WEBINAR SERIES | 20160
James Anderton, CPMP, CxA, LEED GAINDEPENDENT COMMISSIONING CONSULTING, LLC
BUILD. CONNECT. ACHIEVE.
Commissioning ChilledWater Systems
WEBINAR SERIES | 20161
Learning Objectives
PRESENTATION OVERVIEW
• Introduction to Cx CHWS
• Cx CHWS: Basic Concepts
• Cx CHWS: Process and Field Knowledge
• Functional Testing CHWS: Best Practices
• Q&A
WEBINAR SERIES | 20162
Cx Chilled Water Systems (CHWS)INTRODUCTION TO Cx CHWS
Properly commissioned building systems will provide:• Less problems inherited at the end of the project• Improved comfort and indoor air quality• Reduced construction and warranty issues• Complete documentation and critical system operation data• Better tenant and occupant satisfaction• Reduced O & M costs and increased reliability• Lower utility bills• Improved net operating Income• A benchmark for future system operating evaluation• Fully trained operating staff
WEBINAR SERIES | 20163
Cx Chilled Water Systems (CHWS)INTRODUCTION TO Cx CHWS
l AN EARLY START IS ESSENTIAL
l AQUIRE A FULL UNDERSTANDING OF:
l Current system design & approved documents
l Operational requirements (Owner vs FM vs Designer)
l Robust documentation (Effective use of Cx Documents)
l Connecting the gaps
l Owner expectations vs User Experience
l Engineer Equipment Schedule vs Controls Drawings
WEBINAR SERIES | 20164
Cx Chilled Water Systems (CHWS)INTRODUCTION TO Cx CHWS
l KNOWLEDGE OF THE Cx PROCESS
l Design phase
l Construction phase
l Acceptance phase
l Occupancy & warranty phase
l CERTIFICATION AND EXPERIENCE (CCP, CPMP)
WEBINAR SERIES | 20165
Cx Chilled Water Systems (CHWS)Cx CHWS: BASIC CONCEPTS
l REQUIRED KNOWLEDGE OF THE CxA
l Chilled Water System Design and Applications
l Knowledge of Chillers, Boilers, and CEP Safety
WEBINAR SERIES | 20166
Cx Chilled Water Systems (CHWS)Cx CHWS: BASIC CONCEPTS
l REQUIRED KNOWLEDGE OF THE CxA
l Knowledge of Pumps, Hydronics and Piping
l Knowledge of AHU´s, Heat Exchangers, and Ductwork
WEBINAR SERIES | 20167
Cx Chilled Water Systems (CHWS)Cx CHWS: BASIC CONCEPTS
l REQUIRED KNOWLEDGE OF THE CxA
l Knowledge of Condenser Water Systems (As applicable)
l Knowledge of Controls & Control Loops (Floating Setpoints)
WEBINAR SERIES | 20168
Cx Chilled Water Systems (CHWS)Cx CHWS: BASIC CONCEPTS
l IMPORTANT KNOWLEDGE & EXPERIENCE
l Engineering Applications, Fluid Dynamics, Psychometrics
l Construction Installation Methods and Materials
l Operational & Troubleshooting Skillsets
l Knowledge of Factory Startup Procedures (Warranty)
l Knowledge of Test & Balance Procedures (Air & Water)
WEBINAR SERIES | 20169
Cx Chilled Water Systems (CHWS)Cx CHWS: BASIC CONCEPTS
l FIELD EXPERIENCE (I went to College… How do I get it?)
l Construction installation & management
l Architectural & Engineering ConstructionAdministration
l TAB, Controls & Service Technician Work
WEBINAR SERIES | 201610
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
l LAYING THE FOUNDATION FOR EFFECTIVE CX
l Cx CHWS requires a simple but well defined processto catch and track issues (Good Cx will enable closeout of issues timely)
l Timeliness of response, reports, and document delivery
l Follow up, Follow up, and more Follow up
l Properly Executed Cx Process = Efficient CHWS $$$
l Poorly executed Cx Process = Failure to protect Clients
(If you fail to plan – then you plan to fail!)
WEBINAR SERIES | 201611
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
l CREATING / CAPTURING ACCURATE & USEFUL DATA
l Detailed Startup & Prefunctional Checklists (Non-Generic)
l Submittal Process (Define Registries)
l Making good use of the Cx Plan (Simple language)
l Step by step instructions (When, Where, Who & What)
l Communication protocols
l Ensure task items for such milestones as Start-upare clearly defined for each Team member whom isresponsible
WEBINAR SERIES | 201612
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
l EFFECTIVE CONSTRUCTION PHASE Cx
l Installation Observations
l Equipment on Site = Verification Process (Timeliness)
l Study up on the systems to be observed
l Know typical issues (Problem Areas)
l Focus on most common issues 1st
WEBINAR SERIES | 201613
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
Make up Water Pressure Regulator/Relief Valve Sizingl (Incorrect / Under sized)
WEBINAR SERIES | 201614
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
l EFFECTIVE CONSTRUCTION PHASE Cx
l Coming out to the field prepared (Know More!)
l Consistency, Methods and Thoroughness
l Consolidated Floor Plans (Half-Size)
l System & Zone Maps Complete with Room Names
l Safety Gear
l Physically Fit
l High Resolution Camera
WEBINAR SERIES | 201615
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
Safety, Fitness, and Awareness needed at all times during Cx.CHWS are more complex and larger. There is more that can gowrong if you are not prepared to stay vigilant on the jobsite.
WEBINAR SERIES | 201616
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
l TYPICAL AND CRITICAL FIELD ISSUES
l Protection of System Inlets & Outlets
l AHU SA/RA/OA/EA Openings, Coil Connections,Pumpinlets, Motor openings, Cooling Towers & Basins,Ductwork & Piping
l Protection of Staged equipment & during prepand assembly
l Improper use of equipment during construction
WEBINAR SERIES | 201617
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
l TYPICAL AND CRITICAL FIELD ISSUES
l Piping Connections
l Proper Welds or Joint Types
l Piping Pressure
l Piping Supports & Vibration Isolation
l Proper Fasteners, Saddles, Die-Electric separation
l Approved Vibration Isolation (Noisy Pipes)
l Insulation Requirements
WEBINAR SERIES | 201618
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
Piping insulated and protected with sleeve for protection on exteriorapplications
Clearances &Piping Supports
WEBINAR SERIES | 201619
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
Improperly supported CHW Supply and Return Piping duringconstruction. Unnecessary load on Chiller Marine Box.
Potential fordamage to chillerinlet/outlets.
WEBINAR SERIES | 201620
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
l TYPICAL AND CRITICAL FIELD ISSUES
l Comprehensive Flush-out Plan
l Develop Early (As soon as HVAC contractor is hired)
l Ensure plans include specific step by step procedures
l By-pass Coils during initial flushing
l Schedule Flushing / Chemical Treatment (timeliness)
l Flush Water Source (Cleanliness)
l Drip Legs & Strainers (Clean out Included in Plan)
l Dead Ends (Maintaining Flow)
WEBINAR SERIES | 201621
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
l TYPICAL AND CRITICAL FIELD ISSUES
l Chemical Treatment Addition Plan
l Develop Early (As soon as HVAC contractor is hired)
l Ensure plans include specific step by step procedures
l Remove By-passed Coils provide finished flushing
l Drain system Fully, re-flushing till water is crystal clear
WEBINAR SERIES | 201622
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
l TYPICAL AND CRITICAL FIELD ISSUES
l Chemical Treatment Addition Plan
l Maintaining Circulation while adding chemical treatment
l Ensure all valves are open (included in Cx Flush Plan)
l All feed control equipment must be in place
l Certified Contractors & TAB
WEBINAR SERIES | 201623
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
Shot feeder supply and return lines not insulated and condensationforming/dripping 12-16 from connection at CHWS
WEBINAR SERIES | 201624
Cx Chilled Water Systems (CHWS)Cx CHWS: PROCESS & FIELD KNOWLEDGE
l TYPICAL AND CRITICAL FIELD ISSUES
l Locations of Valves & Sensors
l Design drawing locations vs submittals
l Test & Balance Results (Troubleshooting)
l Verification of Sensor Readings during TAB
WEBINAR SERIES | 201625
Cx Chilled Water Systems (CHWS)FUNCTIONAL TESTING: BEST PRACTICES
l Overall System Level Testing
l Goal is for test of all components on a system level
l Ensure individual components are working 1st
l Using BAS sensors? What is the TAB Report Status?
l Controls Loops (Interdependencies & Fine Tuning)
l Tune only one system at a time – either heating, orcooling. Do not try to tune both at the same
l Cascading upwards from sub-systems to parent systems
l Regardless of CxA preference: No PFC – No FPT
WEBINAR SERIES | 201626
Cx Chilled Water Systems (CHWS)FUNCTIONAL TESTING: BEST PRACTICESl Energy Management Controls Systems (BAS)
l Cascading Controls Loops (interdependencies)(Proportional + Integral + Derivative = PID)
P =How far away from setpointI =Time away from setpointD =Approach/Decay speed to/from setpointCommon Factors contributing to an unstable system:• Too much gain (too narrow a throttling range) for a
proportional system.• The controlled variable has too much capacity to be
reasonably controlled.• Incorrect install – Often, the sensor providing feedback is
located in a remote location.• Too much lag time (delay) in the response of the system.
WEBINAR SERIES | 201627
Cx Chilled Water Systems (CHWS)FUNCTIONAL TESTING: BEST PRACTICES
Chiller, Boilers, Cooling Tower Testing
l Senor Locations & Readings
l Safeties, Interlocks,Alarms
l Unit Capacity (Part-Load vs Full Load)
l Staging (Lead/Lag & Demand Response per AHU zone)
l Water Temperature Reset
l Control Accuracy and Stability (Control Loops / Hunting)
The system should not require the controlled device tooperate at an extreme position – this is an indication of lostcontrol.
WEBINAR SERIES | 201628
Cx Chilled Water Systems (CHWS)FUNCTIONAL TESTING: BEST PRACTICES
l Pumping System Testing
l Senor Locations & Readings
l Safeties, Interlocks,Alarms
l Pump Capacity (Part-Load vs Full Load)
l Actuation & Sequencing
l Setpoints and Pressure Reset
l Control Accuracy and Stability (Control Loops / Hunting)
WEBINAR SERIES | 201629
Cx Chilled Water Systems (CHWS)FUNCTIONAL TESTING: BEST PRACTICES
l AHU System Testing
l Senor Locations & Readings
l Safeties, Interlocks,Alarms (EA/RA/OA)
l SATemperature Control (Part-Load vs Full Load)
l Actuation & Sequencing
l Setpoints, Static Pressure Reset
l CHW Valve Control and Water Temp Reset
l Control Accuracy and Stability (Control Loops / Hunting)
WEBINAR SERIES | 201630
Cx Chilled Water Systems (CHWS)O&M: BEST PRACTICES
l Training provided to facilities maintenance staff (FMS)• Understanding & conveying maintenance impacts to the
owner• Developing meaningful operational troubleshooting and
system maintenance procedures• Teaming with the engineer of record, contractor &
manufacturer to yield better results
WEBINAR SERIES | 201631
Cx Chilled Water Systems (CHWS)O&M: BEST PRACTICES
l Typical Chiller Maintenance Tasks
• Check setpoints• Check for fouling of evaporator and condenser tubes• Check water quality• Check for leaks• Conduct oil analysis and change as necessary• Check strainers and valves• Check electrical connections
WEBINAR SERIES | 201632
Cx Chilled Water Systems (CHWS)O&M: BEST PRACTICES
l Typical Cooling Tower Maintenance Tasks
• Setup a testing program/schedule for water quality• Setup strict schedule of water treatment and blown down to
prevent buildup of mineral deposits and premature erosion• Setup a schedule for periodic cleaning• Check condition of fill, wood frame, nozzles, water level
control and degree of approach.• Check for leaks
WEBINAR SERIES | 201633
Cx Chilled Water Systems (CHWS)O&M: BEST PRACTICES
l Typical Pump Maintenance Tasks
• Check for Vibration• Check Bearing temperature• Check for unusual noise• Check for entrapped air at impeller (Cavitation effects)• Check flow @ design RPM and FLA• Check for leaks
WEBINAR SERIES | 201634
Thank YouJames Anderton, CPMP,CxA, LEED GAManaging PrincipalINDEPENDENT COMMISSIONING [email protected]
WEBINAR SERIES | 2016