Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
1
In This Issue
——————————————–—
Highlights of the Month
Land Acquisition Status & Critical Issues
Civil Works & Progress photos at a Glance
What's’ Happening beneath the Ground
Track Works at a Glance
E-News Letter for BMRCL Website only
https://english.bmrc.co.in/News/NewsSection
Shri Durga Shanker Mishra, IAS
Secretary to GoI, Ministry of Housing & Urban Affairs, &
Chairman, Bangalore Metro Rail Corporation Limited
Shri Ajay Seth, IAS
Managing Director
Bangalore Metro Rail Corporation Limited
Address: Bangalore Metro Rail Corporation Limited
3rd Floor, BMTC Complex, K H Road, Shanthinagar,
Bengaluru - 560 027. Web: www.bmrc.co.in
1
August 2020
COMMENCEMENT OF TUNNELING WORK BETWEEN
SHIVAJINAGAR TO RASHTRIYA MILITARY SCHOOL STATIONS
ON 28.08.2020 BY TBM AVANI
Director (Projects & Planning), BMRCL and other officials were present during the occasion
Namma Metro is providing a Safe, Fast, Reliable, Comfortable & Affordable Travel in Bengaluru City
2
2
Sl. No
Reaches
No. of properties Required
No. of properties Acquired
[As per 28(4) & 3(1)]
Handed over to Eng. Section up to August - 2020
Balance to be Handed over to Engg. Section
Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total
1
Reach-1 Extn 38 522 560 38 522 560 38 485 523 0 37 37
Forest Land 21 0 21 0 0 0 21 0 21 0 0 0
2
Reach-2 Extn Station & Viaduct
25 99 124 25 99 124 25 99 124 0 0 0
Challaghatta Depot 10 24 34 10 24 34 10 24 34 0 0 0
3 Reach-3C Extn 3 111 114 3 105 108 3 105 108 0 6 6
4
Reach-4B Extn. 12 294 306 12 294 306 12 294 306 0 0 0
Anjanapura Depot 1 20 21 1 20 21 1 20 21 0 0 0
5
Reach-5 New Line 46 798 844 46 798 844 46 798 844 0 0 0
Hebbagodi Depot 1 57 58 1 57 58 1 57 58 0 0 0
6
Reach-6 (Elevated) 34 222 256 34 222 256 34 222 256 0 0 0
Reach - 6 (UG) 52 281 333 52 276 328 49 275 324 3 6 9
Kothnur Depot 4 64 68 4 64 68 4 64 68 0 0 0
Total 247 2492 2739 226 2481 2707 244 2443 2687 3 49 52
7 ORR Line 21 47 68 21 47 68 20 44 64 1 3 4
8 Airport line 61 299 360 61 299 360 50 69 119 11 230 241
Total 82 346 428 82 346 428 70 113 183 12 233 245
Grand Total 329 2838 3167 308 2827 3135 314 2556 2870 15 282 297
Land Acquisition Status for the month of August, 2020 of Phase-2, ORR -2A & Airport -2B Line
3
3
Critical issues faced regarding Land Acquisition for Phase-2 of the Project
Reach-6 Underground Section
Langford Town Station:- Local Military Authorities (LMA) have sent the proposal for
transfer of 2137.334. sqm of land on permanent basis and 5866.569 sqm on
temporary basis to Army Head Quarters. Matter is being pursued with Defence
Authorities.
Lakkasandra Village Sy. No. 14 and 15:- The re-location of 101 encroachers at
Lakkasandra land is under consideration of Deputy Commissioner, Bangalore
Urban and Karnataka Slum Development Board.
Phase-2 Progress up to 31st August, 2020
0 10 20 30 40 50 60 70 80 90 100
Reach-6-Elev (Gottigere to Swagath Cross Road)
Reach-5-P-3 (Bommanahalli to R V Road)
Reach-5-P-2 (Hosa Road to Bommanahalli)
Reach-5-P1 (Bommasandra to Hosa Road)
Reach-4B (Puttenahalli Cross to Anjanapura Township)
Reach-3C (Hessaraghatta Cross to Bangalore International Exhibition Center)
Reach-2B (Pattanagere to Chellaghatta Depot)
Reach-2A (Mysuru Road to Pattanagere)
Reach-1B (Visvesvaraya Industrial Area to Whitefield)
Reach-1A (Baiyappanahalli to Visvesvaraya Industrial Area)
30
32
70
64
95
65
95
95
91
73
CIVIL WORK PROGRESS IN PERCENTAGE
Series1 Series2 Series3 Series4 Series5 Series6 Series7 Series8
4
Phase– 2 Progress Photos at a glance
R-1A: Works in progress at Doddanekundi Station R-1B : Kundalahalli Station – Roof Portal Erection
R-2A: Side View of Nayandahalli Station R-2B: View of Challaghatta Station Pier Arm Work in Progress
R-3C: BIEC Station Piling Work in progress R-4B: Trial Runs Commenced
4
5
Phase– 2 Progress Photos at a glance
R-5-P1: Erection of segmental span in progress R-5-P2: Muneshwaranagar Station: Platform Level Pier Arm
(PP3) erection work in progress
R-5-P3: Road segment erection in progress R-6-Ele: IIMB Station work in progress
R-6-UG-RT1: North to South Aerial view of Dairy Circle Station R-6-UG-RT1: West to East Aerial view of South Ramp
5
6
6
UNDERGROUND WORKS - REACH 6
DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS
Contractor - M/s Afcons Infrastructure Limited—RT-01
Sl No
RT-01 Progress Details as on 31.08.2020
1 Alignment of RT-1 Between South Ramp to Rashtriya Military School.
2 UG Works are divided into 4 Packages
Package-1
3 Station Works Progress
South Ramp:
Utility diversion work is in progress (95% completed).
Barricading board installation work is in progress (23% completed).
Secant Pile Construction work is in progress (24% completed).
Drain construction work is in progress (76% completed).
Road Diversion work is in progress (65 % completed).
Dairy Circle Station:
Utility diversion work is in progress (85% completed).
Barricading board installation work is in progress (90% completed).
Secant Pile Construction work is in progress (23% completed).
Drain construction work is in progress (26% completed).
Trial trench for utility identification is in progress.
Lakkasandra Station:
Building demolition work is in progress (90% completed).
Work area barricading is in progress (85% completed).
Secant Pile Construction work is in Progress (15% completed).
Drain construction work is in progress (5% completed).
Langford Station:
Work area barricading 5% completed.
Rashtriya Military School (Vellara Launching Shaft):
Secant Pile Construction Work Completed (100% completed).
First level excavation work is in progress (14% completed).
Capping beam Construction Work Completed.
Casting Yard (Baiyappanahalli):
Work area barricading is in progress (85% completed).
Casting of temporary tunnel rings (segments) in progress (92% completed).
Fabrication work of trusses for shed construction is in progress.
Production yard shed foundation (Excavation, PCC, Raft & Column) work is in progress.
RCC beam for rail of overhead Gantry crane is in progress.
Gantry crane erection completed.
Levelling for internal road access work is in progress.
7
7
Rebar Fixing Work for Base Slab in Shivajinagar Station
UNDERGROUND WORKS - REACH 6
DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS
Contractor - M/s Larson & Toubro Ltd—RT-02
Sl No
RT-02 Progress Details as on 31.08.2020
1 Alignment of RT-2 Between Rashtriya Military School to Shivajinagar.
2 UG Works are divided into 4 Packages
Package-2
3 Station Works Progress
Rashtriya Military School Station: Secant Piles are being provided as temporary support structures. 51.6% of the piles for station box and 61.5% of the piles for entry exit have been completed. 16044 Cum (13.49%) of excavation for the station have been completed.
M G Road Station: Secant piles are being provided as temporary support structures. 100% of the Piles for station box and 38.4% of the piles for entry exit have been completed. 49676 Cum (51.1%) of excavation for the station have been completed.
Shivajinagar Station: Secant piles are being provided as temporary support structures. 100.1% of the piles for station box and 67.2% of the piles for entry exit have been completed. 87894 Cum (76.5%) of excavation for the station have been completed.
4 Tunnel Works Progress
TBM 1: AVNI -(Tunnel Boring Starts at Shivajinagar & Ends at Rashtriya Military School)
Site Acceptance Test completed. Installation of Bull flex completed.
TBM work has been started.
TBM 2: LAVI-(Tunnel Boring Starts at Shivajinagar & Ends at Rashtriya Military School) TBM body lowered. Welding works in progress
Piling work in progress at MG Road Station
Excavation work in progress at Vellara Station
Tower Crane erection work in progress at Shivajinagar Station
Fabrication work in progress at
Lakkasandra Yard
8
8
Secant Piling works at North West side
UNDERGROUND WORKS - REACH 6
DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS
Contractor - M/s Larson & Toubro Ltd—RT-03
Sl No
RT-03 Progress Details as on 31.08.2020
1 Alignment of RT-3 Between Shivajinagar to Pottery Town
2 UG Works are divided into 4 Packages
Package-3
TBM Works Progress
Urja TBM (TBM No. 01): Tunnelling between Cantonment station to Shivajinagar has started mining from 14.08.2020 and so far completed 24 m of tunnelling out of 855 m (18 rings out of the total scope of 570 rings). Vindhya TBM (TBM No-2): Testing of various components for commissioning is in progress
3 Station Works Progress
Cantonment Station:
Hard rock excavation using controlled blasting technique is in progress. 44% of total excavation, i.e. 71,666 Cum is completed out of 1,62,000 Cum.
1078 Sqm. of PCC has been completed on south side. Launching area for launching of
second Tunnel Boring Machine is made ready.
Pottery Town Station:
Temporary support system with Secant piles: About 96.9% of the secant piles for station box and 100% of the secant piles for Ancillary Building are completed.
Excavation work for station box: About 11% i.e. 18,355 Cum completed out of 1,72,889 Cum.
Fabrication & Installation of first layer struts and waler beams are in progress
4 Peenya Casting Yard Precast Tunnel segment casting: 21.1% of tunnel rings i.e. 683 Nos. of tunnel rings
out of total requirement of 3244 Nos are completed.
View of Pottery Town work in progress
9
9
Track Works at a Glance
Contractor - M/s Texmaco Rail & Engineering Limited
Sl No Item Description Unit Track Plinth Casting
Sections Track Meters Reach 4
(August 2020) Reach 2
(August 2020)
1 Scope of Work Trm 12580 17628
2 Progress for the month Trm Nil 1220
3 Cumulative progress Trm 11700 7187
4 Access Handed over Trm 11700 14900
R-1 Extn: Flash Butt
Welding of Rails in progress
R-2 Extn: Track Preparation
Work near Jnanabharathi
Station