Item - 31.01 (a) common excavation Effecinecy factor 1 output 32.14 M 3 /hr Factor (A) Material 0.00 A (B) Labaour Construction Foreman Hour 1 0.50 109.63 54.82 Equipment Operator II Hour 1 1.00 128.40 128.40 Helper I Hour 4 1.00 110.63 442.52 Equipment Operator I Hour 1 0.50 49.87 24.94 Surveyors Hour 1 0.50 109.14 54.57 Laborers Hour 7 1.00 9.68 67.76 773.00 B ( c ) Equipment Excavator, wheel type Hour 1 1.00 729.57 729.57 Total Station Hour 1 0.50 50.00 25.00 Light vehicle Hour 1 0.50 125.00 62.50 Hand Tools Hour 1 1.00 5.00 5.00 Dump Trucks Hour 2 1.00 705.02 1410.03 2232.10 3005.10 C Cost / M 3 93.50 D project overhead 0% 0.00 E Hq over head / contractor's profit 0% 0.00 F 93.50 93.50 Unit cost / M 3 = Total of A Total of B Total of C Total cost = A + B + C = Total cost = D + E + F = Soft Exavation 0 to 1.5m depth Item No. Unit Qty Utilization Rate cost

coman exv

  • Upload
    eph

  • View
    224

  • Download
    1

Embed Size (px)

DESCRIPTION

civil

Citation preview

  • Item - 31.01 (a) common excavation

    Effecinecy factor 1

    output 32.14 M3/hr

    Factor

    (A) Material

    0.00 A

    (B) Labaour

    Construction Foreman Hour 1 0.50 109.63 54.82

    Equipment Operator II Hour 1 1.00 128.40 128.40

    Helper I Hour 4 1.00 110.63 442.52

    Equipment Operator I Hour 1 0.50 49.87 24.94

    Surveyors Hour 1 0.50 109.14 54.57

    Laborers Hour 7 1.00 9.68 67.76

    773.00 B

    ( c ) Equipment

    Excavator, wheel type Hour 1 1.00 729.57 729.57

    Total Station Hour 1 0.50 50.00 25.00

    Light vehicle Hour 1 0.50 125.00 62.50

    Hand Tools Hour 1 1.00 5.00 5.00

    Dump Trucks Hour 2 1.00 705.02 1410.03

    2232.10

    3005.10 C

    Cost / M3

    93.50 D

    project overhead 0 % 0.00 E

    Hq over head / contractor's profit 0 % 0.00 F

    93.50

    93.50Unit cost / M3 =

    Total of A

    Total of B

    Total of C

    Total cost = A + B + C =

    Total cost = D + E + F =

    Soft Exavation 0 to 1.5m depth

    Item

    No. Unit Qty

    UtilizationRate cost