1 In This Issue ——————————————–— Highlights of the Month Land Acquisition Status & Critical Issues Civil Works & Progress photos at a Glance What's’ Happening beneath the Ground Track Works at a Glance E-News Letter for BMRCL Website only https://english.bmrc.co.in/News/NewsSection Shri Durga Shanker Mishra, IAS Secretary to GoI, Ministry of Housing & Urban Affairs, & Chairman, Bangalore Metro Rail Corporation Limited Shri Ajay Seth, IAS Managing Director Bangalore Metro Rail Corporation Limited Address: Bangalore Metro Rail Corporation Limited 3rd Floor, BMTC Complex, K H Road, Shanthinagar, Bengaluru - 560 027. Web: www.bmrc.co.in 1 August 2020 C OMMENCEMENT OF TUNNELING WORK BETWEEN S HIVAJINAGAR TO R ASHTRIYA M ILITARY S CHOOL S TATIONS ON 28.08.2020 BY TBM A VANI Director (Projects & Planning), BMRCL and other officials were present during the occasion Namma Metro is providing a Safe, Fast, Reliable, Comfortable & Affordable Travel in Bengaluru City

COMMENCEMENT WORK BETWEEN R M S 28.08.2020 TBM A · 2020. 9. 29. · Drain construction work is in progress (26% completed). Trial trench for utility identification is in progress

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: COMMENCEMENT WORK BETWEEN R M S 28.08.2020 TBM A · 2020. 9. 29. · Drain construction work is in progress (26% completed). Trial trench for utility identification is in progress

1

In This Issue

——————————————–—

Highlights of the Month

Land Acquisition Status & Critical Issues

Civil Works & Progress photos at a Glance

What's’ Happening beneath the Ground

Track Works at a Glance

E-News Letter for BMRCL Website only

https://english.bmrc.co.in/News/NewsSection

Shri Durga Shanker Mishra, IAS

Secretary to GoI, Ministry of Housing & Urban Affairs, &

Chairman, Bangalore Metro Rail Corporation Limited

Shri Ajay Seth, IAS

Managing Director

Bangalore Metro Rail Corporation Limited

Address: Bangalore Metro Rail Corporation Limited

3rd Floor, BMTC Complex, K H Road, Shanthinagar,

Bengaluru - 560 027. Web: www.bmrc.co.in

1

August 2020

COMMENCEMENT OF TUNNELING WORK BETWEEN

SHIVAJINAGAR TO RASHTRIYA MILITARY SCHOOL STATIONS

ON 28.08.2020 BY TBM AVANI

Director (Projects & Planning), BMRCL and other officials were present during the occasion

Namma Metro is providing a Safe, Fast, Reliable, Comfortable & Affordable Travel in Bengaluru City

Page 2: COMMENCEMENT WORK BETWEEN R M S 28.08.2020 TBM A · 2020. 9. 29. · Drain construction work is in progress (26% completed). Trial trench for utility identification is in progress

2

2

Sl. No

Reaches

No. of properties Required

No. of properties Acquired

[As per 28(4) & 3(1)]

Handed over to Eng. Section up to August - 2020

Balance to be Handed over to Engg. Section

Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total

1

Reach-1 Extn 38 522 560 38 522 560 38 485 523 0 37 37

Forest Land 21 0 21 0 0 0 21 0 21 0 0 0

2

Reach-2 Extn Station & Viaduct

25 99 124 25 99 124 25 99 124 0 0 0

Challaghatta Depot 10 24 34 10 24 34 10 24 34 0 0 0

3 Reach-3C Extn 3 111 114 3 105 108 3 105 108 0 6 6

4

Reach-4B Extn. 12 294 306 12 294 306 12 294 306 0 0 0

Anjanapura Depot 1 20 21 1 20 21 1 20 21 0 0 0

5

Reach-5 New Line 46 798 844 46 798 844 46 798 844 0 0 0

Hebbagodi Depot 1 57 58 1 57 58 1 57 58 0 0 0

6

Reach-6 (Elevated) 34 222 256 34 222 256 34 222 256 0 0 0

Reach - 6 (UG) 52 281 333 52 276 328 49 275 324 3 6 9

Kothnur Depot 4 64 68 4 64 68 4 64 68 0 0 0

Total 247 2492 2739 226 2481 2707 244 2443 2687 3 49 52

7 ORR Line 21 47 68 21 47 68 20 44 64 1 3 4

8 Airport line 61 299 360 61 299 360 50 69 119 11 230 241

Total 82 346 428 82 346 428 70 113 183 12 233 245

Grand Total 329 2838 3167 308 2827 3135 314 2556 2870 15 282 297

Land Acquisition Status for the month of August, 2020 of Phase-2, ORR -2A & Airport -2B Line

Page 3: COMMENCEMENT WORK BETWEEN R M S 28.08.2020 TBM A · 2020. 9. 29. · Drain construction work is in progress (26% completed). Trial trench for utility identification is in progress

3

3

Critical issues faced regarding Land Acquisition for Phase-2 of the Project

Reach-6 Underground Section

Langford Town Station:- Local Military Authorities (LMA) have sent the proposal for

transfer of 2137.334. sqm of land on permanent basis and 5866.569 sqm on

temporary basis to Army Head Quarters. Matter is being pursued with Defence

Authorities.

Lakkasandra Village Sy. No. 14 and 15:- The re-location of 101 encroachers at

Lakkasandra land is under consideration of Deputy Commissioner, Bangalore

Urban and Karnataka Slum Development Board.

Phase-2 Progress up to 31st August, 2020

0 10 20 30 40 50 60 70 80 90 100

Reach-6-Elev (Gottigere to Swagath Cross Road)

Reach-5-P-3 (Bommanahalli to R V Road)

Reach-5-P-2 (Hosa Road to Bommanahalli)

Reach-5-P1 (Bommasandra to Hosa Road)

Reach-4B (Puttenahalli Cross to Anjanapura Township)

Reach-3C (Hessaraghatta Cross to Bangalore International Exhibition Center)

Reach-2B (Pattanagere to Chellaghatta Depot)

Reach-2A (Mysuru Road to Pattanagere)

Reach-1B (Visvesvaraya Industrial Area to Whitefield)

Reach-1A (Baiyappanahalli to Visvesvaraya Industrial Area)

30

32

70

64

95

65

95

95

91

73

CIVIL WORK PROGRESS IN PERCENTAGE

Series1 Series2 Series3 Series4 Series5 Series6 Series7 Series8

Page 4: COMMENCEMENT WORK BETWEEN R M S 28.08.2020 TBM A · 2020. 9. 29. · Drain construction work is in progress (26% completed). Trial trench for utility identification is in progress

4

Phase– 2 Progress Photos at a glance

R-1A: Works in progress at Doddanekundi Station R-1B : Kundalahalli Station – Roof Portal Erection

R-2A: Side View of Nayandahalli Station R-2B: View of Challaghatta Station Pier Arm Work in Progress

R-3C: BIEC Station Piling Work in progress R-4B: Trial Runs Commenced

4

Page 5: COMMENCEMENT WORK BETWEEN R M S 28.08.2020 TBM A · 2020. 9. 29. · Drain construction work is in progress (26% completed). Trial trench for utility identification is in progress

5

Phase– 2 Progress Photos at a glance

R-5-P1: Erection of segmental span in progress R-5-P2: Muneshwaranagar Station: Platform Level Pier Arm

(PP3) erection work in progress

R-5-P3: Road segment erection in progress R-6-Ele: IIMB Station work in progress

R-6-UG-RT1: North to South Aerial view of Dairy Circle Station R-6-UG-RT1: West to East Aerial view of South Ramp

5

Page 6: COMMENCEMENT WORK BETWEEN R M S 28.08.2020 TBM A · 2020. 9. 29. · Drain construction work is in progress (26% completed). Trial trench for utility identification is in progress

6

6

UNDERGROUND WORKS - REACH 6

DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS

Contractor - M/s Afcons Infrastructure Limited—RT-01

Sl No

RT-01 Progress Details as on 31.08.2020

1 Alignment of RT-1 Between South Ramp to Rashtriya Military School.

2 UG Works are divided into 4 Packages

Package-1

3 Station Works Progress

South Ramp:

Utility diversion work is in progress (95% completed).

Barricading board installation work is in progress (23% completed).

Secant Pile Construction work is in progress (24% completed).

Drain construction work is in progress (76% completed).

Road Diversion work is in progress (65 % completed).

Dairy Circle Station:

Utility diversion work is in progress (85% completed).

Barricading board installation work is in progress (90% completed).

Secant Pile Construction work is in progress (23% completed).

Drain construction work is in progress (26% completed).

Trial trench for utility identification is in progress.

Lakkasandra Station:

Building demolition work is in progress (90% completed).

Work area barricading is in progress (85% completed).

Secant Pile Construction work is in Progress (15% completed).

Drain construction work is in progress (5% completed).

Langford Station:

Work area barricading 5% completed.

Rashtriya Military School (Vellara Launching Shaft):

Secant Pile Construction Work Completed (100% completed).

First level excavation work is in progress (14% completed).

Capping beam Construction Work Completed.

Casting Yard (Baiyappanahalli):

Work area barricading is in progress (85% completed).

Casting of temporary tunnel rings (segments) in progress (92% completed).

Fabrication work of trusses for shed construction is in progress.

Production yard shed foundation (Excavation, PCC, Raft & Column) work is in progress.

RCC beam for rail of overhead Gantry crane is in progress.

Gantry crane erection completed.

Levelling for internal road access work is in progress.

Page 7: COMMENCEMENT WORK BETWEEN R M S 28.08.2020 TBM A · 2020. 9. 29. · Drain construction work is in progress (26% completed). Trial trench for utility identification is in progress

7

7

Rebar Fixing Work for Base Slab in Shivajinagar Station

UNDERGROUND WORKS - REACH 6

DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS

Contractor - M/s Larson & Toubro Ltd—RT-02

Sl No

RT-02 Progress Details as on 31.08.2020

1 Alignment of RT-2 Between Rashtriya Military School to Shivajinagar.

2 UG Works are divided into 4 Packages

Package-2

3 Station Works Progress

Rashtriya Military School Station: Secant Piles are being provided as temporary support structures. 51.6% of the piles for station box and 61.5% of the piles for entry exit have been completed. 16044 Cum (13.49%) of excavation for the station have been completed.

M G Road Station: Secant piles are being provided as temporary support structures. 100% of the Piles for station box and 38.4% of the piles for entry exit have been completed. 49676 Cum (51.1%) of excavation for the station have been completed.

Shivajinagar Station: Secant piles are being provided as temporary support structures. 100.1% of the piles for station box and 67.2% of the piles for entry exit have been completed. 87894 Cum (76.5%) of excavation for the station have been completed.

4 Tunnel Works Progress

TBM 1: AVNI -(Tunnel Boring Starts at Shivajinagar & Ends at Rashtriya Military School)

Site Acceptance Test completed. Installation of Bull flex completed.

TBM work has been started.

TBM 2: LAVI-(Tunnel Boring Starts at Shivajinagar & Ends at Rashtriya Military School) TBM body lowered. Welding works in progress

Piling work in progress at MG Road Station

Excavation work in progress at Vellara Station

Tower Crane erection work in progress at Shivajinagar Station

Fabrication work in progress at

Lakkasandra Yard

Page 8: COMMENCEMENT WORK BETWEEN R M S 28.08.2020 TBM A · 2020. 9. 29. · Drain construction work is in progress (26% completed). Trial trench for utility identification is in progress

8

8

Secant Piling works at North West side

UNDERGROUND WORKS - REACH 6

DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS

Contractor - M/s Larson & Toubro Ltd—RT-03

Sl No

RT-03 Progress Details as on 31.08.2020

1 Alignment of RT-3 Between Shivajinagar to Pottery Town

2 UG Works are divided into 4 Packages

Package-3

TBM Works Progress

Urja TBM (TBM No. 01): Tunnelling between Cantonment station to Shivajinagar has started mining from 14.08.2020 and so far completed 24 m of tunnelling out of 855 m (18 rings out of the total scope of 570 rings). Vindhya TBM (TBM No-2): Testing of various components for commissioning is in progress

3 Station Works Progress

Cantonment Station:

Hard rock excavation using controlled blasting technique is in progress. 44% of total excavation, i.e. 71,666 Cum is completed out of 1,62,000 Cum.

1078 Sqm. of PCC has been completed on south side. Launching area for launching of

second Tunnel Boring Machine is made ready.

Pottery Town Station:

Temporary support system with Secant piles: About 96.9% of the secant piles for station box and 100% of the secant piles for Ancillary Building are completed.

Excavation work for station box: About 11% i.e. 18,355 Cum completed out of 1,72,889 Cum.

Fabrication & Installation of first layer struts and waler beams are in progress

4 Peenya Casting Yard Precast Tunnel segment casting: 21.1% of tunnel rings i.e. 683 Nos. of tunnel rings

out of total requirement of 3244 Nos are completed.

View of Pottery Town work in progress

Page 9: COMMENCEMENT WORK BETWEEN R M S 28.08.2020 TBM A · 2020. 9. 29. · Drain construction work is in progress (26% completed). Trial trench for utility identification is in progress

9

9

Track Works at a Glance

Contractor - M/s Texmaco Rail & Engineering Limited

Sl No Item Description Unit Track Plinth Casting

Sections Track Meters Reach 4

(August 2020) Reach 2

(August 2020)

1 Scope of Work Trm 12580 17628

2 Progress for the month Trm Nil 1220

3 Cumulative progress Trm 11700 7187

4 Access Handed over Trm 11700 14900

R-1 Extn: Flash Butt

Welding of Rails in progress

R-2 Extn: Track Preparation

Work near Jnanabharathi

Station