Upload
rasool-khan
View
244
Download
1
Embed Size (px)
Citation preview
CL-05-01 Grit blasting - painting Checklist Templa
GRIT blasting & painting check listPage 2 of 4
Project Number :101119DProject Title:Yanbu Export Refinery Project EPC-2
Project Manager:shamimProject Engineer:rasool khan
Document Number:CL-05-11Date:23/06/15
Proposed Work Methodology
Work Party
LocationYANBU
DescriptionSAND BALSTING AND PAINTING
Review of Proposed Procedures & Equipment
Mandatory Requirements
HazardControl MeasureChecked
Unidentified Job Specific HazardsJHA to be carried out by staff detailing on the day hazards that could not be practically assessed prior to attending site in addition to this Check List. All staff to sign on to JHA accepting this form and the on the day hazards and controls. JHA has been completed and approved by the relevant personnel in accordance with the JHA Procedure
Hydro Hazards-Lack of awareness of local asset and other simultaneous operationsProject Manager to notify work party of ALL AL-MUZAIN Assets in area (including Protection , Mechanical, piping fabrication and hot tapping Assets).Work party to inspect and make safe.
General Requirements
HazardControl MeasureN / AChecked
Abrasive blasting equipmentNozzle must have automatic shut off fitted
Hose whip restraints fitted
Earthed for static electricity
Abrasive blasting materialsNo siliceous or toxic dust exposures
Containment of dusts and over blasts
Procedure for lead based paint removal
Clean up required after completion
Washing / showering facilities required
Disposal methods for all waste materials
Surface coatings / paintsSecure temporary flammable material storage
Prevention and containment of spills
Hazardous substances risk assessment
Material data sheets available and understood
Containment of paint overspray
Mechanical ventilation in enclosed areas
Spray booth used for movable items
Solvents and thinnersSecure temporary flammable material storage
Fire and explosionNo ignition sources near spray painting
No ignition sources near flammable store(s)
Appropriate fire fighting equipment on hand
Unauthorised accessRestrict access to blasting / spray painters only
Blasting / painting area to be securely barriered and delineated
Falls from heightsProvision of fixed access / scaffolding
Elevated work platform or similar
Safety harness and lanyard
Lack of co-ordinationWorks Manager to supervise or delegate responsibility
Works Manager to notify Production Manager of date and time of blast(s)
Works Manager to notify Generation Operations of date and time of blast(s)
Contractor to have direct communication with Works Manager
Site Registration (Note: Applies to all Work Parties and personnel working on site)
RequirementChecked
Permit To Work issued
Visitors register sheet or emergency board being used. Site Map issued (showing emergency assembly areas and fire equipment)
AL-MUZAIN O H & S Induction complete
AL-MUZAIN Site induction complete
S
Additional Personal Protective Equipment
RequirementCheckedRequirementCheckedRequirementChecked
Certification
I have personally checked and verified all items on all pages of this check list
Project Manager NameSignatureDate
I acknowledge and agree that all items are detailed on all pages of this check list. I agree to ensure that all employees and sub-contractors engaged in this work will fully comply with all control measures indicated
Manager of Work Party NameSignatureDate
Daily Review
If There is a signficant change in Work and or Conditions a new Check List is Required
Date and TimeReviewed / CommentNew Check List Required
Document Reference: CL 05 11 Revision: 0Date: 23/06/2015