of

Old

Huro

nia

Road

Sew

er

alo

ng L

aclie

Str

eet

TA

BL

E 1

1-1

Waste

wate

r C

olle

ction S

yste

m

Rehabilita

tion

Inflow

and Infiltra

tion P

rogra

m

WW

TC

Im

pro

vem

ents

and

Optim

ization

TW

EN

TY

YEA

R F

OR

EC

AS

T (

in T

HO

US

AN

DS

of

$)

Pro

ject

Sta

ndby P

ow

er

for

Sew

age

Pum

pin

g S

tations

WW

TC

Tert

iary

Tre

atm

ent U

pgra

de

Sew

age P

um

pin

g S

tation

Impro

vem

ents

WW

TC

Expansio

n a

nd

Environm

enta

l A

ssessm

ent (N

ot

required u

ntil beyond 2

042)

Wa

ste

wa

ter

Sys

tem

Ma

ste

r P

lan

Sc

he

du

le o

f W

ork

s

Public

Education P

rogra

m

Page 61

REFERENCES

City of Orillia CNR Trunk Sewer System Future Capacity Study

City of Orillia, July 2003

City of Orillia Eliminating Inflow/Infiltration Implementation Program

City of Orillia, 2007

City of Orillia Inflow/Infiltration Status Report Past, Present & Future

City of Orillia, October 2005

City of Orillia Official Plan

City of Orillia, 2011

City of Orillia Sewage Pumping Stations Rehabilitation Status Report

City of Orillia, October 2005

City of Orillia Wastewater System Master Plan

City of Orillia, 2004

Lake Simcoe Phosphorus Reduction Strategy

Ontario Ministry of the Environment, June 2010

Municipal Class Environmental Assessment

Municipal Engineers Association, 2007

Places To Grow – Growth Plan for the Greater Golden Horseshoe

Ontario Ministry of Infrastructure, January 2012

APPENDIX A

TERMS OF REFERENCE FOR WASTEWATER SYSTEM MASTER PLAN

2012 UPDATE

Page 1

Wastewater System Master Plan 2012 Update

TERMS OF REFERENCE 1.0 Purpose

i) Review and update the 2004 Master Plan.

ii) Summarize progress made since the 2004 Master Plan was prepared. iii) Revise the projections and recommended works to reflect current information

and new legislation and regulations.

iv) Clearly identify the constraints and problems associated with the existing wastewater system and review alternative methods of rectifying these problems.

v) Re-establish a framework to specifically identify wastewater infrastructure

requirements to service population growth, new developments, and new service areas in the most cost effective and environmentally sensitive manner.

vi) Recommend, cost, phase, and schedule major works for future budgeting

and implementation, and identify an EA category for each. 2.0 Project Initiation

i) Initial project team meeting to discuss the WWMP Update and finalize the

terms of reference and project schedule. ii) Invite public comment through Notice of Study Commencement published in

newspaper and on City website. Circulate notice to Council, review agencies, and city departments.

3.0 Review of Existing Documentation

i) Review all background data including all relevant reports and agreements in

place since the 2004 Master Plan was adopted, and other City Master Plans.

Page 2

4.0 Sewage Flows

i) Review of existing statistics for population and development, update to include 2011. The report shall include current data (2011) as well as projections to full build-out.

ii) Review of existing flow information by type of user and drainage area.

iii) Review of existing pumping and flow data.

iv) Review of data and information on the existing collection system and sewage

pumping stations.

v) Assess inflow and infiltration. Review and comment on current inflow and infiltration initiatives.

vi) Identification and filling in of any data gaps. vii) Determine future flows. viii) Review accuracy of the existing HYDRA model and update with current data.

5.0 Wastewater Treatment Centre

i) Review and update description of existing Wastewater Treatment Centre works.

ii) Identify existing deficiencies at the Wastewater Treatment Centre.

iii) Review treatment capacities of all existing components based on current and

projected flows.

iv) Identify requirements for upgrades and expansion to plant with time frames for construction and cost estimates.

6.0 Sewage Pumping Stations

i) Review and update descriptions of existing Sewage Pumping Stations.

ii) Identify existing deficiencies with sewage pumping stations.

iii) Identify requirements for upgrades to existing sewage pumping stations and for additional stations based on projected demand, with time frames for construction and cost estimates.

Page 3

7.0 Collection System

i) Review and update description of existing collection system.

ii) Review and update condition and age of existing sewers.

iii) Analyze collection system using HYDRA model to: • Identify areas with potential capacity problems. • Recommend any changes to existing drainage areas. • Recommend any changes to sanitary and/or trunk sewers required

for the existing and future system.

iv) Identify requirements for additions and improvements to the sewage collection system with time frames for construction and cost estimates.

v) Identify further inflow and infiltration initiatives for implementation in capital

works program including scheduling and estimated costs. 8.0 Analysis Summary

i) Summarize requirements for additions/changes to Wastewater Treatment Centre, drainage areas, sewage pumping stations and collection system.

ii) Present the results in the form of tables, charts and schematics to illustrate

scenarios. 9.0 Biosolids Management

i) Review and update description of current biosolids management practices.

ii) Review and assess relevant past and present reports, recent upgrades to the Wastewater Treatment Centre, and current regulations for biosolids management.

iii) Identify current and potential areas of concern related to biosolids

management.

iv) Identify further studies or projects for implementation in capital works program including scheduling and estimated costs.

Page 4

10.0 Effluent Disposal

i) Review and update description of current effluent disposal practices. ii) Review and assess relevant past and present reports, recent upgrades to

the Wastewater Treatment Centre, and current regulations for effluent disposal.

iii) Identify current and potential areas of concern related to effluent quality, i.e.

nutrients in relation to the Lake Simcoe Phosphorus Reduction Strategy. iv) Identify further studies or projects for implementation in capital works

program including scheduling and estimated costs. 11.0 Reporting

i) Prepare a draft report outlining conclusions and recommendations including:

• Executive summary of the work.

• Summary of 2004 Master Plan under the same headings.

• Updated population and flow projections.

• An update of works carried out since the 2004 Master Plan.

• Updated schedule of capital works with cost estimates and time frame.

ii) Issue the Notice of Study Completion and notify all review agencies and

stakeholders. Provide a period of 30 calendar days for public review and comment.

iii) Finalize the Wastewater System Master Plan Update 2012 identifying the

applicable Class EA category and tentative construction timeline for each recommended project (Schedule A, A+, B or C).

iv) Present to Council Committee and submit copy to Ontario Ministry of the

Environment.

APPENDIX B

SEWAGE PUMPING STATION INFORMATION

APPENDIX C

INVENTORY OF DEVELOPMENT UPDATE INDUSTRIAL, COMMERCIAL & INSTITUTIONAL

CITY OF ORILLIAInventory of Development

January 2012Public Works Department

In order to quantify the total number of I.C.I. units, which can be absorbed withinthe City's boundaries seven categories have been established and are definedas follows:

I. Unserviced - Industrial

Existing Industrial properties located within city limits, which have not asof yet been serviced with sanitary sewers and/or water supply.

II. Serviced Vacant - Industrial

Vacant industrial properties abutting fully serviced, assumed streets andvacant lots on a Registered Plan, which have an executed or imminentdevelopment agreement.

III. Unserviced - Commercial

Existing commercial properties located within city limits, which have notas of yet been serviced with sanitary sewers and/or water supply.

IV. Serviced Vacant - Commercial

Vacant commercial properties abutting fully serviced, assumed streetsand vacant lots on a Registered Plan, which have an executed or imminentdevelopment agreement.

V. Institutional

Institutional properties located on an assumed street, which have not as of yet been serviced.

SCHEDULE "B"INDUSTRIAL, COMMERCIAL & INSTITUTIONAL

City of OrilliaPublic Works Department

DEVELOPMENT CONTROL PROGRAMINVENTORY OF DEVELOPMENT (UPDATE)

January 1, 2012

1

CITY OF ORILLIAInventory of Development

January 2012Public Works Department

I. UNSERVICED - INDUSTRIAL

MAP AREA (ha)REF. LOCATION VACANT

EAST: UI2. Precision Drive - 10 2.88

WEST: A3. Charter Construction Limited 30.80West of Harvie Settlement Road

A7C. Inch Business Park 5.57TOTAL Committed 39.25

UNCOMMITTED:EAST: UI4. Memorial Avenue – 827,845 16.03

Woodland Drive – 50A5S. Champlain Ready Mix Area 25.85

Line 15 NTOTAL Uncommitted 41.88

II. SERVICED VACANT - INDUSTRIAL

MAP AREA (ha)REF. LOCATION VACANT

EAST: VI3. James Street West 1.36175, 195

VI4. West Street - 255 8.27South of Queen St.

VI5. Drinkwater Industrial Park 4.03Brammer Drive – 1, 11, 12, 15, 17, 19, 20, 21, 22, 23Huronia Road - 4425

VI7. WIDE FLANGE INC 0.91Norweld Drive – 19 Lots

WEST: CI1. City Industrial Land 2.1910 Mulcahy Court

CI2. City Industrial Land 1.354 Mulcahy Court

CI3. City Industrial Land 0.71845 West Ridge Boulevard

A4. City Business Park 19.04University Avenue

TOTAL Committed 37.86

2

CITY OF ORILLIAInventory of Development

January 2012Public Works Department

III. UNSERVICED - COMMERCIAL

MAP AREA (ha)REF. LOCATION VACANT

EAST: UC2. 1138806 ONTARIO LIMITED 375 Atherley Road @ Highway 12 Bypass 1.34

TOTAL Committed 1.34

IV. SERVICED VACANT - COMMERCIAL

MAP FLOOR PARCELREF. LOCATION AREA AREA

sq.m. haEAST:C2. DON McDOUGALL 570 0.14 office building

138 & 146 Memorial AvenueC4. WILES HOLDING LIMITED 170 0.56 restaurant and car wash

430 West Street SouthC6. 1298875 ONTARIO INC 800 0.23 medical clinic

298 Forest Ave.C7. ATHERLEY-GILL SHOPPING CENTRE 6000 0.34 shopping mall

130 Atherley Rd @ Front St. & Gill St.C9. SAYTAR DEVELOPMENTS 1200 0.56 commercial plaza

570 Laclie St. @ Sundial Dr.C12. KESBRO INC 1.43 hotel units

640 Atherley Road

WEST: A7D. Miller Pit AreaHighway No. 12 – 7901 3.67

TOTAL - Committed 8,740 6.93

WEST: A7E. Northwest Quadrant Hwy 11/Hwy 12Highway No. 12 - 8023, 2035, 8051Uhthoff Line – 4510 7.30

TOTAL Uncommitted 7.30

TYPE

3

CITY OF ORILLIAInventory of Development

January 2012Public Works Department

V. INSTITUTIONAL

MAP FLOOR PARCELREF. LOCATION AREA AREA

sq.m. haEAST: I2. Pentecostal Church – Existing Unserviced 836 1.41

Westmount Drive NorthWEST: I1. LAKEHEAD UNIVERSITY (Phase 2 & 3) 22.82

University Avenue

TOTAL - Committed 24.23

VI. DEVELOPMENT SUMMARY

CATEGORY AREAha

I. Unserviced Industrial Committed 39.25Uncommitted 41.88

II. Serviced Vacant Industrial Committed 37.86

III. Unserviced Commercial Committed 1.34

IV. Serviced Vacant Commercial Committed 6.93Uncommitted 7.30

V. Institutional Committed 24.23

4

CITY OF ORILLIAInventory of Development

January 2012Public Works Department

CATEGORY AREAha

COMMITTED

I. Unserviced Industrial 39.25

II. Serviced Vacant Industrial 37.86

III. Unserviced Commercial 1.34

IV. Serviced Vacant Commercial 6.93

V. Institutional 24.23

COMMITTED SUBTOTAL: 109.61

UNCOMMITTED

I. Unserviced Industrial 41.88

III. Unserviced Commercial 7.30

UNCOMMITTED SUBTOTAL: 49.18

TOTAL 158.79

January 1, 2012

I C I LAND INVENTORY

SUMMARY

COMMITTED VS UNCOMMITTED

5

APPENDIX D

CITY OF ORILLIA REPORT TO COUNCIL APRIL 9, 2003

WATER AND SEWAGE DESIGN FLOWS

APPENDIX E

HYDRA SANITARY SEWAGE COLLECTION SYSTEM COMPUTER MODEL ANALYSIS

CITY OF ORILLIA SANITARY SEWAGE COLLECTION SYSTEM

HYDRA COMPUTER MODEL ANALYSIS

October 2012

CONTENTS 1.0 BACKGROUND INFORMATION ........................................................................... 1

1.1 Existing Sewage Treatment and Collection System ................................... 1

1.2 Purpose of the Hydraulic Analysis .............................................................. 1

1.3 Basic Model - Existing Conditions ............................................................... 1

2.0 CURRENT SEWAGE FLOW ................................................................................. 2

2.1 General ....................................................................................................... 2

2.2 Existing Flows ............................................................................................. 2

3.0 FUTURE SEWAGE FLOW .................................................................................... 5

3.1 General ....................................................................................................... 5

4.0 HYDRA MODEL .................................................................................................... 6

4.1 General ....................................................................................................... 6

4.2 Input Data ................................................................................................... 6

4.3 Existing Wastewater System ...................................................................... 7

5.0 HYDRAULIC ANALYSIS ....................................................................................... 8

5.1 General ....................................................................................................... 8

5.2 Existing System .......................................................................................... 8

5.3 Ultimate System .......................................................................................... 8

6.0 SUMMARY .......................................................................................................... 12

Wastewater System Master Plan Update HYDRA MODEL

1

1.0 BACKGROUND INFORMATION 1.1 EXISTING SEWAGE TREATMENT AND COLLECTION SYSTEM The existing wastewater system in the City of Orillia consists of 163 km of sanitary sewer, 20 sanitary sewage pumping stations, and a conventional activated sludge Wastewater Treatment Centre with a capacity of 27,300 m3/d (average day). All components of the wastewater system are owned, operated and maintained by the City of Orillia. A description of the sanitary sewage collection system and the Wastewater Treatment Centre is provided in the city of Orillia Wastewater System Master Plan Update 2012. 1.2 PURPOSE OF THE HYDRAULIC ANALYSIS A hydraulic analysis of the Orillia wastewater system was undertaken as part of the Wastewater Master Plan Update. Purposes for completing this analysis are to: Analyze the wastewater collection system using sophisticated computer

software;

Include recent system revisions;

Identify potential system deficiencies;

Evaluate system upgrade alternatives;

Confirm system characteristics and necessary modifications; and

Prepare an updated base model that can be used for analysis of future modifications associated with growth, particularly to the west of Highway 11.

The wastewater collection system has been analyzed using the HYDRA Version 6.4 software developed by PIZER Inc. This software is for the analysis, design, and management of sewer systems. A description of the computer model and results of the analysis are summarized hereinafter. Future system performance analyses can also be made by updating the model with system expansions and upgrades. 1.3 BASIC MODEL - EXISTING CONDITIONS The HYDRA model developed for the 2004 Wastewater System Master Plan was used as a starting point. This base model was reviewed and updated with new and upgraded pipes, manholes, and sewage pumping stations. As well, sewage flows were brought up to date. The original model was created by replicating the wastewater collection system on an OBM base plan. The City’s sanitary sewer mapping and database were used to determine pipe lengths, diameters, grades, and locations, with field checks by staff in areas of uncertainty.

Wastewater System Master Plan Update HYDRA MODEL

2

2.0 CURRENT SEWAGE FLOW 2.1 GENERAL Accurate sewage flow data is necessary to construct a hydraulic model that accurately represents the performance of the existing system. The original model established sewage flows on an industrial, commercial, institutional, and residential basis by:

1) Examination of water records over the past 5 years to determine an average day demand (ADD).

2) ADD for industrial, commercial, and institutional (ICI) users was determined from individual water meter records for these users.

3) The sum of metered ICI use was subtracted from the total ADD to establish the total residential water demand, and an average residential rate of 350 L/cap.d.

4) Sewage flow was then assigned to each of the established sanitary drainage areas in the model.

2.2 EXISTING FLOWS The original model used water meter records for 2002 assigned to each ICI property in litres per day (L/d). High density residential developments were assigned flows similar to ICI as they are also individually metered. For residential properties, the person per household rate of 2.95 was multiplied by the average residential flow rate of 350 L/cap.d. The original model used the parcel map of the City divided into numbered sanitary service (SE) areas. Each SE area was assigned a diurnal curve, allowing the model to accurately reflect actual sewage flow within the collection system, and to determine peak flow. For the 2012 model the following updates to existing flows were completed:

1) Examination of water records over the past 5 years to determine an average day demand of 17,880 m3/day.

2) Addition of new sanitary service areas in West Orillia.

3) Review and update of ICI flows using 2011 water meter records.

4) Addition of residential and ICI flows in West Orillia.

5) Addition of infiltration flows for Sewage Pumping Station zones in areas of known infiltration occurrence, as part of model calibration.

Diurnal curves developed in March 1996 were used in the original model, based on hourly flow data for each zoning type (see Table 1 and Graph 1). In general, peak flows for industrial and residential users do not coincide, and so, to simply add up the peak flows for each type of development would be conservative but would overstate the peak flows actually experienced in each trunk sewer. Alternatively, to apportion the total

Wastewater System Master Plan Update HYDRA MODEL

3

system peak flow equally to each pipe the system would undervalue the peak flow occurring in the trunk sewers. The HYDRA software is sufficiently sophisticated to distribute the peak flows appropriately throughout the simulation, and hence, provides a more accurate representation of the peak sewage flows generated within the sewage collection system. The hourly factors used in creating the model of the diurnal curves were determined using the actual hourly factors experienced on March 16, 1996 as seen in Table 1. TABLE 1 MARCH 16, 1996 HOURLY FACTORS

ZONING DESIGNATION AVG

TIME R1 R2 R3 R4 RM1 RM2 RMH RR R P C1 C2 C3 C4 M1 M2 M3 INST

0:00-1:00 1.5 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1.97

1:00-2:00 1 1 1 1 1 1 1 1 2 2 1 1 1 1 1 1 1 1 1.11

2:00-3:00 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1.00

3:00-4:00 2 2 1 1 1.5 1.5 1.5 2 2 2 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1 1.56

4:00-5:00 3 3 2 2 2.25 2.25 2.25 3 3 3 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1 2.36

5:00-6:00 6.5 6.5 3 3 3 3 3 7.5 7.5 7.5 4 4 4 4 3 3 3 1 4.25

6:00-7:00 8.5 8.5 6.5 6.5 7.5 7.5 7.5 9.5 9.5 9.5 6.5 6.5 6.5 6.5 6.5 6.5 6.5 1 7.08

7:00-8:00 13 13 13.5 13.5 13.5 13.5 13.5 7 7 7 7.5 7.5 7.5 7.5 7.5 7.5 7.5 1.5 9.36

8:00-9:00 5 5 7.5 7.5 7 7 7 5 5 5 8 8 8 8 8 8 8 5 6.78

9:00-10:00 4.5 4.5 5 5 6 6 6 4.5 4.5 4.5 9 9 9 9 8 8 10 8 6.69

10:00-11:00 5 5 4.5 4.5 6 6 6 5 5 5 8 8 8 8 9 9 11 12 6.94

11:00-12:00 5 5 5 5 6 6 6 5 5 5 10 10 10 10 10 10 13 17.5 7.97

12:00-13:00 4 4 5 5 6 6 6 4 4 4 10.5 10.5 10.5 14.5 11 11 12 12 7.78

13:00-14:00 3 3 4 4 6 6 6 3 3 4 10 10 10 10 12 12 10 9 6.94

14:00-15:00 4 4 3 3 6 6 6 4 4 4 7 7 7 7 9 9 9 6 5.83

15:00-16:00 5 5 4 4 6 6 6 5 5 5 6 6 6 6 8 8 8 8 5.94

16:00-17:00 7 7 6 6 6 6 6 7 7 7 6 6 6 6 5 5 5 3 5.94

17:00-18:00 10.75 10.75 10.75 10.75 10.25 10.25 10.25 9 9 9 8 8 8 8 5 5 5 4 8.43

18:00-19:00 8 8 8 8 8 8 8 8 8 8 9 9 9 9 5 5 4 3 7.39

19:00-20:00 5 5 5 5 5 5 5 5 5 5 4 4 4 4 3 3 2 1 4.17

20:00-21:00 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 2 1 2.72

21:00-22:00 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 1 2.42

22:00-23:00 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25 1 1 1 1 1 1 1 1 1.69

23:00-24:00 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 2 2 1 1 1 1 1 1 1 1 1.33

Wastewater System Master Plan Update HYDRA MODEL

4

The average of all the diurnal curves indicate a peak hour factor of 9.36 occurs at approximately 7:00 a.m. with the next highest peak hour factor of 8.43 occurring at about 5:00 p.m., as shown in Graph 1.

GRAPH 1DIURNAL CURVES

0

2

4

6

8

10

12

14

16

18

20

0:0

0-1

:00

1:0

0-2

:00

2:0

0-3

:00

3:0

0-4

:00

4:0

0-5

:00

5:0

0-6

:00

6:0

0-7

:00

7:0

0-8

:00

8:0

0-9

:00

9:0

0-1

0:0

0

10:0

0-1

1:0

0

11:0

0-1

2:0

0

12:0

0-1

3:0

0

13:0

0-1

4:0

0

14:0

0-1

5:0

0

15:0

0-1

6:0

0

16:0

0-1

7:0

0

17:0

0-1

8:0

0

18:0

0-1

9:0

0

19:0

0-2

0:0

0

20:0

0-2

1:0

0

21:0

0-2

2:0

0

22:0

0-2

3:0

0

23:0

0-2

4:0

0

TIME

RE

LA

TIV

E F

LO

W

R1

R2

R3

R4

RM1

RM2

RMH

RR

R

P

C1

C2

C3

C4

M1

M2

M3

INST

AVG

Wastewater System Master Plan Update HYDRA MODEL

5

3.0 FUTURE SEWAGE FLOW 3.1 GENERAL The original model incorporated future projected flows from the development area immediately west of Highway 11 as well as full infilling of the available land within the existing serviced area east of Highway 11. The design criteria used are:

Persons per household = 2.95 Daily per capita flow allowance = 300 L/cap/day Industrial flow allowance = 0.42 L/ha/s (36 m3/ha.d) Commercial flow allowance = 0.32 L/ha/s (28 m3/ha.d) Infiltration flow allowance = 0.04 L/ha/s Peaking factor method = Diurnal Curves Manning's Roughness coefficient = 0.013

The above design criteria are in accordance with City of Orillia standards and are within the rates identified in the MOE Guidelines. The exception being the use of diurnal curves, which were developed from actual flow records and are more accurate than the Harmon method for determining a peaking factor. Note that the ultimate overall future flows discussed in the 2012 Master Plan Update document are 5% higher than those carried in the hydraulic modelling. This allowed for a future re-urbanization of 5% that was not incorporated into the hydraulic model. Re-urbanization will be site specific and can be incorporated into model updates as these sites are identified. As in the original model, analysis of the ultimate flow conditions was completed assuming that the existing wastewater collection system could accommodate all future flows with relatively minor upgrades and modifications. Therefore it was not considered necessary to construct models which assumed the provision of an independent system, conveying flow directly to the Wastewater Treatment Centre, for the annexed lands.

Wastewater System Master Plan Update HYDRA MODEL

6

4.0 HYDRA MODEL 4.1 GENERAL In hydraulic network analysis, a calibrated model is used to evaluate the collection system performance under existing and/or future operating conditions. The computer simulation is typically undertaken for the most limiting condition(s); in this case peak flow. Deficiencies in system performance are usually evident as unacceptably high liquid elevations in the pumping stations and maintenance holes, excessive or insufficient velocities in pipes, or as inconsistent operating conditions. MOE design guidelines suggest the following system requirements, which have been used in these analyses as the limiting acceptable parameters:

velocities in forcemains range from 0.8 to 2.5 m/s.

velocities in gravity sewers range from 0.6 to 3.0 m/s 4.2 INPUT DATA In order to construct the original HYDRA model of the Orillia wastewater collection system, the following preliminary steps were undertaken to determine the correct input data:

1) Pipe lengths were determined by plotting the collection system on a digital OBM base map from which the HYDRA program automatically calculated the lengths. Pipe diameters were determined by analysis of the City’s overall sewage system base plan, and elevations were determined from field records.

2) The pump data for all the sewage pumping station pumps were obtained from drawdown tests. The pump data was input into the HYDRA program.

3) Sewage flow data was determined from a combination of field flow monitoring and an examination of historical water consumption records.

4) After the physical and operational conditions were established and input into the HYDRA program, partial calibration of the model was undertaken to determine pipe roughness coefficients.

Original calibration of the model involved comparison of model results with actual measured results, and manipulation of the roughness coefficients for different pipe sections in the model. It was determined that an assumed pipe roughness coefficient of 0.013 for all pipes best replicated actual conditions in the model. For the 2012 model update, the following additional steps were taken:

1) New and upgraded pipes were digitized and added to the model. The City’s sanitary sewer mapping and database were used as the data source.

Wastewater System Master Plan Update HYDRA MODEL

7

2) Sewage flow data was reviewed and updated using water consumption records for ICI users and population estimates multiplied by an average residential flow rate of 350 L/cap.d.

3) Pump data for all the sewage pumping stations was reviewed and updated to reflect station upgrades since the original model.

4) Further calibration of the model was completed by adding infiltration flow to pumping station zones in known areas of infiltration occurrence.

Calibration of the model involved comparison of model results with actual measured results, and the addition of infiltration flows where appropriate. 4.3 EXISTING WASTEWATER SYSTEM The existing wastewater system is described in Section 3.4 of the main report. Future conditions with respect to population growth, industrial / commercial / institutional (ICI) growth and wastewater flow projections are described in Section 4 of the main report.

Wastewater System Master Plan Update HYDRA MODEL

8

5.0 HYDRAULIC ANALYSIS 5.1 GENERAL In the original model, several alternatives were considered to service future development in Orillia. Since that time, expansion of the collection system has proceeded in line with the preferred alternative. In this model update, the existing system is modelled under both current and future flow conditions. 5.2 EXISTING CONDITIONS The existing wastewater collection system was first analyzed with respect to constraints within the existing system with no future development included. Using the HYDRA computer model, the existing system was analyzed for current peak flow (worst case) conditions. It was confirmed that the existing trunk sewers, sewage pumping stations and Wastewater Treatment Centre can accommodate these peak flows. 5.3 ULTIMATE CONDITIONS The wastewater collection system’s capability to service future development in Orillia was also analyzed. Using the HYDRA computer model the existing system was analyzed assuming that existing infrastructure will be used to service new development. The model identified the following sewers with peak sewage flow at more than 70% of pipe capacity: 250mm dia. sewer between MH 100 and MH 97 on West Street South

250mm dia. sewer between MH 413 and MH 417 on West Street South In addition, the following trunk sewers with peak sewage flow at more than 70% of pipe capacity were identified: 350mm dia. trunk sewer between MH 1346 and MH 1344 on Fittons Road East

600mm dia. trunk sewer between MH 35 and MH 30 of the CNR trunk sewer As well, the model indicated that Sewage Pumping Station No. 10 on Victoria Crescent does not have enough capacity to accommodate flows due to the future infilling of the Victoria Point area.

Wastewater System Master Plan Update HYDRA MODEL

9

6.0 SUMMARY

Computer modelling of the existing wastewater collection system indicates that all existing peak flows can be accommodated. As well, computer modelling of the ultimate conditions predicts that future infilling in the existing serviced areas of the City and full development of West Orillia can be accommodated with a few upgrades to the existing wastewater collection system. These include: upsizing of a few existing sewers and trunk sewers, and an increase in capacity of Sewage Pumping Station No. 5 on Victoria Crescent.

APPENDIX F

MOE POLICY ON SEPTIC SYSTEMS

APPENDIX G

PUBLIC CONSULTATION DOCUMENTATION FOR 2012 MASTER PLAN UPDATE

CITY OF ORILLIA WASTEWATER SYSTEM MASTER PLAN UPDATE

PUBLIC COMMENT INVITED

The City of Orillia is updating its Wastewater System Master Plan, which identifies the wastewater infrastructure requirements to service population growth, new developments, and new service areas. The purpose of this Master Plan update is to address limitations related to the existing wastewater system, both with respect to existing services and future development. This update will continue to follow the Municipal Class Environmental Assessment process. By maintaining this approach, the updated Master Plan will satisfy the first two phases of the Class Environmental Assessment for Municipal Water and Wastewater Projects. This will include a revised schedule of major works for future planning, design, and implementation. Based on study findings, completed works, and the impact of the Lake Simcoe Protection Act and Regulations, the 2012 Wastewater Master Plan update provides an update of works carried out since the period covered by the 2004 Master Plan. It will also include revised projections, additional public consultation, and additional recommended works not a part of the original Master Plan. Public input and comments are invited for incorporation into the wastewater system master planning process, and will be received until January 31, 2012. Subject to comments received, the City of Orillia intends to finalize the update by June 2012. Information will be collected in accordance with the Freedom of Information and Protection of Privacy Act. With the exception of personal information, all comments will become part of the public record. For further information on this project or to see a copy of the Municipal Class Environmental Assessment document, please contact:

Jason Covey, P. Eng. Water & Wastewater Engineer

City of Orillia Public Works – Engineering Division 50 Andrew Street South, Suite 300

Orillia, Ontario L3V 7T5 Phone: (705) 325-2227 Email: [email protected]

This Notice initially issued December 5, 2011.

ENGINEERING DEPARTMENT

December 5, 2011 (Address)

Reference: City of Orillia Wastewater System Master Plan Update

The future development of the City of Orillia depends on the provision of adequate municipal

water and wastewater services. Master Plans are necessary to establish a framework to

specifically identify the water and wastewater infrastructure requirements to service population

growth, new developments, and new service areas. The City of Orillia intends to update its

Wastewater System Master Plan, originally adopted in 2004. Please find enclosed a copy of the

“Public Comment Invited” notice for the 2012 Wastewater System Master Plan Update, that is to

be published in the local papers December 15th, 2011, as well as posted on the City’s website.

This project will encompass further monitoring and analysis of the existing systems, as well as

evaluation of alternative solutions. The ultimate aim of the project will be to recommend, cost,

phase, and schedule major works for future budgeting and implementation, so that development

can progress in an orderly and sustainable manner.

The purpose of this letter is to notify you of the proposed undertaking, and to solicit any

comments or concerns you may have for consideration in the planning process. These should

be submitted to the City of Orillia Public Works Department, Engineering Division by January

31, 2012, so that specific information may be considered. Subject to comments received, the

City intends to finalize the Wastewater Master Plan update by June 2012.

TELEPHONE (705) 325-3975

[email protected]

ORILLIA CITY CENTRE 50 ANDREW ST. S., SUITE 300 ORILLIA, ON. L3V 7T5

Should you have any questions or comments with respect to the 2012 Wastewater Master Plan

Update, please contact:

Jason Covey, P. Eng.

Water & Wastewater Engineer

City of Orillia

Public Works – Engineering Division

50 Andrew Street South, Suite 300

Orillia, Ontario L3V 7T5

Phone: (705) 325-2227

Email: [email protected]

Sincerely,

Jason Covey, P. Eng.,

Water & Wastewater Engineer Enclosure

Environmental Assessment: Review Agencies Mailing List

Agency Contact Name Title Address Mailing City PC Phone #

County of Simcoe Glen Knox Clerk Administration Centre 1110 Highway #26 MIDHURST L0L 1X0 726-9300

Township of Oro-Medonte Doug Irwin Director of Corporate Services / Clerk 148 Line 7 South Box 100 ORO L0L 2X0 487-2171

Township of Ramara Richard Bates Clerk 2297 Highway 12 Box 130 BRECHIN L0L 1B0 484-5374

Township of Severn Henry Sander Clerk 1024 Hurlwood Lane Box 159 ORILLIA L3V 6J3 325-2315

City of Orillia - Department of Planning and Development Ian Sugden Director of Planning and Development 50 Andrew Street South Suite 300 ORILLIA L3V 7T5 329-7241

City of Orillia - Waste Management Advisory Committee Robin Cadeau Committee Coordinator 50 Andrew Street South Suite 300 ORILLIA L3V 7T5 329-7241

City of Orillia - Department of Parks and Recreation Ray Merkley Director of Parks and Recreation 50 Andrew Street South Suite 300 ORILLIA L3V 7T5 329-7251

Ministry of Tourism and Recreation Greg Stewart Regional Consultant 2284 Nursery Road MIDHURST L0L 1X0 739-6696

Ministry of the Environment - Barrie District Office Susan Eves Senior Environmental Officer 54 Cedar Pointe Drive Unit 1201 BARRIE L4N 5R7 739-6441

Ministry of the Environment Central Region, Technical Support Section

Chunmei LiuEnvironmental Resource Planner and EA Coordinator

5775 Yonge Street 8th Floor NORTH YORK M2M 4J1 800-810-8048

Ministry of the Environment Sir/Madam 135 St Clair Avenue West 14th Floor TORONTO M4V 1P5 800-565-4923

Ministry of Municipal Affairs and Housing Yvonne Hurst Area Advisor, Municipal Services Office Central 777 Bay Street 2nd Floor TORONTO M5G 2E5 800-668-0230

Ministry of Natural Resources Kathy Woeller Planner 2284 Nursery Road MIDHURST L0L 1X0 725-7500

Ministry of Transportation Peter Dorton Corridor Management 7th Floor Building "D" 1201 Wilson Avenue DOWNSVIEW M3M 1J8 416-235-4280

Ministry of Aboriginal Affairs Pam WheatonDirector, Aboriginal and Ministry Relationships Branch

720 Bay Street 4th Floor TORONTO M5G 2K1 416-326-4053

Department of Indian and Northern Affairs Mr. Fred HoskingSenior Claims Analyst, Specific Claims Branch Ontario Research Team

10 Wellington St Room 1310 Gatineau, QU K1A 0H4 819-953-1940

Orillia Power Corporation Richie Udell Distribution Manager 360 West Street South ORILLIA L3V 5G8 326-7315

Hydro One Sir/Madam 483 Bay Street 10th Floor Reception TORONTO M5G 2P5

Environment Canada Sir/Madam 4905 Dufferin Street DOWNSVIEW M3H 5T4 416-739-4826

Fisheries and Oceans Canada, Eastern Ontario District Sir/Madam 501 Towerhill Rd. Unit 102 PETERBOROUK9H 7S3 705-750-0269

Parks Canada c/o Trent-Severn Waterway Bob Kerr Severn Sector Supervisor PO Box 9 WASHAGO L0K 2B0 689-2607

Transport Canada - Ontario Region (PHE) Haya FinanEnvironmental Officer, Environment and Engineering

4900 Yonge Street NORTH YORK M2N 6A5 416-952-0475

Simcoe County Board of Education David Few Manager of Property and Planning 1170 Highway 26 MIDHURST L0L 1X0 728-7570

Simcoe Muskoka Catholic District School Board Jennifer Sharpe Manager of Planning 46 Alliance Boulevard BARRIE L4M 5K3 722-3555

Lake Simcoe Region Conservation Authority Mike Walters Watershed Director 120 Bayview Parkway Box 282 NEWMARKET L3Y 4X1 905-895-1281

Simcoe Muskoka District Health Unit Gerry Capko Senior Public Health Inspector 15 Sperling Drive BARRIE L4M 6K9 721-7520

Bell Canada Sir/Madam 136 Bayfield Street 2nd Floor BARRIE L4M 6K9 800-268-9160

Ministry of Health and Long-term Care Sir/Madam 34 Simcoe Street Unit 102 BARRIE L4N 6T4

Union Gas Sir/Madam 425 Memorial Avenue ORILLIA L3V6K2 325-1506

Rogers Cable Inc Sir/Madam 1 Sperling Drive BARRIE L4M 6B8 888-764-3771

Orillia and District Construction Association Sir/Madam PO Box 235 ORILLIA L3V 6J3 326-1844

Métis Nation of Ontario Head Office Sir/Madam Métis Consultation Unit 500 Old St. Patrick Street Unit D OTTAWA K1N 9G4

Page 1 of 2

Environmental Assessment Review Agencies Mailing List

Agency Contact Name Address Mailing City PC Phone #

Beausoleil First Nation Rodney Monague Jr. 1 Ogema Street CHRISTIAN ISLANDL0K 1C0 (705) 247-2051

Chippewas of Georgina Island Brett Mooney RR 2 PO Box N-13 SUTTON WEST L0E 1R0 (705) 437-1337

Chippewas of Mnjikaning First Nation (Rama) Sherry Wilson 5884 Rama Road Suite 200 RAMA L0K 1T0 705-325-3611

Curve Lake First Nation Keith Knott 22 Winookeeda Road CURVE LAKE K0L 1R0 (705) 657-8045

Hiawatha First Nation Laurie Carr 123 Paudash Street HIAWATHA K0L 2G0 (705) 295-4421

Mississaugas of Scugog Island First Nation Tracy Gauthier 22521 Island Road RR# 5 PORT PERRY L9L 1B6 (905) 985-3337

Moose Deer Point First Nation Barron King 3719 Twelve Mile Bay Rd PO BOX 119 MACTIER P0C 1H0 (705) 375-5209

Wahta Mohawk Territory Sir/Madam PO BOX 260 BALA P0C 1A0 (705) 756-2354

Wasauksing First Nation Sir/Madam PO Box 250 PARRY SOUND P2A 2X4 (705) 746-2531

Georgian Bay Métis Council Brenda Laurin 355 Cranston Crescent PO BOX 4 MIDLAND L4R 4K6 (705) 526-7537

Moon River Métis Council Larry Duval 7678 McNiece Crescent BOX 386 WASHAGO L0K 2B0 (705) 689-3941

Williams Treaty First Nation Karry Sandy-Mackenzie 8 Creswick Court BARRIE L4M 2S7

Page 2 of 2

www.www.orillia.ca.ca

50 ANDREW ST. SOUTH, SUITE 300, ORILLIA 705-325-1311

THURSDAY, DECEMBER 22, 2011

JOB OPPORTUNITIESACCOUNTING CLERKTREASURY DEPARTMENTClosing Date: January 4, 2012 at Noon.

PARK/FACILITY OPERATORPARKSAND RECREATION DEPARTMENTClosing Date: January 4, 2012 at Noon.

2012 SUMMER EMPLOYMENT OPPORTUNITIESPARKSAND RECREATION DEPARTMENTSummer Park/Facility Staff andSummer Camp StaffClosing: February 24, 2012 at Noon.

Please visit our website at www.orillia.ca for further information

No Meeting - Monday, December 26, 2011

Month at a GlanceMonday, January 2 – No Meeting

Monday, January 9 – Council CommitteeMonday, January 16 - Council

Monday, January 23 – Council Committee

Full Agenda Packages are available at www.orillia.caContact the City Clerk’s Department at 705-325-1311 or [email protected]

to confirm meeting schedules and meeting times.

UPCOMING MEETINGS

EVENTS

UPCOMING EVENTSBleeker Ridge January 5A Cappella in The Barbershop Style January 7Banff Mountain Film FestivalWorld Tour 2012 January 12 & 13Gerry Dee-Life After Teaching January 15The Jim Cuddy Band January 25Abba Mania & The Best of Elton(Tribute Artists) January 28Paul Brandt – NOW February 1Leaving Home February 9 – 19Adventures with The Symphony February 25Richard Scarry’s Busytown March 6Lighthouse Live! March 10The Stampeders March 22

2012 Summer Theatre Flex Pacs Now Available...4 Great Shows For 1 Great Price!

THE ORILLIA OPERA HOUSEBOX OFFICE: 705-326-8011www.orilliaoperahouse.ca

ORILLIA FARMERS’ MARKETCHRISTMAS EVE DAY ‘BAKING & BIRD’ MARKET!

50 Andrew Street South, City Centre7:30 a.m. to 12:30 p.m.

this Saturday.You’ll love what our vendors have for you!

NOT ONLY cranberries, baking (some gluten-free),honey products, beef products, knitwear,

dips, onions, squash, preserves,gourds, garlic, potatoes, beef jerky, meat pies,

cabbage, maple syrup, fresh-frozen birds, parsnip –BUT ALSO stocking stuffers, tree ornaments, quality crafts,

seasonal décor, art prints, books, felted wear, jewellery PLUS:Kathy’s Kakes: chocolates and fudge!

William’s metal Christmas trees with lights ready to go!ALL MADE WITH DEDICATION AND CARE – BUY LOCAL!

Bring your family, meet your friends.Enjoy sausage, somosa, soup, coffee.

In the Performance Area: music by ‘the Coopers’, StaffanRiddaeus, Jill Jambor

Park in nearby Municipal Parking lots and City Centre lotat no charge while you shop.

December 31: NO MARKET – vendor vacation!January 7, 2012: Market continues through Winter indoors.

Thank you for supporting Orillia Farmers’ Market and its ven-dors through 2011! Merry Christmas! Happy New Year 2012!

Smoking only in designated smoking area.Please do not walk your pet on the Market while you are shopping.

For information please telephone 705-238-7955 or go onlineto our website: www.orilliafarmersmarket.on.ca

or ‘like’ us on ‘Facebook’Member: Farmers’ Markets Ontario; Orillia Chamber of Commerce;

Simcoe County Farm Fresh Marketing Association.

CITY OF ORILLIANOTICE OF APPLICATION FORA ZONING BY-LAW

AMENDMENTTAKE NOTICE that an application has been received from Terry andSherry Knappett for a proposed Zoning By-law Amendment (File No.D14-787) pursuant to the provisions of the Planning Act as follows:

Description of the Land:

The subject land is located on the west side of Peter Street North, northof the intersection of Peter Street North and North Street East. Thesubject land is known municipally as 329 Peter Street North.

Purpose and Effect of the Proposed Zoning By-law Amendment:Re: Zoning By-law Amendment Application No. D14-787

(329 Peter Street North)

Thesubject landsaredesignatedas“LivingArea–StableNeighbourhood”in the City’s Official Plan. The subject lands are currently zoned “SecondDensity Residential” (R2) under Zoning By-law 2005-72, as amended.The Applicant has applied for a Zoning By-law Amendment to rezonethe lands to “Second Density Residential Exception” (R2-X) to permit atriplex dwelling.

Related Applications:

There are no related applications under the Planning Act in processwhich apply to the subject lands.

Information Available:

Additional information and material relating to the proposal is availablefor review during business hours, in the Planning Office, Orillia CityCentre, 3rd Floor, 50 Andrew Street South, Suite 300, Orillia, Ontario.For further information, you may also contact Jeff Duggan at 705-325-2171 or Branko Vidovic at 705-325-7471.

Oral andWritten Submissions – Appeal:

If a person or public body does not make oral submissions at a PublicMeeting or does not make a written submission to the Council of theCorporation of the City of Orillia before the proposed Zoning By-lawAmendment is passed, the person or public body is not entitled to appealthe decision of the Council of the Corporation of the City of Orillia to theOntario Municipal Board.

If apersonorpublicbodydoesnotmakeoral submissionsataPublicMeeting,or does not make a written submission to the Council of the Corporation ofthe City of Orillia before the proposed Zoning By-lawAmendment is passed,the person or public body may not be added as a party to the hearing ofan appeal before the Ontario Municipal Board unless, in the opinion of theBoard, there are reasonable grounds to do so.

Individuals who make written submissions should be aware that theirsubmission and any personal information in their correspondence willbecome part of the public record and made available to the Applicant,Committee and Council.

Dated: December 22, 2011

NOTICE

CITY OF ORILLIAWASTEWATER SYSTEM MASTER PLAN

PUBLIC COMMENT INVITEDThe City of Orillia is updating its Wastewater System Master Plan,which identifies the wastewater infrastructure requirements to servicepopulation growth, new developments, and new service areas. Thepurpose of this Master Plan update is to address limitations related tothe existing wastewater system, both with respect to existing servicesand future development.

This update will continue to follow the Municipal Class EnvironmentalAssessment process. By maintaining this approach, the updatedMaster Plan will satisfy the first two phases of the Class EnvironmentalAssessment for Municipal Water and Wastewater Projects. This willinclude a revised schedule of major works for future planning, design,and implementation.

Based on study findings, completed works, and the impact of the LakeSimcoe Protection Act and Regulations, the 2012 Wastewater MasterPlan update provides an update of works carried out since the periodcovered by the 2004 Master Plan. It will also include revised projections,additional public consultation, and additional recommended works not apart of the original Master Plan.

Public inputandcommentsare invited for incorporation into thewastewatersystem master planning process, and will be received until January 31,2012. Subject to comments received, the City of Orillia intends to finalizethe update by June 2012. Information will be collected in accordancewith the Freedom of Information and Protection of Privacy Act. With theexception of personal information, all comments will become part of thepublic record.

For further information on this project or to see a copy of the MunicipalClass Environmental Assessment document, please contact:

Jason Covey, P. Eng.Water & Wastewater Engineer

City of OrilliaPublic Works – Engineering Division50 Andrew Street South, Suite 300

Orillia, Ontario L3V 7T5Phone: 705-325-2227Email: [email protected]

NOTICE

CITY OF ORILLIAFLUORIDATION OF CITY DRINKINGWATER

PUBLIC FORUMYour opportunity to be a part of the City’s public consultation process toconsider fluoridation of drinking water in Orillia, featuring:• Information tables and a chance to meet with experts• Presentations/comments from pre-registered individuals• Opportunity for informal comments and questions

Hosted by:The City of Orillia’s Public Works Department

andThe Simcoe Muskoka District Health Unit

Wednesday, February 29th, 20126:30 p.m. to 9:30 p.m.Council Chamber

First Floor, City Centre Building, 50 Andrew Street South

Individuals wishing to make a formal presentation must register in ad-vance:• Registrations must be received on or before Wednesday, January25th, 2012.

• To register, submit your name, address, phone number, email, andthe purpose of your presentation to Jason Covey at 705-325-2227or [email protected].

• While we anticipate a maximum of 10 minutes for each speaker, thetime allotted will depend on the number of registrations received.

Additional comments, questions, and concerns will also be acceptedfollowing the public forum until Friday, March 30th, 2012. For more infor-mation on the public consultation process visit:http://www.orillia.ca/en/livinginorillia/haveyoursay.asp.

NOTICEREMINDERREMINDER- CHRISTMAS HOLIDAY

CLOSURES 2011CITY ADMINISTRATION OFFICES50 Andrew Street South City Centre

Closed: Fri., Dec. 23 through to Fri., Dec. 30Open: Monday Jan 2

20 James St. W. Municipal Operations CentreClosed from 11:30 a.m. Fri., Dec. 23 – 8:00a.m. Dec 28Closed from 11:30 a.m. Fri., Dec. 30 – 8:00a.m. Jan 3, 2012

40 Kitchener St. Wastewater Treatment CentreClosed from 11:30 a.m. Fri., Dec. 23 – 8:00a.m. Dec 28Closed from 11:30 a.m. Fri., Dec. 30 – 8:00a.m. Jan 3, 2012

100 Kitchener St. Waste Diversion Site

*

*No Marriage Licences or Lottery Licences will be issued from Dec. 23through to Dec. 30, 2011

OPERA HOUSEBox Office Open all week including Dec. 24 11 a.m. – 3:00 p.m.

Closed Dec.25 – Jan.1Administration Offices Closed Dec.23 – Jan. 1

ORILLIA PUBLIC LIBRARY500 Gill Street Mon., Dec. 19-Thurs., Dec. 22 Open 10 a.m. - 8 p.m.

Fri., Dec. 23 Open 10 a.m. - 6 p.m.Sat., Dec. 24 Open 9 a.m. - 1 p.m.Sun., Dec.25 & Mon., Dec.26, Tues., Dec.27ClosedWed., Dec. 28 & Thurs., Dec. 29 Open 10 a.m. - 8 p.m.Fri., Dec. 30 Open 10 a.m. - 6 p.m.Sat., Dec. 31 Open 9 a.m. - 1 p.m.Sun., Jan. 1 and Mon., Jan.2 Closed

ORILLIA TRANSITFri., Dec.23 Regular Service from 6:15am to 10:15pm (10:45pm

final)Sat., Dec 24 Regular Service at 8:45am to 5:45pm (6:15pm final)Sun., Dec. 25 NO SERVICEMon., Dec. 26 NO SERVICETues., Dec. 27 - Thur., Dec. 29 Regular Service from 6:15am to 10:15pm (10:45pm

final)Fri., Dec. 30 Regular Service from 6:15am to 10:15pm (10:45pm

final).Sat., Dec. 31 Regular Service from 8:45am to 6:15pm, FREE transit

service from 6:15 p.m. to 1:15 a.m. For moreinformation, please call 705-326-8300

ORILLIA WHEELCHAIR LIMOUSINE SERVICESat. Dec. 24 & Sat. Dec.31 Regular Service from 12:00pm to 5:00pm

After Hours Service from 8:00am to 12:00pm & 5:00pmto 7:00pm(last booking not later than 6:30pm)Sat., Dec. 24

Sun., Dec. 25 NO REGULAR OR AFTER HOURS SERVICEMon., Dec. 26 NO REGULAR OR AFTER HOURS SERVICE

For more information, please call 705-327-0411

Christmas tree collection runs from Tues, Dec 27, 2011 to Fri, Jan 13, 2012.

The regular collection schedule will resume Mon, Jan 9, 2012.

Questions? Call 705-325-3522.

ORILLIA TRANSIT SERVICE NOTICE

Saturday, December 31stStarting @ 6:15 P.M.

(Free service on all buses from 6:15 p.m. to1:15 a.m. Regular fares apply prior to 6:15 p.m.)

LAST DEPARTURE FROM DOWNTOWNSunday, January 1st @ 12:45 a.m.

“Season’s Greetings from Orillia Transit”FOR MORE INFORMATION CALL.705-326-8300

COURTESY OF THE STAFF ANDMANAGEMENT OF YOUR LOCAL

SAFETY NOTICEHoliday Fire Safety

andYour ChristmasTree

• Get a freshly cut tree. It will stay green longer and be less of a firehazard. Try to pick a tree with a strong green colour and noticeablefragrance.

• Always test for freshness before buying.A tree with high moisture con-tent is safer. Very few needles should fall when the butt of the tree istapped on the ground; needles should bend, not break; and the stumpshould be sticky with resin.

• Place the tree in a stand that will hold 2 to 3 litres of water and top it updaily. Make sure it is always immersed in water: If water drops belowthe trunk, the stem may reseal itself, requiring a fresh cut. Use a treestand that has widespread legs for better balance.

• Do not set your tree up near a heat source such as a radiator, televi-sion, fireplace, heating duct or sunny window. It should not block doorsor windows.

• Never use lighted candles on or near the tree.

• Remove the tree within 10 to 14 days. After that amount of time in aheated building, even the freshest tree can start to dry out.

Last but not least ... make sure your smoke detectors work!

For more information please contact the Orillia Fire Department, FirePrevention Division, 705-325-5215

www.www.orillia.ca.ca

50 ANDREW ST. SOUTH, SUITE 300, ORILLIA 705-325-1311

THURSDAY, JANUARY 5, 2012

CITY OF ORILLIAFLUORIDATION OF CITY DRINKINGWATER

Your opportunity to be a part of the City’s public consultationprocess to consider fluoridation of drinking water in Orillia,featuring:

• Information tables and a chance to meet with experts• Presentations/comments from pre-registered individuals• Opportunity for informal comments and questions

Hosted by:The City of Orillia’s Public Works Department

andThe Simcoe Muskoka District Health Unit

Wednesday, February 29th, 20126:30 p.m. to 9:30 p.m.Council Chamber

First Floor, City Centre Building,50 Andrew Street South

Individuals wishing to make a formal presentation must registerin advance:

• Registrations must be received on or beforeWednesday, January 25th, 2012.

• To register, submit your name, address, phone number,email, and the purpose of your presentation to JasonCovey at 705-325-2227 or [email protected].

•While we anticipate a maximum of 10 minutes for eachspeaker, the time allotted will depend on the number ofregistrations received.

Additional comments, questions, and concerns will also beaccepted following the public forum until Friday, March 30th,2012. For more information on the public consultation processvisit: http://www.orillia.ca/en/livinginorillia/haveyoursay.asp.

This Notice initially issued December 15th, 2011.

PUBLIC FORUM

CONTRACT NO. RWS-10-28WATERMAIN REPLACEMENT AND ASPHALT RESURFACING ON

ARGYLE AVENUE FROMWESTMOUNT DRIVETO DALLAS STREET

Sealed tenders plainly marked as to content will be received by the City of Orillia,Public Works Department – Engineering Office, 50 Andrew Street South, Suite300, Orillia, Ontario, L3V 7T5 until:

Thursday, January 26, 20121:00 p.m. (Local Time)

On the same day, commencing at 1:00 p.m., local time, the tenders will beopened and read publicly in the City Centre Brooks Boardroom, 50 AndrewStreet South, Orillia, Ontario.

The work consists of:

• installation of approximately 250m of 150mm diameter watermain• pulverizing and resurfacing approximately 250m of roadway

Plans, Specifications and Contract Documents may be obtained from the City ofOrillia Public Works Department - Engineering Office for a non-refundable depositof $56.50 ($50.00 + $6.50 HST).

A certified cheque or bid bond of five percent (5%) of the tender shall besubmitted with the tender document.

The lowest or any tender not necessarily accepted.

TENDER

PARKINGOVERNIGHT PARKING RESTRICTION

The City of Orillia would like to take thisopportunity to remind all residents thatas of November 15, 2011 through April 15,2012, no person shall park a vehicle on anymunicipal street or any municipal parkinglot between the hours of 12:00 a.m. and 7:00a.m. This prohibition is in effect whether itis snowing or not. There is zero tolerance,

all vehicles will be ticketed and/or towed.

Monday, January 9, 2012Closed Session matters will be discussed prior to

the meeting reconvening in Open Session at 7:00 p.m.Watch the meeting on Rogers Cable (Channel 10).

Full Agenda Packages are available at www.orillia.caContact the City Clerk’s Department at 705-325-1311 or

[email protected] to confirm meeting schedules and meeting times.

Month at a Glance

Monday, January 16 – CouncilMonday, January 23 – Council Committee

Monday, January 30 – CouncilMonday, February 6 – Council Committee

COUNCIL COMMITTEE MEETING

EVENTS

UPCOMING EVENTSBleeker Ridge January 5A Cappella in The Barbershop Style January 7Banff Mountain Film FestivalWorld Tour 2012 January 12 & 13Gerry Dee-Life After Teaching January 15The Jim Cuddy Band January 25An Evening with Tame January 27Abba Mania & The Best of Elton(Tribute Artists) January 28Paul Brandt – NOW February 1Leaving Home February 9 – 19Adventures with The Symphony February 25Richard Scarry’s Busytown March 6Lighthouse Live! March 10The Stampeders March 22

2012 Summer Theatre Flex Pacs Now Available...4 Great Shows For 1 Great Price!

THE ORILLIA OPERA HOUSEBOX OFFICE: 705-326-8011www.orilliaoperahouse.ca

ATHLETE OF THE YEAR2011 CITY OF ORILLIA ATHLETE OFTHEYEAR

Official nomination forms for the 2011 Athlete of the Year Award are availableon the City’s website (www.orillia.ca) or at the Parks and Recreation office(3rd Floor, 50 Andrew St. South).

Residents are encouraged to nominate an outstanding localathlete who meets the following criteria:

1) The athlete should have accomplished a high level of athletic achievementover the past year.

2) The athlete need NOT be of Olympic calibre.3) Past winners are not eligible.4) An individual must be nominated, not a team.5)Your nominee will be judged on the basis of his/her individual ability,

dedication to training schedule, and good sportsmanship.

NOMINATION DEADLINE –FRIDAY, JANUARY 13, 2012 by NOON

(Late or incomplete nominations will NOT be considered)

RETURN FORMTO: Orillia Parks and Recreation Department50 Andrew Street South, Suite 300, Orillia ON L3V 7T5

ORILLIA FARMERS’ MARKETBegins again! 50 Andrew Street South, City Centre

7:30 a.m. to 12:30 p.m. this Saturday.You’ll love what our vendors have for you!

Baking (some gluten-free), preserves, honey products, beef products,knitwear, dips, onions, cold-cellar vegetables, garlic, potatoes, beef jerky,

meat pies, cabbage, maple syrup, parsnip, fabricwear.BUY LOCAL!

Bring your family, meet your friends.Enjoy sausage, somosa, soup, coffee.

Park in nearby Municipal Parking lots and City Centre lotat no charge while you shop.

Market continues through Winter indoors.

Smoking only in designated smoking area.Please do not walk your pet on the Market while you are shopping.

For information please telephone705-238-7955 or go online to our website:

www.orilliafarmersmarket.on.caor ‘like’ us on ‘Facebook’

Member: Farmers’ Markets Ontario;Orillia Chamber of Commerce;

Simcoe County Farm Fresh Marketing Association.

WASTEWATER SYSTEM MASTER PLANPUBLIC COMMENT INVITED

The City of Orillia is updating its Wastewater System Master Plan, which identifiesthe wastewater infrastructure requirements to service population growth, newdevelopments, and new service areas. The purpose of this Master Plan update isto address limitations related to the existing wastewater system, both with respectto existing services and future development.

This update will continue to follow the Municipal Class Environmental Assessmentprocess. By maintaining this approach, the updated Master Plan will satisfy thefirst two phases of the Class Environmental Assessment for Municipal Water andWastewater Projects. This will include a revised schedule of major works for futureplanning, design, and implementation.

Based on study findings, completed works, and the impact of the Lake SimcoeProtection Act and Regulations, the 2012 Wastewater Master Plan update providesan update of works carried out since the period covered by the 2004 Master Plan.It will also include revised projections, additional public consultation, and additionalrecommended works not a part of the original Master Plan.

Public input and comments are invited for incorporation into the wastewater systemmaster planning process, and will be received until January 31, 2012. Subject tocomments received, the City of Orillia intends to finalize the update by June 2012.Information will be collected in accordance with the Freedom of Information andProtection of Privacy Act.With the exception of personal information, all commentswill become part of the public record.

For further information on this project or to see a copy of the Municipal ClassEnvironmental Assessment document, please contact:

Jason Covey, P. Eng.Water & Wastewater Engineer

City of OrilliaPublic Works – Engineering Division50 Andrew Street South, Suite 300

Orillia, Ontario L3V 7T5Phone: 705-325-2227Email: [email protected]

CITY OF ORILLIA

THANK YOU2012 COUNCIL MEETING SCHEDULE

CITY OF ORILLIA

Office of the City Clerk705-325-1311

[email protected]

Regular Council Meetings - 7:30 p.m. - Council ChamberCouncil Committee Meetings (Open Session) - 7:00 p.m.- Council Chamber Council Committee Meetings (Closed

Session, if necessary) are held prior to the Open Session inthe Couchiching Boardroom (Main Floor)

**The July and August combined Council Committee + CouncilMeeting Dates shall be scheduled earlier in the day.

REMINDERUnder provincial legislation unpaid water and sanitary sewer billsbecome the responsibility of the property owner.

When a tenant vacates a property, the water and sewer accountwill be put in the name of the property owner. The property ownerwill then receive all water bills and notices unless we have writtenauthorization from the property owner to put the bills into the newtenant’s name.

The City will attempt collection from the tenant addressed on thebill. However, if unsuccessful, these charges will be added to theproperty’s tax roll.

The City’s collection efforts do not begin until 3 successive billingshave gone unpaid. Property owners may call the City regardingthe status of an account at any time during regular business hours.

JOB OPPORTUNITIES2012 SUMMER EMPLOYMENT OPPORTUNITIESPARKSAND RECREATION DEPARTMENTSummer Park/Facility Staff andSummer Camp StaffClosing Date: February 24, 2012 at Noon.

Please visit our website at www.orillia.ca for furtherinformation.

Severn Sound Environmental Association, North Simcoe Stewardship,and the City of Orillia are working together to provide residents withreasonably priced, native tree and shrub seedlings for planting in earlyspring 2012.

Tree seedlings must be pre-ordered. The deadline for ordering is Fri-day, January 27th, 2012.

Program details are available at the City of Orillia office and online atwww.severnsound.ca/trees.htm

2012 TREE SEEDLING DISTRIBUTION PROGRAM

CONTRACT NO. RWS-12-25RECONSTRUCTON OFWEST STREET

FROMTHE HIGHWAY 12 BYPASSTO OLIVE CRESCENT

Sealed tenders plainly marked as to content will be received by the City of Orillia,Public Works Department – Engineering Office, 50 Andrew Street South, Suite300, Orillia, Ontario, L3V 7T5 until:

Wednesday, January 25, 20121:00 p.m. (Local Time)

On the same day, commencing at 1:00 p.m., local time, the tenders will beopened and read publicly in the Brooks Boardroom, 50 Andrew Street South,Orillia, Ontario.

The work consists of reconstruction of West Street from the Highway 12 Bypassto Olive Crescent, including replacement of existing watermains and sanitarysewers as well as road reconstruction and appurtenant works as follows:

• installation of approximately 190m of 450mm diameter sanitary sewer andappurtenances

• installation of approximately 420m of 200mm diameter watermain• road reconstruction of approximately 560m

Test pits will be excavated on Wednesday, January 18, 2012 at 1:00 p.m.

Plans, Specifications and Contract Documents may be obtained from the City ofOrillia Public Works Department - Engineering Office for a non-refundable depositof $56.50 ($50.00 + $6.50 HST).

A certified cheque or bid bond of five percent (5%) of the tender shall besubmitted with the tender document.

The lowest or any tender not necessarily accepted.

TENDER

THE CORPORATION OFTHE CITY OF ORILLIATHE CORPORATION OFTHE CITY OF ORILLIAPUBLICWORKS DEPARTMENTPUBLICWORKS DEPARTMENT

Would like to say

Thank Youto our sponsor

for providing Free Bus Service for theNewYear’s Eve Bus Service 2011

1

Jason Covey

From: Don Boswell <[email protected]>Sent: December-15-11 12:07 PMTo: JASON COVEYCc: Ralph VachonSubject: City of Orillia Wastewater System Master Plan Update

I am writing in response to your letter of December 6, 2011 inquiring about claims in the above noted area. In determining your duty to consult, you may wish to contact the First Nations in the vicinity of your area of interest to advise them of your intentions. To do this you may:

1. find the Reserves in your area of interest by consulting a map of the region such as the Province of Ontario Ministry of Aboriginal Affairs online map at http://www.ainc-inac.gc.ca/ai/scr/on/rp/mcarte/mcarte-eng.asp ; then

2. search for the First Nations located on those Reserves by using the INAC Search by Reserve site at http://pse5-esd5.ainc-inac.gc.ca/fnp/Main/Search/SearchRV.aspx?lang=eng.

To determine the First Nations in your area of interest who have submitted claims please consult the Reporting Centre on Specific Claims at http://pse4-esd4.ainc-inac.gc.ca/SCBRI/Main/ReportingCentre/External/ExternalReporting.aspx?lang=eng. It should be noted that the reports available on the INAC website are updated regularly and therefore, you may want to check this site often for updates. In accordance with legislative requirements, confidential information has not been disclosed. Please rest assured that it is the policy of the Government of Canada as expressed in The Specific Claims Policy and Process Guide that:

“in any settlement of specific native claims the government will take third party interests into account. As a general rule, the government will not accept any settlement which will lead to third parties being dispossessed.”

We can only speak directly to claims filed under the Specific Claims Policy in the Province of Ontario. We cannot make any comments regarding potential or future claims, or claims filed under other departmental policies. This includes claims under Canada’s Comprehensive Claims Policy or legal action by a First Nation against the Crown. You may wish to contact the Assessment and Historical Research Directorate at (819) 994-6453, the Consultation and Accommodation Unit at (613) 944-9313 and Litigation Management and Resolution Branch at (819) 934-2185 directly for more information. You may also wish to visit http://www.ainc-inac.gc.ca/ai/mr/is/acp/acp-eng.asp on the INAC website for information regarding the Federal Action Plan on Aboriginal Consultation and Accommodation. To the best of our knowledge, the information we have provided you is current and up-to-date. However, this information may not be exhaustive with regard to your needs and you may wish to consider seeking information from other government and private sources (including Aboriginal

2

groups). In addition, please note that Canada does not act as a representative for any Aboriginal group for the purpose of any claim or the purpose of consultation. I hope this information will be of assistance to you. I trust that this satisfactorily addresses your concerns. Sincerely, Don Boswell Senior Claims Analyst Ontario Research Team Specific Claims Branch

1

Jason Covey

From: Dorton, Peter (MTO) <[email protected]>Sent: December-23-11 10:50 AMTo: JASON COVEYCc: Siddiqui, Fayyaz (MTO); O'Brien, Bernard (MTO); Jeganathan, Ayvun (MTO)Subject: City of Orillia Wastewater System Master Plan UpdateAttachments: orillia wastewater.pdf

Jason: In response to your attached circulation of December 6, 2011, MTO has no specific concerns or comments to offer at this time. Please be aware however that any proposed works with MTO highway right-of-way or in close proximity of MTO highways will be subject to MTO permit approvals (in accordance with Sections 34 and 38 of the Public Transportation and Highway improvement Act). We would suggest that any such proposals be circulated and reviewed with us early in the process. Please feel free to contact me if you have any questions Thanks, Peter Dorton Project Manager MTO Central Region Corridor Management Section 7th Floor, Building D 1201 Wilson Avenue Downsview, ON M3M 1J8 Ph: 416-235-4280 Fx: 416-235-4267 Email: [email protected]

1

Jason Covey

From: Ball, Jerry <[email protected]>Sent: January-18-12 4:35 PMTo: JASON COVEYSubject: Wastewater System Master Plan Update

Jason I have no definite concerns at this time, however I would ask that you keep me informed of the process.  In going forward and considering growth and new developments and our shared boundary it would beneficial for the Township of Oro‐Medonte  to be updated on the new Master Plan . Thank You 

Jerry Ball, CRSS Director Transportation & Environmental Services Township of Oro-Medonte       

  Please consider the environment before printing this email.

This e-mail may contain PRIVILEGED AND CONFIDENTIAL INFORMATION and is intended solely for the use of the individual or entity to whom it is addressed. If you are not the intended recipient, please notify the sender by e-mail. Further, you should not copy, disclose, or distribute this e-mail or its contents to any other person and any such actions are unlawful. This e-mail may contain viruses. The Township of Oro-Medonte has taken every reasonable precaution to minimize this risk, but is not liable for any damage you may sustain as a result of any virus in this e-mail. You should carry out your own virus checks before opening the e-mail or attachment. The Township of Oro-Medonte reserves the right to monitor and review the content of all messages sent to or from this e-mail address. Messages sent to or from this e-mail address may be stored on the Township of Oro-Medonte’s e-mail system.

MUNICIPAL CLASS ENVIRONMENTAL ASSESSMENT WASTEWATER SYSTEM MASTER PLAN 2012 UPDATE

NOTICE OF COMPLETION The City of Orillia has updated its Wastewater System Master Plan, which identifies the wastewater infrastructure requirements to service population growth, new development, and new service areas. The purpose of the Master Plan update is to address limitations related to the existing wastewater system, both with respect to existing services and future development. This update has continued to follow the Municipal Class Environmental Assessment process. By maintaining this approach, the updated Master Plan satisfies the first two phases of the Class Environmental Assessment for Municipal Water and Wastewater Projects. This includes a revised schedule of major works for future planning, design, and implementation. Based on study findings, completed works, and impacts of the Lake Simcoe Protection Act and Regulations, the 2012 Wastewater Master Plan update provides an update of works carried out since the period covered by the 2004 Master Plan. It also includes revised projections, additional public consultation, and additional recommended works not a part of the original Master Plan including: upgrades/improvements to the existing system, construction of new trunk sewer mains, construction of new sewage pumping stations, and upgrading/expanding the wastewater treatment system. In keeping with the master planning process these projects will be scheduled over a number of years with some projects completed in stages. For further information or to view a copy of the 2012 Wastewater System Master Plan Update, the existing Wastewater System Master Plan, or the Municipal Class Environmental Assessment, please contact Jason Covey, P. Eng., Water/Wastewater Engineer at the Department of Public Works – Engineering, 50 Andrew St. S., Suite 300, Orillia, ON, L3V 7T5, 705-325-2227 or [email protected]. Subject to comments received as a result of this Notice, the City intends to proceed with the works as scheduled. If concerns arise regarding this project that cannot be resolved in discussion with the municipality, a request may be sent to the Minister of the Environment for the project to comply with Part II of the Environmental Assessment Act (referred to as a Part ll Order), which addresses individual environmental assessments. Requests must be received by the Minister of the Environment at 135 St. Clair Avenue, 10th Floor, Toronto, ON M4V 1P5 within 30 calendar days of this Notice with a copy of the request sent to the City of Orillia’s Director of Public Works. Information will be collected in accordance with the Freedom of Information and Protection of Privacy Act. With the exception of personal information, all comments will become part of the public record. This Notice initially issued January 28th, 2013.

ENGINEERING DEPARTMENT

January 28, 2013 (Address)

Reference: City of Orillia Wastewater System Master Plan Update

The future development of the City of Orillia depends on the provision of adequate municipal

water and wastewater services. Master Plans are necessary to establish a framework to

specifically identify the water and wastewater infrastructure requirements to service population

growth, new developments, and new service areas. The City of Orillia’s Wastewater System

Master Plan was originally adopted in 2004 with the recommendation that it be revised and

updated every five (5) years to reflect changes and completed works within the system. Please

find enclosed a copy of the “Notice of Completion” for the 2012 Wastewater System Master Plan

Update that is to be published in the local papers January 31st, 2013 as well as posted on the

City’s website.

This project encompasses further monitoring and analysis of the existing systems, as well as

evaluation of alternative solutions. The ultimate aim of the project is to recommend, cost, phase,

and schedule major works for future budgeting and implementation, so that development can

progress in an orderly and sustainable manner.

The purpose of this letter is to notify you of the completion of the 2012 Wastewater System

Master Plan Update, and to solicit any comments or concerns you may have for consideration in

the planning process. These should be submitted to the City of Orillia Public Works Department,

Engineering Division by March 15th, 2013, so that specific information may be considered.

Subject to comments received, the City intends to proceed with the works as outlined in the

2012 Wastewater Master Plan Update.

TELEPHONE (705) 325-3975

[email protected]

ORILLIA CITY CENTRE 50 ANDREW ST. S., SUITE 300 ORILLIA, ON. L3V 7T5

Should you have any questions or comments with respect to the 2012 Wastewater Master Plan

Update, please contact:

Jason Covey, P. Eng.

Water & Wastewater Engineer

City of Orillia

Public Works – Engineering Division

50 Andrew Street South, Suite 300

Orillia, Ontario L3V 7T5

Phone: (705) 325-2227

Email: [email protected]

Sincerely,

Jason Covey, P. Eng.,

Water & Wastewater Engineer Enclosure

50 ANDREW ST. SOUTH, SUITE 300, ORILLIA 705-325-1311

www.orillia.ca

THURSDAY, JANUARY 31, 2013

ANNUAL VALVE OPERATING PROGRAM

The City’s Public Works Department will beconducting its annual valve operating program overthe next few months. This involves locating andoperating watermain valves within the City’s waterdistribution system. This preventive maintenancemeasure is necessary to ensure that valves areoperational and functional in the event of a failure.

During the operating program, residents may notice poor pressure and/or red-coloured water coming from their taps. The discoloured wateris not hazardous and the situation is temporary. But, if detected, thepublic is requested to simply open their cold water taps in order to clearthe system.

Please call 705-329-7249 if you have any questions.

NOTICE OF PUBLIC MEETINGPROPOSED FEE INCREASE ON BUILDINGPERMIT APPLICATIONS AND A REVISION

TO THE BUILDING BY-LAWTake Notice that the Council of the Corporation of the City of Orillia willhold a Public Meeting on Monday, February 4, 2013, at 6:15 p.m. inthe Council Chamber, Orillia City Centre, 50 Andrew St. S., to considerproposed fee increases by the City of Orillia to By-law Number 2007-17.

DescriptionBy-law Number 2007-17 sets out the requirements and fees forBuilding Permits in the City of Orillia. Pursuant to Section 7(6) ofthe Building Code Act, a public meeting is required concerning anyproposed changes.

Information AvailableAdditional information and material relating to the proposal is availablefor review in the Building Division Office at the Orillia City Centre, 3rdFloor, 50 Andrew Street S., Orillia. For further information, you maycontact Kelly Smith, Chief Building Official at 705-325-2214 or bye-mail at [email protected].

Dean Brody SOLD OUT February 12Dancock’s Dance various dates & times February 7-17Ballet Creole’s “Tounkande” February 20The Rez Sisters by Thomson Highway April 11 – 21The 39 Steps June 11 – July 12Forever Plaid July 16 – Aug. 9Same Time Next Year Aug. 13 – Sept. 13The Complete Works of William Shakespeare Sept.17 - 27“The Real Mr. d” 2013 Comedy Tour October 19

Visit www.orilliaoperahouse.caor call the box office at705-326-8011 for more

information or to buy tickets.

ORILLIA OPERA HOUSE

2013 SUMMER SEASONFLEX PACS NOW AVAILABLE!

4 GREAT SHOWS FOR1 GREAT PRICE!

BOARDS AND COMMITTEES VACANCIESThe City is currently seeking new members for the following Boards andCommittees:

• Commemorative Awards Committee• Orillia Youth Opportunities Committee – Student Members• Recreation Advisory Committee• Waste Management Advisory Committee

For Committee descriptions visit(www.orillia.ca/insidecityhall/boards&committees)Please note that qualifications vary by Committee and applicants may beinterviewed.

Application deadline is Noon on Monday, February 4, 2013.For more information or an application,

please contact the City Clerk’s Department705-325-1311 or [email protected]

ORILLIA FARMERS’ MARKETINDOOR VENDORS EVERY SATURDAY ALL WINTER

50 Andrew Street S., City Centre, 7:30 a.m. to 12:30p.m.

You’ll love what we have for you!

• Fresh baking (including gluten free) -cookies, bread, muffins, etc.

• Preserves, jams and jellies• Vegetables,maple syrup, honey andgranola, coated nuts

• Beef, cheese, eggs• Knitting, leather belts, soap, pottery, etc.

STAY FOR LUNCH and enjoy homemade hearty soups,samosas, sausage on a bun etc.

Park at the City Centre lot at no charge while you shop.For more information please call 705-238-7955 or go online to

website: www.orilliafarmersmarket.on.ca or “like” us on “Facebook”.

2013 TREE SEEDLING DISTRIBUTION PROGRAMSevern Sound Environmental Association, North SimcoeStewardship, and the City of Orillia are working together

to provide residents withreasonably priced, nativetree and shrub seedlings forplanting in early spring 2013.

Tree seedlings must be pre-ordered. The deadline forordering is Friday, January25th, 2013.

Program details are available online at www.severnsound.ca/trees.htm or by calling Michelle Hudolin at Severn SoundEnvironmental Association (705-527-5166 ext. 202).

NOTICE OF COMPLETION

MUNICIPAL CLASS ENVIRONMENTAL ASSESSMENTWASTEWATER SYSTEMMASTER PLAN 2012 UPDATE

The City of Orillia has updated its Wastewater SystemMaster Plan, which identifies the wastewater infrastructurerequirements to service population growth, new development,and new service areas. The purpose of the Master Plan updateis to address limitations related to the existing wastewatersystem, both with respect to existing services and futuredevelopment.

This update has continued to follow the Municipal ClassEnvironmental Assessment process. By maintaining thisapproach, the updatedMaster Plan satisfies the first two phasesof the Class Environmental Assessment for Municipal Waterand Wastewater Projects. This includes a revised schedule ofmajor works for future planning, design, and implementation.

Based on study findings, completed works, and impacts ofthe Lake Simcoe Protection Act and Regulations, the 2012Wastewater Master Plan update provides an update of workscarried out since the period covered by the 2004 MasterPlan. It also includes revised projections, additional publicconsultation, and additional recommended works not a part ofthe original Master Plan including: upgrades/improvements tothe existing system, construction of new trunk sewer mains,construction of new sewage pumping stations, and upgrading/expanding the wastewater treatment system. In keeping withthe master planning process these projects will be scheduledover a number of years with some projects completed instages.

For further information or to viewa copy of the 2012WastewaterSystem Master Plan Update, the existing Wastewater SystemMaster Plan, or theMunicipal Class Environmental Assessment,please contact Jason Covey, P. Eng., Water/WastewaterEngineer at the Department of Public Works – Engineering, 50Andrew St. S., Suite 300, Orillia, ON, L3V 7T5, 705-325-2227or [email protected].

Subject to comments received as a result of this Notice,the City intends to proceed with the works as scheduled. Ifconcerns arise regarding this project that cannot be resolvedin discussion with the municipality, a request may be sentto the Minister of the Environment for the project to complywith Part II of the Environmental Assessment Act (referred toas a Part ll Order), which addresses individual environmentalassessments. Requests must be received by the Minister ofthe Environment at 135 St. Clair Avenue, 10th Floor, Toronto,ON M4V 1P5 within 30 calendar days of this Notice with a copyof the request sent to the City of Orillia’s Director of PublicWorks. Information will be collected in accordance with theFreedom of Information and Protection of Privacy Act. With theexception of personal information, all comments will becomepart of the public record.

This Notice initially issued January 28th, 2013.

OVERNIGHT PARKING RESTRICTION

TENDERContract No. SST-13-27 – Closed-circuit television inspection(CCTV) of sanitary and storm sewer pipes.

The work under this contract includes supplying all labour,equipment, supervision and material to complete the CCTVinspection of approximately 10,000 metres of sanitary (90%)and storm sewer pipes (10%). Plans, specifications, and contractdocuments may be obtained from the Public Works Department.

Sealed tender plainly marked as to content will be received bythe City of Orillia, Public Works Department, 50 Andrew St. S.Suite 300, Orillia, Ontario, L3V 7T5 by Friday, February 15, 2013,1 p.m. (Local Time)

The lowest tender or any tender may not necessarily beaccepted.

For more information contact Kyle Mitchell at 705-325-3224 [email protected]

Monday, February 4, 2013Recreation Facilities Committee - TBD

Public Meeting re Building Permit Fees – 6:15 p.m.followed by Regular Council Meeting – 7:00 p.m.

Full Agenda Packages are available atwww.orillia.ca

Contact the City Clerk’s Department at 705-325-1311 or [email protected] toconfirm meeting schedules and meeting times.

Month at a GlanceMonday, February 11 – Council Committee

Monday, February 18 – No Meeting (Family Day)Monday, February 25 – Council

Monday, March 4 – Council Committee

UPCOMING MEETINGS

2013 interim tax bills for the City ofOrillia have been mailed. Installmentdates are March 15, 2013 and May15, 2013.

If you have not received yourbill please contact the TreasuryDepartment at 705-329-7239

Payments can be made at most Financial Institutions. Failure toreceive the tax bill does not relieve the property owner from paymentof taxes or liability for penalty for late payment.

INTERIM TAX BILLS

JOB OPPORTUNITYThe City’s Public Works Department – Environmental Servicesgroup has an opening for a Wastewater Treatment PlantOperator.

Compensation for this position is $20.71 to $26.88 per hourpursuant to the wage schedule for IBEW – Public Worksemployees and includes a comprehensive benefits package.For more information, specific job details and qualifications,visit www.orillia.ca

Applicants are invited to submit a resume in MS Word formatin confidence by February 8, 2013 at noon to:

Lori Bolton, CHRP,Director of Human Resources,

City of Orillia,50 Andrew St. S., Suite 300

Orillia, ON L3V 7T5Fax: 705-325-5904 Email: [email protected]

WASTE DIVERSION SITE HOURS

The City reminds residents that parkingis prohibited on any municipal street ormunicipal parking lot between the hoursof midnight and 7 a.m. from November 15,2012 through April 15, 2013.

Illegally parked cars can delay or impair theCity’s snow plowing and sanding operations. Illegally parkedvehicles will be ticketed and/or towed.

The City’s waste diversion site and household hazardous waste

depot, 100 Kitchener St, operate under the following winter

hours until March 31, 2013:

Monday – Friday 8:30 a.m. to 4:30 p.m.Saturday 8:30 a.m. to 1 p.m.

For more information about what you can dispose of, visit

www.orillia.ca or call 705-325-3522.

50 ANDREW ST. SOUTH, SUITE 300, ORILLIA 705-325-1311

www.orillia.ca

THURSDAY, FEBRUARY 7, 2013

ANNUAL VALVE OPERATING PROGRAM

Dean Brody SOLD OUT February 12Dancock’s Dance various dates & times February 7-17Ballet Creole’s “Tounkande” February 20The Rez Sisters by Thomson Highway April 11 – 21The 39 Steps June 11 – July 12Forever Plaid July 16 – Aug. 9Same Time Next Year Aug. 13 – Sept. 13The Complete Works of William Shakespeare Sept.17 - 27“The Real Mr. d” 2013 Comedy Tour October 19

Visit www.orilliaoperahouse.caor call the box office at705-326-8011 for more

information or to buy tickets.

ORILLIA OPERA HOUSE

2013 SUMMER SEASONFLEX PACS NOW AVAILABLE!

4 GREAT SHOWS FOR1 GREAT PRICE!

ORILLIA FARMERS’ MARKETINDOOR VENDORS EVERY SATURDAY ALL WINTER

50 Andrew Street S., City Centre, 7:30 a.m. to 12:30 p.m.On Saturday, February 9, 2013, the first 50 customers

wearing red will receive a Valentine Gift from thebooth of Kathy’s Kakes

• Fresh baking (including gluten free) -cookies, bread, muffins, etc.

• Preserves, jams and jellies• Vegetables,maple syrup, honey andgranola, coated nuts

• Beef, cheese, eggs• Knitting, leather belts, soap, pottery, etc.

Park at the City Centre lot at no charge while you shop.For more information please call 705-238-7955 or go online to

website: www.orilliafarmersmarket.on.ca or “like” us on “Facebook”.

JOB OPPORTUNITIESThe City’s Parks, Recreation and Culture Department hasopenings for summer contract employment. Opportunitiesinclude:

Submit a resume in confidence in MS Word format byFebruary 22, 2013 at noon to:

Lori Bolton, CHRP,Director of Human Resources,City of Orillia,50 Andrew St. S., Suite 300Orillia, ON L3V 7T5Fax: 705-325-5904Email: [email protected]

• Summer Coordinator• Waterfront Supervisor andAssistant Supervisor

• Camp Supervisor• Sports Coordinator• Lifeguard/Instructor• Camp Counsellor

• Turf Maintenance• Washroom Attendant• Special Event Maintenance• Horticulture• Facility Operator• Grounds Maintenance• Recycle/Garbage Program

RETAIL BUSINESS HOLIDAYS ACT

NOTICE OF COMPLETIONMUNICIPAL CLASS ENVIRONMENTAL ASSESSMENTWASTEWATER SYSTEMMASTER PLAN 2012 UPDATE

The City of Orillia has updated its Wastewater System MasterPlan, which identifies the wastewater infrastructure requirementsto service population growth, new development, and new serviceareas. The purpose of the Master Plan update is to addresslimitations related to the existing wastewater system, both withrespect to existing services and future development.

This update has continued to follow the Municipal ClassEnvironmental Assessment process. By maintaining this approach,the updated Master Plan satisfies the first two phases of the ClassEnvironmental Assessment for Municipal Water and WastewaterProjects. This includes a revised schedule of major works for futureplanning, design, and implementation.

Based on study findings, completed works, and impacts of theLake Simcoe Protection Act and Regulations, the 2012 WastewaterMaster Plan update provides an update of works carried out sincethe period covered by the 2004 Master Plan. It also includesrevised projections, additional public consultation, and additionalrecommended works not a part of the original Master Plan including:upgrades/improvements to the existing system, construction of newtrunk sewer mains, construction of new sewage pumping stations,and upgrading/expanding the wastewater treatment system. Inkeeping with the master planning process these projects will bescheduled over a number of years with some projects completedin stages.

For further information or to view a copy of the 2012 WastewaterSystem Master Plan Update, the existing Wastewater System MasterPlan, or the Municipal Class Environmental Assessment, pleasecontact Jason Covey, P. Eng., Water/Wastewater Engineer at theDepartment of Public Works – Engineering, 50 Andrew St. S., Suite300, Orillia, ON, L3V 7T5, 705-325-2227 or [email protected].

Subject to comments received as a result of this Notice, the Cityintends to proceed with the works as scheduled. If concernsarise regarding this project that cannot be resolved in discussionwith the municipality, a request may be sent to the Ministerof the Environment for the project to comply with Part II of theEnvironmental Assessment Act (referred to as a Part ll Order), whichaddresses individual environmental assessments. Requests must bereceived by the Minister of the Environment at 135 St. Clair Avenue,10th Floor, Toronto, ON M4V 1P5 within 30 calendar days of thisNotice with a copy of the request sent to the City of Orillia’s Directorof Public Works. Information will be collected in accordance withthe Freedom of Information and Protection of Privacy Act. With theexception of personal information, all comments will become part ofthe public record.

This Notice initially issued January 28th, 2013.

Monday, February 4, 2013Recreation Facilities Committee - TBD

Public Meeting re Building Permit Fees – 6:15 p.m.followed by Regular Council Meeting – 7 p.m.

Full Agenda Packages are available atwww.orillia.ca

Contact the City Clerk’s Department at 705-325-1311 or [email protected] toconfirm meeting schedules and meeting times.

Month at a GlanceMonday, February 11 – Council Committee

Monday, February 18 – No Meeting (Family Day)Monday, February 25 – Council

Monday, March 4 – Council Committee

UPCOMING MEETINGS

JOB OPPORTUNITYDIRECTOR OF PUBLIC WORKS

The City is seeking an accomplished professional to join their SeniorManagement Team as the Director of Public Works.

Duties:

• Direct, plan, manage and review the activities and operationsof the Public Works Department, which includes the Engineeringand maintenance of the Water Distribution and Sanitary SewerInfrastructure, Transportation (including transit) and Roads andParks Maintenance areas.

• Oversee the preparation of engineering plans and specifications,bidding, tendering, competency of contractors and vendors, andthe selection criteria for public contracts.

• Coordinate the preparation of reviews and updates to the sanitarysewer, water distribution piping system, and wastewater collectionpiping system in consultation with the Director of EnvironmentalServices.

• Monitor the project management for the construction of themunicipal public works projects.

• Responsible for all maintenance on roads, sidewalks, ditches,boulevards, storm sewers, snow plowing, street lights, trafficcontrols and traffic signage.

• Oversee the day-to-day operation and maintenance of the City’sparks and trails including all aspects of horticulture, arboriculture,turf maintenance, playgrounds, and boat launches.

• Prepare reports, make recommendations/presentations andattend Council Committee, Council Committee in Closed Session,Senior Management Team, community group, public and/or othermeetings as required.

Qualifications:

• University degree in Engineering or related field, together with atleast 10 years of management experience in a municipal unionizedenvironment.

• Possession of a Professional Engineering designation an asset.

• Considerable knowledge of civil engineering principles, practicesand methods as applicable to a municipal setting.

• Strong computer skills using MS Office applications, includingWord, Excel, Email, the Internet and Great Plains Dynamics.

•Possessexcellent public relations,writtenandoral communications,organizational and time management skills, with the ability to setpriorities.

• Must possess a valid Class “G” driver’s licence with an acceptabledriver’s abstract and reliable vehicle.

The salary range for this position is Category 11 of the Salary Grid forExempt staff $106,350 - $129,271, plus a comprehensive benefitspackage. Interested applicants are invited to submit a resume in (MSWord format) confidence by February 26, 2013 at noon to:

Lori Bolton, CHRP,Director of Human Resources,

City of Orillia,50 Andrew Street South, Suite 300,

Orillia, ON L3V 7T5Fax (705) [email protected]

WATERFRONT AREA CONCESSIONREQUEST FOR PROPOSALS

Proposals are invited from local entrepreneurs interested inproviding and operating a concession stand in 2013 at thefollowing locations:

J.B. Tudhope Memorial Park (one spot available)•

Westerly side of Centennial Drive, north of the former•Ossawippi Restaurant (two spots available)

Details and instructions to those interested in submitting aproposal are available at the City’s Clerk’s Office, 50 AndrewSt. S. Suite 300.

Deadline for sealed proposals is noon on Wednesday, February27, 2013 and will be received by Shawn Crawford, Manager ofLegislative Services, 50 Andrew St. S., Suite 300, Orillia, L3V 7T5.

2013 interim tax bills for the City ofOrillia have been mailed. Installmentdates are March 15, 2013 and May15, 2013.

If you have not received yourbill please contact the TreasuryDepartment at 705-329-7239

Payments can be made at most Financial Institutions. Failure toreceive the tax bill does not relieve the property owner from paymentof taxes or liability for penalty for late payment.

INTERIM TAX BILLS

BATTERY RECYCLINGBatteries should not be thrown out with your regulargarbage as they contain heavy metals that can leach intothe ground and cause damage to the environment. Spenthousehold batteries and rechargeable batteries can berecycled at the following locations in and around Orilliaat no charge:

Household Hazardous Waste Depot, 100 Kitchener St.•– Call 705-325-3522

Canadian Tire, 1017 Brodie Dr. – Call 705-325-7414•

Cavalcade Color Lab, 70 Front St. N.•– Call 705-326-4502

Future Shop, 3200 Monarch Dr. – Call 705-325-0519•

HD Supply Brafasco, 99 Forestview Rd.•– Call 705-326-2500

Home Depot, 3225 Monarch Dr. – Call 705-327-6500•

The Source, 1029 Brodie Dr. (Orillia Square Mall)•- Call 705-327-0145)

The Source, 975 West Ridge Blvd. – Call 705-325-1145•(accepts rechargeable batteries only)

For more information, please call the numberslisted above. If youwould like your business addedto this list, please call the Waste ManagementAdvisory Committee office at 705-329-2452.

Under the Retail Business Holidays Act the City of Orilliahas a by-law that allows smaller businesses to be openon all statutory holidays except Christmas Day, NewYear’s Day, Good Friday and Easter Sunday.

Larger stores that have 2,400 square feet of retailspace or more and employing four or more employeesare not covered under the general by-law and mustmake separate application to the City. A number oflarger businesses have done this. The process takesa minimum of 60 days and includes submitting anapplication to Council, with a $100 fee, a Public Meetingwith 30 days public notice, the consideration of a by-lawand, if passed, a 30-day appeal period.

If you are the owner or operator of a larger store andrequire further information, please contact Janet Nyhof,Deputy Clerk at the Orillia City Centre at 705-325-2108.

The City of Orillia Public Works Departmentwill be conducting its annual valve operatingprogram over the next few months. Thisinvolves locating and operating watermainvalves within the City’s water distributionsystem. This preventive maintenancemeasure is necessary to ensure that valvesare operational and functional in the event ofa failure.

During the operating program, residents may notice poorpressure and/or red-coloured water coming from their taps.The discoloured water is not hazardous and the situation istemporary. But, if detected, the public is requested to simplyopen their cold water taps in order to clear the system.

Please call 705-329-7249 if you have any questions.

1

Jason Covey

From: Dorton, Peter (MTO) <[email protected]>Sent: February-01-13 11:36 AMTo: Jason CoveyCc: Siddiqui, Fayyaz (MTO); O'Brien, Bernard (MTO); Jeganathan, Ayvun (MTO); Iannacito, Phil (MTO)Subject: RE: City of Orillia Wastewater System Master Plan UpdateAttachments: 20130201102011783.pdf

Hi Jason: In response to your attached circulation of January 28, 2013, comments provided below remain applicable. Thanks, Peter D.

From: Dorton, Peter (MTO) Sent: December 23, 2011 10:50 AM To: '[email protected]' Cc: Siddiqui, Fayyaz (MTO); O'Brien, Bernard (MTO); Jeganathan, Ayvun (MTO) Subject: City of Orillia Wastewater System Master Plan Update Jason: In response to your attached circulation of December 6, 2011, MTO has no specific concerns or comments to offer at this time. Please be aware however that any proposed works with MTO highway right-of-way or in close proximity of MTO highways will be subject to MTO permit approvals (in accordance with Sections 34 and 38 of the Public Transportation and Highway improvement Act). We would suggest that any such proposals be circulated and reviewed with us early in the process. Please feel free to contact me if you have any questions Thanks, Peter Dorton Project Manager MTO Central Region Corridor Management Section 7th Floor, Building D 1201 Wilson Avenue

2

Downsview, ON M3M 1J8 Ph: 416-235-4280 Fx: 416-235-4267 Email: [email protected]

1

Jason Covey

From: Jason CoveySent: February-04-13 10:21 AMTo: Liu, Chunmei (ENE)Cc: Panko, Dan (ENE); Percival Thomas; Andrew SchellSubject: RE: Wastewater System Master Plan Update

Ms. Liu, Thank you for speaking with me this morning on the phone. Per our conversation we will send a hardcopy to you for review following completion of the public review period and approval of the document by City Council. As discussed, the City of Orillia’s Wastewater Treatment Centre is not projected to require expansion until beyond the horizon of this Master Plan Update, due in part to slower than anticipated growth. Thank you, Jason R. Covey, P. Eng. Water & Wastewater Engineer Public Works - Engineering Division City of Orillia 705-325-2227 [email protected]  NOTICE: This e-mail contains information that may be confidential. If you are not the intended recipient, any disclosure or other use of this e-mail or the information contained in it or attached to it may be unlawful and is strictly prohibited. If you have received this e-mail in error, please notify the sender immediately and delete this e-mail without reading, printing, copying or forwarding it to anyone. Thank you for your kind cooperation. 

From: Liu, Chunmei (ENE) [mailto:[email protected]] Sent: Thursday, January 31, 2013 11:01 AM To: Jason Covey Cc: Panko, Dan (ENE) Subject: Wastewater System Master Plan Dear Mr. Covey, We received the Notice of Completion for the above-noted Class EA project. Please send us a hardcopy for review. Please also be aware that the ministry’s 30-day review starts when the Master Plan document is received. Thanks,

2

Chunmei Liu EA and Planning Coordinator 416-326-4886

1

Jason Covey

From: [email protected]: February-07-13 2:26 PMTo: Jason CoveySubject: Re: City of Orillia Wastewater System Master Plan

I will forward your letter to Tony  Thanks 

From: Jason Covey [mailto:[email protected]] Sent: Thursday, February 07, 2013 01:19 PM To: MCCORMICK Brian Subject: RE: City of Orillia Wastewater System Master Plan Mr. McCormick, Thank you for your response. I will ensure that our distribution list is updated for future master plans. Were you able to forward our letter to Mr. Ierullo or should we send him a copy directly? Thank you, Jason R. Covey, P. Eng. Water & Wastewater Engineer Public Works - Engineering Division City of Orillia 705-325-2227 [email protected]  NOTICE: This e-mail contains information that may be confidential. If you are not the intended recipient, any disclosure or other use of this e-mail or the information contained in it or attached to it may be unlawful and is strictly prohibited. If you have received this e-mail in error, please notify the sender immediately and delete this e-mail without reading, printing, copying or forwarding it to anyone. Thank you for your kind cooperation. 

From: [email protected] [mailto:[email protected]] Sent: Thursday, February 07, 2013 12:05 PM To: Jason Covey Subject: FW: City of Orillia Wastewater System Master Plan

2

  Thank you for your letter of Jan 28.    Please do not send letters to Hydro One reception.    If the request relates to planning or environmental assessment issues, you can address letters to   Mr Tony Ierullo Hydro One Networks Sustainment Investment Planning 483 Bay Street Toronto, ON M5G2P5  Thanks  Brian McCormick Mgr Environmental Services and Approvals Hydro One Networks