Clinton Street Bridge over the Maumee River ODOT Project DEF-15-14.77 April 1, 2015 Stakeholder’s Meeting

Clinton Street Bridge over the Maumee River ODOT Project DEF-15-14.77 April 1, 2015 Stakeholder’s Meeting

Embed Size (px)

Citation preview

Clinton Street Bridge over the Maumee River

ODOT Project DEF-15-14.77April 1, 2015

Stakeholder’s Meeting

Review the project and why it’s happening Share the results of the Feasibility Study Identify stakeholder concerns Obtain stakeholder input

Purpose of Stakeholder Meeting

Address deteriorated condition of existing bridge

Improve pedestrian and bicycle accommodations City of Defiance Strategic Plan

Improve Americans with Disabilities Act (ADA) access to the bridge

Improve vertical sight distance at Fort Street

Project Purpose

Deteriorated condition of existing bridge

Deteriorated condition of existing bridge

Improve Pedestrian and Bicycle Accommodations

Improve Americans with Disabilities Act (ADA) access to the bridge

Improve vertical sight distance at Fort Street

Possible congestion issues Accident history Southbound left turn from Clinton Street to

River Road (City of Defiance request) Rear-end accidents at south end of bridge

Investigate…

Congestion Area?

Congestion Area?

Congestion Area?

Southbound Left Turn at River Drive

Cause of Accidents?

Includes the bridge and the next two intersections north and south of bridge

Engineering and environmental studies are performed within the study area

Larger than the actual project work limits Why? Actual project work limits have not yet

been determined.

Study Area

Study Area(Yellow Outline)

Underground storage tanks (current and former) Pontiac and Fort Defiance Parks Maumee River and mussels Several structures over 50 years old (none eligible

for the National Register of Historic Places) One archaeological site (southwest corner;

destroyed according to State Historic Preservation Office)

Concerns?

Environmental Concerns on the Project

Alternatives are first studied Feasible Alternatives are then determined A Preferred Alternative is then identified Draft Feasibility Study was submitted to

ODOT in December 2014 Revised Draft version available at this

meeting and on District 1 website

Alternatives Evaluation

New four-lane bridge on existing piers (similar to existing bridge)

New five-lane bridge on existing piers Allows southbound left turn from Clinton Street

to River Drive. New four (or five) - lane bridge on new piers

DEF-15-14.77 Study Alternatives

Roundabout at Clinton Street and River Drive Flatter horizontal curve at south end of

bridge Neither a true feasible alternative

Also studied….

Reusing the existing piers as part of the new bridge was studied.

Concrete chloride contamination and the potential for active corrosion of reinforcing steel are estimated.

Piers can be reused, but… Repair might last 20 years (or less) Future repair likely

Conclusion: Reusing existing piers is not feasible.

Re-Use of Existing Piers

Goal: 75 year design life for new bridge construction

Wider sidewalks than the existing bridge Dedicated bike lanes (5 feet wide) adjacent

to each sidewalk ADA compliant crossings off bridge Improves vertical sight distance at Fort

Street

Feasible Alternative 1Entirely New Four-Lane Bridge

Feasible Alternative 1 - Entirely New Four-Lane Bridge

Feasible Alternative 1 - Entirely New Four-Lane Bridge

Feasible Alternative 1 Actual appearance

(including lighting) to be determined later in design

process

Same 75 year design life goal Same sidewalk, bike lanes, vertical sight

distance improvement as Feasible Alternative 1

Difference: Wider bridge to accommodate new lane north of bridge to allow southbound left turn at River Drive

Feasible Alternative 2Entirely New Five-Lane Bridge

Feasible Alternative 2 - Entirely New Five-Lane Bridge

Feasible Alternative 2 - Entirely New Five-Lane Bridge

Feasible Alternative 2 Actual appearance

(including lighting) to be determined later in design

process

Construction cost Traffic safety Environmental impacts Adjacent property impacts (public and

private) Utility impacts (public and private) Maintenance of traffic during construction How well do they address project purpose?

Factors Affecting Feasible Alternative Evaluation

Why? Less construction and R/W cost ($8.7M) than

Alternative 2 ($9.9M) Less impact to Circle K parcel than Alternative

2 Essentially the same intersection level of

service (a measurement of vehicle delay at traffic signals) as Alternative 2

Preferred Alternative – Feasible Alternative 1 (Entirely New Four-

Lane Bridge)

Feasible Alternative 2 - Entirely New Five-Lane Bridge (Circle K Impacts)

Feasible Alternative 2 - Entirely New Five Lane Bridge (Circle K Impacts)

Congestion – Signals for both alternatives operate at an acceptable level of service (LOS) and with acceptable queues for the 2039 design year traffic

Accidents in area are less than statewide averages

Wider bridge and vertical curve improvement will help driver visibility at south end

Feasible Alternatives - Traffic Summary

Alternative 1 has either the same or fewer environmental impacts as Alternative 2.

Alternative 2 does have more underground storage tank and commercial property impacts than Alternative 1.

Both have approximately the same impacts to existing utilities in the project area.

Feasible Alternatives – Environmental and Utility Impacts Summary

Final appearance not yet determined Construction costs are currently based on

standard ODOT bridge type City preference is current bridge lighting Stakeholder and public comments will be

sought

Bridge Aesthetics(How the new bridge will look)

US 24 Bridge over the Maumee River(West of Defiance)

Goal - maintain at least local traffic during construction.

Preferred Alternative - one lane of vehicular traffic to be maintained in each direction

Pedestrian and bicycle access may be temporarily suspended

Two construction seasons likely (maintain traffic or detour)

Maintaining Traffic During Construction

Construction in 2019 (preliminary estimate) Depends on funding, environmental

concerns, right-of-way acquisition, and completion of construction plans

Project schedule updates will be provided as changes in the schedule are known.

Current Project Schedule

Funding will be secured when Preferred Alternative is finalized.

ODOT has several funding options. Right-of-way acquisition anticipated to begin

in 2016 or 2017.

Project Funding

Additional stakeholder meetings will be held The initial public involvement meeting will

be held May 14, 2015 at Defiance High School (6:00 pm)

Comments, concerns, or any information you can provide are appreciated!

Stakeholder Concerns/Input

Comments after the meeting should go to: Jenn Gasser, ODOT District 1, (419) 999-6871,

[email protected] or Jeff Griffin, Burgess & Niple, (614) 459-2050,

[email protected] Future project information – go to District 1

website, Construction Projects & click on DEF SR 15 Clinton Street Bridge (http://www.dot.state.oh.us/districts/D01/PlanningPrograms/Projects/defiance15/Pages/default.aspx)

Stakeholder Concerns/Input