25
3/4/2015 1 CRMCA SOUTHERN MARKETING O COLD WEATHER CONCRETE PRACTICES SUCCESSFUL COLD WEATHER CONCRETING

COLD WEATHER CONCRETE PRACTICES - CRMCAcrmca.org/wp-content/uploads/2015/03/Cold-Weather-Concreting... · COLD WEATHER CONCRETE PRACTICES ... •Hot water •Heat Aggregate •

Embed Size (px)

Citation preview

3/4/2015

1

CRMCA SOUTHERN MARKETING

O

COLD WEATHER CONCRETE PRACTICES

SUCCESSFULCOLD WEATHER

CONCRETING

3/4/2015

2

3/4/2015

3

3/4/2015

4

ACI DEFINITION OF COLD WEATHER

Cold Weather - A period when, for more than 3 consecutive days, the

following conditions exist:

• The Average daily air temperature is less than 40 ºF (5 ºC), and

• The air temperature is not greater than 50 ºF (10 ºC) for more than

one-half of any 24 hour period.

3/4/2015

5

9

U.S. FREEZE / THAW ZONE MAP

Annual average number

of days temperatures

fall below 32 °F (0 °C)

Less than 30

30 to 90

91 to 150

151 to 210

More than 210

10

Temperature, °F Approx. Setting Time, hrs.

70 6

60 8

50 11

40 14

32 Concrete Freezes

CONCRETE FREEZES!

Setting Time of Concrete at Various

Temperatures

3/4/2015

6

11

Effect of Early Freezing

12

A 10 degree drop in

concrete temperature

will DELAY set time by

approximately

2 – 2 ½ hours

Rule of Thumb

3/4/2015

7

Increased Contractor

Labor Costs

Extended Concrete Setting Times

14

Increased Contractor Labor Costs

3/4/2015

8

15

• Prevent damage to concrete due to freezing at early stages

• Assure that the concrete develops the required strength for safe removal of forms

• Maintain curing conditions that foster normal strength development

• Limit rapid temperature changes

• Provide protection consistent with the intended serviceability of the structure

OBJECTIVES OF SUCCESSFUL

COLD WEATHER CONCRETING

• Materials

• Mix Design

• Placement Conditions

• Curing conditions and length of time

• Protection

What Can We Influence

3/4/2015

9

• GOAL is to ACCELERATE and INCREASE

Maximum Temperature

• Provide concrete with predictable setting

times

• Maintain Air entrainment and workability

• Minimize Plastic and Drying shrinkage

Materials & Mix Design

Speed up the early hydration (heat gain) of

concrete can be obtained by using one or more

of the following:

• Additional portland cement

• Use Type III Cement

• Hot water

• Heat Aggregate

• Use of calcium chloride

• Use of a non-chloride accelerating admixture

Cold Weather Concreting (Producer)

3/4/2015

10

19

0

2

4

6

8

10

12

14

12:35

10:40

8:55

Effect of Cement Content on Setting Time

Performance

Concrete and Ambient Temperature: 50 °F (10 °C)In

itia

l Tim

e o

f Se

t -

Ho

urs

Cement Content, lb/yd³ (kg/m³)

420 (250) 520 (310) 600 (355)

20

An increase of 1

sack of cement, will

improve the set time

by about 1 hour

Why?

Lower unit water

content

Rule of Thumb

3/4/2015

11

21Age of Test, Days

Com

pre

ssiv

e S

trength

, % o

f 28 D

ay,

73°F

(23°C

) Cure

d C

oncre

te

40

20

0

60

80

1 3 7

Mixed and

cured at 55°F (13°C)

Age of Test, Days

Com

pre

ssiv

e S

trength

, % o

f 28 D

ay,

73°F

(23°C

) Cure

d C

oncre

te

40

20

0

60

80

1 3 7

Mixed and

cured at 55°F (13°C)

Early Age Compressive Strength for

Type I and Type III Cement

22

Early Age Compressive Strength For

Type I and Type III Cement

Age of Test, Days

Com

pre

ssiv

e S

tren

gth

, %

of

28 D

ay,

73°F

(2

3°C

) C

ure

d C

oncre

te

40

20

0

60

80

1 3 7

Mixed and

cured at 40°F (4°C)

Type III

Type I

Early Age Compressive Strength for

Type I and Type III Cement

3/4/2015

12

23

“An accelerating admixture is a material

added to concrete for the purpose of

reducing the time of setting and

accelerating early strength development.”

“Accelerating admixtures are useful for

modifying the properties of concrete,

particularly in cold weather, to:”

Chemical Admixtures for Concrete

ACI 212.3

24

• Expedite the start of finishing operations

• Reduce the time required for proper curing

and protection

• Increase the rate of early strength

development to permit earlier removal of

forms and earlier opening of construction

for service

Chemical Admixtures for Concrete

ACI 212.3

3/4/2015

13

25

Accelerated setting time characteristics

• Earlier finishing of slabs

• Increased early and ultimate strength

• Reduced protection time in cold weather

• Earlier stripping and reuse of forms

Accelerating Admixtures

26

Calcium Chloride

Accelerating admixtures containing calcium chloride

Non-chloride accelerating admixtures

Non-chloride accelerating admixtures for use in

concrete placed in sub-freezing temperatures

Classes of Accelerating Admixtures

3/4/2015

14

• Concrete should never be placed on a

frozen subgrade

• On a frozen subgrade, heat will migrate

rapidly away from the bottom of the

concrete retarding setting time

• Thaw the subgrade not just the surface

• Reschedule for a warmer day!!

Placing Concrete on Ground

Concrete bleeding

Bleed water can freeze on surface

Bleed water capillary channels can freeze within the concrete

Cold subgrades

Rapid migration of heat from concrete will affect setting time

Uneven settlement may occur, causing cracking

Plastic Concrete Problems in Cold Weather

3/4/2015

15

29

Surface crusting which can cause:

Blisters

Delamination

Scaling (premature/over finishing)

Finishing Problems in Cold Weather

3/4/2015

16

All snow, ice and frost must be removed from

forms, reinforcement and other embedments

Must protect from all sides

Use of Type III cement, additional cement and/or

non-chloride accelerators will reduce the length

of protection period, HOWEVER, know the effects

each will have on the plastic and hardened

properties

Cold Weather Concreting Above Ground

3/4/2015

17

3/4/2015

18

36

1

2

4

Minimum Concrete temperature as placed and maintained

Minimum concrete temperature as mixed for indicated air temperature

Air Temperature

-

Above 30 °F

Below 0 °F

<12 in. 12-36 in.

55 °F 50 °F

60 °F 55 °F

3 0 to 30 °F 65 °F 60 °F

70 °F 65 °F

Table 3.1 – Recommended Concrete

Temperatures

37

DURATION OF RECOMMENDED PROTECTION FOR % OF

STANDARD-CURED 28-DAY STRENGTH

50 6 9 3

65 11 14 5

85 21 28 16

95 29 35 26

Percentage of

Standard-cured

28-day strength

At 50 °F (10 °C), days

Type of Cement

I II III

3/4/2015

19

3/4/2015

20

41

8.1 – Introduction ― “Newly placed concrete

must be protected from drying so that adequate

hydration can occur. Normally, measures must

be taken to prevent evaporation of moisture

from concrete. During cold weather, when the

air temperature is below 50 ºF(10 ºC),

atmospheric conditions in most areas will not

cause excessive drying.”

Concrete Curing

42

8.2 - Curing during the protection period

When dry heating is used, the concrete should

be covered with an impervious material or

curing compound.

Water curing is not recommended.

Concrete Curing

3/4/2015

21

Things to watch

Carbonation CO2

Vent or have heat source from outside

Watch Carbonation from other trades equipment

Watch blowing hot air across a fresh slab

Heating

3/4/2015

22

45

8.3 - Curing following the protection

period “…if a curing compound is applied

during the first period of above-freezing

temperature after protection is removed,

the need to conduct further curing

operations if the temperature should rise

above 50 ºF(10 ºC) is eliminated.”

Concrete Curing

46

Effect of Curing on Compressive

Strength

Age, Days

125

100

75

50

25

0

150

3 7 28 90 180

Moist-cured entire time

In air after 7 days

In air after 3 days

In air entire time

Com

pre

ssiv

e st

reng

th,

perc

ent

of

28-

day

moi

st-c

ure

d c

oncr

ete

Effect of Curing on Compressive

Strength

3/4/2015

23

Cylinders should be protected and stored in

protective area between 60°F and 80°F for the first

24 hours.

Record field storage conditions with a high / low

thermometer.

Field cure cylinders for form removal should be

representative of the structure and not used for

quality assurance.

Recommend using maturity meter for in place

strength data.

Testing

49

110

100

80

60

40

20

0

3 6 9 12 18 24

Sta

nd

ard

28

-Da

y C

om

pre

ssiv

e S

tren

gth

Age at which specimens were frozen, in hours

Effect of Freezing on 28-Day

Compressive Strength

3/4/2015

24

50

“Work on your project named here shall

conform to all requirements of ACI

306.1,Standard Specification for Cold Weather

Concreting, published by the American

Concrete Institute, Detroit, Michigan, except

as modified by the requirements of these

Contract Documents.”

Sample Cold Weather Spec.

51

The entire team must:

Plan ahead

Be prepared

Be concerned

Schedule work

Instruct and inspect

Successful Cold Weather Concreting

Practices

3/4/2015

25

52

Quality concrete can be successfully placed at low ambient temperatures

ACI 306R Guide, ACI 306 specification and ACI 308 Guide should be followed

More cement, Type III Cement, heat and/or accelerating admixtures may all be used to accelerate concrete setting time and increase early strength development

Conclusions and Recommendations

53

“Cold Weather Concreting”

Reported by

ACI Committee 306

“Standard Specification for Cold Weather Concreting”

Reported by

ACI Committee 306

“Standard Practice for Curing Concrete”

Reported by

ACI Committee 308

Resources