Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Claimant’s Memoranda Of Argument (RMIT University)
- 1 -
16th International Maritime Law Arbitration Moot, 2015
CLAIMANT’S MEMORANDA OF ARGUMENT
Team 18
IN THE LONDON ARBITRATION TRIBUNAL
BETWEEN:
WESTERN TANKERS INCORPORATED
(Claimants)
-AND-
LESS DEPENDABLE TRADERS PROPRIETARY LIMITED
(Respondents)
Team 18
| Elise Steegstra | Paul Melican | Olivia Dean | Naomi Keessen | Gavin van Rensburg |
Claimant’s Memoranda Of Argument (RMIT University)
- 2 -
-TABLE OF CONTENTS-
ABBREVIATIONS Page 5
AUTHORITIES Page 6
STATEMENT OF FACTS Page 16
ARGUMENTS Page 17
PART ONE: JURISDICTION Page 17
A. THE EXPRESS AND VALID ARBITRATION AGREEMENT FOUND IN THE
CHARTERPARTY SPECIFIES THE SEAT OF LONDON
B. THIS TRIBUNAL HAS THE POWER TO RULE ON ITS OWN JURISDICTION
C. KNOWN APPROACHES OF ENGLISH COURTS WHEN DECIDING THESE
MATTERS
D. THE CORRECT COMMENCEMENT OF THIS MATTER UNDER THE ARBITRATION
ACT 1996.
PART TWO: BREACH OF CONTRACT Page 19
A. THE CONTRACT OF CARRIAGE
B. CONTRACTUAL TERMS AND THE INCORPORATION OF TERMS
C. THE FAILURE OF THE RESPONDENT TO DELIVER BUNKERS
D. THE FAILURE OF THE RESPONDENT TO MAKE PAYMENT ON TIME
E. ABROGATION OF THE CARRIER’S INCORPORATED DUTY OF CARE
PART THREE: REPUDIATION OF CONTRACT Page 23
PART FOUR: FRUSTRATION OF CONTRACT Page 24
A. THE SUPERVENING AND UNFORESEEN CIRCUMSTANCES
B. THE LACK OF DEFAULT ON THEIR SIDE OF THE PARTY
Claimant’s Memoranda Of Argument (RMIT University)
- 3 -
C. THE CONTRACTUAL OBLIGATION INCAPABLE OF BEING PERFORMED
BECAUSE IN SUCH A CIRCUMSTANCE PERFORMANCE WOULD BE RADICALLY
DIFFERENT FROM THAT, WHICH WAS UNDERTAKEN BY THE CONTRACT
D. ONCE APPLIED THE CONTRACT WOULD CEASE TO BIND EITHER PARTY
E. THERE ARE NO EXCEPTIONS FOR TIME CHARTERPARTIES
F. INVOLUNTARY BAILMENT
PART FIVE: TORT OF FRAUD Page 28
A. THERE IS PROOF THAT A FRAUD WAS COMMITTED
B. THE FALSE REPRESENTATION PROMISING BUNKERING WAS MADE
KNOWINGLY
C. THE FALSE REPRESENTATION PROMISING BUNKERING WAS MADE
RECKLESSLY AND CARELESSLY
D. THERE WAS RELIANCE ON THIS PROMISE OF BUNKERING
E. DAMAGE OCCURRED BECAUSE OF THIS MISREPRESENTATION.
PART SIX: NEGLIGENT MISSTATEMENT Page 30
A. THERE IS PROOF THAT THE RESPONDENTS MADE A NEGLIGENT
MISSTATEMENT
PART SEVEN: THERE WAS NO NEGLIGENCE BY THE MASTER OR CREW Page 31
A. THE CONSTRUCTION OF THE NEGLIGENCE EXCEPTIONS DOES NOT ALLOW A
CASE TO BE RAISED
B. THE MASTER DEVIATED UNDER AGENCY AUTHORISATION AND AS A RESULT
THERE IS NO CLAIM TO ANSWER FOR MISDELIVERY OF CARGO
C. THERE WAS NO NEGLIGENCE IN THE NAVIGATION OR MANAGEMENT OF THE
SHIP
Claimant’s Memoranda Of Argument (RMIT University)
- 4 -
D. EXCEPTIONS LAST FOR THE DURATION OF THE POSSESSION OF THE GOODS IN
QUESTION AND
E. THE MASTER AND CREW ARE NOT LIABLE FOR ACTS OF PIRACY ON THE
HIGH SEAS
PART EIGHT: TORT OF CONVERSION WAS NOT COMMITTED Page 36
A. A LIEN HAS BEEN CREATED THROUGH THE CHARTERPARTY;
B. THE CLAIMANT HAS NOT UNDERTAKEN SUFFICIENT INTENTIONAL CONDUCT
TO HAVE CONVERTED THE GOODS IN QUESTION;
C. GOODS LOST OR DESTROYED CANNOT BE SUBJECT TO AN ACT OF
CONVERSION
PART NINE: VESSEL WAS SEAWORTHY Page 38
1. ALL OF THE OBLIGATIONS OF THE OWNER WERE MET
2. THE CONDITION ON REDELIVERY IS A MATTER FOR THE RESPONDENT
PART TEN: QUANTIFICATION OF DAMAGES Page 40
A. DAMAGES UNDER THE LAW OF CONTRACT
B. DAMAGES UNDER THE LAW OF TORT
C. INTEREST AS PER THE ARBITRATION ACT 1996
D. CONSIDERATION OF LIMITATION OF LIABILITY.
PRAYER FOR RELIEF Page 43
Claimant’s Memoranda Of Argument (RMIT University)
- 5 -
-ABBREVIATIONS-
B/L; BoL Bill of Lading Bunker Fuel used to operate ships Bunkering Action of supplying a ship with bunkers (fuel). Note stemming is placing
bunker into ship BMP4 Best Management Practices for Protection against Somalia Based Piracy,
Version 4 – August 2011 CHOPT Charterers options CP Charter party ENS Electronic navigation systems Ex pipe Used to describe a mode of delivery for marine fuels or bunkers to ships IFO Intermediate fuel oil Laycan Lay day cancelling date MEP Most Economic Power MT Metric tonnes NOP Normal operating power OPL Off port limitations PDPR Per day, pro rata Redel Redelivery ST4 Shelltime 4 Charter party contract STS Ship to ship transfer TCT Time charter trip VO Voyage orders WAF West Africa
Claimant’s Memoranda Of Argument (RMIT University)
- 6 -
-AUTHORITIES-
CASES
A
AB v South West Water Services Ltd [1993] Q.B. 507
Addis v Gramophone Co. Ltd [1909] A.C. 488
‘The Agios Lazaros’ [1976] 2 Lloyd’s Rep 47
Akai Pty Ltd v People’s Insurance Company Ltd [1999] I.L.Rd. 24
Alderslade v Hendon Laundry [1945] K.B. 189
Anastassia v Ungle-Export (1934) 49 L1.L.Rep. 1
Angus v Clifford [1981] 2 Ch 449 at 471
Annen v Woodman (1810) 3 Taunt. 299
Applyby v Myers (1867) L.R. C.P. 651
Armstrong v Strain [1951] 1 TLR 856 at 871
Assicurazione v Bessie Morris [1892] 2 Q.B. 652
Athens Maritime Enterprises Corporation v Hellenic Mutual War Risks Association (Bermuda) Ltd [1982] 2 Lloyd's Rep. 483 Australasian SN Company v Morse (1871-1873) LR 4 PC 222 B
Balihache J in Admiral Shipping Co v Weidner Hopkins [1916] 1 K.B.429.
Bank Line v Capel & Co [1919] A.C. 435
Bank of Australasia v Clanline [1916] 1 KB 39 55
Banques Bruxelles Lambert S.A. v Eagles Star Insurance Co. Ltd [1995] Q.B. 375
Black Sea & Danube Shipping Co v Goeland Transport & Trading Co. (1942) L.I.L.R. 192
BP Refinery (Westernport) Pty Ltd v Shire of Hastings (1977) 180 CLR 266
Claimant’s Memoranda Of Argument (RMIT University)
- 7 -
Bradford Third Benefit BS v Borders [1941] 2 All ER 205
‘The Brimnes’ [1975] QB 929, CA
Briscoe v Powell (1905) 22 T.L.R. 128
British Crane Hire Corp Ltd v Ipswich Plant Hire Ltd (1975) QB 303
British Transport Commission v Gourley [1956] A.C. 185 at p. 187 British Westinghouse Electric v Underground Electric Railways Co. of London Ltd [1912] A.C. 673 Byrne v Australian Airlines Ltd (1995) 185 CLR 411 B.T.P. Tiozafr Ltd v Pioneer Shipping Ltd and Armada Marine S.A. (The Nema) [1982] A.C. 72 Burgess v Wickham (1863) 3 B & S. 669
|C
Calico Printers’ Association v Barclays Banks (1931) 36 Com.Cas. 197
Canada Steamship Lines v The King [1952] A.C. 192 (p.C.)
Canadian Pacific (Bermuda) Ltd v Logan Martime Overseas (The Fort Kipp) [1885] 2 Lloyd’s Rep. 168 Caparo v Dickman [1990] 2 AC 605 ‘The Carron Park’ (1890) 15 P.D. 203 Chapelton v Barry Urban District Council [1940] 1KB 532 ‘The Captain George K’ [1970] 2 Lloyd’s Rep. 21 Cargo ex Argos, Gaudet v Brown (1872) LR 5 PC 134 Carras v. London and Scottish Assurance [1936] 1 K.B. 291
Chartered Mercantile Bank of India v Netherlands India S.N. Co (1883) Chellew Navigation Co v Applequist (1933) 38 Com.Cas 218 China Pacific SA v Food Corporation of India (‘The Winson’) [1982] AC 939 Christopher Brown Ltd v Genossenchaft Oestereichischer Waldbestizer Holwirtscafsbetriebe Registrierte GmbH [1954] i QB 7 City of Baroda (Owners) v Hall Line (1926) 42 T.L.R. 717
Claimant’s Memoranda Of Argument (RMIT University)
- 8 -
City of Lincoln v Smith [1904] Cosmos Bulk Transport Inc v China National Foreign Trade [1978] 1 Lloyd's Rep 53 C.P.R. v Board of Trade (1925) 22 L.I.L.R. 1 (H.L.) Czarnikow v Koufos [1969] 1 A.C. 350 D
Dahl v Nelson, Donkin and Company (1881) 6 App Cas 38
Daniels v Harris (1874() L.R. 10 C.P. 1
‘The David Agmashenebli' [2003] 1 Lloyds Rep 92
Davis Construction Ltd v Foreham U.D.C. [1956] A.C. 14
De Clermont v General Steam Navigation Co. (1891) 7 T.L.R. 187
Derry v Peek (1989) 14 App.Cas. 337
The 'Dolphina' [2011] SGHC 273
E
‘The Eastern City’ [1958] 2 Lloyd’s Rep 127 E.Clemens Horst Co v Norfolk etc.& Co. (1906) 11 Comm.Cas. 141 Eddington v Fitzmaurice (18885) 29 ChD 459 Embiricos v Reid [1914] 3 K.B. 45 Empresa Cubana Importada de Alimentos “Alimport” v Iasmos Shipping Co. S.A. (The Good Friend) [1984] 2 Lloyd's Rep. 586 ‘The Eugenia’ [1964] 2 Q.B. 226 at p 240 F
Fercometal SARL v Msc Mediterranean Shipping Co SA (The Simona) [1988] 2 Lloyd's Rep 199
The ‘Fjord Wind’ [2000] 2 Lloyds Rep 191 (C.A.)
G
Geipel v Smith (1872) L.R. 7 Q.B. 404
Giertsen v Turnbull, 1908 S.C. 1101
Claimant’s Memoranda Of Argument (RMIT University)
- 9 -
Golden Arces Ltd v Queensland Estates Pty Ltd [1969] Qd R 378
Golden Fleece Maritime & another v. ST Shipping [2007] EWHC 1890 (Comm)
Goose v Wilson Sandford [2001] Lloyd's Rep PN 189
Gosse Millerd v Candaian Govt. Merchant Marine [1929] A.C. 223 (H.lL) Great Northern Railway Co v Swaffield (1874) LR 9 Ex 132 The ‘Gregos’ [1994] 1 WLR 1465 Gulnes v Imperial Chemcial Industries (1937) 43 Com.Cas 96 H Hadley v Baxendale (1854) 9 Ex. 341 Hedley Byrne & Co v Ltd v Heller Partners [1964] AC 465 Henderson v Stevenson (1875) LR 2HL Sc 470 ‘The Hermosa’ [1982] 1 Lloyd’s Rep 570, p 572-573 Hertford Foods Ltd v Lidl GmbH [2001] EWCA Civ 938 The ‘Hill Harmony’ [2001] 1 AC 638 Hong Kong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd [1962] 1 All ER 474 Howard Marine & Dredging Co Ltd v A Ogden & Sons (Excavations) Ltd [1978] QB 574 Houghland v R.R. Low (Luxury Coaches) Ltd [1962] 1 QB 694 Hourani v Harrison (1927) 32 Com.Cas. 305 I
The ‘Indian City’ [1939] AC 562 The ‘Island Archon’ [1994] 2 Lloyd's Rep 227 Ingram v Little [1961] 1 QB 31 J
Jackson v Union Marine (1874) L.R. 10 C.P. 125
James Finlay & Co. v Kwik Hoo Tong [1929] 1 K.B. 400
James Buchanan & Co v Hay’s Transport Services and Duncan Barbour and Son [1972 2 L1.L.R
Claimant’s Memoranda Of Argument (RMIT University)
- 10 -
535
Joseph Constentine v Imperial Smelting Corporation [1942] A.C. 154
Joseph Travers and Sons Ltd v Cooper [1915] 1 KB 73
J. Lauritzen A.S. v Wijsmuller B.V. (The Super Servant Two) ˆ[1990] I1 Lloyd’s Rep 1
K
Kulukundis v Norwhich Union [1937] I K.B.
L
Larrinaga v Societe Franco-Americaine (1922) 28 Com.Cas 1
Leesh River Tea v British India Steam Navigation Co. [1966] 2 Lloyd's Rep. 193
Lewis v Averay [1972] 1 QB 198
Livingstone v Raywards Coal Co. (1880) 5 App. Cas. 25 at p. 39
Lloyd v Guibert (1865) LR 1 QB 115
London and North-Western Railway Company v Hudson and Sons [1920] AC 324
Ludsin Overseas Ltd v Eco3 Capital Ltd [2012] EWHC 1980 (Ch)
M
Maritime National Fish v Ocean Trawlers [1935] A.C. 524
Marriot v Yeoward [1909] 2 K.B. 987
McCarthy v St Paul International Insurance Co Ltd [2007] FCAFC 28; 175 FCR 402
McFadden v Blue Star Line [1905] 1 K.B. 697 at p 706
Mead v Babington [2007] EWCA 518
Miramar Maritime Corporation v Holborn Oil Trading Ltd [1984] 1 AC 676
Monarch SS Co v Karishamns [1949] A.C. 196
Morris v C.W. Martin & Sons Ltd [1965] 2 Lloyds Rep 63
Motor Oil Hellas (Corinth) Refineries SA v Shipping Corp of India (The Kanchejunga) [1990] 1
Lloyd’s Rep 391
Claimant’s Memoranda Of Argument (RMIT University)
- 11 -
N
National carriers Ltd v Panalpina (Northern) Ltd [1981] A.C. 675
Nickoll v Ashton [1901] 2 K.B. 126
Norman v Binnington (1890) 25. Q.B.D. 475
Northumbrian Shipping v Timm [1939] AC 397
O
Owners of SS. Lord v Newsum [1901] 1 K.B. 846
Osmium Shipping Corp v Cargill International SA [2012] EWHC 571 (Comm)
Overseas Tankship (U.K.) v Morts Dock & Engineering Co. (The Wagon Mound) [1961] A.C. 388
P
Pacific Basin IHX Ltd v Bulkhandling Handymax AS [2012] 1 C.L.C. 1QB (Commercial Court)
Palace Shipping Company v Gans Steamship Line [1916] 1 KB 138
Parker v South Eastern Railway Co Ltd [1877] 2 CPD 416
Pasley v Freeman (1789) 3 Term Rep 51
Paterson Steamships v Canadian Co-operative Wheat Producers [1934] AC 538 PC
‘The Pearlmoor’ [1904] P 286
Perera v Vandiyar [1953] 1 W.L.R. 672
Petroleo Brasileiro SA v ENE Kos 1 Ltd [2012] UKSC 17; [2012] 2 AC 164
Phillips v Brooks[1919] 2 KB 243
Photo Production Ltd v Securicor Transport Ltd [1980] AC 367
Potts v Union SS. Co. of New Zealand [1946] N.Z.L.R. 276
Price v Union Lighterage Co. [1904] 1 K.B. 412
Pyman v Hull and Barnsley Co. [1915] 2 K.B. 729
R
Re Privacy Hire Gentium [1934] A.C. 586 (P.C.)
Red “Superior” v Dewar & Webb [1909] 1 K.B. 998 (C.A.)
Claimant’s Memoranda Of Argument (RMIT University)
- 12 -
Republic of Bolivia v Indemnity [1909] I K.B. 784
Robinson v Harman (1848) I Exch 850
Rookes v Barnard [1964] A.C. 1129
Royscot Trust Ltd v Rogerson [1991] 3 All ER 294
Rutter v Palmer [1922] 2 K.B. 87
Ruxley Electronics & Construction Ltd v Forsyth [1995] 3 W.L.R. 118
S
Scottish Navigation Co. v Souter [1917] K.B. 222
Shearman v Folland [1950] 2 K.B. 43 at p. 49 Shipton Anderson v Harrison [1915] 3 K.B. 676 SK Shipping (S) PTE Ltd v Petroexport Ltd [2009] EWHC 2974 (Comm) Slough Estates plc v Welwyn Hatfield DC [1996] 2 PLR 50 Spiliada Maritime Corp v Cansulex Ltd [1987] AC 460
Stanton v Richardson (1984) L.R. 9 C.P. 390
The’ Stork’ [1955] 2 QB 68 (Court of Appeal)
The ‘Starsin’ [2003] 1 Lloyds Rep 571
Sutcliffe v CC of West Yorkshire [1996] RTR 86
T
Tattersall v National Steamship Co. (884) 12 Q. B.D. 297
Taylor v Caldwell (1863) 3 B. & S. 826
Thin v Richards [1892] 2 Q.B. 141
Third Equitable Benefit BS v Borders [1941] 2 All ER 205
Transfield Shipping Inc v Mercator Shipping Inc [2008] 2 Lloyd’s Rep 275
Travers v Coopers [1915] K.B. 73
Tsakiroglou v Noblee Thori [1962] A.C. 93
TW Thomas & Co Limited v Portsea Steamship Company Limited [1912] 1 AC 1 at 129
Claimant’s Memoranda Of Argument (RMIT University)
- 13 -
V
Varnish v The Kheti (1949) 82 Li.L.R. 525
Victoria Laundry (Windsor) Ltd v Newman Industries Ltd (1949) 2 KB 528
W
Whalley v Wry (1799) 3 Esp 74
Worms v Storey (1855) ii Ex, 427; The Rona (1884) 51 L.T. 28
Wye SS. Co v Compagnie P.O. [1922] 1 K.B. 617
Claimant’s Memoranda Of Argument (RMIT University)
- 14 -
-AUTHORITIES-
BOOKS
R Aikens, R Lord and M Bools, Bills of Lading (Informa, 1st ed, 2006)
Simon Baughen, ‘Shipping Law’ (Cavendish Publishing, 3rd ed, 2004)
Hugh Beale, Chitty on Contracts (Sweet & Maxwell, 30th ed, 2008)
Terrance Coghlin, Andrew W. Barker et al, Time Charters (Informa, 6th ed, 2008)
Stewart Boyd, Andrew Burrows and David Foxton, Scrutton on Charterparties and Bills of Lading
(Sweet & Maxwell, 20th ed, 1996)
Norman Palmer, ‘Palmer on Bailment’, (Sweet & Maxwell, 3rd ed, 2009)
Martin Dockray, ‘Cases & Materials on the Carriage of Goods by Sea’, (Cavendish Publishing, 3rd
ed, 2004)
Brian Harris ‘Ridley’s Law of the Carriage of Goods by Land Sea and Air’, (Sweet & Maxwell, 8th
ed, 2010)
E.R. Hardy Ivamy, ‘Casebook on Shipping Law’, (Lloyd’s of London Press, 4th ed, 1987)
Lane Kendall and James Buckley. ‘Business of Shipping’, (Cornell Maritime, 7th ed, 2001)
John Mo, International Commercial Law (Lexis Nexis Butterowrths, 5th ed, 2013)
P M North, Cheshire’s Private International Law (Butterworths, 9th ed, 1974)
Jeannie Paterson et al ‘Principles of Contract Law’, (Thomson Reuters, 4th ed, 2009
Other
Chief Justice Allsop, ‘Recent Charterparty Decisions’, (Speech delivered at a lunchtime lecture for
MLAANZ and University of Newcastle, 26 June 2013).
Claimant’s Memoranda Of Argument (RMIT University)
- 15 -
-AUTHORITIES-
CONVENTIONS, RULES AND STATUTES
INTERNATIONAL
United Nations Commission on International Trade Law, Arbitration Rules 1976
Convention on Limitation of Liability for Maritime Claims 1976
Protocols to Amend the Limitation of Liability for Maritime Claims 1996
Protocol to Amend the International Convention for the Unification of Certain Rules of Law
Relating to Bills of Lading (The Hague Visby Rules) 1968
DOMESTIC
Arbitration Act 1996 (UK)
Carriage of Goods By Sea Act 1971 (UK)
Law Reform (Contributory Negligence) Act 1945 (UK)
Merchant Shipping Act 1995 (UK)
Misrepresentation Act 1967 (UK)
Torts (Interference with Goods) Act 1977 (UK)
MISCELLANEOUS ‘English law - Due diligence to maintain a vessel's condition’ The Gard News 188, November 2007, http://www.gard.no/ikbViewer/web/updates/content/52513/english-law-due-diligence-to-maintain-a-vessels-condition Charterparty repudiation’, Steamship Mutual, http://www.steamshipmutual.com/publications/Articles/ProVictor0210.html Chief Justice Allsop, ‘Recent Charterparty Decisions’, (Speech delivered at a lunchtime lecture for MLAANZ and University of Newcastle, 26 June 2013).
Claimant’s Memoranda Of Argument (RMIT University)
- 16 -
-STATEMENT OF FACTS-
1. Between the 3rd March and 2nd May the Western Dawn completed a range of appropriate
certification, inspection and questionnaires at the port of Singapore. All of these inspections and
questionnaires were satisfactory and passed without issue.
2. On the 26th May, the contract was concluded for the charterers LDT, to chart the vessel
Western Dawn, on an amended ST4 CP with rider clauses for 3 months +/- 30 days.
3. On the 27th May the Charterers gave the first set of VO for the vessel to load at Singapore.
4. On the 3rd June, the Charterers represented that a sufficient supply of bunkers would be
‘available passing Durban or Cape Town’.
5. On the 8th June, the Bill of Lading was duly created and on the 23rd June, a recapitulation
was executed between the charterer and the owner, specifying the terms of the CP.
6. On the 28th June the Charterers, via ASA2 as agents, represented that sufficient bunkers
would be available ‘on arrival STS Area 1’. ASA2 instructed the Master that the vessel was
under ‘control’ of ASA2 as the ‘agency’ of the charterers and via ‘local instruction’ would
discharge the cargo.
7. Prior to the vessel’s arrival at the alternative discharge place in international waters off the
Angolan coast, the good Master repeatedly confirmed (on the 28-29th June and 1-3rd July) that
the vessel would be ‘taking bunkers on arrival’.
8. On the 3rd July the charterers did not pay hire as stipulated by the terms of the CP.
9. On the 4th July, the Western Dawn arrives at OPL Luanda, and tenders notice of readiness.
On the same day, the Charterers considered the vessel off hire
10. On the 17th July the Master advised of a pirate attack and cargo diversion where 5 crew were
injured and cargo was stolen. Due to no instruction from the Charterer and low bunker supply,
the vessel proceeded directly to Cape Town for emergency assistance.
Claimant’s Memoranda Of Argument (RMIT University)
- 17 -
PART ONE: JURISDICTION
11. The Claimant submits this Tribunal has jurisdiction to hear this dispute because: (A) the
express and valid arbitration agreement within the CP specifies the seat of London; (B) this
Tribunal has the power to rule on its own jurisdiction; (C) of the known approach of English
Courts when deciding these matters; and (D) the correct commencement of this matter under the
Arbitration Act 1996 (UK).
A THE EXPRESS AND VALID ARBITRATION AGREEMENT FOUND IN THE
CHARTERPARTY SPECIFIES THE SEAT OF LONDON
12. The law governing contracts of carriage are determined by principles of private international
law and mandatory regulation applicable in the forum of the dispute.1
13. Per the CP agreed between the Claimant and Respondent, the ST4 proforma with
amendments, states at clause 46(a), (the choice of law clause) that the laws of England will
apply.
14. Per 46 b) of the CP it is stated all charter disputes shall be referred to Arbitration in London.
15. The claimant relies on Akai Pty Ltd v People’s Insurance Company Ltd,2 which states
‘where parties have bargained for English law, the court should give effect to that intention’.
16. The B/L states all CP clauses are incorporated into the B/L; therefore the Choice of law
clause is incorporated as ‘general words of incorporation of an applicable law clause are
effective’.3
17. As a commercial contract, both contracting parties would expect disputes arising out of the
agreement to be resolved in the one jurisdiction and as there is a close relationship between the
B/L and the CP, disputes arising from either document must be resolved and read together.4
1 Lloyd v Guibert (1865) LR 1 QB 115 2 [1999] I.L.Rd. 24. 3 R Aikens, R Lord and M Bools, Bills of Lading (Informa, 1st ed, 2006)
Claimant’s Memoranda Of Argument (RMIT University)
- 18 -
18. We contend London is the seat of arbitration and English Law applies to this matter.
B THIS TRIBUNAL HAS THE POWER TO RULE ON ITS OWN
JURISDICTION
19. Per s 30 of the Arbitration Act 1996 (UK), the claimant contends the tribunal has
competence to rule on its own substantive jurisdiction as there is a valid arbitration agreement
and the matters submitted are in accordance with the arbitration agreement.
20. The claimant relies on established precedent stating that an arbitral tribunal has inherent
power to rule on its own jurisdiction, including questions as to the validity of the arbitration
agreement.5
C KNOWN APPROACHES OF ENGLISH COURTS WHEN DECIDING
THESE MATTERS
21. The methods used to determine the governing law of a contract is through reference to
express intention of the parties and the ‘connection’ test6 whereby Courts refererence the
implied intention of the parties7 as a decisive factor.8
22. The intention of the Claimant was clear that any dispute matters were to be heard in
London.
23. The Respondent may assert they did not intend for disputes to be heard in London,9 however
we refer to Golden Acres Ltd v Queensland Estates Pty Ltd,10 which states a court may neglect
‘intention’ in special circumstances in the interests of the parties and justice.
4 Per the approach taken in The 'Dolphina' [2011] SGHC 273. 5 Christopher Brown Ltd v Genossenchaft Oestereichischer Waldbestizer Holwirtscafsbetriebe Registrierte GmbH [1954] i QB 7, 12-3. 6 As seen in Viva Vino Import Corporation v Farnses Vuni Srl 2000 US Dist LEXIS 12347. 7 John Mo, International Commercial Law (Lexis Nexis Butterowrths, 5th ed, 2013) 755. 8 P M North, Cheshire’s Private International Law (Butterworths, 9th ed, 1974) 201. 9 Moot problem, page 2, where the Charterers state they have had arbitral problems in London. 10 [1969] Qd R 378.
Claimant’s Memoranda Of Argument (RMIT University)
- 19 -
D THE CORRECT COMMENCEMENT OF THIS MATTER UNDER THE
ARBITRATION ACT 1996
24. This matter is brought in accordance with section 14(3) of the Arbitration Act 1996 (UK);
the arbitrator is named in the agreement to which these arbitral proceedings have commenced
and the Claimant has served the Respondent written notice requiring them to submit that matter.
25. Regarding the case of ‘The Agios Lazaros’11, notice was provided in writing and was valid.
26. We rely on the UN Commission on International Trade Law, Arbitration Rules 197612;
notice of arbitration should contain: a demand the dispute be referred to arbitration; names and
contact details of the parties; identification of the arbitration agreement that is invoked;
identification of any contract or other legal instrument out of or in relation to which the dispute
arises; a brief description of the claim and an indication of the amount involved if any remedy is
sought.
27. The Claimant submissions are clearly in writing containing details of the: parties; arbitration
agreement; dispute; and prayer for relief and as such this action has been brought correctly
under the Arbitration Act 1996.
PART TWO: BREACH OF CONTRACT
28. There has been a breach of contract by the Respondent because of (A) The contract of
carriage; (B) The incorporations of terms; (C) The failure of the Respondent to deliver bunkers;
(D) The failure of the Respondent to make payment; and (E) Abrogation of the carriers duty of
care.
A THE CONTRACT OF CARRIAGE
11 [1976] 2 Lloyd’s Rep 47. 12 Art 3.
Claimant’s Memoranda Of Argument (RMIT University)
- 20 -
29. Contracts of carriage are governed by general common law, however are distinguished from
commercial contracts as goods are transferred for purposes of relocation and to perform discrete
trade undertakings of sale and purchase, performed via private contract. 13
30. Only the carrier (herewith the Charterer) can exercise control over the performance of the
carriage and care for the goods in transit, so there is commercial risk borne in bailing goods.14
31. Third parties frequently facilitate contractual performance for ancillary actions such as
loading, discharging, trans-shipping and delivery and these services create individual
contractual and non-contractual legal relationships, raising challenges when apportioning
liability for breach.15
32. The cargo is carried via a carriage contract16 and regulatory considerations include
mandatory state regulation, the Hague-Visby convention17 made applicable by the Carriage of
Goods by Sea Act 197118 and the private contractual terms agreed between parties per the ST4
agreement.
B CONTRACTUAL TERMS AND THE INCORPORATIONS OF TERMS
33. Contractual terms once had three categories,19 however are now either fundamental terms
(or conditions) and ordinary terms (or warranties).20 If one party breaches a fundamental term
the innocent party may end the contract with damages.21
34. The terms of the contract must have been brought to the attention of the parties at the time
the contract was made.22 For standard forms such as this, the bound party must receive
‘reasonably sufficient’ notice of those terms for valid incorporation.23
13 Brian Harris ‘Ridley’s Law of the Carriage of Goods by Land Sea and Air’, (Sweet & Maxwell, 8th ed, 2010). 14 Ibid. 15 Ibid. 16 cf: London and North-Western Railway Company v Hudson and Sons [1920] AC 324. 17 Protocol to Amend the International Convention for the Unification of Certain Rules of Law Relating to Bills of Lading (The Hague Visby Rules), 1968 18 s1. 19 Hong Kong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd [1962] 1 All ER 474. 20 Photo Production Ltd v Securicor Transport Ltd [1980] AC 367. 21 Jeannie Paterson et al ‘Principles of Contract Law’, (Thomson Reuters, 4th ed, 2009. 22 Henderson v Stevenson (1875) LR 2HL Sc 470; Chapelton v Barry Urban District Council [1940] 1KB 532.
Claimant’s Memoranda Of Argument (RMIT University)
- 21 -
35. If there is an insufficient course of dealings between parties, as with this case as it is a first
time interaction, certain conditions of contract may not be deemed as incorporated.24 Standard
industry terms of trade amounting to customary dealings disregard a course of dealings and
serve to incorporate customary terms as implied.25
36. The Claimant asserts the following customary industry dealings are to be impliedly
incorporated into the CP as fundamental conditions: the carrier’s duty of care to the vessel,
cargo, servants and shipowner, including provision of sufficient bunkers with allowance for
contingencies26 and a duty not to direct the ship to a place of peril.27
C THE FAILURE OF THE RESPONDENT TO DELIVER BUNKERS
37. The Claimant contends the Respondent breached the contract by failing to deliver an
adequate supply of bunkers based on the incorporation of the Carriers overriding duty of care
(‘the duty’).
38. The duty developed to prevent unfair reliance by carriers on exclusion clauses, is based on
the Carrier’s role as bailee of goods28and is ‘a special duty to exercise due care and skill in
relation to the carriage of the goods and a special duty to furnish a ship fit for its adventure at its
inception’.29
39. In Northumbrian Shipping v Timm30 it was stated that: bunkering stages should be fixed at
voyage commencement; fuel sufficient for the intended stage and a margin for contingencies
should be loaded; and allowance for contingencies should not be reduced due to STS transfers
even if the contract allows liberty to deviate.31 This approach to carrying a reserve supply of fuel
23 Parker v South Eastern Railway Co Ltd [1877] 2 CPD 416. 24 Hertford Foods Ltd v Lidl GmbH [2001] EWCA Civ 938. 25 British Crane Hire Corp Ltd v Ipswich Plant Hire Ltd (1975) QB 303. 26 Northumbrian Shipping v Timm [1939] AC 397. 27 ‘The Eastern City’ [1958] 2 Lloyd’s Rep 127. 28 Martin Dockray, ‘Cases & Materials on the Carriage of Goods by Sea’, (Cavendish Publishing, 3rd ed, 2004). 29 Paterson Steamships v Canadian Co-operative Wheat Producers [1934] AC 538 PC. 30 [1939] AC 397. 31 Martin Dockray, ‘Cases & Materials on the Carriage of Goods by Sea’, (Cavendish Publishing, 3rd ed, 2004).
Claimant’s Memoranda Of Argument (RMIT University)
- 22 -
aligns to common, mandated requirements of marine underwriters regarding safety of life at
sea.32
40. The Claimants assert by provisioning the absolute minimum volume of bunkers, 950 mt, not
990mt as required,33 the Respondents breached their duty to furnish a ship fit for adventure.
a) Issue of Speed and Fuel Consumption
41. As the Respondents failed to sufficiently stem the vessel upon departure and continued to
not repair this deficiency, the vessel was inadequately bunkered which compelled the Master to
reduce the vessel to MEP and not NOP as stipulated per the VO.34
42. The ‘The Apollonius’35 raised the legal question of whether the charterers were entitled to
damages due to failure to prosecute the voyage with ‘utmost diligence.’36
43. The Claimants rely on this case, that the speed warrant is subject to the owners being
protected from the consequences of any exception clause that may be applicable.
44. The Claimants assert that actions of the Master in following alternative voyage order
instructions impacted his ability to prosecute the voyage with utmost dispatch and are exempted
as they are a direct result of the following actions and responsibilities of the Respondents: from
insufficiently stemming the vessel upon departure which placed the vessel in a position of
sensitivity should any unforeseen circumstances ensue; from following the orders of a
nominated agent, the ASA2 which placed the vessel at the mercy of rogues at sea and; from
failing to maintain vital communications to the Master for 25 days.
D THE FAILURE OF THE RESPONDENT TO MAKE PAYMENT
45. If a ship owner has a record of accepting late payment for hire, this conduct may waive the
right to withdraw from contract for a future late payment, unless notice has expressly been given
that the owner insists on timely future payments.37
32 Lane Kendall and James Buckley. ‘Business of Shipping’, (Cornell Maritime, 7th ed, 2001) 183, 306. 33 Moot problem, page 25 where the Master states requirements incorporating contingencies. 34 Moot problem, page 42. 35 Cosmos Bulk Transport Inc v China National Foreign Trade [1978] 1 Lloyds Rep 53 36 Martin Dockray, ‘Cases & Materials on the Carriage of Goods by Sea’, (Cavendish Publishing, 3rd ed, 2004)
Claimant’s Memoranda Of Argument (RMIT University)
- 23 -
46. This exception does not apply as there is no record of previous dealings between the parties,
therefore there is no established conduct that late payment has been or will be accepted.
47. The Claimants claim the contract has been breached by failure to make payment.
E ABROGATION OF THE CARRIER’S INCORPORATED DUTY OF CARE
48. Unless there is an express exclusionary clause, a charterer has a duty of care not to direct
a ship to a place known as unsafe.38 ‘The Eastern City’39 defined a safe port in the following
terms: ‘[if] the particular ship can reach it, use it and return from it without, in the absence
of some abnormal occurrence, being exposed to danger which cannot be avoided by good
navigation and seamanship..’
49. ASA2 were the Respondents nominated agents, per the communication ‘continue to liaise
with your STS coordinator..’40 The ASA2 VO instructions directed the vessel to a place of peril.
50. Nominating an unsafe port is a breach of contract and therefore subsequent damage to the
vessel or cargo is apportioned to the principles of causation and remoteness of damage.41
PART THREE: AN OBJECTIVE INTENTION NOT TO PERFORM HAS REPUDIATED THE CONTRACT
51. For repudiation to be made, there must be: a clear, unequivocal and absolute expression; by
words or conduct; that would lead a reasonable person to conclude the other party does not
intend to fulfil its contractual obligations; and the innocent party takes as a demonstration other
party does not intend to perform the contract.42
52. The Respondents advised bunker supplies would pass ‘either Durban or Cape Town’ and
that ‘everything is under control’.43 The Master messaged the Charterers on 8 occasions with no
37 The Brimnes [1975] QB 929, CA 38 Martin Dockray, ‘Cases & Materials on the Carriage of Goods by Sea’, (Cavendish Publishing, 3rd ed, 2004). 39 [1958] 2 Lloyd’s Rep 127. 40 Moot problem, page 40. 41 The Stork [1955] 2 QB 68 (Court of Appeal). 42 “The Hermosa” [1982] 1 Lloyd’s Rep 570, p 572-573; Fercometal SARL v Msc Mediterranean Shipping Co SA (The Simona) [1988] 2 Loyd’s Rep 199; SK Shipping (S) PTE Ltd v Petroexport Ltd [2009] EWHC 2974 (Comm) 43 Moot problem, page 26, 28.
Claimant’s Memoranda Of Argument (RMIT University)
- 24 -
response and protested that bunkers were not supplied as promised.44 The Respondent asserted
coordinates for bunkering are ‘Area 1’;45 which were not defined in the CP, VO or prior
communications. The Master’s pleas for explanation are ignored.46
53. The leading authority falls to the ‘The Hermosa,’47 affirmed in SK Shipping (S) PTE Ltd v
Petroexport Ltd,48 for repudiating a shipping contract via conduct by words, where the history
and context of the communications and demonstrates an objective intention not to perform.
54. No bunkering schedule was provided, per customary norms, containing ports on the
itinerary, locations to re-bunker, estimated quantity to be loaded and estimations of oil to be
consume.49
55. The Charterers repudiated the contract, evidenced by their words and conduct and are fully
liable for payment of the whole contracted on-hire period and for subsequent damages incurred
via loss of cargo, personal injury (physical and mental) to crew and damage to vessel.
PART FOUR: FRUSTRATION OF CONTRACT
56. In the alternative the Claimant submits the contract should be discharged because of
frustration of the commercial purpose of the adventure. This is on the basis of (A) Supervening
and unforeseen circumstances; (B) The lack of default on their side of the party; (C) The
contractual obligation is incapable of being performed because in such a circumstance
performance would be radically different from that which was undertaken by the contract; (D)
Once applied the contract would cease to bind either party and; (E) There are no exceptions for
TCP.
A THE SUPERVENING AND UNFORESEEN CIRCUMSTANCES
44 Moot problem, page 32. 45 Moot problem, Page 33, 34. 46 Moot problem, Page 34. 47 [1982] 1 Lloyd’s Rep 570, p 572-573. 48 [2009] EWHC 2974 (Comm). 49 Lane Kendall and James Buckley. ‘Business of Shipping’, (Cornell Maritime, 7th ed, 2001) 312.
Claimant’s Memoranda Of Argument (RMIT University)
- 25 -
57. For a contract to be declared frustrated there must be circumstances which prevent the
contract from being able to be performed50 which can include the subject matter of the contract
or something essential for its performance is destroyed.51
a) Destruction of Essential Item for Performance
58. The Claimants assert that piracy occasioned severe vessel damage to navigational and radio
equipment in the wheelhouse, the main deck hose crane and the starboard side ladder.52
Performance of the contract relies on this essential equipment, therefore this is a supervening
and unforeseen circumstance.
59. This argument depends on the time53 and expense54 of repairing the vessel.
b) Where the circumstances supervene which render performance of the
contract in the time contemplated by both parties impossible
60. To conclude the circumstances have come to such a delay that they frustrate the commercial
purpose of the adventure depends on the facts of the matter before the tribunal.55
61. Prolongation of the voyage by interruption of the contemplated route is capable of
frustrating the contract of carriage in law.56 It is acknowledged such a delay would need to be
radical.57
62. The Claimants argue from the 17th July 2014 the vessel was 13 days behind the original
ETA. This existing delay, combined with the MEP speed due to limited bunkers to Cape Town58
and repair time, should be considered a radical prolongation of the voyage.
B THE LACK OF DEFAULT ON EITHER SIDE OF THE PARTY 50 Jeannie Paterson et al ‘Principles of Contract Law’, (Thomson Reuters, 4th ed, 2009 51 Taylor v Caldwell (1863) 3 B. & S. 826; Applyby v Myers (1867) L.R. C.P. 651; Nickoll v Ashton [1901] 2 K.B. 126; Shipton Anderson v Harrison [1915] 3 K.B. 676; Gulnes v Imperial Chemcial Industries (1937) 43 Com.Cas 96. 52 Moot problem, page 42 53 Jackson v Union Marine (1874) L.R. 10 C.P. 125. 54 Assicurazione v Bessie Morris [1892] 2 Q.B. 652; Carras v. London and Scottish Assurance [1936] 1 K.B. 291; Kulukundis v Norwich Union [1937] 1 K.B. 1. 55 Stewart C. Boyd, Andrew S. Burrows and David Foxton, Scrutton on Charterparties and Bills of Lading (Sweet & Maxwell, 20th ed, 1996) 27. 56 The Eugenia [1964] 2 Q.B. 226 at p 240; The Captain George K [1970] 2 Lloyd’s Rep. 21 at p. 31. 57 Ibid. 58 Moot problem, page 42.
Claimant’s Memoranda Of Argument (RMIT University)
- 26 -
63. Given that the frustrating event has now been proven, the onus of proving that it arose
through the default of the other party rests upon us as the party alleging the default.59
64. The Claimants contend the failure of the Respondent to provide sufficient bunkering at
various points of the journey frustrated this contract, as the Western Dawn was forced to travel
at MEP60 and lie floating whilst waiting for essential bunkers61 in an area with known piracy
threats.
65. These events caused the ship to be seized and cargo to be stolen, which frustrated the
contract.
C THE CONTRACTUAL OBLIGATION INCAPABLE OF BEING
PERFORMED BECAUSE IN SUCH A CIRCUMSTANCE PERFORMANCE
WOULD BE RADICALLY DIFFERENT
66. For a contract to be frustrated, circumstances must render the contractual obligation
incapable of being performed because in such circumstances performance would have been a
thing radically different from that which was undertaken by the contract.62
67. Ultimately this is a ‘conclusion is almost completely determined by what is ascertained as
the mercantile usage and understanding of commercial men.’63
68. The Claimants raise the argument that the CP agreed a hire period of 3 months +/- 30 days64
for a ship that was seaworthy with a final delivery to the Mediterranean on the conclusion of the
CP.65
69. The damaged ship journeyed to Cape Town with damage resulting from fraudulent claims.66
59 Joseph Constentine v Imperial Smelting Corporation [1942] A.C. 154. 60 Moot problem, page 32. 61 Moot problem page 41. 62 Daivs Construction Ltd v Foreham U.D.C. [1956] A.C. 14 per Lord Radcliffe at pp. 728, 729; National carriers Ltd v Panalpina (Northern) Ltd [1981] A.C. 675, at pp. 688 and 717; B.T.P. Tiozafr Ltd v Pioneer Shipping Ltd and Armada Marine S.A. (The Nema) [1982] A.C. 724. At 751, 752. 63 B.T.P. Tiozafr Ltd v Pioneer Shipping Ltd and Armada Marine S.A. (The Nema) [1982] A.C. 724. At 751, 752 Lord Roskill citing Lord Radcliffe in Tsakiroglou v Noblee Thori [1962] A.C. 93 at p. 124. 64 Moot problem, page 5. 65 Ibid. 66 Hedley Byrne & Co Ltd v Heller & Partners Ltd [1964] AC 465; Caparo v Dickman [1990] 2 AC 605.
Claimant’s Memoranda Of Argument (RMIT University)
- 27 -
70. The vessel must now undergo repairs, which will be costly and timely, therefore
performance of the contract will be greatly different to those originally agreed to in the CP.
D ONCE APPLIED THE CONTRACT WOULD CEASE TO BIND EITHER
PARTY
71. Once the doctrine of frustration applies, the contract ceases to bind either party,67 the
contract is terminated and there is no requirement for either party to elect to terminate the
contract.68
72. The contract can be brought to an end even if it has been partly performed.69
73. The CP has been frustrated by the above events, notwithstanding the contract was partly
performed and the Claimants cannot be required to complete the remainder of the CP
agreement.
E THERE ARE NO EXCEPTIONS FOR TIME CHARTERPARTIES
74. Historically, the doctrine of frustration could not apply to a time CP in its ordinary form,70
which was displaced.71 Time CP are subject to the usual incidents of the law of contract.72
75. There are no exceptions in applying the doctrine of frustration to this matter and we contend
the contract be declared frustrated, pursuant to the above arguments.
F INVOLUNTARY BAILMENT
76. If deemed the VO of ASA2 were not authorised, the CP was frustrated from the date of these
instructions, 28 June.73 From this point the Claimants were involuntary bailees of the cargo and
claim recovery of costs for bunkers and storage at market rates from this date.
67 Jackson v Union Marine Co. (19874) L.R. 10 C.P. 125 at 144, Geipel v Smith (1872) L.R. 7 Q.B. 404 at 410. 68 Larrinaga v Societe Franco-Americaine (1922) 28 Com.Cas 1 at p.2,Bank Line v Capel [1919] A.C. 435 at p. 454, Maritime National Fish v Ocean Trawlers [1935] A.C. 524, J. Lauritzen A.S. v Wijsmuller B.V. (The Super Servant Two) ˆ[1990] I1 Lloyd’s Rep 1. 69 Embiricos v Reid [1914] 3 K.B. 45. 70 Balihache J in Admiral Shipping Co v Weidner Hopkins [1916] 1 K.B.429. 71 Scottish Navigation Co. v Souter [1917] K.B. 222. 72 Stewart C. Boyd, Andrew S. Burrows and David Foxton, Scrutton on Charterparties and Bills of Lading (Sweet & Maxwell, 20th ed, 1996) 29. 73 Moot problem, page 35.
Claimant’s Memoranda Of Argument (RMIT University)
- 28 -
77. Costs were incurred to care for the goods, thus additional benefit was conferred to the
Respondents as their goods were cared for longer than was contractually accounted for.74
78. The standard of care required of the bailee, whether gratuitous or not, is the standard
required dependent on the circumstances of the case.75 The circumstances of this case are
extraordinary and in the circumstances the Master exercised all reasonable care.
PART FIVE: TORT OF FRAUD
79. The Claimant submits a tort of fraud has been committed by the Respondent in failing to
provide bunkering as promised because (A) There is proof that a fraud was committed; (B) The
false representation promising bunkering was made knowingly; (C) In the alternative the false
representation promising bunkering was made recklessly and carelessly; (D) There was reliance
on the promise of bunkering; (E) Damage occurred because of this misrepresentation and (F)
Motive and gain are not considerations.
A THERE IS PROOF THAT FRAUD WAS COMMITTED
80. To make a Tort of Fraud reliance falls to Derry v Peek,76 demanding proof of the fraud. The
Claimants reference communications whereby the Master was falsely promised stems.77
81. If the representation was true at the time it was made, the effect of making that statement
required it to be corrected when it became false.78
B THE FALSE REPRESENTATION PROMISING BUNKERING WAS MADE
KNOWINGLY
82. Per Derry v Peek,79 we contend that the false representation of promising stems was made
knowingly, or without belief in its truth, or recklessly, or carelessly whether it be true or false.
74 Cargo ex Argos, Gaudet v Brown (1872) LR 5 PC 134; Great Northern Railway Co v Swaffield (1874) LR 9 Ex 132; China Pacific SA v Food Corporation of India (‘The Winson’) [1982] AC 939. 75 Houghland v Low Luxury Coaches Ltd [1962] 1 QB 694. 76 (1989) 14 App.Cas. 337. 77 Moot problem, page 28, 33. 78 Slough Estates PLC v Welwyn Hatfield CT [1996] 2 PLR 50. 79 (1989) 14 App.Cas. 337
Claimant’s Memoranda Of Argument (RMIT University)
- 29 -
83. The Respondent had actual knowledge of the false representation per Armstrong v Strain:80
‘there must be knowledge in the narrower sense; and conscious knowledge of the falsity must
always amount to wickedness and dishonesty’.
84. The Claimants submit the Respondent had conscious knowledge that sufficient bunkers
would not be delivered to the Master at Luanda, as they had consciously planned to do.
C IN THE ALTERNATIVE THE FALSE REPRESENTATION PROMISING
BUNKERING WAS MADE RECKLESSLY, CARELESSLY
85. In the alternative, he Respondent was reckless and careless of the truth of their bunkering
promise.
86. The Claimants rely on Angus v Clifford81 which held: ‘Not caring, in that context, did not
mean not taking care, it meant indifference to the truth, the moral obliquity of which consists in
a wilful disregard of the importance of the truth.’
87. The Respondent had wilful disregard for the truth, demonstrated by their repudiatory
actions.
D THERE WAS RELIANCE ON THIS PROMISE OF BUNKERING
88. For this tort to be successful it must be found that the Respondent intended the Claimant to
rely upon the statement.82 The statement in question for this matter is that of the promise of
bunkering to be supplied to the vessel en route at Durban and Cape Town.
89. Presently, authorities have not determined if the ‘intention’ requirement is actual intention,
or if it is simply reasonable foreseeable.83
90. For reliance to be made, it must be shown the Claimant was induced to act by the fraudulent
statement84 and the maker of the statement intended for the Claimant to rely on the statement.85
80 [1951] 1 TLR 856 at 871 81 [1981] 2 Ch 449 at 471 82 Mead v Babington [2007] EWCA 518. 83 Hugh Beale, Chitty on Contracts (Sweet & Maxwell, 30th ed, 2008) 6-030 84 Goose v Wilson Sandford [2001] Llyods Rep PN 189 85 Bradford Third Equitable ex v Boarders [1941] 2 All ER 205 at 211
Claimant’s Memoranda Of Argument (RMIT University)
- 30 -
91. The statement was one factor inducing the Claimant to act; it does not need to be the only
factor.86
92. The Claimants contend they were induced to enter into contract on belief adequate
bunkering would be provisioned and assert reliance on the fraudulent representation regarding
bunkering and state this element of the tort has been met.
E DAMAGE OCCURRED BECAUSE OF THIS MISREPRESENTATION
93. The final element is that the Claimant suffered financial loss owing to the fraud.87
F MOTIVE AND GAIN ARE NOT CONSIDERATIONS
94. Per Pasley v Freeman,88 the essence of action was the deception of the Claimant. It is not
material that the Respondent did not gain from this deception.
95. In reliance on Bradford Third Benefit BS v Borders,89 the Respondent’s motive is of no
relevance.
PART SIX: NEGLIGENT MISSTATEMENT
96. Claims for loss by negligent misstatement for carriage contracts are made via the principles
of Hedley Byrne v Heller90 and the test laid down in Caparo v Dickman.91
97. The Claimant must establish the Respondent owed a duty of care which was breached which
occasioned damage; the duty is to take reasonable care that information and advice is sound.92
98. Notions that the duty is only imposed to those claiming skill and competence in the matter
of the representation are rejected,93 but remain relevant to determining if the reliance was
reasonable.94
86 Eddington v Fitzmaurice (18885) 29 ChD 459. 87 Brian Harris ‘Ridley’s Law of the Carriage of Goods by Land Sea and Air’, (Sweet & Maxwell, 8th ed, 2010). 88 (1789) 3 Term Rep 51. 89 [1941] 2 All ER 205, which was followed in Ludsin Overseas Ltd v Eco3 Capitial Ltd [2012] EWHC 1980 (Ch) 90 Hedley Byrne & Co Ltd v Heller & Partners Ltd [1964] AC 465. 91 [1990] 2 AC 605. 92 Jeannie Paterson et al ‘Principles of Contract Law’, (Thomson Reuters, 4th ed, 2009. 93 Howard Marine & Dredging Co Ltd v A Ogden & Sons (Excavations) Ltd [1978] QB 574. 94 Jeannie Paterson et al ‘Principles of Contract Law’, (Thomson Reuters, 4th ed, 2009.
Claimant’s Memoranda Of Argument (RMIT University)
- 31 -
99. To seek relief via rescission or damages, a causal and not too remote link must lie between
the misrepresentation and entry into contract, through proof of reliance on the representation.95
100. The loss must be reasonably foreseeable to the person liable for the misstatement
with a sufficient relationship of proximity between the party relying on the misstatement and the
party liable and it must be fair, just and reasonable to impose a duty of care.96
101. The Respondent owed the Claimants a duty of care to sufficiently stem the vessel
and per customary industry dealings were knowledgeable of this fundamental duty. The
Claimants contracted in belief this duty would be executed in good faith and as such
experienced loss.
102. In the alternative the Claimants seek statutory relief via s 2(1) of the
Misrepresentation Act 1967 (UK), which reverses the burden of proof and per Royscot Trust Ltd
v Rogerson97 damages are assessed as with tort of fraud; all direct loss is recoverable, whether
or not it was foreseeable.98
PART SEVEN: THERE WAS NO NEGLIGENCE OF THE MASTER AND CREW
103. There can be no case of negligence or incompetence against the Master of the
Western Dawn because: (A) The construction of the negligence exception does not allow a case
to be raised; (B) There was no negligence in the navigation or management of the ship; (C)
These exceptions last for the duration of the possession of the goods in questions and; (D) The
Master and crew are not liable for acts of piracy on the high seas.
A CONSTRUCTION ON NEGLIGENCE EXCEPTIONS
104. The general principles of construction relating to whether an exception clause
excludes liability for negligence are that negligence is most obviously excluded where the
95 Jeannie Paterson et al ‘Principles of Contract Law’, (Thomson Reuters, 4th ed, 2009. 96 Caparo v Dickman [1990] 2 AC 605; Brian Harris ‘Ridley’s Law of the Carriage of Goods by Land Sea and Air’, (Sweet & Maxwell, 8th ed, 2010). 97 [1991] 3 All ER 294. 98 Simon Baughen, ‘Shipping Law’ (Cavendish Publishing, 3rd ed, 2004).
Claimant’s Memoranda Of Argument (RMIT University)
- 32 -
exception clause uses the word ‘negligence’ or a synonym for it.99 General words such as ‘not
responsible for damage, however caused’ will normally be construed as excluding liability for
negligence where the Respondent could realistically only have been liable for negligence. 100
105. Per clause 27 of the ST4 CP agreement signed between the parties to this matter, the
word negligence is used and we rely on this clause.
106. As this clause is often construed strongly against shipowners,101 the Claimants in this
matter contend there was no personal negligence for the appointment of the Master as he was
neither drunk nor incompetent.102
107. As clause 27 contains an express exception of negligence of the shipowner’s
servants, full effect will be given to it so even the most culpable recklessness does not render the
Claimant liable. 103
108. As a result, and in spite of this clause being harshly construed against the Claimant,
it is not possible for the Claimant to be held responsible for the negligence of the Master or of
the servants of the ship due to the construction of the term.
B THE MASTER DEVIATED UNDER AGENCY AUTHORISATION AND
THERE IS NO CLAIM TO ANSWER FOR MISDELIVERY OF CARGO
109. Clause 13 (a) of the CP states ‘the master (although appointed by owners) shall be
under the orders and directions of charterers as regards employment of the vessel, agency and
other arrangements’.
99 Canada Steamship Lines v The King [1952] A.C. 192 (p.C.). Also see Travers v Coopers [1915] K.B. 73; Pyman v Hull and Barnsley Co. [1915] 2 K.B. 729; Rutter v Palmer [1922] 2 K.B. 87; Calico Printers’ Association v Barclays Banks (1931) 36 Com.Cas. 197; Alderslade v Hendon Laundry [1945] K.B. 189; Varnish v The Kheti (1949) 82 Li.L.R. 525. 100 Ibid. 101 Price v Union Lighterage Co. [1904] 1 K.B. 412; The Pearlmoor [1904] P 286. 102 City of Lincoln v Smith [1904], Brett L.J. in Chartered Mercantile Bank of India v Netherlands India S.N. Co (1883). 103 Briscoe v Powell (1905) 22 T.L.R. 128. In Marriot v Yeoward [1909] 2 K.B. 987 it was held that even felonious acts by a servant of the shipowner were covered by “any act, neglect, or default, whatsoever” of servants etc.
Claimant’s Memoranda Of Argument (RMIT University)
- 33 -
110. An agent's authority may be actual, which is expressly or implicitly agreed by the
principal or agent, or apparent by express or implied representation by the principal that the
agent is invested with authority.104
111. It is argued the VO provided by ASA2, coupled with the representation from the
Respondents to ‘liaise with your STS coordinator’105 amount to sanctioned directions from an
Agency and as such the Master is indemnified from any detrimental resulting consequences.
112. A relevant legal question is whether the ‘effective’ cause of the loss was an ‘insured
peril’ or an ‘indemnifying event’.106 It is decided law that this indemnity, expressed in Clause 13
(a), applies when the orders are both contractually valid and also not justified by the contract.107
113. Regards to the indemnity and necessity for loss, it has been articulated that causation
is contextual and a matter of construction;108 the intended scope of loss is not one of
foreseeability, but whether the order was the ‘effective cause’ of the loss and not a ‘mere’, ‘but
for cause as there can be no other causes.109 Similarly worded indemnities have been found to
apply where there is a direct causal link between orders given and resultant consequences.110
114. We assert that as a direct result of VO provided by ASA2 the Master complied to
deviate the ship to the stated destination for the purposes of essential bunkering.
115. The B/L states the Master must deliver the ship to the discharge port or as close as
the ‘vessel may safely get’. The vessel was delivered, under instruction, to a location close to
the stipulated discharge port, within the Luanda OPL limits and owing to the subsequent
emergency encountered by the vessel, the Master therefore delivered the ship as close as safely
possible.
104 Brian Harris ‘Ridley’s Law of the Carriage of Goods by Land Sea and Air’, (Sweet & Maxwell, 8th ed, 2010) 105 Moot problem, page 40. 106 McCarthy v St Paul International Insurance Co Ltd [2007] FCAFC 28; 175 FCR 402 107 The ‘Island Archon’ [1994] 2 Lloyds Rep 227 as approved in Petroleo Brasileiro SA v ENE Kos 1 Ltd [2012] UKSC 17; [2012] 2 AC 164 108 Petroleo Brasileiro SA v ENE Kos 1 Ltd [2012] UKSC 17; [2012] 2 AC 164 109 Chief Justice Allsop, ‘Recent Charterparty Decisions’, (Speech delivered at a lunchtime lecture for MLAANZ and University of Newcastle, 26 June 2013). 110 The ‘Hill Harmony’ [2001] 1 AC 638 at 656
Claimant’s Memoranda Of Argument (RMIT University)
- 34 -
116. The Master’s obligation of delivery was performed as best as possible under the
emergency circumstances.111
117. Given the very close location of the point of the ship under direction and the
nominated discharge point, it is very likely the piracy would have occurred in any event, as the
ship would have sailed close to the area in sailing to the discharge port.112
118. The ‘liberty’ clause within the B/L entitles the Claimants and Master to deviate as
necessary. There is no specified route which must be taken, only the most usual route and the
Master is under no requirement to take the fastest or most direct route (unless expressly required
which was not contracted for in this instance).113
119. The duties of the Master were discharged in good faith, notwithstanding teh cargo
was delivered to a rogue.114
C THERE WAS NO NEGLIGENCE IN THE NAVIGATION OR
MANAGEMENT OF THE SHIP
120. The exception from the above negligence clause must be addressed. The first is the
negligence in the navigation or in the management of the ship, which is found in the Carriage of
Goods By Sea Act 1971, Article IV, Rule (2)(a).
121. This act holds neither carrier nor vessel responsible for loss or damage arising for
any act, neglect, or default of the Master, or of other servants in the navigation or management
of the ship.
122. In reliance on this finding we argue the choice of the Master to continue to the next
port, as best as he could, without further instruction from the Respondent’s agent could not be
held as negligence as it was judgement in the management or navigation of the ship.
111 Dahl v Nelson, Donkin and Company (1881) 6 App Cas 38; ‘The Eastern City’ [1958] 2 Lloyd’s Rep 127. 112 Palace Shipping Company v Gans Steamship Line [1916] 1 KB 138. 113 ‘The Indian CIty’ [1939] AC 562 114 McKean v McIvor (1870) LR 6 ex 36.
Claimant’s Memoranda Of Argument (RMIT University)
- 35 -
123. We rely on the findings in Owners of SS. Lord v Newsum,115 which decided the error
of the Master in choosing the route he should pursue was not held as ‘negligence, default or
error in judgement in the management or navigation of the ship’.
124. We rely on the findings that if the cause of the damage is solely or even primarily a
neglect to take reasonable care of the cargo, the ship is liable. But if the cause of the damage is a
neglect to take reasonable care of the ship, or some part of the ship, as distinct from the cargo,
the ship is released from liability.116
125. We argue that if there was negligence, it was a failure to take reasonable care of the
ship, and protect it from piracy. As a result the ship is released from liability.
D THIS EXCEPTION LASTS FOR THE DURATION OF THE POSSESSION
OF THE GOODS IN QUESTIONS
126. In constructing this argument we must consider during which time this exception is
allowed.
127. We therefore rely on the general rule, which states that the exceptions limit the
shipowners liability during the whole time in which he is in possession of the goods as a
carrier.117
128. This was also found to cover negligence during loading and to apply to the whole
time during which the vessel was engaged in performing the contract contained in the charter.118
129. This would effectively mean the Claimant could not be found liable for the entire
passage of the journey, as negligence was found outside of the navigation or management of the
ship.
E THE MASTER AND CREW ARE NOT LIABLE FOR ACTS OF PIRACY ON
THE HIGH SEAS.
115 [1901] 1 K.B. 846. 116 Gosse Millerd v Candaian Govt. Merchant Marine [1929] A.C. 223 (H.lL). 117 Norman v Binnington (1890) 25. Q.B.D. 475 at p. 478; The Carron Park (1890) 15 P.D. 203, per Wright J. In De Clermont v General Steam Navigation Co. (1891) 7 T.L.R. 187 at p.188. 118 The Carron Park (1890) 15 P.D. 203,
Claimant’s Memoranda Of Argument (RMIT University)
- 36 -
130. The New English Dictionary defines piracy as ‘robbery and depredation on the sea or
navigable rivers, etc., or by descent from the seas upon the coast, by persons not holding a
commission from an established civilised state’.119
131. Sufficient authorities suggest that pirates are a permissible exception under the
Carriage of Goods By Sea Act 1971, under Rule 2 of Article 5, which at (f) considers Acts of
public enemies and at (q) ‘any other cause arising without the actual fault or privity of the
carrier, or without the fault or neglect of the agents or servants of the carrier.’120
132. We argue in line with the precedent, that loss of goods via piracy relieves the
shipowner of the burden to prove the loss was not caused by his negligence.121
133. In the instant case it is clear the loss of the goods was via piracy and therefore the
Claimant, as the shipowner, is not required to prove the loss was not caused by negligence.
PART EIGHT: THE TORT OF CONVERSION WAS NOT COMMITTED
134. The Respondent alleges the Claimant has committed a tort of conversion, also
known as trover. We argue this allegation is rebutted because (A) A common law special lien
has been created through the CP; (B) The Claimant has not undertaken sufficient intentional
conduct to have converted the goods in question; (C) Failure to deliver goods because they have
been lost or destroyed by accident or carelessness is not conversion and; (D) Goods lost or
destroyed cannot be subject to an act of conversion.
A A LIEN HAS BEEN CREATED THROUGH THE CHARTERPARTY
135. When considering what sort of lien has been created under a CP, we must consider
that it will be limited to what is expressly given.122
119 See Republic of Bolivia v Indemnity [1909] I K.B. 784; Re Privacy Hire Gentium [1934] A.C. 586 (P.C.) and Athens Maritime Enterprises Corporation v Hellenic Mutual War Risks Association (Bermuda) Ltd [1982] 2 Llyod’s Rep. 483. 120 City of Baroda (Owners) v Hall Line (1926) 42 T.L.R. 717; Hourani v Harrison (1927) 32 Com.Cas. 305; Potts v Union SS. Co. of New Zealand [1946] N.Z.L.R. 276; Leesh River Tea v British India Steam Navigation Co. [1966] 2 Llyod’s Rep. 193. 121 Czech v General Steam Co. (1867) L.R. 3 C.P. 14.
Claimant’s Memoranda Of Argument (RMIT University)
- 37 -
136. As a result, a lien must be read subject to the express terms of the charter.123
Therefore we must turn to the terms found in the CP.
137. As per clause 26 of the ST4 CP agreement between the Claimant and Respondent,
the owners have lien upon all cargoes and all freights, sub-freights and demurrage for any
amounts due under the charter.
138. Thus by looking at the lien created, the Claimant has an express lien over all cargo
and freights, and therefore cannot be considered to have converted the cargo whilst waiting for
the payment of freight.
B THE CLAIMANT HAS NOT UNDERTAKEN SUFFICIENT INTENTIONAL
CONDUCT TO HAVE CONVERTED THE GOODS IN QUESTION
139. For the tort of conversion to be made there must be ‘intentional, wrongful
interference of a substantial nature with the Claimant’s possession or right to possession of the
goods.’124
140. The Respondent is claiming the chartererers and/or the receivers named on the BoL
have not taken possession of the goods named on the bill.
141. This does not amount to an intentional, wrongful interference of the goods and there
is no intention by the Claimant to interfere with the natural owners right.
142. The required elements for the tort of conversion cannot be made from these facts.
C GOODS LOST OR DESTROYED CANNOT BE SUBJECT TO AN ACT OF
CONVERSION
143. Under the Torts (Interference with Goods) Act 1977, s 2(2) there can be no action for
conversion of loss or destruction of goods if a bailee allowed the breach of his duty to the bailor
thus the Respondent cannot claim conversion for the goods lost at sea during the pirate attack.
122 See E. Clemens Horst Co v Norfolk etc.& Co. (1906) 11 Comm.Cas. 141 and Red “Superior” v Dewar & Webb [1909] 1 K.B. 998 (C.A.). 123 Canadian Pacific (Bermuda) Ltd v Logan Martime Overseas (The Fort Kipp) [1885] 2 Lloyd’s Rep. 168. 124 Lewis v Averay [1972] 1 QB 198
Claimant’s Memoranda Of Argument (RMIT University)
- 38 -
144. Bailees are required to take reasonable care of the goods in their keeping and they
can be found liable for loss or destruction unless they can disprove fault.125
145. The Claimant disproves their fault in the matter as they were not provided with
sufficient bunkers to ensure they could take reasonable care of the goods in their keeping.
PART NINE: THE VESSEL WAS SEAWORTHY
146. We contend the Western Dawn, the vessel subject to this CP, was seaworthy as
required under the CP as: (A) All of the obligations of the owner were met; (B) the condition on
redelivery is a matter for the Respondent.
A ALL OF THE OBLIGATIONS OF THE OWNER WERE MET IN REGARD
TO SEAWORTHINESS
147. At common law there is implied in every contract for the carriage of goods by sea a
warranty by the carrier that the vessel is seaworthy , unless this warranty is expressly
excluded.126 That the the vessel is not as safe as other vessels does not amount to a breach of
warranty.127
148. A time charter includes an undertaking of seaworthiness at the beginning of the
time.128 If the Master proceeds on such a voyage without using an opportunity to remedy the
unseaworthy condition of his ship the owner will be liable for his negligence unless protected by
exceptions.129
149. Under the Carriage of Goods by Sea Act 1971 s 3 and CP clause 1 there is an
undertaking the shipowner will, exercise due diligence to make the ship seaworthy.
125 Sutcliffe v CC of West Yorksire [1996] RTR 86 126 Bank of Australasia v Clanline [1916] 1 KB 39 55. 127 Burgess v Wickham (1863) 3 B&S 669 128 Giertsen v Turnbull, 1908 S.C. 1101. 129 Worms v Storety (1855) ii Ex, 427; The Rona (1884) 51 L.T. 28.
Claimant’s Memoranda Of Argument (RMIT University)
- 39 -
150. To consider what is seaworthy in any given situation, we must consider the relative
nature of the ship,130 the particular voyage she is contracted for,131 the particular stages of that
voyage being different in navigation forms132 and the particular cargo being carried.133
151. One of the tests for seaworthiness is: Would a prudent owner require the defect
should be made good before sending his ship to sea, had he known of it? If he would, the ship
was not seaworthy.134 It is important to note the undertaking does not require absolute perfection
or a guarantee of safe carriage135
152. Based on the facts there is nothing to suggest the ship was not seaworthy at the
outset of the voyage. As a result we contend that all obligations of the owner were executed
regarding the seaworthiness of the Western Dawn.
B THE CONDITION ON REDELIVERY IS A MATTER FOR THE
RESPONDENT
153. Time charters usually provide that the charter will redeliver the vessel in the same
good order and condition (with fair wear and tear excepted) as delivered to them.
154. If, however on redelivery the ship has, due to the charter’s breach of contract been
damaged, he is liable for the damages. He is not liable for hire during the period occupied by the
repairs.136
155. It is noted the words ‘fair wear and tear excluded’ will not necessarily protect the
charter even if the damage to the ship has been caused without negligence.137
130 Burgess v Wickham (1863) 3 B & S. 669 131 Empresa Cubana Importada de Alimentos “Alimport” v Iasmos Shipping Co. S.A. (The Good Friend) [1984] 2 Lloyd’s Rep. 586. 132 Thin v Rochards [1892] 2 Q.B. 141; Daniels v Harris (1874() L.R. 10 C.P. 1; Annen v Woodman (1810) 3 Taunt. 299. 133 Stanton v Richardson (1984) L.R. 9 C.P. 390; Tattersall v National Steamship Co. (884) 12 Q. B.D. 297 134 McFadden v Blue Star Line [1905] 1 K.B. 697 at p 706. 135 Stewart C. Boyd, Andrew S. Burrows and David Foxton, Scrutton on Charterparties and Bills of Lading (Sweet & Maxwell, 20th ed, 1996) 97. 136 Wye SS. Co v Compagnie P.O. [1922] 1 K.B. 617; Black Sea & Danube Shipping Co v Goeland Transport & Trading Co. (1942) L.I.L.R. 192 at p 195. 137 Chellew Navigation Co v Applequist (1933) 38 Com.Cas 218, C.P.R. v Board of Trade (1925) 22 L.I.L.R. 1 (H.L.)
Claimant’s Memoranda Of Argument (RMIT University)
- 40 -
156. Per previous arguments that the ship was damaged due to the Respondents breach of
contract. The Charterers are therefore liable for damages occasioned to the vessel.
PART TEN: DAMAGES
157. Via the above arguments the Claimant has a right to damages which are (A)
Damages under the law of contract (B) Damages under the law of tort (C) Interest as per the
Arbitration Act 1996. (D) Consideration of limitation of liability.
A DAMAGES UNDER THE LAW OF CONTRACT
158. The usual aim of damages for breach of contract is to put the plaintiff into the
position they would have been in if the contract had been performed.138 The measure of damages
is governed by Hadley v Blaxendale:139 damages are limited to those flowing naturally from the
breach (direct loss) except where the parties had in contemplation extraordinary further
damages.140
159. Where once the test was causation flowing from foreseeable consequences, now it
requires the parties to have mutually contemplated the loss at time of contracting as a probable
financial consequence: ‘The Achilleas’.141
160. Claims for damages are restricted; damage cannot be recovered for a loss that is too
remote.
161. The test for remoteness is that the loss should be such as may fairly and reasonable
be considered arising naturally or as may reasonably be supposed to have been in the
contemplation of both parties at the time they made the contract and a probable result of the
breach of it.142
138 Robinson v Harman (1848) I Exch 850, 855; Monarch SS co v Karishamns [1949] A.C. 196, 220; Czarnikow v Koufos [1969] 1 A.C. 350, 414; Ruxley Electronics & Construction Ltd v Forfyth [1995] 3 W.L.R. 118, 112, 131-132. 139 (1854) 9 Exch 341. 140 Hadley v Blaxendale (1854) 9 Exch 341; Also Victoria Laundry (Windsor) Ltd v Newman Industries Ltd (1949) 2 KB 528. 141 Transfield Shipping Inc v Mercator Shipping Inc [2008] 2 Lloyd’s Rep 275. 142 Hadley v Baxendale (1854) 9 Ex. 341 at p. 354, per AldersonB.
Claimant’s Memoranda Of Argument (RMIT University)
- 41 -
162. We must take into account that this is a two limbed test: the first limb starts at the
disjunctive ‘or’. The second limb deals with special circumstances, known to both parties at the
time the contract was made without which, knowledge that damage caused would not
reasonably have been considered as fairly and reasonably within contemplation of the parties.143
163. We assert both parties considered piracy in the geographical area in which they were
sailing, as arising naturally in the course of dealings.
164. Given the nature of shipping, it is reasonable to state the parties hold special
knowledge of this area and its piracy threat and therefore the second knowledge portion of the
test is met.
165. On this basis we contend we should be awarded damages to a sufficient amount to
put the Claimant in the position they would have been in had the contract not been performed
and we take this to be a repaired ship and medical expenses of the injured crew to be paid.
166. Exemplary damages cannot be award for breach of contract144 and none are
requested.
a) DUTY TO MITIGATE
167. Per contract law, the Claimant has a duty to mitigate loss and damages will not be
awarded for losses that could have reasonably been avoided.145
168. It should be noted that the duty to mitigate does not oblige the party not in default to
take any action, which would seriously damage his commercial reputation.146
169. We therefore contend that stopping the ship at port, when there was promise of
bunkers at a later stage of the journey, would have seriously damaged the commercial reputation
of the Claimant and there was no obligation to take such action.
B DAMAGES UNDER THE LAW OF TORT
143 Czarnikow v Koufos [1969] 1 A.C. 350, Per Lord Upjohn at pp 421 – 422. 144 Addis v Gramophone Co. Ltd [1909] A.C. 488; Perera v Vandiyar [1953] 1 W.L.R. 672. 145 British Westinghouse Electric v Underground Electric Railways Co. of London Ltd [1912] A.C. 673. 146 James Finlay & Co. v Kwik Hoo Tong [1929] 1 K.B. 400.
Claimant’s Memoranda Of Argument (RMIT University)
- 42 -
170. We raise a claim for damages under the law of tort as per contract law, the usual
claim for tortious damages is to put the plaintiff into as good a position as they would have been
in had the tort not been committed.147
171. The advantage of this claim is that the level of liability is wider. The test for damages
under tort is simply that the Respondent is liable for any type of damage, which is reasonably
foreseeable as liable to apply even in the most unusual case, unless the risk is so small that a
reasonable person would in the whole circumstances feel justified in neglecting it.148
172. In line with this test, we submit that the Respondent should be liable for damages
done to the ship and crew, as it was reasonably foreseeable that a ship drifting in the area
prescribed by the Respondent would be susceptible to piracy, given the nature and known
history of the area.
173. We also raise the point that exemplary damages can be raised under the law of tort.149
a CONTRIBUTORY NEGLIGENCE
174. We understand that contributory negligence can lead to a reduction of damages for
most torts and if a situation of contributory negligence is found, it shall not defeat the claim, but
the damages recoverable shall be reduced to the extent the courts thinks just and equitable.150
175. We contend that no actions of the Claimant could have been considered contributory
in this matter and therefore this section does not apply.
176. In the alternative we contend any actions considered as contributory were of a minor
nature.
C INTEREST AS PER THE ARBITRATION ACT 1996
147 Livingstone v Raywards Coal Co. (1880) 5 App. Cas. 25 at p. 39; Shearman v Folland [1950] 2 K.B. 43 at p. 49; British Transport Commission v Gourley [1956] A.C. 185 at p. 187; Banques Bruxelles Lambert S.A. v Eagles Star Insurance Co. Ltd [1995] Q.B. 375, ay pp, 401 – 403. 148 Overseas Tankship (U.K.) v Morts Dock & Engineering Co. (The Wagon Mound) [1961] A.C. 388 149 Rookes v Barnard [1964] A.C. 1129; AB v South West Water Services Ltd [1993] Q.B. 507. 150 Law Reform (Contributory Negligence) Act 1945, s 1.
Claimant’s Memoranda Of Argument (RMIT University)
- 43 -
177. Per s49 of the Arbitration Act 1996, we contend that interest should be awarded for
damages arising out of this situation and simple or compound interest should be awarded from
the date of decision until payment, at a rate and with such rests as the Tribunal considers meets
justice.
D CONSIDERATION OF LIMITATION OF LIABILITY
178. Per s185 of the Merchant Shipping Act 1995, the Convention on Limitation of
Liability for Maritime Claims 1976 ‘Convention’151 has force in the United Kingdom.
179. Per Art 1 of the Convention, shipowners may limit their liability in accordance with
Art 2 unless it is proved the loss resulted from a personal act or omission, committed with intent
to cause loss, or done recklessly with knowledge that loss was a likely result.152
180. The vessel has a gross tonnage of 59,315153 and in applying the formula, we calculate
the limit of liability of a shipowner for personal injury is 41,987,600 SDR.154
181. We calculate the limit of liability of a shipowner for property claims as 21,993,800
SDR.155
-PRAYER FOR RELIEF-
For the reasons set out above, the Claimant requests this Tribunal to:
DECLARE that this Tribunal has jurisdiction to hear the merits of the Claimant’s claims;
FIND that the Respondent is liable for breach of contract and/or the tort of fraud;
AWARD damages to the Claimant and interest on the amounts claimed.
151 Entry into force 13 May 2004 152 Convention on Limitation of Liability for Maritime Claims 1976, Art 4 153 Moot problem, page 48 154 Convention on Limitation of Liability for Maritime Claims 1976, Art 8 155 Ibid. Note amendments to the 1996 protocol enter into force as of 8 June 2015 which therefore will not retrospectively apply to this case.