Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore. STRAWMAN Presented FERC Little Rock technical conference. White Paper DRAFT ATTACHMENT K Presented FERC Atlanta technical conference. Solicited additional feedback prior to summit. - PowerPoint PPT Presentation

Citation preview

Page 1: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

Cleco Transmission Planning SummitAttachment K

November 15, 2007Terry Whitmore

Page 2: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K OVERVIEW

• STRAWMAN– Presented FERC Little Rock technical conference. – White Paper

• DRAFT ATTACHMENT K– Presented FERC Atlanta technical conference. – Solicited additional feedback prior to summit.

Page 3: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

Cleco Power Annual Transmission Planning Process

Capital Projects for Years 2 – 5 and

New/Revised

August

Cleco performs Reliability Assessment

March

Simulate AdditionalStudies

April - July

OASIS PostingPreliminary

Results

July

September - October

CustomersData Submittal

Request Economic Studies

December

July

OASIS PostingFinal Results

July

Stakeholder Summit(Present Results)

April

Stakeholder SummitReliability/ Economic

OASIS POSTING

April

September - February

SPP Model Development

Process (Years 1-10)

Page 4: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Definitions

• Base Case Model

• Critical Energy Infrastructure Information (CEII)

• Confidential Information

• Planning Criteria

• Construction Plan

Page 5: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Definition Comments

• Comment - Confidential Information– Definition too broad

• Cleco Response– Cleco disagrees. Consistent with FERC’s model of

Protective Order & confidentiality provisions of OATT.

• Comment - Construction Plan– What is construction plan limited to 5 years

• Cleco Response– Five year time frame came from Cleco’s budgeting dept.

Cleco agrees that a plan should exist to include proposed projects up to 10 years.

Page 6: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Definition Comments

• Comment -Base Case Model – Specify time period

– Indicate changes & discrepancies in SPP & SERC models

– Stakeholders should have input into SPP & SERC

• Cleco Response– MMWG set model time frame

– Cleco submits data for Cleco’s CA

– Data same for Cleco in both SPP & SERC

– Stakeholders need to participate through SPP & SERC process not Cleco.

Page 7: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Planning Process

• Model Development including input by stakeholders.

• 10 year plan (Construction Plan 1-5, Proposed Plan 6 - 10).

• Coordinated regional planning with adjacent transmission owners.

Page 8: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Planning Process Comments

• Comment - Input into planning criteria.– Cleco response. Planning criteria is industry

accepted.

• Comment - Coordinated regional planning with adjacent transmission owners.– Cleco response. Agree. Only adjacent systems are

monitored. Change Attach K to transmission owners.

Page 9: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Coordination

• Stakeholders may request formation of committee.

• Open & welcome input from stakeholders.

• Post calendar of events on OASIS as well as email exploder to keep stakeholders up to date on planning process as well as allow comments and input.

• Affected systems

Page 10: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Coordination Comments

• Comment - Summit is to inform stakeholders rather than solicit input & no follow up.

• Cleco Response - Section 5.1 clearly states stakeholders may comment and provide input. Flow chart shows posting pre & post summit.

• Comment – Company & affiliates can’t hold more than one seat on stakeholder committee

• Cleco Response – Cleco agrees and language will be changed.

Page 11: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Coordination Comments

• Comment – Stakeholder may request any issue related to transmission planning be considered by committee.

• Cleco Response – Cleco agrees and language will be changed.

Page 12: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Openness

• Willing to share all information, but must protect confidential information including CEII.

• Require requester to sign confidentiality agreement.

Page 13: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Openness Comments

• Comment – Signing a confidentiality agreement is too excessive.

• Cleco Response – consistent with OATT and we are referring ONLY to confidential information. Non confidential information does not apply.

Page 14: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Transparency

• Cleco will allow stakeholder to request base case power flow models, planning criteria, as well as assumptions for verification and validation of studies provided appropriate confidentiality agreements are in place.

• Post construction plan on OASIS.

Page 15: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Transparency Comments

• Comment - Stakeholder should be allowed to download information directly rather than make a request.

• Cleco response – White paper does not specify downloading, only process to obtain information. Cleco is evaluating technical options including eRoom or FTP server

Page 16: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Information Exchange

• Firm PTP reservations will be modeled during active timeframe of TSR, unless it qualifies for rollover rights (5 years or more).

• Network customers (native load & non-native load) submit a 10 year load forecast & DNR’s.

Page 17: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Comparability

• All stakeholders are treated comparably whether network, Point to Point, or pre 888.

• Models and supporting data are available for replication & duplication of results.

Page 18: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Dispute Resolution

• Any party may dispute planning process by providing written notice of such dispute.

1. Representatives of each party shall negotiate to resolve dispute within 10 business days

2. Executive management of each party (30 days)

3. Hire an external mutually agreed upon mediator

4. File section 206 complaint with commission

Page 19: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Dispute Resolution Comments

• Comment – Should not apply to pre 888 agreements.

• Cleco response – Agree, it is an OATT attachment.

• Comment – Who is independent regional planning authority?

• Cleco response – SPP

Page 20: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Regional Participation

• Cleco participates in SPP & SERC (Entergy) model development processes.

• Coordinate with affected systems

• Joint planning meetings w/ Entergy (SERC) & SPP.

• Voting member of SPP TWG.

Page 21: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Economic Planning Studies

• Separate queue on OASIS for TSR & generator interconnection.

• Study annually three (3) highest priorities as established by stakeholders (previously 1)

Page 22: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Economic Planning Studies Comments

• Comment – May be impracticable to submit data at time of economic study request.

• Cleco response – Disagree. Execute study, scope & details must be included.

• Comment – Confidentially of data.

• Cleco response – Agree. Language will be added for confidential information.

Page 23: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Economic Planning Studies Comments

• Comment – Cost of studies above 3 will be assigned to requesting parties.

• Cleco response – Agree. Language will be modified.• Comment – Requesting parties be billed as study

cost are incurred rather than prepayment.• Cleco response – Draft language to be consistent with

OATT for study cost payments.

Page 24: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Cost Allocation

• Reliability Upgrades – LPSC rate base for planning criteria violations.

• Economic Upgrades– Cost allocated to beneficiary.

Page 25: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Cost Allocation Comments

• Comment – Stakeholders should have input into Planning criteria.

• Cleco response – Cleco’s planning criteria is in accordance with NERC reliability standards & SPP criteria.

• Comment – Clarity is needed is defining an economic study.

• Cleco response – Disagree. Clearly stated that if Cleco’s planning criteria is not violated which is reliability, then it is an economic upgrade.

Page 26: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Recovery of Planning Cost

• Cleco will recover cost for three economic studies annually through existing rate structure.

• Requestor will pay for any additional studies.

Page 27: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

FERC Order 890 Attachment K Recovery of Planning Cost Comments

• Comment – Parties should not be exposed to TP’s cost exceeding estimate.

• Cleco’s response – Disagree. OATT requires TC’s to pay for studies.

Page 28: Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore

Questions