Upload
foster
View
61
Download
0
Tags:
Embed Size (px)
DESCRIPTION
CLIC DB injector front end update on the work package. Description of the work package Drive Beam Klystron status Overview of the ongoing work Collaborations Outlook, planning. CLIC DB injector front end update on the work package. - PowerPoint PPT Presentation
Citation preview
CLIC DB injector front end update on the work
package
Steffen Döbert, BE-RF
Description of the work package
Drive Beam Klystron status
Overview of the ongoing work
Collaborations
Outlook, planning
CLIC DB injector front end update on the work
package
Steffen Döbert, BE-RF
Original: Work package in EV, ‘CLIC0 Drive Beam’, with the
goal to built a full injector up to 12 MeV for integrated beam
tests until 2017
Reduced scope: ‘CLIC Drive Beam injector R&D’ with the
goal to do key hardware development and independent tests
to enable the construction of an injector after 2017
CLIC DB front end
Gun, sub-harmonic bunching, bunching, three accelerating structures,5 long pulse klystrons and modulators, diagnostics, beam line
Gun SHB 1-2-3
PB Buncher Acc. Structures
IOTs ?, 500 MHz
Modulator-klystrons, 1 GHz, 15 MW
~ 140 keV ~ 12 MeV
Diagnostics
~ 3 MeV
CLIC DB front endHardware R&D
Reduced scope: Gun, sub-harmonic buncher, rf-unit, diagnostics, injector design
Gun
SHB 1Acc. Structures
500 MHz
Modulator-klystron, 1 GHz, 20 MW
~ 140 keV Diagnostics
What is part of the work package ?
Development and validation of an rf unit for the CLIC DB (Modulator, Klystron, Accelerating-Structure, test stand)
Design of the injector, mainly beam dynamics, SHB design +prototype, beam diagnostics design + prototypes
Design, prototype and test of a electron source suitable for the DB injector, gun test area, diagnostics
Contributions from different CLIC activities, collaborations and CERN groups
10 MW L-band klystrons for ILC
In terms of achieved RF efficiency, the klystrons with RF circuit adopted by Toshiba and CPI provides values very close to the 70%, as is specified in CLIC CDR (67.8% for CPI and 68.8% for Toshiba. These values validate the feasibility of a slightly higher efficiency with minimised design/fabrication efforts, when scaled in frequency down to 1.0 GHz.
Igor Syratchev
20 MW L-band klystron for CLICGun topology scaling scenarios
Our study of scaling the existing technology shows reasonable evidence that 6 beam MBK with 20 MW peak RF power might be the best compromise for the CLIC-type L-band klystron, providing high (>70%) efficiency, long (>150 000 hours) life time and operated at a reasonable (164 kV) cathode voltage. This choice also may be the most cost efficient.
Tentative klystron parameters
PARAMETER VALUE UNITSRF FrequencyBandwidth at -1dBRF Power:Peak PowerAverage PowerRF Pulse width (at -3dB)HV pulse width (at full width half height)Repetition RateHigh Voltage applied to the cathodeTolerable peak reverse voltageEfficiency at peak powerRF gain at peak powerPerveanceStability of RF output signal at nominal working pointRF phase ripple [*]RF amplitude ripplePulse failures (arcs etc.) during 14 hour continuous test periodMatching load, fundamental and 2nd harmonicAverage radiation at 0.1m distance from klystronOutput waveguide type,
999.516≥ 1 ≥ 2015015016550tbd, ≤ 180 tbd65 ≥ 67 ≤ 70tbd, > 48tbd ±1 (max)±1 (max)< 1-2tbd< 1WR975 pressurised
MHzMHz MWkWμsμsHzkVkV%dBμA/V1.5
RF deg% VSWRμSv/h2-3 bar
Status: Preparation of call for tender
Klystron Modulator and test stand
Status: see presentation from D. Aguglia
1 GHz test stand (needed in 2015): Aim to share high power test stands in the rf group, possible candidate sides (~50 m2 needed): Bldg. 112 (LHC), 150 (CLIC), 152 (Linac4)
• Create a 1 GHz test stand together with TE-EPC to test the two prototype modulators and klystrons into loads
• Establish HV and rf- measurements to study and demonstrate stability of the DB rf-system
• Use facility to test DB accelerating structure and components with high power under nominal parameters
Sub-harmonic bunching system
Status: RF design existing, mechanical design advanced,Next: launch prototype (in aluminum ?)
Power source: 500 MHz, 34-82 kW, wide band (60 MHz) sources needed for fast phase switching. Started to discuss with industry.
Hamed Shaker, see IPAC paper
DB injector review and optimization
Shahin Sanaye Hajari, see as well IPAC paper
Final phase space at 50 MeV after re-optimization of the injector with realistic rf parameters, 4% satellites, good longitudinal phase
space
DB injector review and optimization
Total losses reduced from 30% to 11%
Shahin Sanaye Hajari, see as well IPAC paper
Gun Test FacilityGun test area:former GTF available, Bldg. 162-R-004/008, needs some refurbishment
Gun simulationsUsing EGUN
-5 -4 -3 -2 -1 0 1 2 3 4 5-15
-10
-5
0
5
10
15
R [mm]
Ang
le [m
rad]
e ~ 12 mm mrad
Gun simulationsEmittance vs voltage
100 120 140 160 180 20010
15
20
25
gun voltage [kV]
rms
emitt
ance
[mm
mra
d]
3 4 5 6 7 8 9 10 11 12 13 1410
15
20
25
30
35
40
45
50
55
60
gun current [A]
rms
emitt
ance
[mm
mra
d]
16Centre d’études scientifiques et techniques d’Aquitaine (CESTA)29/01/2013
Ez
Er
B
Ez
Er
B
Typical MAGIC snapshot: particle positions in r-z
Typical MAGIC snapshot: kinetic energy of particles along z
Contour plots of field components at t=35nsJacques Gardelle
1-2/2013 3-4/2013 1-2/2014 3-4/2014
SLAC design study based on YU156
SLAC mechanical design with YU156
Fabrication Test
Concept for GTF Prepare local and purchase equipment
HV-test for PS ready install equipment
Gun test
Design GUN CERN-CESTA based on YU796 and YU156 modular ?
Mechanical design based on YU796
Fabrication Test
Modulator design CESTA
Prototype Prototype at CERN
Concepts for HV deck electronics
Design of pulser electronics
Fabrication and tests
Ready for use
DB-Gun strategy and planning
Beam diagnosticsGas Jet Monitor
• Fire a supersonic gas jet across the beam pipe• Jet can be arranged as a ‘screen’ at 45 to beam• Most gas collected in a receiving chamber
• Advantages over residual gas monitor:– Cross-section, not separate profiles– Localised higher pressure -> faster profile measurement– Reduce vacuum contamination & losses
• Two limits to resolution: – Beam Space Charge -> Need strong B and E field for extraction– Gas Jet Thickness -> Possible matter-wave focusing with Zone Plate
• Test Stand at Cockcroft Institute, U.K.
Beam
Jet generation
Pumping Pumping Pumping
Collection chamber
Gas source
Shaping
Adam’s Summary Profile measurement for the CLIC drive beam
poses challenges due to very high intensity: Interceptive monitors would be
destroyed Strong space charge effect makes
ionisation monitors tricky to implement.
Care needed to avoid wakefields A number of options are being explored A varied ‘toolkit’ of solutions will probably
needed to cover the full DB energy range
Collaborations(existing or under discussion)
CEA-CESTA: Gun and injector design, HV-modulator for the gun
IPM: Injector and SHB design NCNR: DB accelerating structure and DB beam
dynamics IFIC: DB diagnostics, BPM and profile monitor SLAC: gun design
Modulator: see Davide’s presentation Klystron: collaboration with industry
Outlook,Rough planning, milestones
Task 2013 2014 2015 2016
Gun test areaprepare gun test area
ready for first tests
testing with HV modulator testing
Gun design Prototype, first tests gun tests
SHB Buncher fabricationtesting low power testing high power
500 MHz power source specifications purchase needed for test
1 GHz structurespecs, mech. design construction low power test
high power test
Diagnostis design design tests in gun area ?
LLRF specs fabrication+testready for klystron test
1 GHz klystrons tender, contract Design reviewReceive first prototype Klystron 2
1 GHz Modulator R&D R&D Receive first MDK MDK2
1 GHz rf test stand specs, location prepareReceive MDK, klystron
Ready for testing
RF stability Measure CTF3, DESY? Measure SLAC ?
END
CLIC DB injector specifications
Parameter Nominal value UnitBeam Energy 50 MeV
Pulse Length 140.3 / 243.7 ms / ns
Beam current 4.2 A
Bunch charge 8.4 nC
Number of bunches 70128
Total charge per pulse 590 mC
Bunch spacing 1.992 ns
Emittance at 50 MeV 100 mm mrad
Repetition rate 100 Hz
Energy spread at 50 MeV 1 % FWHM
Bunch length at 50 MeV 3 mm rms
Charge variation shot to shot 0.1 %
Charge flatness on flat top 0.1 %
Allowed satellite charge < 7 %
Allowed switching time 5 ns
Task description
Task What is planned Who is involvedKlystron Tender, Purchase, Follow up,
receptionEV, BE-RF; Steffen, Igor, Gerry
Modulator Develop, follow up, reception, test TD, TE-EPC; David + Collaborations
Test stand, LLRF, WG-system
Prepare test area to test klystron with modulator into load and structure, enable measurements
EV, BE-RF; Steffen, Nuria, Gerry, LucaTD, TE-EPC; David
RF,HV stability
Measure existing systems to check specifications and possible solutions
EV, BE-RF, TE-EPC, BE-ABP
Acc-structure RF-design, Mechanical design, built prototype, test
XB, BE-RF, Collaboration,NCNR Poland ?
Task description
Task What is planned Who is involvedInjector design
Beam dynamics design and optimization of the full injector
EV/BP, BE-ABP; Shahin, Avni, CEA-CESTA
SHB SHB design, built and test prototype, 500 MHz power source
EV, BE-RF; Hamed, MME
Diagnostics Study BPM and profile monitor for DB, prototype ?
TD, BE-BI, Thibaut, Adam, Alfonso
Electron source
Design, prototypes, test EV, BE-RF + CollaborationsSLAC, CEA-CESTA, Steffen, Mohsen, MME
Gun test area
Revive LIL-GTF to allow gun testing, HV-power supply
EV, BE-RF, Steffen, Stephane, Lukas, Alexandra, CEA-CESTA (HV-PS)
Space
Gun test area:former GTF available, Bldg. 162-R-004/008, needs some refurbishment
1 GHz test stand: Aim to share high power test stands in the rf group, possible candidate sides (~50 m2 needed):
Bldg. 112 (LHC), 150 (CLIC), 152 (Linac4)
Gun geometryaim for modular design
Typical example
DB-accelerator structure
Input and output coupler design finishedCorrect match, input reflection < 30 dB.(red and green: two different geometries; red is final)
RF-design existing, next steps: mechanical design and prototypeCollaboration with National Center for Nuclear Research in Poland to built a prototype under preparation
Rolf Wegener