20
Click to edit Master title style Edit Master text styles Second level - Third level o Fourth level Fifth level AGDC Interim President’s Report Joe Dubler January 9, 2020

Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Click to edit Master title style

• Edit Master text styles Second level

- Third leveloFourth levelFifth level

AGDC Interim President’s ReportJoe DublerJanuary 9, 2020

Page 2: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Click to edit Master title style

• Edit Master text styles Second level

- Third leveloFourth levelFifth level

• Continue to represent State of Alaska in AKLNG:Work with BP/ExxonMobil going well

On time/approximately 50% under budget

• BP sale to Hilcorp Have begun meeting with Hilcorp to gauge interest in AKLNG

• FY 21 Budget proposal submitted by the Governor: $3,431,600 operating expenditures for AGDC; $97,400 operating expenditures for DEC; $521,700 operating expenditures for DNR; and $20 million in statutory designated program receipts for AGDC.

With the ability to receive funds from third parties, staff is comfortable that the requested appropriation will be sufficient to continue work at an appropriate level in FY21.

2

AGDC Fourth Quarter Review

Page 3: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Click to edit Master title style

• Edit Master text styles Second level

- Third leveloFourth levelFifth level

• Met with Mat-Su Borough Manager John Moosey about their objections to AKLNG expressed in multiple filings with FERC

• Attended RDC conference:Darlene Gates (XOM), in her presentation to the conference,

discussed Exxon’s desire to monetize ANS gasQilak LNG presented their project concept

3

AGDC Fourth Quarter Review (continued)

Page 4: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Click to edit Master title style

• Edit Master text styles Second level

- Third leveloFourth levelFifth level

Upcoming Activities

• Continue work on regulatory effort• Ongoing work with BP & ExxonMobil:Cost reduction workVenture structure work

• Continue soliciting partners for participation in FEEDSignificant work has been done over the past several years

and several of those relationships are expected to continue, most likely subject to confidentiality agreementsWith sufficient financial interest from third parties, AKLNG

will be in a position to begin and complete FEED within the next two to three years

4

Page 5: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Click to edit Master title style

• Edit Master text styles Second level

- Third leveloFourth levelFifth level

5

Financial SummaryALASKA GASLINE DEVELOPMENT CORPORATIONFiscal Year to Date Statement of Activitives(in thousands of dollars)as of November 30, 2019 Unaudited

YTD Costs YTD CostsLNG Project Expenditures 2,360 Core Staff 810

Asset Mgmt 1AGDC General & Admin Function 2,813 FERC Labor 18

Total 5,173 FERC Engr 1,029FERC EIS 439FERC Legal 2FERC RSA 14FERC BLM 48

2,360

General and Administrative by Department / Function

YTD Costs YTD CostsExecutive 700 Personnel 1,647Commercial 458 Travel 8External Affairs 173 Services 463Legal 83 RSA Services 6Finance 376 Services - Mgmt Consulting 629Administrative Services 609 Commodities 39Data Management 414 Depreciation 21

Total 2,813 Total 2,813

G&

A by Department

G&

A by Function

Total Expenditures

AKLNG

Expenditures

Page 6: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Click to edit Master title style

• Edit Master text styles Second level

- Third leveloFourth levelFifth level

6

Financial Summary AFE

ALASKA GASLINE DEVELOPMENT CORPORATIONFiscal Year to Date Statement of Activitivesas of November 30, 2019 Unaudited

AFE - Program Management6201 809,710 6203 - 6204 - 6205 850 6206 - 6207 - 6208 17,655 6209 13,783 6210 48,024 6211 1,029,384 6212 438,717 6213 1,563

Subtotal 2,359,684

Total AFE 2,359,684 Total Other 2,812,456Total 5,172,140

Page 7: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Click to edit Master title style

• Edit Master text styles Second level

- Third leveloFourth levelFifth level

Page 8: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Alaska LNG Project Technical and Regulatory Update

Frank Richards, Senior Vice President of Program ManagementJanuary 9, 2020

Page 9: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Milestone Date

FERC Public Comment Meetings September 9 - 12, 2019

BLM Public Subsistence Hearings September 17 & 19, 2019

AGDC Post-Public Meeting Update Meeting September 17, 2019

Draft EIS Comments Due to FERC by 5:00 PM EST October 3, 2019

FERC Milestones Achieved:

Milestone Date

Publication of Notice of Availability of Final EIS March 6, 2020

Issuance of Final FERC Order June 4, 2020

Future FERC Milestones:

2

FERC Schedule & Milestones

Page 10: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

FERC Work Program Status

• FERC Data Request #9 (Engineering) completed November 27, 2019 (92 requests)

• FERC Data Request #10 (Environmental) received November 22, 2019 included 56 requests with a 10 day response request

• FERC Data Request #11 (Engineering) received November 22, 2019 included 9 requests with a 20 day response request

• AGDC completed and submitted 65 responses for 100% completion of DR#10 and DR#11 by December 23, 2019

• FERC Staff issued a total of 1,895 data requests (both environmental and engineering) since July 2017

3

Page 11: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

FERC Work Program Dashboard

4

Page 12: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Permit Agency Status Note

Letter of Recommendation USCG Issued Complete

Natural Gas Export DOE Issued Complete

Essential Fish Habitat Consultation NOAA Issued Complete

Strain-Based Design PHMSA Issued Complete

Crack Arrestor Spacing PHMSA Issued Complete

Mainline Block Valve Spacing PHMSA Issued Complete

Three Layer Polyethylene Coating PHMSA Issued Complete

Major Permit Status – Complete

5

Page 13: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Other Permit Status

• ROW lease application through Denali National Park & Preserve (DNPP) advancing with National Park Service (NPS) NPS provided comments December 23, 2019 Meeting held January 7, 2020 to discuss comments Coordinating NPS wetland comments with Corps permitting effort

• ROW lease applications submitted to Department of Natural Resources (DNR) for Point Thomson Transmission Line (PTTL) on October 25, 2019 and GTP, Mainline Pipeline, & Liquefaction Facilities on October 31, 2019 60 day public notice period ending January 14, 2020 Providing responses to DNR questions on application, Cook Inlet crossing, and

storage tanks at the liquefaction facility • PHMSA issued public notice of their assessment and draft conditions

for the for Pipe-in-Pipe Special Permit in the Federal Register December 10, 2019 60 day public comment period ending February 10, 2020

6

Page 14: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Permit Agency Status Note

Prevention of Significant Deterioration - Air Permit - GTP ADEC In Process Public comment closed; AGDC responding to

RFI by Jan 8; anticipated Q1 2020

Pipe-in-Pipe PHMSA In Process Public notice period; anticipated Q2 2020

Siting Review Letter of Determination PHMSA In Process Due 30 days prior to FERC FEIS; anticipated Q1

2020

Right-of-Way - State ADNR In Process Public notice period; anticipated Q3 2020

Section 106 Review FERC In Process

Misc. cooperating agencies; Programmatic Agreement anticipated Q1 2020; AGDC outreach meetings underway as agreed with SHPO, BLM, NPS

LNG Terminal/EIS FERC In Process DEIS complete; FEIS anticipated March 6, 2020

Right-of-Way – Federal BLM In Process Application submitted; anticipated June 2020

Major Permit Status – In Process

7

Page 15: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Permit Agency Status Note

MMPA Incidental Take (Whale) NMFS In Process

Cook Inlet: Published in Federal Register; active ongoing negotiations regarding mitigation. Prudhoe Bay: Anticipated Q2 2020

MMPA Incidental Take USFWS In Process Sea Otter: Published in Federal Register; Polar Bear anticipated Q2 2020

Endangered Species Act Consultation NOAA In Process Package deemed complete; anticipated Q2 2020

Endangered Species Act USFWS In Process Consultation request received; anticipated Q2 2020

Bridge Permits for original route USCG In Process Public notice complete; anticipated Q3 2020

Right-of-Way - DNPP NPS In Process Application submitted; anticipated June 2020

Section 404 Wetlands USACE In Process Public comment period; anticipated Q3 2020

Section 401 Water Quality EPA & ADEC In Process Application in progress

Major Permit Status – In Process

8

Page 16: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Permit Agency Status Note

Bald & Golden Eagle Protection Act USFWS AGDC

Action Application developed; submittal Q1 2020

Prevention of Significant Deterioration – Air Permit –LNG Facility

ADEC AGDC Action

Application developed; public comment period anticipated Q1 2020

Major Permit Status – AGDC Action

9

Page 17: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Cost Reduction Work Program Status

• Contracted with Fluor Corporation to evaluate cost reduction opportunities and update the Class 4 Cost Estimate to Q4 $2019

• Scope of work includes 10 major tasks• Updated Class 4 Cost Estimate will be provided as input into

common economic model• Objective is to provide decision support package if the Project is

commercially and technically viable

10

Page 18: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Capital Costs:• Task 1 A - Emerging Markets - Best Country Sourcing & Material Pricing

Update, & Q4 2019 Escalation

• Task 1 B - Emerging Markets - Use of High Value Engineering Center’s • Task 2 - Technology - Use of High Efficiency Fin Fans • Task 3 A - Market - Source line pipe as 80-foot spiral-welded steel pipe

produced in USA • Task 3 B - Market - Optimize Project Management Team• Task 3 C - Market - Optimize Contracting Strategy • Task 4 - Modularization - Optimize LNG Plant Modularization

11

Cost Reduction Tasks

Page 19: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

Capital Cost (cont.):• Task 5 A - Secondary - Reduce Nikiski Camp Size and related support costs

• Task 5 B - Secondary - Adjust Contingency to Q4 2015 Estimate Percentages • Task 6 - AGDC Items - Reduce Prepare for FEED and FEED (ERL) cost estimate

to account for AGDC major permitting earned value• Task 7 - Partnering - Eliminate on Site Power Generation at LNG Plant

Operating Costs• Task 8 - Opex Impact

Other• Task 9 - Additional Reduction Opportunities Identified by Fluor• Task 10 - Class 4 Cost Estimate Update

12

Cost Reduction Tasks

Page 20: Click to edit Master title styleagdc.us/wp-content/uploads/2020/01/Jan2020-Board... · 1/1/2020  · Click to edit Master title style • Edit Master text styles Second level - Third

AGDC.us