INTERREG III B CADSES Neighbourhood Programm 2000-2006 “ HERITOUR ”. Work Package 3 - Planning Activities. Clara Puech European Projects Coordinator EGNATIA EPIRUS Foundation. 16-17 September 2005 Somlóvásárhely, Hungary. WORK PACKAGE 3 - Planning Activities - PowerPoint PPT Presentation
Citation preview
Clara PuechEuropean Projects Coordinator
EGNATIA EPIRUS Foundation
INTERREG III B CADSESNeighbourhood Programm 2000-2006
“HERITOUR”
16-17 September 2005
Somlóvásárhely, Hungary
Work Package 3 - Planning Activities
WORK PACKAGE 3 - Planning Activities
WP LEADER: EGNATIA EPIRUS FOUNDATION
Coordination of Work Package 3
Extensive experience and know-how in
cultural, tourism & ITC related initiatives
Participation in local management activities
Contribution to project methodology
Evaluation of project results and
dissemination activities
WORK PACKAGE 3 - Planning Activities
OBJECTIVES
Preservation of local cultural heritage in European villages
Assessment of local cultural heritage based on transnational and regional cooperation
Elaboration of feasibility studies and marketing strategies on possible transnational thematic cultural routes
Architectural planning activities for investment proposals
Implementation of marketing tools
WORK PACKAGE 3 - Planning Activities
OVERVIEW
Task 3.1 – Assessment of the local cultural heritage
Task 3.2 – Survey and Analysis of target groups
Task 3.3 – Feasibility Study . Part 1
Task 3.4 – Feasibility Study . Part 2
Task 3.5 – Architectural Planning . Part 1
Task 3.6 – Architectural Planning . Part 2
Task 3.7 – Marketing planning
Task 3.8 – Transnational marketing plan
Task 3.9 – Architectural Planning . Part 3
WORK PACKAGE 3 - Planning Activities
Task 3.1 – Assessment of local cultural
heritage
Month of start: January 2006
Month of completion: March 2006
Duration: 3 months
Assessment of local cultural heritage
Preparation of a database of cultural heritage, for tourism planning purposes
WORK PACKAGE 3 - Planning Activities
Task 3.2 – Survey and Analysis of target
groups
Month of start: April 2006
Month of completion: July 2006
Duration: 3 months
Target groups/areas Surveys based on questionnaires
Publication of brochures in native, English and German languages
WORK PACKAGE 3 - Planning Activities
Task 3.3 – Feasibility Study . Part 1
Tourism Product Development
Month of start: July 2006
Month of completion: September 2006
Duration: 2 months
Analysis of cultural heritage protection needs and methods
Analysis of best practices for each cultural tourist route
Proposals for regional and transnational thematic routes
Analysis of attraction potential
WORK PACKAGE 3 - Planning Activities
Task 3.4 – Feasibility Study . Part 2
Operational Planning
Month of start: October 2006
Month of completion: December 2006
Duration: 2 months
Operational planning
Management methods
Financial plans
WORK PACKAGE 3 - Planning Activities
Task 3.5 – Architectural Planning . Part 1
Month of start: August 2006
Month of completion: December 2006
Duration: 4 months
Construction plans for visitor-friendly infrastructure in the New Atlantis small region, Hungary
Initial architectural plans in the Region of Epirus, Greece and Gödöllö and Vicinity Region, Hungary
WORK PACKAGE 3 - Planning Activities
Task 3.6 – Architectural Planning . Part 2
Month of start: January 2007
Month of completion: April 2007
Duration: 4 months
Construction plans in New Atlantis, Hungary
WORK PACKAGE 3 - Planning Activities
Task 3.7 – Marketing planning
Month of start: December 2006
Month of completion: February 2007
Duration: 3 months
Elaboration of marketing plans for each local projects
Preparation of a marketing budget
WORK PACKAGE 3 - Planning Activities
Task 3.8 – Transnational marketing plan
Month of start: February 2007
Month of completion: April 2007
Duration: 3 months
Elaboration of a transnational marketing plan
WORK PACKAGE 3 - Planning Activities
Task 3.9 – Architectural Planning . Part 3
Month of start: May 2007
Month of completion: August 2007
Duration: 4 months
Architectural plan for the construction of a bicycle road in the New Atlantis Region
Implementation of visitor-friendly infrastructure in Belluno Province, Italy
WORK PACKAGE 3 - Planning Activities
Task 3.1 – Assessment of local cultural
heritage
Methodology
Key Idea: Route based Approach3.1.1 Collection of Assets relevant for cultural related
tourism
Coordinator: EEF in close collaboration with P3, 2.1 WP Leader
Contributors: All Partners
Deadline: end December 2005
Objectives: Identify Cultural Assets / Tourist related attractions & activities and related source and level of information
Methodology: Based on results of 2.1
WORK PACKAGE 3 - Planning Activities
Task 3.1 – Assessment of local cultural
heritage
Methodology
Key Idea: Route based Approach3.1.2 Definition of structure and common fields
Coordinator: EEF
Contributors: All Partners
Deadline: end January 2006
Objectives: Identification/Validation of database structure & fields
Methodology: EEF proposal (based on 3.1.1)
Review by all Partners
Improvement
HYPERTOUR DatabaseChurches - Fields
3.1.3 Database Prototype
Coordinator: EEF
Contributors: All Partners
Deadline: end of February 06 (Consortium Meeting in Epirus, Greece)
Objectives: Development of Database Prototype
Methodology: Development of database (ACCESS)
Presentation to Partners at CM in February 2006
Feedback from Partners
Improvement
WORK PACKAGE 3 - Planning Activities
Task 3.1 – Assessment of local cultural
heritage
Methodology
Key Idea: Route based Approach
EPCON DatabaseHotels – Database Structure
3.1.4. Content Collection and Edition
Coordinator: EEF
Contributors: All Partners
Deadline: end of March 2006 (=deliverable)
Objectives: Data input
Methodology: Instructions regarding data edition - EEF
Collection and entry of data – All Partners
WORK PACKAGE 3 - Planning Activities
Task 3.1 – Assessment of local cultural
heritage
Methodology
Key Idea: Route based Approach
EPCON Database
WORK PACKAGE 3 - Planning Activities
Tasks 3.2 to Tasks 3.9
Methodology to be presented at the next Consortium Meeting