17
1 June 12, 2014 NRC Vendor Workshop Commercial- Grade Dedication of Software George Lipscomb Electrical Vendor Inspection Branch Division of Construction Inspection & Operational Programs Office of New Reactors

Commercial- Grade Dedication of Software · • Users of design and analysis software – Part 50 or 52 licensee / applicant – Nuclear vendors • Topics for another presentation

  • Upload
    others

  • View
    5

  • Download
    1

Embed Size (px)

Citation preview

1

June 12, 2014 NRC Vendor Workshop

Commercial-Grade

Dedication of Software

George Lipscomb Electrical Vendor Inspection Branch Division of Construction Inspection

& Operational Programs Office of New Reactors

2

Agenda

• Design & analysis software – Regulatory framework – Quality programs – Requirements and guidance – Revision 1 of EPRI 1025243 – Software QA implementation

• Questions

Courtesy SCANA

3

Target Audience

• Users of design and analysis software – Part 50 or 52 licensee / applicant – Nuclear vendors

• Topics for another presentation – Use of other types of software – Instrumentation & control software – Software development

Design and Analysis Software

• Finite element analysis • Piping analysis • Seismic analysis • Thermal and flow analysis • Nuclear physics • Electrical system analysis • Accident analysis

4

Regulatory Framework

• Safety-related structures, systems, and components (SSC)

• Basic component • Commercial grade item (CGI) • Dedication (CGD)

5

Software Quality Assurance

6

Affect safety function

Design and analysis software

Make

No safety function affect

Buy

QA Controls

Internal controls: Quality & technical External controls:

PO, audits, witness 4 Methods-

Inspect/test, survey, witness, or historical

Commercial-grade Dedication

Safety-related

Computer Program Use

Software QA Programs

• Control under Appendix B program • Few software-specific QA regulations • Control flexibility

– separate software control procedures – program vs. project requirements

• Details in NQA-1 or IEEE standards

7

Requirements

• Appendix B to Part 50 (QA) – Provisions of specific QA program

• Part 21 (reporting and dedication) • Part 50.5 (complete and accurate

information) • Plant licensing basis • Vendor purchase requirements

8

Design Software Guidance

• Potentially required: – NQA-1 Requirement 3 - design controls – NQA-1 Subpart 2.7 - software controls – NQA-1 Subpart 2.14 - dedication – Various IEEE standards

• Additional: – NQA-1 Subpart 4.1 - software QA guide

9

Dedication Guidance

• EPRI NP-5652 • ASME NQA-1-2008 with 2009 Addenda • Revision 1 of EPRI 1025243

10

Courtesy SCANA

EPRI 1025243

• Acceptance of commercial design & analysis software – Rev 0 issued June 2012 – Rev 1 issued December 2013

• Draft Guide (DG)-1305 conditionally endorses Rev 1

• Public comment expected late 2014

11

Methodology – 3 Scenarios

12 © Electric Power Research Institute

Methodology - CGD

13 © Electric Power Research Institute

Software Dedication Attributes

• Failure mechanisms – conceptual, arithmetic & interface errors

• Identification characteristics – product selection & identification

• Critical characteristics – physical, performance & dependability

14

Software QA Implementation

• Leverage existing control processes • Focus of affect on safety function • Consider data, computer program and

operating environment • Configuration control • Error control and Defect reporting • Access control / data security • Documentation

15

Considerations (NQA-1)

• Software acquisition (Subpart 2.7) • Configuration control (Subpart 2.7) • Problem reporting and corrective actions

(Subpart 2.7) • Design Analysis (Requirement 3)

16

Questions

George Lipscomb (301) 415-6838

[email protected]