 GRIT BLASTING & P AINTING – CHECK LIST Page 1 of 4 PROJECT NUMBER :101119D PROJECT TITLE:Y ANBU EXPORT REFINERY  PROJECT EPC-2 PROJECT MANAGER:SHAMIM PROJECT ENGINEER:RASOOL KHAN DOCUMENT NUMBER:CL-0-11 DATE:2!"0#"1 PROPOSED $ORK  METHODOLOGY $ORK  PARTY LOCATION  Y ANBU DESCRIPTION SAND BALSTING AND PAINTING RE%IE$ OF PROPOSED PROCEDURES & EUIPMENT MANDATORY  REUIREMENTS HA'ARD CONTROL MEASURE CHECKED Unidentied Job Specic Hazad!  JHA to be ca ied o"t b# !ta$ detai%ing on t &e da# &azad! t&at co"%d not be pactica%%# a!!e!!ed pio to attending !ite in addition to t&i! (CHECK  LIST)' A%% !ta$ to !ign on to JHA accepting t&i! fo( and t&e on t&e da# &azad! and conto%!' JHA &a! been co(p%eted and appo)ed b# t&e e%e)ant pe!onne% in accodance *it& t&e JHA Poced"e H#do Hazad!+ Lac, of a*aene!! of %oca% a!!et and ot&e !i("%taneo"! opeation! Po-ect .anage to notif# *o, pat# of ALL AL+.U/AIN A!!et! in aea 0inc%"ding Potection .ec&anica% piping fabication and &ot tapping A!!et!2'3 o, pat# to in!pect and (a,e !afe' GENERAL REUIREMENTS HA'ARD CONTROL MEASURE N " A CHECKED Aba!i)e b%a!ting e"ip(ent Nozz%e ("!t &a)e a"to(atic !&"t o$ tted Ho!e *&ip e!taint! tted 5at&ed fo !tatic e%ecticit# Aba!i)e b%a!ting (ateia%! No !i%iceo"! o to6ic d"!t e6po!"e! 7ontain(ent of d"!t! and o)e b%a!t! Poced"e fo %ead ba!ed paint e(o)a% 7%ean "p e"ied afte co(p%etion 3a!&ing 8 !&o*eing faci%itie! e"ied Di!po!a% (et&od! fo a%% *a!te (ateia%! S"face coating! 8 paint! Sec"e te(poa# 9a((ab%e (ateia% !toage P e)ention and contain(ent of !pi%%! DOCUMENT REFERENCE: CL – 0 – 11 RE%ISION: 0 DATE: 2!"0#"201

CL-05-11 Grit Blasting - Painting Checklist Template

Embed Size (px)

Citation preview

CL-05-01 Grit blasting - painting Checklist Templa

GRIT blasting & painting check listPage 2 of 4

Project Number :101119DProject Title:Yanbu Export Refinery Project EPC-2

Project Manager:shamimProject Engineer:rasool khan

Document Number:CL-05-11Date:23/06/15

Proposed Work Methodology

Work Party

LocationYANBU

DescriptionSAND BALSTING AND PAINTING

Review of Proposed Procedures & Equipment

Mandatory Requirements

HazardControl MeasureChecked

Unidentified Job Specific HazardsJHA to be carried out by staff detailing on the day hazards that could not be practically assessed prior to attending site in addition to this Check List. All staff to sign on to JHA accepting this form and the on the day hazards and controls. JHA has been completed and approved by the relevant personnel in accordance with the JHA Procedure

Hydro Hazards-Lack of awareness of local asset and other simultaneous operationsProject Manager to notify work party of ALL AL-MUZAIN Assets in area (including Protection , Mechanical, piping fabrication and hot tapping Assets).Work party to inspect and make safe.

General Requirements

HazardControl MeasureN / AChecked

Abrasive blasting equipmentNozzle must have automatic shut off fitted

Hose whip restraints fitted

Earthed for static electricity

Abrasive blasting materialsNo siliceous or toxic dust exposures

Containment of dusts and over blasts

Procedure for lead based paint removal

Clean up required after completion

Washing / showering facilities required

Disposal methods for all waste materials

Surface coatings / paintsSecure temporary flammable material storage

Prevention and containment of spills

Hazardous substances risk assessment

Material data sheets available and understood

Containment of paint overspray

Mechanical ventilation in enclosed areas

Spray booth used for movable items

Solvents and thinnersSecure temporary flammable material storage

Fire and explosionNo ignition sources near spray painting

No ignition sources near flammable store(s)

Appropriate fire fighting equipment on hand

Unauthorised accessRestrict access to blasting / spray painters only

Blasting / painting area to be securely barriered and delineated

Falls from heightsProvision of fixed access / scaffolding

Elevated work platform or similar

Safety harness and lanyard

Lack of co-ordinationWorks Manager to supervise or delegate responsibility

Works Manager to notify Production Manager of date and time of blast(s)

Works Manager to notify Generation Operations of date and time of blast(s)

Contractor to have direct communication with Works Manager

Site Registration (Note: Applies to all Work Parties and personnel working on site)

RequirementChecked

Permit To Work issued

Visitors register sheet or emergency board being used. Site Map issued (showing emergency assembly areas and fire equipment)

AL-MUZAIN O H & S Induction complete

AL-MUZAIN Site induction complete

S

Additional Personal Protective Equipment

RequirementCheckedRequirementCheckedRequirementChecked

Certification

I have personally checked and verified all items on all pages of this check list

Project Manager NameSignatureDate

I acknowledge and agree that all items are detailed on all pages of this check list. I agree to ensure that all employees and sub-contractors engaged in this work will fully comply with all control measures indicated

Manager of Work Party NameSignatureDate

Daily Review

If There is a signficant change in Work and or Conditions a new Check List is Required

Date and TimeReviewed / CommentNew Check List Required

Document Reference: CL 05 11 Revision: 0Date: 23/06/2015