Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Class’ Perspective on Wind Turbine Jack-up VesselsThe International Jack-up Barge Owners Association Meeting, Dartford21st June 2011, Speaker Thomas Jahnke (GL ND)
presentation title | 2011-06-20 | No. 2
Contents
• Offshore Wind Market and Requirements• Generations of Wind Turbine Installation Vessels (examples)• Rules and Regulation—Statutory• Rules and Regulation—Structure• Jacking System• Conclusion
presentation title | 2011-06-20 | No. 3
Summary of the offshore wind energy market in the EU
• Total installed capacity of 3,000 MW
• Meeting 0.3 % of total EU electricity demand
• Avoiding almost 7 Mio tons of CO2 annually
Year 2010
• Total installed capacity of 150,000 MW
• Meeting between 13 % and 17 % of total EU electricity demand
• Avoiding almost 300 Mio tons of CO2 annually
Year 2030
presentation title | 2011-06-20 | No. 4
Offshore Windfarming development –deeper and further, Trend until 2025
North
ern E
urop
e
Southern Europe
Nor
ther
n Eu
rope
Source: EWEA.org
Current Projects
Planned Projects
presentation title | 2011-06-20 | No. 5
Increasing Turbine Sizes and Weights
300 - 500 t100 - 120m310 - 400 t6 MW~ 170 t75 - 90 m~ 185 t3.6 MW
~ 110 t75 - 90 m~ 110 t3 MW
Tower WeightHub HeightNacelle Weight (incl. Rotor)Turbine Size
2.3 MW 3.6 MW Source: Siemens Wind Power
Already the world‘s biggest rotating machines
presentation title | 2011-06-20 | No. 6
Foundations
1 2 3 4
1000 t~ 35 - 60 m~ 50 mTripod4
700 - 900 t~ 25 - 60 mup to 70 mJacket3
1000 - 1500 t~ 30 m Ø~ 20 mGravity2
600 - 700 t~ 4 - 5 m Ø~ 35 mMonopile1
Typical Weight Typical Size Typical Waterdepth
Type
presentation title | 2011-06-20 | No. 7
Generation I Combined crane and working barges
Generation II Jackup barges without propulsion
Generation III Self-propelled Jackup vessels
WTIV Generation I to III
presentation title | 2011-06-20 | No. 8
Design Concepts WTIV - Generation I
presentation title | 2011-06-20 | No. 9
Design Concepts WTIV - Generation II
Source: hochtief- construction.de
Jackup Barge THOR, GL• Self-Elevating • Non-self-propelled• Crane 500t• Waterdepth <=40m• 70 x 40m• Upgrade plans exist (self-propelled)
GL-Deliverables• Analysis and Verification• Newbuilding Classification• Plan Approval & Newbuilding Supervision• Fleet in Service
presentation title | 2011-06-20 | No. 10
Design Concepts WTIV - Generation III
RWEInnogy-WTIV, GL• Self-Elevating (<45m water depth)• Self-Propelled• Crane 800t• DP2 Capability• 100 x 40m
GL-Deliverables• Analysis and Verification• Newbuilding Classification• Plan Approval• Newbuilding Supervision
Source: RWE Innogy
presentation title | 2011-06-20 | No. 11
Design Concepts WTIV - Generation IIIBeluga Hochtief Offshore TIS, GL• Self-Elevating (<50m water depth)• Self-Propelled• Crane <= 1500t• DP2 Capability• 135 x 43 m
GL-Deliverables• Analysis and Verification• Newbuilding Classification• Plan Approval• Newbuilding Supervision
Source: beluga-hochtief-offshore.com
presentation title | 2011-06-20 | No. 12
Design Concepts WTIV - Generation III
Source: Swire Blue Ocean
Swire Blue Ocean WTIV, GL•Self-Elevating (<60m water depth)•Self-Propelled•Crane <= 1200t @ 31m•DP2 Capability, 13 knots•155 x 49 m
GL-Deliverables•Analysis and Verification•Newbuilding Classification•Plan Approval•Newbuilding Supervision
presentation title | 2011-06-20 | No. 13
Challenges in design ofWind Turbine Installation Vessels (WTIV)
Basic Factorswind turbine sizewater depthdistance from shoreoptimization of given weather
window
Questions to be answeredself propelled / no propulsion / fuel type?jacking / non jacking?large deck area for working?sailing speed size of crane and lifting appliances?Accommodation?Dynamic Positioning?
what is the best design to meet the requirements best?
presentation title | 2011-06-20 | No. 14
Rules and Regulations – A Class Challenge
• Is it a ship?• Is it a jackup?• Is it a heavy lifter?• Is it a passenger vessel?
presentation title | 2011-06-20 | No. 15
Rules and Regulations—Statutory
• SOLAS 74/88, International Convention for Safety of Life at Sea 2009• ILLC 66/88, International Convention for Load Lines; Revision 2004• MARPOL 73/78, International Convention for the Prevention of Pollution from
Ships, Annex I – IV• IS Code 2008, International Code on Intact Stability• Guidelines for the Construction and Design of Offshore Supply Vessels 2006• Code of Safety for Special Purpose Ships, 2008• Code for the Construction and Equipment of Mobile Offshore Drilling Units,
1989 amendment by Res. MSC.187(79) 2004• Ballast Water Management Convention, 2004
presentation title | 2011-06-20 | No. 16
In-between the rules• MODU Code in jacked position vs.
SPS Code in floating condition• Mining Authorities vs.
Coastal Flag State Authorities• Intact Stability Code / Weather criterion• SPS Code 2008 / Safe return to port requirements
GL activities• Roadmap through regulation – jungle• Active member in IMO working groups• Proactive partner with close contact to Flag State Administrations
presentation title | 2011-06-20 | No. 17
Rules and Regulations - Two sets for Classification
• GL Rules for Classification and Construction, Ship Technology, Seagoing Ships
• GL Rules for Classification and Construction, Ship Technology, Offshore Service Vesselsincluding class notation WTIS for Wind Turbine Installation Vessels
• GL Rules for Classification and Construction, Industrial Services, Offshore Technology
• GL has established Rules for Mobile Offshore Units
presentation title | 2011-06-20 | No. 18
Rules and Regulations - Two sets for Classification
• The term Offshore Engineering part considers the following components:Legs, Leg Wells, Jacking unit incl. gears, guides, rack chocks (if applicable), steel categorization.
• In addition, the global strength of the vessel for the elevated condition needs to be analyzed. Overturning stability, pre-load capacity and fatigue requirements are to be covered by the Offshore Engineering Part.
presentation title | 2011-06-20 | No. 19
Rules and Regulations—Structure
It would not be considered to install wind turbines in areas with high probability for low wind speeds.
presentation title | 2011-06-20 | No. 20
Significant wave heightsLimits for Lifting of Jack-up
Time Window for Lifting with Design Wave:Hs=1.0m -> 38% of the year possibleHs=1.5m -> 59% of the year possibleHs=2.0m -> 77% of the year possible
presentation title | 2011-06-20 | No. 21
Independent Dynamic Global Structural Analysis (Survival & Operating Loading Condition)
Check of • Overturning Stability• Leg Strength• Jacking Capacity • Structure around Leg Well
Results:• Tubular Legs with Pin/Hole Jacking System: Leg Strength is governing• Lattice Legs with Rack/Pinion Jacking System: Jacking Capacity is governing
presentation title | 2011-06-20 | No. 22
Jacking SystemRack/Pinion System:• Number of jacking cycles are much higher compared to Drill Units Fatigue• High loads arise also during operation condition (crane operation)• Use of rack chock system is not always planed• Additional crane load not considered (Crane around Leg Design)
Pin/Hole System:• Bearing pressure in hole requires high strength steel quality (>500 MPa), large pipewall thickness (t>80mm) as well as large pin diameter
presentation title | 2011-06-20 | No. 23
Conclusion1. The offshore wind market is a new market and experience is missing:
- Ship designer are starting with Jack-up designs- Yards are building the first Jack-up- Ship operators are entering the offshore wind market
2. Need for a suitable IMO regulation (MODU, SPS, Stability)3. Thoroughly planning of a newbuilding WTIV according to the market needs4. Owner/designer should contact as early as possible the flag state for their special
requirements for a newbuilding WTIVs (MODU/SPS-Code)5. Control of Wear at Jacking System (especially Rack/Pinion)6. Current WTIVs Jacking Systems with Crane around Leg Design does not consider
increased leg load at crane leg
GL Contacts:
GL-Hamburg Tel: +49 40 36149-ExtEmail: [email protected]
Thomas Jahnke (Speaker, Struc. Engineer Offshore Installations)Ext: 106
Ulrich Hachmann (Head of Department Offshore Installations)Ext: 267 (structural matters)
Rasmus Stute (Head of Department Offshore Service Vessels)Ext: 7419 (class matters)
Christoph Witte (Head of Department Project Management)Ext: 7534 (statutory matters)