    JOB PROCEDURE FOR SOIL INVESTIGATION

    (PROCEDURENO: 6724-700-50-47-JP-001)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR, RATNAGIRI

    CLIENT : M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED

    . (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)

    CONSULTANT : M/s ENGINEERS INDIA LIMITED

    CONTRACTOR : M/s SAVAIR ENERGY LIMITED

    PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

    ORGANIZATION SEL SEL SEL EIL

    SIGNATURE

    NAME GANESH K. RAKESH P. MILIND D.

    DATE

  • 8/12/2019 Civil and Structural

    2/79

    Page2of

    (PROCEDURE NUMBER:6724-700-50-47-JP-001)

    JOB PROCEDURE FOR SOIL INVESTIGATION

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. PROCEDURE5. INSPECTIONS & RECORDS

  • 8/12/2019 Civil and Structural

    3/79

    Page3of

    PROCEDURE NO.6724-700-50-47-JP-001

    JOB PROCEDURE FOR SOIL INVESTIGATION

    1.0 PURPOSE The purpose of this procedure is for testing of soil and to ensure that proper quality control and system

    is exercised at site for design of compressor /other foundations as per codes / standards.

    2.0 SCOPE This procedure covers supervision and method of testing & record keeping for soil investigation.

    3.0 REFERENCE As per contract specifications IS Codes / Standards

    4.0 PROCEDURE: Area where soil testing to be done will be barricaded and ensured that no encumbrances are there Marking of testing location at site and same will be verified whether it is as per drawing or not Rig with mortar pump to be erected on testing points. Required water connection to be made, Drilling shall be started, Required level, required test, Samples can be collected and tested. Required test (SPT) Record to be maintained, Log book of boring to be maintained by SEL & periodic checking to be done by EIL/GAIL if required, Boring shall be done up to required depth as per contract / soil conditions All collected samples and test shall be carried out in approved lab and report generated, Finally all soil report shall be prepared. and submitted to EIL / GAIL

    5.0 RECORDS: Site inspection notes / Reports of site test as per ITP No: 6724-700-50-47-ITP-001 Review test & inspection documents.

  • 8/12/2019 Civil and Structural

    4/79

    INSPECTION & TEST PLAN FOR SOIL INVESTIGATION

    DOC.NO.6724-700-50-47-ITP-001

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRESSOR ,

    RATNAGIRI

    SR NO ACTIVITY SEL EIL

    RECORDS TO

    BE

    SUBMITTED/

    FORMAT NO

    Remarks

    1 POSITION OF TEST LOCATION WC S YES

    2 A) REVIEW OF CALIBRATION CERTIFICATESOF INSTRUMENTS / TESTING EQUIPMENTS

    B) FIELD CALIBRATION, IF ANY

    WC

    WC

    HP

    W

    YES

    YES

    Calibration

    Certificate t

    be submitted

    3 BORING & SAMPLING WC W YES4

    IN SITU TESTING (SPY, CPT, PILE LOAD

    TEST, ETC)WC S YES

    5 LAB TESTING (AS APPLICABLE) WC RW YES Test report tbe submitted

    6 MONITORING OF WATER LEVEL WC SINSPECTION & TEST DOCUMENTS

    REVIEW TEST & INSPECTION DOCUMENTSWC RW YES

    Prepared by Reviewed by Checked by Approved by

    SEL SEL SEL EIL

  • 8/12/2019 Civil and Structural

    5/79

    Page1of

    JOB PROCEDURE FOR EXCAVATION

    (PROCEDURENO: 6724-700-50-47-JP-002)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR, RATNAGIRI

    CLIENT : M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED

    . (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)

    CONSULTANT : M/s ENGINEERS INDIA LIMITED

    CONTRACTOR : M/s SAVAIR ENERGY LIMITED

    PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

    ORGANIZATION SEL SEL SEL EIL

    SIGNATURE

    NAME GANESH K. RAKESH P. MILIND D.

    DATE

  • 8/12/2019 Civil and Structural

    6/79

    Page2of

    (PROCEDURE NUMBER: 6724-700-50-47-JP-002)

    JOB PROCEDURE FOR EXCAVATION

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. PROCEDURE5. INSPECTIONS & RECORDS

  • 8/12/2019 Civil and Structural

    7/79

    Page3of

    JOB PROCEDURE FOR EXCAVATION

    1. PURPOSE The purpose of this procedure is for supervision of all excavation works and to ensure that proper quality

    control is exercised at site.

    2. SCOPE This procedure covers supervision of excavation work and method of record keeping for all earth work in

    soil, soft rock and hard rock.

    3. REFERENCE All works relating to excavation work will be confirmed to contract document. special condition design basis

    4. PROCEDURESURVEY WORK

    Initial survey to be done and locate the location of earth work as per approved drawings Survey to be done with reference to the existing plant foundation and reference drawing. With reference drawing centre line co ordinate to be marked at site (pegging) Excavation boundary line with margin to be marked. Initial joint level to be recorded and joint record to be maintained by SELEXCAVATION

    Initial excavation permission to be taken from plant in charge. Required barricading to be done. Location of existing underground system to be marked / if required manual trial pit will be done Earth work will be done by manually / mechanically as per the site condition. During the earth work required shoring & strutting will be done to hold the collapsed earth or foundation.

  • 8/12/2019 Civil and Structural

    8/79

    Page4of

    Required lighting arrangement will be done and other suitable measures for protection against accident duto open excavation.

    Making of dewatering arrangement so that excavation area to be dry. For hard rock, breaker to be made available with all safety measures and required permission. For any underground system across the excavation, necessary clearance to be obtained from Engineer - in

    charge.

    Excavation to be done in slope / steps as per the site condition. Final dressing to be done as per the drawing. Excavated earth will be stored at designated location without affecting plant operation and brought back fo

    back filling if found good.

    5. INSPECTION AND DOCUMENTATION All the excavation area shall be inspected for firm bed sides, leaks, location as given in the drawings. All excavation will be inspected by Engineer or the contractor. All inspection to be done as per approved ITP.

    Initial joint level record to be maintained by SEL

    Excavation bed level to be jointly recorded by SEL Measurement of shoring to be recorded. Soft rock / hard rock initial level and measurement to be recorded jointly and record to be submitted for

    information only to consultant

    Record to be submitted as per ITP NO : 6724-700-50-ITP-002

  • 8/12/2019 Civil and Structural

    9/79

    Page 1 of 2

    INSPECTION & TEST PLAN FOR EXCAVATION

    DOC.NO. : 6724-700-50-47-ITP-002

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR , RATNAGIRI

    SR

    NOACTIVITY SEL EIL

    RECORDS TO BE

    SUBMITTED/

    FORMAT NO

    Remarks

    1 a. Calibration certificate of measuring &testing / Instruments

    b.Field calibration, if any

    W

    W

    HP

    S

    YES

    YES

    2 Layout checkingW S

    YES As per

    Drawing

    3 Taking initial levels W S YES Level Record

    4 Slope of excavation, benching, overburden,

    shoring & Strutting (In case of deep

    excavation)

    W S

    5 Check for sub soil water, dewatering

    requirements As per specifications.W S

    6 Check for bottom level of excavation W S

    7 Stacking of different types of soils separatelyW S

    8 List of obstacle encountered (Cables, pipes,

    conduits Etc.)W S

    YES Make as built

    Drawing

  • 8/12/2019 Civil and Structural

    10/79

    Page 1 of 2

    9 Barricading of excavated pits for safety and

    Protection from rain. W S

    FOR HARD ROCK

    1 Obtaining license from district authorities for

    Undertaking blasting operation.W RW

    YES Permission

    Letter

    2 Storing of explosive materials as per

    explosive Rules.W S

    3 Prominent display of red flags around the

    area To be blasted.W S

    4 Check the dimensions of bore holes. W S

    5 Stacking of hard rock for useable/ non-

    useableW S

    INSPECTION & TEST DOCUMENTS

    Completeness of inspection and test records W RW YES (As Per ITP)

    Prepared by Reviewed by Checked by Approved by

    SEL SEL SEL EIL

  • 8/12/2019 Civil and Structural

    11/79

    Page1of

    JOB PROCEDURE FOR BACKFILLING

    (PROCEDURENO: 6724-700-50-47-JP-003)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR, RATNAGIRI

    CLIENT : M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED

    . (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)

    CONSULTANT : M/s ENGINEERS INDIA LIMITED

    CONTRACTOR : M/s SAVAIR ENERGY LIMITED

    PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

    ORGANIZATION SEL SEL SEL EIL

    SIGNATURE

    NAME GANESH K. RAKESH P. MILIND D.

    DATE

  • 8/12/2019 Civil and Structural

    12/79

    Page2of

    (PROCEDURE NUMBER:6724-700-50-47-JP-003 )

    JOB PROCEDURE FOR BACKFILLING

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. MATERIAL5. PROCEDURE6. INSPECTIONS & RECORDS

  • 8/12/2019 Civil and Structural

    13/79

    Page3of

    JOB PROCEDURE FOR BACKFILLING

    1.0 PURPOSE The purpose of this procedure is for supervision of all backfilling works and to ensure that proper quality

    control is exercised at site.

    2.0 SCOPE This procedure covers supervision of job and method of record keeping for all backfilling work.

    3.0 REFERENCE All works relating to backfilling work will confirm to contract document.

    4.0 MATERIAL Backfilling soil to be approved by Engineer in charge. Required soil testing prior to backfilling to be done.

    5.0 PROCEDURE Before backfilling area to be cleaned and backfilling permission to be obtained from EIL. Backfilling around foundation shall be with suitable soil Backfilling shall be done in layer as specified in specification and compacted till 95 % of max. Dry density i

    achieved with watering, rolling and ramming by manually / mechanically by compactor up to the level

    shown in drawing.

    Required test of compaction shall be carried out layer by layer and recorded jointly.6.0 INSPECTION & DOCUMENTATION

    Each & every layer to be inspected by Engineer as per ITP No : 6724-700-50-47-ITP-003 Required compaction test to be taken with the consultation of Engineer in charge and lab test

    conducted

    Compaction record to be maintained as per ITP

  • 8/12/2019 Civil and Structural

    14/79

    INSPECTION & TEST PLAN FOR BACKFILLING

    DOC. NO. - 6724-700-50-47-ITP-003

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRESSOR ,

    RATNAGIRI

    SR

    NOACTIVITY SEL EIL

    RECORDS TO BE

    SUBMITTED/

    FORMAT NO

    Remarks

    1 Checking of Materials i.e. Earth WC S Yes2

    Adequate slope, benching in excavation forsafety

    WC S3

    Calibration certificate of measuring & testing

    Field calibration, if any.

    WC

    WC HPS YesYes4 Layout, line & level. WC S5

    Ensure proper laying & joining, grouting atManholes/ chambers prior to back filling

    WC S6

    Check for supports / firm bed / sub soilwater level.

    WC S7 Testing for leakages by blocking pipe ends. WC W8

    Hydrostatic testing and other tests, removalof Blockages, cleaning & flushing of system

    WC HP Yes9 Back filling in layers consolidating & watering WC S Yes10 Compaction Test WC RM Yes11

    Check for MS rungs in proper position, inlet /Outlet pipe levels in manholes.

    WC S12 Soil Treatment , if any WC RM13 Preparation of As built drawings WC RW Yes

    INSPECTION & TEST DOCUMENTS

    Completeness of inspection and test records WC RW Yes

    Prepared by Reviewed by Checked By Approved by

    SEL SEL SEL EIL

  • 8/12/2019 Civil and Structural

    15/79

    Page1of

    JOB PROCEDURE FOR BLACK TOPPING(PREMIX CARPETING)

    (PROCEDURENO: 6724-700-50-47-JP-004)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR, RATNAGIRI

    CLIENT : M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED

    . (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)

    CONSULTANT : M/s ENGINEERS INDIA LIMITED

    CONTRACTOR : M/s SAVAIR ENERGY LIMITED

    PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

    ORGANIZATION SEL SEL EIL EIL

    SIGNATURE

    NAME GANESH K. RAKESH P. MILIND D.

    DATE

  • 8/12/2019 Civil and Structural

    16/79

    Page2of

    (PROCEDURE NUMBER: 6724-700-50-47-JP-004)

    JOB PROCEDURE FOR BLACK TOPPING (PREMIX CARPETING)

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. PROCEDURE5. INSPECTIONS & RECORDS

  • 8/12/2019 Civil and Structural

    17/79

    Page3of

    JOB PROCEDURE FOR BLACK TOPPING (PREMIX CARPETING)

    1. PURPOSEThe purpose of this procedure is for supervision of Black Topping for road work and to insure that proper

    quality control is exercised at site

    2. SCOPEThis procedure covers supervision of Black Topping for road work and method of record keeping for all

    Black Topping at site.

    3. REFERENCE All work related to Black Topping will be conformed to EIL contract document IS codes Design Basis

    4. MATERIALRequired material for Black Topping shall be as per EIL specifications

    5. PROCEDURE Material approval to be done Review of calibration of plant Review of calibration of instrument/ testing of equipment WBM top surface to be properly clean , and joint around aggregate to be clean properly Checking of road camber / level

    Tack coat to be applied as per specification

    Required thickness of premix carpeting after rolling to be spread During the spreading of premix carpet, bitumen temperature and its consumption to be check Take the premix sample for check test (as applicable) Seal coat to be spread over the premix carpet

  • 8/12/2019 Civil and Structural

    18/79

    Page4of

    Finally compacted thickness of black topping to be checked and it should be as per drawing / specifiedin specification.

    Prepared the berm by sites of road in specified width Remove all surplus earth from the road sites & dumped designated area Final inspection of black topping will done jointly and any defect found to be repaired immediately.

    6. INSPECTION AND TEST DOCUMENTReview of test and inspection reports as per ITP NO 6724-700-50-47-ITP-004

  • 8/12/2019 Civil and Structural

    19/79

    INSPECTION & TEST PLAN FOR BLACK TOPPING

    DOC. NO. - 6724-700-50-47-ITP-004

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR , RATNAGIRI

    Sr.No.

    Activities SEL EIL Record tosubmitted

    Remarks

    1 Approval of source of materials WC Rw

    2 Review of calibration certificates of instruments / testing

    equipments

    Field calibration if any

    WC

    WC

    HP

    W

    3 Surface preparation & check for camber / level WC S

    4 Checking/ testing of material wherever required WC W

    5 Tack coat application WC S

    6Premix carpeting(including thickness of carpeting) and

    rollingWC S

    7 Seal coat (Including thickness of seal coat) WC S

    8 Check for camber and levels WC S

    9 Check for bitumen temperature and consumption WC S

    10 Premix sample check test (as applicable) WC W

    11 Removal of surplus earth WC S

    12 Berm preparation WC S

    13 Final inspection WC HP

    INSPECTION AND TEST DOCUMENTSReview test and inspection documents

    WC Rw

    PREPARED BY REVIEWED BY CHECKED BY APPROVED BY

    SEL SEL SEL EIL

  • 8/12/2019 Civil and Structural

    20/79

  • 8/12/2019 Civil and Structural

    21/79

    Page2of

    (PROCEDURE NUMBER: 6724-700-50-47-JP-005)

    JOB PROCEDURE FOR CONCRETING WORK

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. MATERIAL5. PROCEDURE6. INSPECTIONS & DOCUMENTATION

  • 8/12/2019 Civil and Structural

    22/79

    Page3of

    JOB PROCEDURE FOR CONCRETING WORK

    1.0 PURPOSE The purpose of this procedure is for supervision of concreting works and ensures that proper quality

    control is exercised at site.

    2.0 SCOPE The procedure covers supervision of concreting works and method of record keeping for concreting

    work at site.

    3.0 REFERENCE All plain and reinforced concrete work will comply with the requirements mentioned in EIL specification Design Basis

    4.0 MATERIALAll material required for the concreting / RCC work shall be as per EIL specification

    5.0 PROCEDUREFor PCC / RCC approval of design mix

    Required grade concrete to be approved by mix design / RMC Trial cubes will be taken at batching plant / at site as per the design mix of specified grade of contract

    as per design

    Testing will be done at 3 days, 7 days, and 28 days. If results are found acceptable then design mix / RMC will be approved. Bed level of excavation shall be checked jointly by contractor and consultant and permission may be

    obtained to do the PCC work.

    Required shuttering to be done as per the drawing with proper supports and height. Reinforcement steel bars which are bending earlier as per the approved bar bending schedule are to be

    placed as per drawings and bindings as per specified wires.

    Required laps, chairs, spacer bars to be provided.

  • 8/12/2019 Civil and Structural

    23/79

    Page4of

    Required bolts, inserts, plates, openings / pockets to be fixed as per drawings. Top level of concrete to be marked on shuttering. Pre pour checking by our Engineer and consultant to be done and obtained the clearance for

    concreting the next day.

    Concreting will be done by mixer m/c / RMC which is required to meet quality standards Concreting will be done in layer and compaction of concrete will be done by vibrator machines in

    layers.

    Finally top of concrete will be finished as required in spec. drawings and shall match exact foundationtop

    Required testing cubes will be taken for testing of desired strength at 7 days, & 28 days in approvedlab.

    From next day onward cubes will be puts under the water filled tank/sump. Shuttering will be removed after 24 hours and surfaces to be observed and seen that concrete will be

    ok or not.

    Compressor foundation to be done in single pour only (monolithic)6.0 INSPECTION & DOCUMENTATION

    Vibrating & compaction of concreting to be inspected during concrete. Cubes to be taken and its to be numbers, with date of casting grade, fdn. no,

    Location etc

    Final finishing to be observed. Pre pour cards to be filled up before concreting. Pour concrete to be filled up after concreting. Records of material / RMC to be submitted. Others will be as per ITP No : 6724-700-50-47-JP-005A, 6724-700-50-47-JP-005B, 6724-700-50-47-JP-

    005C, 6724-700-50-47-JP-005D

  • 8/12/2019 Civil and Structural

    24/79

    INSPECTION & TEST PLAN FOR PLAIN CEMENT CONCRETE (PCC)

    DOC.NO.- 6724-700-50-47-JP-ITP-005A

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR , RATNAGIRI

    SR

    NOACTIVITY SEL EIL

    RECORDS TO

    BE

    SUBMITTED/

    FORMAT NO

    Remarks

    1

    a. Review of calibration certificates ofinstruments / testing Equipments.

    b. Field calibration, if any.

    WC

    WCHP

    W

    2Checking of layout and materials,

    compaction of sub gradeWC S

    3 Mix proportion. WC S

    4 Check for shuttering, dewatering if any WC S5 Concreting with proper compaction. WC S6 Checking of top level of PCC. WC S YES7 Curing. WC S

    INSPECTION & TEST DOCUMENTS

    Review test and inspection documents. WC RW

    Prepared By Reviewer by Checked By Approved by

    SEL SEL SEL EIL

  • 8/12/2019 Civil and Structural

    25/79

    INSPECTION & TEST PLAN FOR RCC ( SUB STRUCTURE)

    DOC.NO.- 6724-700-50-47-JP-ITP-005B

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRESSOR ,

    RATNAGIRI

    SR

    NOACTIVITY SEL EIL

    RECORDS TO

    BE

    SUBMITTED/

    FORMAT NO

    Remarks

    1 Approval of source of materials. WC RW YES2

    Approval of agency for providing Ready

    Mix concrete (RMC)WC W YES APPROVED

    VENDOR

    3

    a) Calibration certificate of measuring& testing Equipments / instruments

    of RMC plant

    b)

    Field calibration, if any

    WC

    WCHP

    W

    YES

    YES

    4Checking of layout & condition of PCC /

    Leveling course.WC S YES

    5 Checking / testing of materials. WC S YES6 Design Mix Approval WC HP YES Design mix doc7

    Check for line & level of shuttering including

    Its condition, quality and rigidity.WC S

    8Check for sub-soil water & dewateringarrangement, if any

    WC S YES

    9Placing of reinforcement & covers to

    reinforcement.WC W

    10Check for inserts, Anchor bolts and pipe

    sleeves, pockets etc.WC S YES

  • 8/12/2019 Civil and Structural

    26/79

  • 8/12/2019 Civil and Structural

    27/79

    INSPECTION & TEST PLAN FOR RCC ( SUPER STRUCTURE)

    DOC.NO.- 6724-700-50-47-JP-ITP-005C

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR , RATNAGIRI

    SR

    NOACTIVITY SEL EIL

    RECORDS TO BE

    SUBMITTED/

    FORMAT NO

    Remarks

    1 Approval of source of materials. WC RW2

    Approval of agency for providing Ready Mixconcrete (RMC)

    WC W YES

    3

    a) Calibration certificate of measuring &testing Equipments / instruments of RMCPlant

    b) Field calibration, if any

    WC

    WCHP

    W

    YES

    YES

    4 Checking of layouts WC S YES5 Checking / testing of materials. WC RW YES6 Design Mix Approval WC HP YES7

    Check for line & level of shuttering andscaffolding / Vertical bracing includinghoisting arrangement.

    WC S8

    Placing of reinforcement & covers toreinforcement

    WC W9

    Check for inserts, bolts, pipe sleeves, MSrungs, concealed Electrical conduits, fanhooks, dowel, welding etc. if any.

    WC S YES10 Check for pockets / openings WC S11 Check for expansion joints, if any WC S12

    Check for water stoppers, slopes, stoppers, ifany

    WC S13 Pour Card WC HP 6724-700-50-47-IR-001 &

    002

    14Quality records of RMC like Delivery Ticketinformation

    WC RW YES15 Concreting, testing, compaction, & finishing. WC RM YES16 Casting of cubes. WC RM

    17 Curing. WC S

  • 8/12/2019 Civil and Structural

    28/79

  • 8/12/2019 Civil and Structural

    29/79

    INSPECTION & TEST PLAN FOR RCC (CRITICAL STRUCTURE)

    DOC.NO.- 6724-700-50-47-JP-ITP-005D

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRESSOR ,

    RATNAGIRI

    SRNO

    ACTIVITY SEL EIL

    RECORDS TO BE

    SUBMITTED/

    FORMAT NO

    Remarks

    1 Approval of source of materials. WC RW YES2 Approval of agency for providing Ready

    Mixed Concrete (RMC)WC RW YES

    3Calibration certificate of measuring & testingequipments / instruments

    WC RW YES4 Checking of layout. WC S YES5 Checking / testing of materials. WC W YES6 Soil strata below PCC WC S7 Design of Mix. WC HP YES8

    Check for line & level of shuttering and

    scaffolding / vertical bracing Includinghoisting arrangements, shoring and strutting. WC

    S

    9Placing of reinforcement & coverts toreinforcement

    WC S10

    Check for inserts, Anchor bolts, pipe sleeves,MS rungs, concealed electrical Conduits, fanhooks, dowel, etc. including welding if any

    WC W YES11 Check or pockets / openings WC W12

    Detailed work plan including equipment,manpower & other sources

    WC RW YES13 Pour Card. WC HP 6724-700-50-47-IR-001 &

    002

    14Quality records of RMC like delivery ticket

    InformationWC RW YES

    15 Concreting, testing, Compaction & finishing. WC W YES

  • 8/12/2019 Civil and Structural

    30/79

    16 Casting of Cubes WC RW

    17 Curing. WC S

    18

    Testing of cubes. 7 Days

    28 Days

    WC

    WC

    RW

    W

    6724-700-50-47-IR-003

    19 Removal if formwork / staging WC20

    Verification of dimension viz. AFC drawingsand tolerances

    WCS YES

    21 Check for water tightness, rendering, if any. WC S

    22 Preparation of As built drawings. WC RW YES

    INSPECTION & TEST OCUMENTS

    Completeness of inspection and test records WC RW YES

    Note: Compressor Foundation shall be done by Single pour only

    Prepared By Reviewed by Checked By Approved by

    SEL SEL SEL EIL

  • 8/12/2019 Civil and Structural

    31/79

    Page 1 of 2

    POUR CARD I (PROGRAMME OF CONCRETING)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTERCOMPRESSOR , RATNAGIRI

    CLIENT : M/s RGPPL, RATNAGIRI FORMAT NO: 6724-700-50-47-IR-001 REV.NO. - 0

    PMC : M/s EIL REPORT NO :

    DATE :

    1. Reference document :

    2. Type of Structure :

    3. Levels From : To :

    4. Grade of Concrete / Approved Design Mix

    5. Brand Name, Grade and consignment no. cement

    6. Estimated volume of concrete :

    7. Quantity of cement required :

    8. Reinforcement checking details :

    No. Dia. Length

    a) Laps

    b) Separators

    c) Chairs

    d) Any other

    Remarks

  • 8/12/2019 Civil and Structural

    32/79

  • 8/12/2019 Civil and Structural

    33/79

  • 8/12/2019 Civil and Structural

    34/79

    Page 2 of 2

    8. Number of cubes taken :

    9. Quantity of concrete poured :

    10. Pour completion time : AM/PM : Date :

    11. Curing Method

    Traditional Curing compound

    Blankets / foils / gunny bags Others ( specify)

    12. Period for removal of form work.

    13. Any defect (s) observed during concreting :

    M/s SAVAIR ENERGY LIMITED M/s GAIL/EIL

    NAME

    SIGN

    DATE

  • 8/12/2019 Civil and Structural

    35/79

    Name of work :

    Reference : Type of Cement :

    W / C Ratio : Max. size of Aggregate

    CRUSHING STRENGTH RESULTS OF CONCRETE CUBES

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRE

    CLIENT : M/s RGPPL, RATNAGIRI FORMAT NO: 6724-700-50-47-IR-003

    PMC : M/s EIL REPORT NO :

    DATE :

    CubeNo.

    Id.MarkOn

    Cube

    Type &Location

    ofStructure

    Date of Age(days)

    Dimensions of Cube Vol.of

    Cube(m)

    Wt.of

    Cube(kg)

    Unit WT.(kg/m)

    SurfaceArea(cm)Casting Testing L

    (Cm)B

    (Cm)H

    (Cm)

  • 8/12/2019 Civil and Structural

    36/79

    M/s SAVAIR ENERGY LIMITED M/s GA

    NAME

    SIGN

    DATE

  • 8/12/2019 Civil and Structural

    37/79

    Page1of

    JOB PROCEDURE FOR MICRO GRADING

    (PROCEDURENO: 6724-700-50-47-JP-006)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR, RATNAGIRI

    CLIENT : M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED

    . (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)

    CONSULTANT : M/s ENGINEERS INDIA LIMITED

    CONTRACTOR : M/s SAVAIR ENERGY LIMITED

    PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

    ORGANIZATION SEL SEL SEL EIL

    SIGNATURE

    NAME Ganesh K. Rakesh P. Milind D.

    DATE

  • 8/12/2019 Civil and Structural

    38/79

    Page2of

    (PROCEDURE NUMBER:6724-700-50-47-JP-006)

    JOB PROCEDURE FOR MICRO GRADING

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. PROCEDURE5. INSPECTIONS & RECORDS

  • 8/12/2019 Civil and Structural

    39/79

    Page3of

    JOB PROCEDURE FOR MICRO GRADING

    1. PURPOSEThe purpose of this procedure is for supervision of micro grading work and to insure that proper quality

    control is exercised at site

    2. SCOPEThis procedure covers supervision of micro grading and method of record keeping for micro grading work

    at site.

    3. REFERENCE All work related to micro grading shall be as per specification

    4. PROCEDURE Review the calibrating certificate of instrument Take the initial level of micro grading area Remove the extra soil , debris, where level is higher than the required and back fill the soil where level

    is lower

    Area to be graded in gradient so that water can easily flow in drain Finish the area with small roller or with hand compactor Take final level & record it Final inspection will be made jointly

    5. INSPECTION AND TEST DOCUMENTReview test and inspection reports with level records as per ITP No 6724-700-50-47-ITP-006

  • 8/12/2019 Civil and Structural

    40/79

  • 8/12/2019 Civil and Structural

    41/79

    Page1of

    JOB PROCEDURE FOR STRUCTURAL STEEL WORK

    (PROCEDURENO: 6724-700-50-47-JP-007)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR, RATNAGIRI

    CLIENT : M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED

    . (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)

    CONSULTANT : M/s ENGINEERS INDIA LIMITED

    CONTRACTOR : M/s SAVAIR ENERGY LIMITED

    PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

    ORGANIZATION SEL SEL SEL EIL

    SIGNATURE

    NAME GANESH K. RAKESH P. MILIND D.

    DATE

  • 8/12/2019 Civil and Structural

    42/79

    Page2of

    (PROCEDURE NUMBER:6724-700-50-47-JP-007)

    JOB PROCEDURE FOR STRUCTURAL STEEL WORK

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. MATERIAL5. PROCEDURE6. INSPECTIONS & DOCUMENTATION

  • 8/12/2019 Civil and Structural

    43/79

    Page3of

    JOB PROCEDURE FOR STRUCTURAL STEEL WORK

    1.0 PURPOSE The purpose of this procedure is for supervision of structural steel works and to ensure that proper

    quality control is exercised at site.

    2.0 SCOPE The procedure covers supervision and method of record keeping for structural steel work at site.

    3.0

    REFERENCE

    All structural steel work will comply with the requirements mentioned in EIL specification and shop /field painting as per EIL specification and respective IS, BIS, SP codes and specification.

    IS Codes Design Basis

    4.0 MATERIAL All material shall be confirm to their respective specifications given in EIL specification and IS codes,

    BIS, SP codes.

    5.0 PROCEDURE Material to be procured from standard / approved vendors only with all MTC reports. If MTC are not

    available / co related with materials will be tested with approved lab taking samples from received

    material at site.

    Qualified welder to be qualified / approved before taking up the welding job. Shop fabrication will be made before starting of actual fabrication at site and approved on the basis of

    design drawings.

    On the basis of shop fabrication drawing, actual fabrication of structural steel shall start. Periodical checking / inspection will be done by our Engineer & necessary approval may be obtained. Fit up checking / alignment checking will be done by Engineer & required clearance will be obtained. After complete fabrication completed final checking / clearance will be done by us / consultant as per

    ITP

  • 8/12/2019 Civil and Structural

    44/79

    Page4of

    Fabricated material will be shifted to shot blasting shed and surface will be prepared by shot blasting(Sa 2.5) and primer painting as per EIL Specification, shall be done. Inspection will be by Engineer /

    EIL as per ITPs

    Material will be transported to site from fabrication shop after primer painting Foundation top to be chipped off properly to binding grouting material Nuts / bolt be grease level

    plates to be ground.

    Required capacity crane to be arranged and erection of structural will be done; proper nuts with locknuts tighten.

    After alignments of main structural balance component to be fixed and final alignment to be done andapproval to be taken from consultant.

    Welding work shall start as per EIL specification and on final welding completed necessary clearancewill be obtained.

    No compromise shall be made on moment connections and weld length for structural steel in bracing& to which shall be as per standards & IS

    After completion of all final welding, weld joints shall be cleaned & painting to be done as per EILspecification

    Finally handing to be done and document to be submitted, All above work shall be done with all safety precaution

    6. INSPECTION & DOCUMENTATION Periodically inspection will be got it to EIL. Final alignment report to be prepared. All fit up; weld visual, etc. record to be submitted. Handing over report to be submitted. All test reports of material to be submitted. Record to be submitted as per ITP NO : 6724-700-50-47-ITP-007

  • 8/12/2019 Civil and Structural

    45/79

    INSPECTION & TEST PLAN FOR STRUCTURAL STEEL WORK

    DOC.NO.6724-700-50-47-ITP-007

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRESSOR ,

    RATNAGIRI

    Sr.

    NoActivity SEL EIL

    Records To Be

    Submitted/

    Format No

    Remarks

    A PRE FABRICATION ACTIVITIES

    1

    a) Reviews\ of calibration certificates ofinstruments / testing.

    b) b) Field calibration, if any.WC

    HP

    W

    YES

    2

    Checking of structural steel materials supplied by

    the contractor / Manufacturers test certificate /

    testing (as applicable).

    WC RW YES

    3

    Welding Filler material approval / qualification.

    a) Manufacturing test certificates / documents.b) Testing, if any.

    WC RW

    4 WPS / PQR WC W YES5 Welders performance qualification. WC W YES6 Layout checking. WC S7 Welding equipment and accessories. WC S8 Preparation and approval of fabrication drawings. WC RW YESB FABRICATION ACTIVITIES

    1 Materials as per design drawing WC RW2 Check straightness and non-warping of members. WC S3 Dimensional and fit-up checks including provision WC S YES

  • 8/12/2019 Civil and Structural

    46/79

  • 8/12/2019 Civil and Structural

    47/79

    Name of Work :

    Reference No. : Location / co-ordinates / gr

    Layout clearance obtained : Yes / No

    SL.No.

    ItemNo.

    Material &Dimensionalclearance

    Shop Fit up ShopWelding

    Cleaning &PrimerPainting

    ErectionFit Up

    Alignment& Leveling

    FieldWelding

    Gc

    SEL EIL SEL. EIL SEL EIL SEL EIL SEL EIL SEL EIL S

    STRUCTURE FABRICATION AND ERECTION REPORT

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRE

    CLIENT : M/s RGPPL, RATNAGIRI FORMAT NO: 6724-700-50-47-IR-004

    PMC : M/s EIL REPORT NO :

    DATE :

  • 8/12/2019 Civil and Structural

    48/79

    M/s SAVAIR ENERGY LIMITED M/s GA

    NAME

    SIGN

    DATE

  • 8/12/2019 Civil and Structural

    49/79

    Name of work: ______________________________ Location/coordinates

    Reference no : _______________________________ Layout clearance obt

    Sr No Item No Material anddimensionalclearance

    Plumb reading onNorth/ south face

    Plumb reading onWest/ east face

    Alignment &level ok/not

    S

    A B A B ALIGN LEVEL

    STRUCTURAL COLUMN VERTICALITY CHECKING REPORT

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRE

    CLIENT : M/s RGPPL, RATNAGIRI FORMAT NO: 6724-700-50-47-IR-005

    PMC : M/s EIL REPORT NO :

    DATE :

  • 8/12/2019 Civil and Structural

    50/79

    M/s SAVAIR ENERGY LIMITED M/s GA

    NAME

    SIGN

    DATE

  • 8/12/2019 Civil and Structural

    51/79

    Page1of

    JOB PROCEDURE FOR SHEETING WORK

    (PROCEDURENO: 6724-700-50-47-JP-008)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR, RATNAGIRI

    CLIENT : M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED

    . (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)

    CONSULTANT : M/s ENGINEERS INDIA LIMITED

    CONTRACTOR : M/s SAVAIR ENERGY LIMITED

    PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

    ORGANIZATION SEL SEL SEL EIL

    SIGNATURE

    NAME Ganesh K. Rakesh P. Milind D.

    DATE

  • 8/12/2019 Civil and Structural

    52/79

    Page2of

    (PROCEDURE NUMBER:6724-700-50-47-JP-008 )

    JOB PROCEDURE FOR SHEETING WORK

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. PROCEDURE5. INSPECTIONS & RECORDS

  • 8/12/2019 Civil and Structural

    53/79

    Page3of

    JOB PROCEDURE FOR SHEETING WORK

    1. PURPOSEThe purpose of this procedure is for supervision of sheeting work and to insure that proper quality control

    exercised at site

    2. SCOPEThis procedure covers supervision of sheeting work and method of record keeping for all sheeting work at site

    3. REFERENCE Sheeting work will be conformed to EIL contract document Contract manual Standards Material Sheeting shall be conformed to EIL contract document IS codes Design Basis Special condition

    4. PROCEDURE Shed roof structure to be completed in all respect like truss, purling, rigid ,welding, alignment, level etc Take all safety requirement before erection of sheet on roof structure Check the sufficient quantity material received at site or not Erect the sheet with proper overlapping each other by crane / rope and pulley Put the J bolt with , nut, washer, bitumen washer etc & tight properly with purling & sheet Put the wind strip as per AFC drawing Erect the ridged , drain etc as per drawing & specification Cladding to be done as per AFC drawing

  • 8/12/2019 Civil and Structural

    54/79

    Page4of

    Complete the entire work in all respect Final inspection to be done & hand over to GAIL / EIL

    5. INSPECTION AND TEST DOCUMENT Site inspection reports as per ITP No : 6724-700-50-47-ITP-008 Test report of all materials

  • 8/12/2019 Civil and Structural

    55/79

    INSPECTION & TEST PLAN FOR SHEETING

    DOC. NO. - 6724-700-50-47-ITP-008

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR , RATNAGIRI

    Sr.No

    Activities SEL EILRecord to besubmitted

    Remarks

    1 Material test reports WC Rw Yes

    2 Completion of structure WC W -

    3 Fixing of sheets , Ridges, Corner, Gutter etc WC Rw -

    4Checking of J bolt fixing wind Tie & bitumenwasher

    WC W Yes

    5 Final Inspection WC W Yes

    INSPECTION & TESTING DOCUMENTS

    Site Inspection Report WC Rw Yes

    PREPARED BY REVIEWED BY CHECKED BY APPROVED BY

    SEL SEL SEL EIL

  • 8/12/2019 Civil and Structural

    56/79

    Page1of

    JOB PROCEDURE FOR WBM ROAD

    (PROCEDURENO: 6724-700-50-47-JP-009)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR, RATNAGIRI

    CLIENT : M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED

    . (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)

    CONSULTANT : M/s ENGINEERS INDIA LIMITED

    CONTRACTOR : M/s SAVAIR ENERGY LIMITED

    PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

    ORGANIZATION SEL SEL EIL EIL

    SIGNATURE

    NAME GANESH K. RAKESH P. MILIND D.

    DATE

  • 8/12/2019 Civil and Structural

    57/79

    Page2of

    (PROCEDURE NUMBER: 6724-700-50-47-JP-009)

    JOB PROCEDURE FOR WBM ROAD

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. PROCEDURE5. INSPECTIONS & RECORDS

  • 8/12/2019 Civil and Structural

    58/79

  • 8/12/2019 Civil and Structural

    59/79

    Page4of

    Dry rolling will be done Spreading the murum and rolling Spread the water and rolled till the proper binding of metal Check the thickness after compaction If the thickness found less , rectification will be done Spread the second layer with murum and rolled and sequence layer to be spread as per AFC drawing Total thickness of wbm is as per the AFC drawing

    6. INSPECTION AND TEST DOCUMENTReview of test reports and site inspection documents as per ITP No: 6724-700-50-47-ITP-009

  • 8/12/2019 Civil and Structural

    60/79

    INSPECTION & TEST PLAN FOR WBM ROAD

    DOC.NO. - 6724-700-50-47-ITP-009

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRESSOR ,RATNAGIRI

    Sr.No

    Activities SEL EILRecord to besubmitted

    1

    Review of calibration Certificates of instruments & testingequipments

    Field calibration , if any

    WC

    WC

    HP

    W

    YES

    YES

    2Layout checking including road crossing and taking initiallevel

    WC S

    3 Approval of source & checking & testing of material(wherever required)

    WC HP YES

    4 Filling (if any) compaction, providing camber in sub-base including levels

    WC S

    5 Spreading metal to required thickness, line & level,dryrolling including spreading of screening material WC

    S

    6 Check for camber and levels over metalling WC S YES

    7 Spreading murum / sand, watering and rolling WC S

    8 Checking thickness after each layer and rectificationthereof (if any)

    WC W YES

    9 Checking Quantity of aggregate by excavation of trialpits as per IRC Code

    WC WYES

    INSPECTION AND TEST DOCUMENT

    Review test and inspection document WC Rw

    PREPARED BY REVIEWED BY CHECKED BY APPROVED BY

    SEL SEL SEL EIL

  • 8/12/2019 Civil and Structural

    61/79

    Page1of

    JOB PROCEDURE FOR FIRE PROOFING

    (PROCEDURENO: 6724-700-50-47-JP-010)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR, RATNAGIRI

    CLIENT : M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED

    . (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)

    CONSULTANT : M/s ENGINEERS INDIA LIMITED

    CONTRACTOR : M/s SAVAIR ENERGY LIMITED

    PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

    ORGANIZATION SEL SEL SEL EIL

    SIGNATURE

    NAME GANESH K. RAKESH P. MILIND D.

    DATE

  • 8/12/2019 Civil and Structural

    62/79

    Page2of

    (PROCEDURE NUMBER: 6724-700-50-47-JP-010)

    JOB PROCEDURE FOR FIRE PROOFING

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. PROCEDURE5. INSPECTIONS & RECORDS

  • 8/12/2019 Civil and Structural

    63/79

    Page3of

    PROCEDURE NO. 6724-700-50-47-JP-010

    JOB PROCEDURE FOR FIRE PROOFING

    1. PURPOSEThe purpose of this procedure is for supervising of Fire proofing work and to insure that proper quality

    control is exercised at site

    2. SCOPEThis procedure covers supervision of Fire proofing work and method of record keeping for Fire proofing

    work at site.

    3. REFERENCE Work related to fire proofing will be conformed to EIL specification Special condition IS codes and standards Design basis

    4. MATERIAL Material required for Fire proofing shall be as per respective EIL specification As per IS codes

    5. PROCEDURE Required material will be procured from standard / approved vendor only with MTC report. If MTC

    report not available then take the material received sample and send to approved lab for testing with

    respective IS code

    Approved the required grade of concrete , with its trial cubes testing result Locate the structure where fire proofing to be done Weld the squared nuts on structure at 400 mm distance all around Patch up the weld portion with specified primer, paint Put the specified welded wire mesh on structure and tied up properly with 16 gauge binding wire

  • 8/12/2019 Civil and Structural

    64/79

    Page4of

    Put the shuttering as per the specified thickness of fire proofing and standard Rigid the shuttering with clams, supports Pour the approved grade of concrete, required testing cube to be taken Finally finishing will be done with 1:2 cement mortar , if required Put the final coat of approved shed snowcem paint

    6. INSPECTION AND TEST DOCUMENTReview of test reports & Inspection reports as per ITP NO 6724-700-50-47-ITP-010

  • 8/12/2019 Civil and Structural

    65/79

    INSPECTION & TEST PLAN FOR FOR FIRE PROOFING

    DOC.NO.6724-700-50-47-ITP-010

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR , RATNAGIRI

    Sr.No

    Activities SEL EILRecord to besubmitted

    Remarks

    1 Approval of source of material WC Rw

    2Instrument , Testing equipment, calibratingcertificate

    WC HP Yes

    3 Field calibration if any WC W Yes

    4 Checking/ testing of material WC W/Rw Yes

    5 Design mix approval WC HP Yes

    6 Checking of weld mesh fixing , nut fixing etc WC W

    7 Checking of shuttering and scaffolding etc WC S

    8 Pour card WC HP6724-700-50-47-IR-001&002

    9 Concreting , testing , finishing WC W YES

    10 Casting of cubes WC W

    11 Testing of cubes 7 days 28 days

    WCWC

    WW

    YESYES

    6724-700-50-47-IR-003

    12 Removal of form work / staging WC S

    13 Curing WC S

    14 Surface painting WC S

    INSPECTION & TESTING DOCUMENTS

    Review test & site Inspection reportWC Rw YES

    PREPARED BY REVIEWED BY CHECKED BY APPROVED BY

    SEL SEL SEL EIL

  • 8/12/2019 Civil and Structural

    66/79

    Page 1 of 2

    POUR CARD I (PROGRAMME OF CONCRETING)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTERCOMPRESSOR , RATNAGIRI

    CLIENT : M/s RGPPL, RATNAGIRI FORMAT NO: 6724-700-50-47-IR-001 REV.NO. - 0

    PMC : M/s EIL REPORT NO :

    DATE :

    1. Reference document :

    2. Type of Structure :

    3. Levels From : To :

    4. Grade of Concrete / Approved Design Mix

    5. Brand Name, Grade and consignment no. cement

    6. Estimated volume of concrete :

    7. Quantity of cement required :

    8. Reinforcement checking details :

    No. Dia. Length

    a) Laps

    b) Separators

    c) Chairs

    d) Any other

    Remarks

  • 8/12/2019 Civil and Structural

    67/79

    9. Pre pour inspection details Checked NA

    a) Survey / Layout.

    b) Sub soil compaction.

    c) Completion of underground works.

    d) Cleanliness.

    e) Cover to reinforcement.

    f) Anchor bolt.

    g) Sleeves / pockets.

    h) Water stopper.

    i) Formwork.

    j) Slopes.

    k) Construction / Expansion joints.

    l) Admixtures.

    m) Any other.

    Remarks

    10. Clearance for Electrical / MechanicalWorks required / not required

    Electrical Mechanical

    11.The above structures finally inspected on at AM/PM and found / not found satisfaction for

    concreting.

    Remarks, if any

    M/s SAVAIR ENERGY LIMITED M/s GAIL/EIL

    NAME

    SIGN

    DATE

    Page 2 of 2

  • 8/12/2019 Civil and Structural

    68/79

    Page 1 of 2

    POUR CARD II (OBSERVATIONS DURING CONCRETING)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR , RATNAGIRI

    CLIENT : M/s RGPPL, RATNAGIRI FORMAT NO: 6724-700-50-47-IR-002 REV.NO. - 0

    PMC : M/s EIL REPORT NO :

    DATE :

    1. a) Quality of course aggregates

    Satisfactory Not to Satisfactory

    b) Quality of fine aggregates

    Satisfactory Not to Satisfactory

    c) Bulk of sand taken into account

    Yes No

    2. Quality of Water

    Satisfactory Not Satisfactory

    3. Machinery mobilization

    a) Mixture machine

    b) Ready mix concrete dumpers

    c) Vibrators

    d) Pumps

    e) Hoists

    4. Pour start time AM/PM : Date :

    5. Slump

    6. W/C Ratio

    7. Type Of Weather

    Normal Abnormal

    Detail of abnormality :

    (Precautions taken for < 5 C and > 40 C, rainy season)

  • 8/12/2019 Civil and Structural

    69/79

    Page 2 of 2

    8. Number of cubes taken :

    9. Quantity of concrete poured :

    10. Pour completion time : AM/PM : Date :

    11. Curing Method

    Traditional Curing compound

    Blankets / foils / gunny bags Others ( specify)

    12. Period for removal of form work.

    13. Any defect (s) observed during concreting :

    M/s SAVAIR ENERGY LIMITED M/s GAIL/EIL

    NAME

    SIGN

    DATE

  • 8/12/2019 Civil and Structural

    70/79

    Name of work :

    Reference : Type of Cement :

    W / C Ratio : Max. size of Aggregate

    CRUSHING STRENGTH RESULTS OF CONCRETE CUBES

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRE

    CLIENT : M/s RGPPL, RATNAGIRI FORMAT NO: 6724-700-50-47-IR-003

    PMC : M/s EIL REPORT NO :

    DATE :

    CubeNo.

    Id.MarkOn

    Cube

    Type &Location

    ofStructure

    Date of Age(days)

    Dimensions of Cube Vol.of

    Cube(m)

    Wt.of

    Cube(kg)

    Unit WT.(kg/m)

    SurfaceArea(cm)Casting Testing L

    (Cm)B

    (Cm)H

    (Cm)

  • 8/12/2019 Civil and Structural

    71/79

    M/s SAVAIR ENERGY LIMITED M/s GA

    NAME

    SIGN

    DATE

  • 8/12/2019 Civil and Structural

    72/79

    Page1of

    JOB PROCEDURE FOR UNDERGROUND PIPING

    (PROCEDURENO: 6724-700-50-47-JP-012)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR, RATNAGIRI

    CLIENT : M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED

    . (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)

    CONSULTANT : M/s ENGINEERS INDIA LIMITED

    CONTRACTOR : M/s SAVAIR ENERGY LIMITED

    PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

    ORGANIZATION SEL SEL SEL EIL

    SIGNATURE

    NAME GANESH K. RAKESH P. MILIND D.

    DATE

  • 8/12/2019 Civil and Structural

    73/79

    Page2of

    (PROCEDURE NUMBER:6724-700-50-47-JP-012)

    JOB PROCEDURE FOR UNDERGROUND PIPING

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. PROCEDURE5. INSPECTIONS & RECORDS

  • 8/12/2019 Civil and Structural

    74/79

    Page3of

    JOB PROCEDURE FOR UNDERGROUND PIPING

    1. PURPOSEThe purpose of this procedure is for supervising of under ground piping work (RCC/ CI) to insure that

    proper quality control is exercised at site

    2. SCOPEThis procedure covers supervision of under ground piping (RCC/ CI) and method of record keeping for

    underground work at site.

    3. REFERENCE WORK RELATED TO UNDER ground piping (RCC/CI) work will be conformed to EIL contract document Special condition IS codes Design Basis Approved drawing for construction

    4. MATERIALRequired material for underground piping work (RCC/CI) shall be as per respective EIL specifications

    5. PROCEDURE Material to be procured from standard / approved vendor only , with all MTC report If MTC report not available / co related with material will be tested in approved lab , by sending of

    sample from received material at site

    Review of calibration certification of instrument / testing equipment Field calibration will be done if required Layout for piping , manhole to be done at site as per AFC drawing Before excavating the trench or manhole, underground obstruction will be checked. If found anything

    necessary precaution will be taken to protect it.

  • 8/12/2019 Civil and Structural

    75/79

    Page4of

    Joint level to be taken if required After excavated trench for piping and for manhole/ chamber bed level to be checked and recorded Lay the pipe line as per AFC drawing and jointing will be done Make the manhole / chamber as per AFC drawing and grouting with pipe line All joints will be curved Before hydro test all joints, bed , supports etc will be visually checked Hydro test will be done by filling of water in line & manhole chambers for leaking of joints Record to be maintained Removal of any blockages , cleaning and flushing of the system Back filling will be done in specified layers and complexion test will be carried out Checking of MS rings in manhole chambers , proper grouting with pipes for inlet / outlet pipes, and

    level of inlet / outlet and manhole to be checked

    Finally as built drawing will be prepared and hand over the system to EIL / GAIL6. INSPECTION AND TEST DOCUMENTS as per ITP No: 6724-700-50-47-ITP-012

    REVIEW TEST AND INSPECTION DOCUMENTS

  • 8/12/2019 Civil and Structural

    76/79

    INSPECTION & TEST PLAN FOR UNDERGROUND PIPING

    DOC.NO. - 6724-700-50-47-ITP-012

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER COMPRESSOR ,RATNAGIRI

    Sr.No

    Activities Contractor EILRecord to be

    submittedRemarks

    1 Checking of material WC W YES

    2 Adequate slope, benching in excavation for safetypurposes if required

    a) review of calibration certificates ofinstruments / testing equipments

    b) Field calibration, if any

    WC

    WC

    S

    HP

    YES

    YES

    3 Layout Line & level WC W

    4 Laying & joining, grouting at manhole/chambers WC S

    5 Check for supports/firm bed / sub soil water level WC S YES

    6 Testing for leakages by blocking pipe ends WC S YES

    7 Hydro-testing and other test, Removal ofblockages, Cleaning & flushing of system

    WC W YES

    8 Back filling in layers WC HP

    9Check for MS rungs in proper position, inlet/outletpipe levels in manholes

    WC S

    10 Preparation of As Built Drawings WC S YES

    INSPECTION & TESTING DOCUMENTS

    Review test & Inspection DocumentWC Rw

    PREPARED BY REVIEWED BY CHECKED BY APPROVED BY

    SEL SEL SEL EIL

  • 8/12/2019 Civil and Structural

    77/79

    Page1of

    JOB PROCEDURE FOR DISMANTLING OF RCC (EXISTING)

    (PROCEDURENO: 6724-700-50-47-JP-013)

    PROJECT : PROCUREMENT AND INSTALLATION OF ADDITIONAL BOIL OFF GAS (BOG) BOOSTER

    COMPRESSOR, RATNAGIRI

    CLIENT : M/s RATNAGIRI GAS AND POWER PRIVATE LIMITED

    . (Promoters: M/S NTPC Limited & GAIL (INDIA) Limited)

    CONSULTANT : M/s ENGINEERS INDIA LIMITED

    CONTRACTOR : M/s SAVAIR ENERGY LIMITED

    PREPARED BY CHECKED BY REVIEWED BY APPROVED BY

    ORGANIZATION SEL SEL SEL EIL

    SIGNATURE

    NAME GANESH K. RAKESH P. MILIND D.

    DATE

  • 8/12/2019 Civil and Structural

    78/79

    Page2of

    (PROCEDURE NUMBER: 6724-700-50-47-JP-013)

    JOB PROCEDURE FOR DISMANTLING OF RCC (EXISTING)

    CONTENTS

    1. PURPOSE2. SCOPE3. REFERENCE4. PROCEDURE5. INSPECTIONS & RECORDS

  • 8/12/2019 Civil and Structural

    79/79

    JOB PROCEDURE FOR DISMANTLING OF RCC (EXISTING)

    1. PURPOSEThe purpose of this procedure is for supervising of dismantling of RCC (Existing) and to insure that proper

    safety and other damages could not be at site

    2. SCOPEThis procedure covers supervision of dismantling of RCC (Existing) and record keeping for dismantling of

    RCC work at site.

    3. REFERENCE Work related to dismantling of RCC (Existing) will be conformed to EIL specification

    4. PROCEDURE Mark the structure to be dismantled Disconnect all the services like power gas supply , water etc Barricading the area where dismantling work placeVerify & ensure the all workers should used appropriate PPE Keep the fire fighting arrangement Check the gas cutter , Jack hammer, Air compressor condition Mark or decide the where initial debris of dismantling to be stored Make the disposal arrangement from the mark or decided area to designated area Take all the precautions so that neighboring structure could not be damage