PRESENTATION ON METRO NEED AND PLAN STATUTORY CLEARANCES FROM MINISTRY OF RAILWAYS / CMRS METRO NEED AND PLAN 19.09.2009 1

CMRL-Presentation on Procedure for Safety Clearances -I

Embed Size (px)

DESCRIPTION

Safety Procedures

Citation preview

Page 1: CMRL-Presentation on Procedure for Safety Clearances -I

�PRESENTATION

�ON

METRO NEED AND PLAN

STATUTORY CLEARANCES

FROM

MINISTRY OF RAILWAYS / CMRS

�METRO NEED AND PLAN

�19.09.2009

1

MINISTRY OF RAILWAYS / CMRS

Page 2: CMRL-Presentation on Procedure for Safety Clearances -I

1. Metro Rail (Amendment) Act 2009 is applicable to

Chennai Metropolitan area.

2. Clause 7 of Chapter IV of the Act specifies appointment

of Commissioners of Metro Railway Safety (CMRS).

3. Clause 14 of Chapter V ‘opening of Metro railway’

requires sanction of the Central Government beforerequires sanction of the Central Government before

opening of a Metro Railway for public carriage. Vide

Clause 21 these powers can be delegated to CMRS.

http://www.delhimetrorail.com 2

Page 3: CMRL-Presentation on Procedure for Safety Clearances -I

4. Clause 15 of the Chapter V specifies formalities to be

complied before giving sanction:

“I. The Central Government obtain a report from CMRS

that

a. CMRS has made careful inspection of the Metro

Railway and Rolling Stock

b. The Moving and Fixed dimension has not

infringed.

c. The track structure, strength of bridges,c. The track structure, strength of bridges,standard of signalling system, tractionsystem, general structural character of civilworks and the size of, maximum gross loadupon ,the axles of any rolling stock, complywith the requirements .

d. In his opinion, Metro Railway can be opened for

the public carriage of passengers without any

danger to the public using it.”

http://www.delhimetrorail.com 3

Page 4: CMRL-Presentation on Procedure for Safety Clearances -I

Considering these legal aspects certain approvals are

obtained by CMRL from the Central Government.

Central Government in terms of Section 2, Clause 1(a) of

Metro Act in relation to technical planning and safety of

Metro Railway means the Ministry of Government of IndiaMetro Railway means the Ministry of Government of India

dealing with railways.

http://www.delhimetrorail.com 4

Page 5: CMRL-Presentation on Procedure for Safety Clearances -I

CMRL vide letter no. 161/CMR/2011 dated 11-02-2011 haveasked for procedures and documentations required forobtaining statutory clearances from Ministry of Railways andCMRS in respect of :

1. Rolling Stock.

2. Track Structure

3. Signalling and Telecommunication.

4. OHE Traction System.

5. Civil Structures.5. Civil Structures.

6. Safety and Man Power Planning

7. Opening of the section by CMRS.

In addition to above fire clearance from Fire Officer forArchitectural plans and compartmentation etc of sations isrequired at planning stage. Subsequently at operationalstage occupancy certificate from Fire Department would berequired. This is a prerequisite to CMRS inspection.

http://www.delhimetrorail.com 5

Page 6: CMRL-Presentation on Procedure for Safety Clearances -I

1. Approval of SOD is desirable before procurement.

2. Submission of request to the Carriage Directorate of the

RDSO for issue of provisional Speed Certificate for

conducting Oscillation and EBD trial.

� Request is to be enclosed with technical details of-Request is to be enclosed with technical details of-

� Rolling Stock

� Track

� Bridges

� Viaduct

� Tunnels

� Signalling & Traction System

� For detail refer Annexure 1and 2

http://www.delhimetrorail.com 6

Page 7: CMRL-Presentation on Procedure for Safety Clearances -I

3. Application to CMRS for conducting Oscillation and EBDtrials.

� Application to be enclosed with the followingCertificates/ Documents-

a. Joint Safety Certificate signed by HODs of

Rolling stock, Operation, S&T, Electrical

Traction and Track.

b. Track Certificate by track HOD.

c. Bridge Engineers Certificate by Chief Bridge

Engineer / CPM / CE (Construction).

d. Copy of RDSO’s Speed Certificate along with

compliance of Conditions stipulated in the

certificate.

e. safety procedure for testing and

commissioning

f. Time Table for trials

http://www.delhimetrorail.com 7

Page 8: CMRL-Presentation on Procedure for Safety Clearances -I

g. EIG sanctions and compliance of conditions ifany

h. Sanction of Dept. of Telecommunication fordynamic clearance.

i. Copy of approved Schedule of Dimension

j. OHE Fitness Certificate

k. General Introduction of Rolling Stockk. General Introduction of Rolling Stock

l. Track Structure Approval

� CMRS insists on trial section length of 10 KMs (minimum).

� Condonation of infringement to SOD (if any) by Ministry ofRailways required before submission of application toCMRS.

http://www.delhimetrorail.com 8

Page 9: CMRL-Presentation on Procedure for Safety Clearances -I

4. Final Speed Certificate is issued by RDSO based on results ofOscillation and EBD trials.

5. Application (in3 sets) for sanctioning of Rolling Stock to besubmitted to the Secretary (Civil Engineering)/ MOR throughCMRS/CCRS for MOR’s approval.

Documents to be enclosed with the application:

� Final Speed Certificate

� Form XIX- Joint Safety Certificate� Form XIX- Joint Safety Certificate

� Form VIII- Brief particulars of Rolling Stock and technical

details of the System

� Bridge Certificate

� Track Certificate

� Track Structure Approval

http://www.delhimetrorail.com 9

Page 10: CMRL-Presentation on Procedure for Safety Clearances -I

� OHE Certificate

� Form XVII- infringement of moving and Fixed Dimensions

jointly signed by HODs of Civil, track, S&T, Electrical ,

and Rolling Stock.

� EMC Control Plan

� RDSO’s Oscillation trial report� RDSO’s Oscillation trial report

� RDSO’s EBD trial report

� Approval of Signal and Train control System

� Approval of Electrical Traction System.

http://www.delhimetrorail.com 10

Page 11: CMRL-Presentation on Procedure for Safety Clearances -I

� Railway Board has circulated a performance criteria offastening system for ballastless track vide letter no.2009/proj./MAS/9/2 dated 21-05-2010.

� The proposal of Track structure chosen by a Metroadministration is submitted to the Railway board (in 2sets) along with the following:sets) along with the following:

� Details of Rails

� Plinth / slab design

� Fastening system

� Details of performance (minimum 5 years)

� Test Reports (Item 4.4 and beyond in the performancecriteria)

� Technical calculation and Drawings (Anchor Bolt,plinth reinforcement etc.)

http://www.delhimetrorail.com 11

Page 12: CMRL-Presentation on Procedure for Safety Clearances -I

� One set of proposal is submitted to RDSO by the Railway

Board for appraisal.

� If necessary, further details are submitted to RDSO/Railway

Board and clarification provided.

� Compliance of Performance Criteria submitted by DMRC to

MOR is given under Annexure-3

http://www.delhimetrorail.com 12

Page 13: CMRL-Presentation on Procedure for Safety Clearances -I

� Signal and Telecom System submitted to Ministry of

Railways for approval of:

1. Type of Signalling

2. Back up Signalling

3. Interlocking

4. Train Control System

5. Type of Track Circuits.

6. Point Machine for M/L and Depot.

7. Redundancy in cab equipment for ATP (cab

signalling)

8. Technical clearance for telecommunication.

9. Positive Train Identification.

10. Platform screen door. (Annexure 4)

http://www.delhimetrorail.com 13

Page 14: CMRL-Presentation on Procedure for Safety Clearances -I

Telecommunication System

� Proposed Telecommunication System shall comprise of the

following five subsystem

1. Fibre Optic Transmission system

2. Telephone System

3. Train Mobile radio system

4. Public Address system and4. Public Address system and

5. Closed Circuit Television (CCTV) system.

http://www.delhimetrorail.com 14

Page 15: CMRL-Presentation on Procedure for Safety Clearances -I

� Approval For Flexible OHE

As Delhi Metro’s Flexible OHE design is similar to that

Indian Railways and Standard follows are as per Indian

Railways Traction manual and hence no separate

clearance was required.

Same approach can be adopted by CMRL. They may

advice to the MOR.

� Approval For Rigid OCS

• Design is submitted to Ministry of Railways for

technical approval. (Annexure-A)

http://www.delhimetrorail.com 15

Page 16: CMRL-Presentation on Procedure for Safety Clearances -I

� The Electrical Inspector General (EIG) is to be approached

for giving clearances for

� Energisation of the 25 kV OHE and sectioning and

paralleling posts.

� Receiving Sub Stations

� 33 kV Sub –Stations

� DG sets etc.

� The application is sent along with the format 10-03 & 10-

15 for Flexible OHE and 10-03 to 10-12 for Rigid OHE duly15 for Flexible OHE and 10-03 to 10-12 for Rigid OHE duly

signed by concerned officers involved in construction and

O&M wing.

� Any accident due to electrocution to be reported to EIG.

http://www.delhimetrorail.com 16

Page 17: CMRL-Presentation on Procedure for Safety Clearances -I

� Nomination of EIG is done by the Ministry of Power

� The Min. of Power is to be approached for authorization

to EIG of Railways or EIG of State Government (Annexure

D & Annexure E).

� Lifts

Lift Inspector of concerned state Government will need

to be approached at two stages i.e. Pre erection

permission and subsequently for lift license at

commissioning stage.commissioning stage.

� Escalators

For escalators, a nominated Escalator Inspector of

State Govt. is approached for approval.

We understand that there is no inspector of

escalator in Tamil Nadu. However, it may be checked.

These are also prerequisite to CMRS inspection.

http://www.delhimetrorail.com 17

Page 18: CMRL-Presentation on Procedure for Safety Clearances -I

� Loading standards for Viaduct and Bridges is submitted to

the Railway Board for approval.

� These would include:

� Dead Load

� Live Load

Forces due to curvature and eccentricity of Track� Forces due to curvature and eccentricity of Track

� Temperature effect

� Friction resistance of expansion bearing

http://www.delhimetrorail.com 18

Page 19: CMRL-Presentation on Procedure for Safety Clearances -I

� Longitudinal forces

� Racking force

� Forces on parapets

� Wind pressure effect

� Force and effect due to earthquake

� Force due to derailment

� Live Load for platform.(Annexure – I)

http://www.delhimetrorail.com 19

Page 20: CMRL-Presentation on Procedure for Safety Clearances -I

� SAFETY Clearances

� No safety related clearance from outside agency

except statutory clearance by CMRS is required.

� Manpower Planning� Manpower Planning

� No clearance from any outside agency except CMRS

who will have to satisfy that adequate maintenance

facilities and trained manpower is available before

commissioning .

http://www.delhimetrorail.com 20

Page 21: CMRL-Presentation on Procedure for Safety Clearances -I

1. Nomination of CMRS to be notified by MOUD with the

concurrence of Ministry of Civil Aviation

2. Application to CMRS for statuary inspection of section

following prerequisites need to be firmed up–

a) Sanction of Rolling Stock by MOR.a) Sanction of Rolling Stock by MOR.

b) Approval of Track Structure by MOR.

c) Approval of Signal and Train Control Supply System

by MOR

d) Approval of Electrical Traction system by MOR

e) Approval of Schedule of Dimension by MOR

f) General Rules for Opening to be notified by MOUD.

g) Loading Standards by MOR.

http://www.delhimetrorail.com 21

Page 22: CMRL-Presentation on Procedure for Safety Clearances -I

3. Manuals and Procedures required

a. Track Maintenance

b. Rolling Stock operation and maintenance.

c. signal engineering.

d. AC Traction.

e. Train Operating Procedures.

f. Station and Depot working orders.

4. The application is submitted to CMRS in 3 identical originalsets. CMRS keeps one for his office and forward the othersto CCRS and MOR.to CCRS and MOR.

� Documents submitted along with application are to besigned by officer not below SAG Level. These documentsare

4.1 Administrative note

4.2 Forms :

i. Curve abstract - Form I

http://www.delhimetrorail.com 22

Page 23: CMRL-Presentation on Procedure for Safety Clearances -I

ii. Gradient abstract - Form II

iii. Bridge abstract - Form III

iv. Viaduct abstract - Form IV

v. Important Bridge abstract - Form V

vi. Ballast and permanent way - Form VI

vii. Station and station sites - Form VII

viii. Brief particulars of rolling stock - Form VIII

ix. Brief particulars of Traction Installation - Form IXix. Brief particulars of Traction Installation - Form IX

x. Power Supply Installation abstract - Form X

xi. Restricted OHE clearance abstract -Form XI

xii. Electrical crossing over metro railway Track abstract

-Form XII

xiii. Traction maintenance depot abstract -Form XIII

http://www.delhimetrorail.com 23

Page 24: CMRL-Presentation on Procedure for Safety Clearances -I

xiv. Ventilation smoke management and Fire safety measures

- Form XIV

xv. Brief particulars of signal and train control system-

- Form XV

xvi. Certificate from Chief Executive Officer - Form XVI

xvii. Infringement of moving and fixed dimensions- Form XVII

xviii. Load deflection test of Bridges - Form XVIII

xix. Joint Safety certificate for Rolling Stock - Form XIX

xx. Signalling safety Certificate - Form XX

4.3 Index plan and sections

4.4 Drawings

i. Station architectural / Layout

ii. Running Section

iii. OHE Layout Plans

iv. Signalling Scheme plans for section and control table

http://www.delhimetrorail.com 24

Page 25: CMRL-Presentation on Procedure for Safety Clearances -I

4.5 Station working orders of station and control table

4.6 Check List of Question and Answers.

4.7 Clearance of Fire safety measures of stations by local

Authority.

4.8 EIG Sanction and compliance of conditions.4.8 EIG Sanction and compliance of conditions.

4.9 Clearance from Department of telecommunication

4.10 Certificate regarding safety instructions &

precautionary measures.

4.11 License for working of lifts and elevators (If applicable)

http://www.delhimetrorail.com 25

Page 26: CMRL-Presentation on Procedure for Safety Clearances -I

� CMRS inspects the section by Motor Trolley accompanied by the Directors/officers nominated by CEO and other SAG/JAG level officers.

� Following aspects are examined:� Station to be manned with trained staff, having knowledge of relevant rules and procedures.

� Adequacy of all works pertaining to station exit/entry, firemen’s staircase, platform, staircases, lighting and ventilation etc.firemen’s staircase, platform, staircases, lighting and ventilation etc.

� Passenger facilities such as toilets, ticket office functioning, AFC system, Escalators, lifts etc.

� Fire protection, detection, suppression and disaster management measures.

� Adequate public announcement and display system.� proper signage and boards at prominent locations and technical rooms are properly manned.

http://www.delhimetrorail.com26

Page 27: CMRL-Presentation on Procedure for Safety Clearances -I

� Railings on viaduct in elevated section, at platform and

staircases etc.

� Walkway in tunnels.

� Measurement of curves, turnouts, track features, track

spacing, clearances of parapets, tunnels and other

features.

� Measurement of OHE clearance, signals etc.

� All electrical and signaling systems with the assistance of

Dy.CRS S&T and Electrical.

� After trolleying down both UP and DN lines, the

confirmatory speed test by train is done on both the lines

including emergency evacuation system from train, ATP

functions etc.

http://www.delhimetrorail.com 27

Page 28: CMRL-Presentation on Procedure for Safety Clearances -I

� Following the inspection, CMRS accords sanction for

opening of corridor for introduction of commercial

services.

� A detailed inspection report is prepared and submitted to� A detailed inspection report is prepared and submitted to

MOR, MOUD and DMRC by CMRS.

http://www.delhimetrorail.com 28

Page 29: CMRL-Presentation on Procedure for Safety Clearances -I

Thank YouThank YouThank YouThank You

www. delhimetrorail.com