commissioning of hydro.ppt

Embed Size (px)

Citation preview

  • 7/28/2019 commissioning of hydro.ppt

    1/59

    COMMISSIONING

    HYDRO POWER STATION

  • 7/28/2019 commissioning of hydro.ppt

    2/59

  • 7/28/2019 commissioning of hydro.ppt

    3/59

    Dam

    Reservoir

    Power intake (Penstock)

    Power house

    Turbine

    Draft tubeMain inlet valve

    Generator

    Bus Duct

    Field Excitation System

    Governing System

    SCADA System

    Station Transformer

    Balance of PlantProtection system & switchgear

    LV/ HV distribution

    DC, UPS Battery

    Switch Yard

    Following are the main components of a Hydroelectric Power Plant

    INTRODUCTION

  • 7/28/2019 commissioning of hydro.ppt

    4/59

    Dome

    Stator

    Rotor

    Generator Shaft

    Turbine Shaft

    Spiral Casing

    Stay Ring

    Runner

    Draft Tube

  • 7/28/2019 commissioning of hydro.ppt

    5/59

  • 7/28/2019 commissioning of hydro.ppt

    6/59

  • 7/28/2019 commissioning of hydro.ppt

    7/59

  • 7/28/2019 commissioning of hydro.ppt

    8/59

  • 7/28/2019 commissioning of hydro.ppt

    9/59

    COMMISSIONING

    Definition

    Testing of new equipments to checkits conformity with contractualspecifications, as well as operation ofthe equipment until formallyaccepted by the Customer.

    Commissioning usually occurs afterfirst erection of a new unit.

  • 7/28/2019 commissioning of hydro.ppt

    10/59

    Commissioningactivities consistof various tests:

    Pre-commissioning tests

    Prior to filling waterways

    After filling waterways

    Initial Run test

    Test Run

    COMMISSIONING

  • 7/28/2019 commissioning of hydro.ppt

    11/59

    READINESS CRITERION

    Commissioning activities in hydro project begin with the filling of waterways on

    the down stream side (common tailrace) and up stream side (Head Race or

    Penstock) of the machine. This implies readiness of hydro set which broadlycomprises of following equipments and their readiness criteria :

    1. Draft Tube and Liner, Spiral casing, Tail Race Channel, Penstock and gates etc. for

    their erection and checks from the point of view of cleanliness, civil grouting work for

    the hollow portions between metal and concrete contact surfaces etc.

    2. It is to be ensured that there is no impediments in the free flow of water from any

    projecting lumps of concrete/reinforcement rods etc.

    3. The grouting plugs have been welded and flush grinded as per Drawing requirement

    and no obstruction exists from any local bending of metallic liners etc. in the water

    path.

    4. Painting work of underwater parts with black anticorrosive paint has been completed.

  • 7/28/2019 commissioning of hydro.ppt

    12/59

    The Machine itself has been made ready mechanically along with its auxiliaries. This will

    include the following major equipments/systems/works and other preparations :

    Turbine & Turbine Pit :

    1. Runner blade and chamber clearances have been checked and found OK to ensure that

    no rubbing is likely to occur during start up and running.

    2. Air inflated repair seal of Turbine shaft is OFF and cooling water to working seal willbe available when CW system is charged.

    3. Turbine bearing oil is at proper level neither too high nor too low let the drawing be

    followed at this stage. Keep record of pumping holes in the skirt if provided-whether

    plugged and how many.

    4. Manual/Auto greasing of guide vanes etc. has been done for smooth operation.

    5. Easy mobility along with sufficient lighting both AC/DC provided in the pit.

    READINESS CRITERION

  • 7/28/2019 commissioning of hydro.ppt

    13/59

    6. Dry stroking of guide apparatus/ MIV have been done upto full rated oil pressure of

    OPU through governor. Record Opening/Closing and damping times.

    7. Dowelling work etc. of bearing housing etc. has been completed.

    8. Fulfillment of all requirements given in O&M manuals/check lists of the project to

    be ensured.

    9. De-watering of draft tube checked twice by closing the draft tube gates.

    10. Turbine top cover drainage system is operational and in Auto to avoid turbine pit

    flooding during first filling of TRC and subsequently during penstock filling etc.

    Preferably additional pumping arrangement, not dependent on Electric Supply (i.e.

    Air Operated) be provided as quantity of leakage water from shaft, Guide vane cup

    seals, etc. is not known at this time. This is more necessary when starting a machineafter a long delay after erection.

    READINESS CRITERION

  • 7/28/2019 commissioning of hydro.ppt

    14/59

    Generator & Generator Barrel :

    1. Generator and its sub assemblies have been fully erected as per drawing and cleaned

    with dry compressed air/cloth. Check top and bottom air guide clearances whichshould be at least 8-10 mm ( as per drawing requirement) from the rotor fan blades.

    2. Stator/Rotor gap must be free from any foreign object which is usually checked by

    taking a rope all around the gap along the full height of the stator core.

    3. Check and ensure that Generator barrel/bracket areas are free from foreign objects,hanging wires/cables, loose electrical connections, loose clamps etc.

    4. Bearing vapour seal segments may not be assembled in position during initial runs to

    avoid likelihood of rubbing until performance in terms of vibration and wobble is

    proved up to full speed (This is not applicable for vapour seals of wool felt type).

    5. Initial bedding of slip ring carbon brushes, cleaning of slip rings etc. has been done.

    Carbon brushes to be kept disengaged from the slip rings, during initial runs as no

    excitation is to be given during this time. Should be in for proper bedding .

    READINESS CRITERION

  • 7/28/2019 commissioning of hydro.ppt

    15/59

    6. Dowelling of stator frame/brackets etc. has been done and secondary concreting of

    Stator and lower bracket foundations have fully cured. Epoxy grouting of foundationbolts to be ensured. Tightening of all bolts and their locking particularly of the

    rotor/rotor lead clamps/pole to pole joints etc. to be carefully checked.

    7. Generator Barrel water mist Fire Extinguishing system commissioned and kept ready in

    manual/Auto mode, which is to be switched on prior to voltage build up/

    synchronisation/loading.

    8. Brake system is already tested for reliable lifting and release 10 times from HP

    compressor/pressure reducer air system or L P air system along with Limit Switch

    operation for indication/control. Free operation of brakes to be ensured. Auto operation

    of Brake is to be disabled during initial period (Brake Air Pressure should be adjusted

    for 4-5 Kg/cm2

    ). Brakes should be applied at a speed as given in design which is usually20 to 25% of rated speed). Required oil should be filled up in air filter unit.

    READINESS CRITERION

  • 7/28/2019 commissioning of hydro.ppt

    16/59

    9. Generator bearings oil should be at proper level as per Drawing and this should be

    marked in gauge glass. Operation of low/high level float switches should be checked.

    10. Performance of HS Lube system to be proved. Check lifting of Rotor from HS lube

    pressure by 4 dial gauges placed at X and Y positions i.e at 4 points to know

    amount and uniformity of lift all around. The HS Lube pressure should not exceed

    specified design value. Safety relief valve to be adjusted depending on the pressure

    required for jacking. HP lub oil pressure switches/gauge to be adjusted for normal &

    low pressure. Ensure no loose connections in the electrical circuits to avoid sparking

    and consequent fire hazard in these enclosed spaces.

    READINESS CRITERION

    PRE REQUISITES FOR

  • 7/28/2019 commissioning of hydro.ppt

    17/59

    1. 440 V 3 Phase AC supply

    2. 240 V 1 Phase A.C. supply

    3. 220 V DC or 110 V D.C. Power supply system

    4. 48 V DC Power supply system

    5. Dewatering, Drainage and leakage collection system and their pumping arrangement.

    6. 11 KV or 13.75 KV along with cable etc. for commissioning of excitation system.

    7. 24 V DC power supply system.

    8. The intake gates, draft tube gates and butterfly valves are tested for safe and reliable

    operation and equipped with operator personnel and telephonic connection .

    9. Oil supply system.

    10. Compressed air system.

    11. Completion of cable laying , termination @ earthing

    12. 240 V AC UPS supply.

    PRE- REQUISITES FOR

    COMMISSIONING

    PRE REQUISITES FOR

  • 7/28/2019 commissioning of hydro.ppt

    18/59

    13. Readiness of water conducting system .

    14. Civil works in the vicinity of active and sensitive electrical and mechanica

    machinery/equipment are finalized. Floors are clean and dry.

    15. Station earthling system is in full and reliable condition.

    16. Main fire fighting system for the power house cavern in safe operating

    condition, including the portable fire extinguishers.

    17. Ventilation, illuminations, communication, and Air-conditioning available

    on a permanent base.18. Readiness of protective covers, guards ladders and covering of floor holes

    and pits.

    PRE- REQUISITES FOR

    COMMISSIONING

    PRE COMMISSIONING

  • 7/28/2019 commissioning of hydro.ppt

    19/59

    PRE-COMMISSIONING

    TEST/CHECKS

    Pre-commissioning

    Tests:

    Test between completion oferection of the equipment andinitial run.

    Tests/Checks prior to filling

    waterways Tests/Checks after filling of

    waterways

    TEST/CHECKS PRIOR TO

  • 7/28/2019 commissioning of hydro.ppt

    20/59

    TEST/CHECKSPRIORTO

    FILLINGWATERWAYS1. Inspection of all the turbine waterways and removal of all

    foreign or loose objects.

    2. Calibration of scales for wicket gate opening and whereapplicable, for runner blades, needles and deflectorsincluding their cam relationships; and also measurementof clearances.

    3. Operation of pressure oil units, MIV, governors, automaticand manually operated starting and stopping devices andsignaling devices.

    4. Oil levels and pressures in governing system; Condition ofall oil filters.

    TESTS/CHECKS PRIOR TO

  • 7/28/2019 commissioning of hydro.ppt

    21/59

    TESTS/CHECKSPRIORTO

    FILLINGWATERWAYS

    5. Protective devices such as oil level and temperature alarms and

    relays, with adjustment if needed.

    6. Times of opening and closing of governing elements, i.e. wicket

    gates, runner blades of turbines with movable blades, needles

    and deflectors of impulse turbines.

    7. MIV opening and closing times.

    8. Bearing and seal clearances and functioning of hydrostatic

    lubrication system.

    TESTS/CHECKS PRIOR TO

  • 7/28/2019 commissioning of hydro.ppt

    22/59

    TESTS/CHECKSPRIORTO

    FILLINGWATERWAYS

    9. Operation of drainage pumps and dewatering pumps.

    10. Oil, grease and water supply to all bearings and seals

    requiring lubrication or cooling.

    11. Operation of braking system of the unit.

    TESTS/CHECKS

  • 7/28/2019 commissioning of hydro.ppt

    23/59

    TESTS/CHECKS

    AFTERFILLINGWATERWAYS

    1. The Tail water gate shall be opened first after filling the draft

    tube and spiral case up to tail water level through a fillingvalve of the draft tube gates. Check for leaks is to be made.The whole waterway should be filled slowly and manuallythrough a bypass valve of the penstock.

    2. Operation of emergency protection devices which actuatesthe intake gate/MIV and closure of guide vanes and stoppageof machine is to be checked.

    3. If the protective devices and emergency closing system work

    satisfactorily, and no unusual leakage or deformation isobserved, Initial run of the Machine can be initiated.

  • 7/28/2019 commissioning of hydro.ppt

    24/59

    INITIAL RUN

    After the permission for initial run, locking devices and brakes are

    released and the turbine wicket gates or needles are openedunder manual control, slowly as per manufacturersrecommendations and bring the speed up to at least the minimumstated value.

    If any noise, scraping or other abnormal phenomena is observed,the unit should be shut down immediately and thorough inspectionis to be carried out to find out the cause of the problem and rectifythe same.

  • 7/28/2019 commissioning of hydro.ppt

    25/59

    Time

    Unit speed

    Servomotor stroke

    Temperature of bearing

    Shaft run out

    MeasurementsItems:

    Tachometer

    Dial indicatorInstruments to

    be used:

    INITIAL RUN

    TEST RUN

  • 7/28/2019 commissioning of hydro.ppt

    26/59

    TEST RUN

    Mechanical Spinningwithout Excitation

    Spinning with Excitation

    Synchronization with thegrid

    Load run and LoadRejection Tests

    Test

    Runconsistsof :

    MECH SPINNING WITHOUT

  • 7/28/2019 commissioning of hydro.ppt

    27/59

    MECH. SPINNINGWITHOUT

    EXCITATION

    1. The unit is kept under manual control at or above starting

    speed until bearing temperatures are stabilized.

    2. If any temperature is excessive or increases too rapidly, the

    unit shall be shut down and the causes of this phenomenon is

    to be investigated and corrected.

    3. If all goes well, the unit speed shall be increased in

    prearranged steps up to the rated value, remaining at each

    successive speed until the rate of rise of all bearing

    temperatures is satisfactory to the manufacturer'srecommendation.

    MECH. SPINNINGWITHOUT

  • 7/28/2019 commissioning of hydro.ppt

    28/59

    During each speed step of test run, at least the followingmeasurements / observations should be made:

    1. Deformation of covers and bearing supports

    2. Noise or vibration in the turbine and/or generator

    3. Operating conditions for the oil pressure and other pumps.

    4. Condition of oil in the bearings and pressure oil systems. If

    water is observed in oil, the leaks shall be located andeliminated. If oil foaming is observed, the cause shall belocated and eliminated.

    5. Temperatures of bearings and lubricating oil.

    6. Shaft run out at turbine and generator bearings and axialdisplacement of rotating parts is measured.

    7. At some agreed speed value, the action of braking systemshall be checked.

    M C . S GW OU

    EXCITATION

    MECH. SPINNINGWITHOUT

  • 7/28/2019 commissioning of hydro.ppt

    29/59

    Tachometer

    Vibration meter (Structure)

    Dial indicator

    Thermometer

    Instrumentsto be used:

    . SEXCITATION

    SPINNING WITH EXCITATION

  • 7/28/2019 commissioning of hydro.ppt

    30/59

    SPINNINGWITH EXCITATION After bearing run, the machine is prepared for short

    circuit test.

    For this test, we do three phase shorting at generator

    terminal then the excitation is increased from zero up

    to the full load stator current.

    During this test, operation and stability test of

    differential protections are also checked.

    After SCC test, we go for high voltage test for statorwinding.

    BASIC TESTCIRCUITFOR SCC TEST

    SCC TEST

  • 7/28/2019 commissioning of hydro.ppt

    31/59

    SCC TEST

    A

    B

    SCC TEST

  • 7/28/2019 commissioning of hydro.ppt

    32/59

    C

    SCC TEST

    SCHEMATICCONNECTIONDIAGRAMFOR

  • 7/28/2019 commissioning of hydro.ppt

    33/59

    SCC TEST

    HV TEST FOR STATOR WINDING

  • 7/28/2019 commissioning of hydro.ppt

    34/59

    HVTESTFOR STATORWINDING Used for testing the dielectric strength of generator

    stator winding insulation.

    For less than 10MW, test voltage (r.m.s.) shall be1000V+2*Rated voltage; subject to minimum of 1.5kV.

    For machines with a rated voltage 6 kV or greater,

    when power frequency equipment is not available, then

    by agreement a DC test may be carried out at a voltage

    1.7 times the r.m.s. values to be chosen in case of ACtest.

    For more than 10 MW, Test Voltage (r.m.s.) shall be

    For voltage less than and equal

    to 24kV

    2*Rated voltage + 1000 V

    For voltage more than 24kV Subject to agreement

    OCC TEST

  • 7/28/2019 commissioning of hydro.ppt

    35/59

    OCC TEST

    After successfully completing the HV test, OCC test is

    carried out.

    In OCC test, excitation cable is restored and voltage isbuild up to rated voltage in steps of 1KV. Then, Open

    Circuit Characteristic Curve is drawn.

    Operation of Stator earth fault protection is also checked by

    creating actual earth and performance test of all voltage

    relays is also carried out .

    BASIC TESTCIRCUIT

    FOR OCC TEST

    SCHEMATICCONNECTIONDIAGRAMFOR

  • 7/28/2019 commissioning of hydro.ppt

    36/59

    OCC TEST

    SYNCHRONIZATIONWITHTHE GRID

  • 7/28/2019 commissioning of hydro.ppt

    37/59

    Phase sequence of Generator voltage and Gridvoltage must be the same.

    Two voltages must be equal, i.e. IV1I - IV2I=0.

    The generator frequency must be nearly equal tothe Grid frequency, i.e. f1- f2 0.

    At the instant of synchronizing, the two voltagesmust be almost co-phasal, i.e. 12 0.

    The

    followingconditionsmust besatisfied:

    Finally the machine is synchronized with the grid at

    the partial load.

    SYNCHRONIZATIONWITHTHE GRID

  • 7/28/2019 commissioning of hydro.ppt

    38/59

    The degree of criticality of these parameters are in thefollowing order:

    ,V,f.

    The inertia of the incoming machine being very smallagainst that of the grid, even with considerable f, themachine will easily be pulled into synchronism.

    Voltage difference, if large, can result in heavy exchange ofVAR and can result in voltage fluctuations, if large enoughleading to instability.

    Large can result in heavy exchange if MW, often goodenough to cause torsional damage to the shaft system.

    LOAD RUN ANDLOAD REJECTION TESTS

  • 7/28/2019 commissioning of hydro.ppt

    39/59

    LOAD REJECTION TESTS

    When the generator and switching equipment has been

    declared ready for operation , the unit is synchronized.

    During the load rejection tests, all necessary precautions shallbe taken to ensure that rated values of penstock andturbine stresses will not be exceeded. Such precaution

    may include setting governor timing.

    When adjustments are made on governor or regulating devicesall tests which might be affected by the adjustment shallbe repeated.

    LOAD RUN ANDLOAD REJECTION TESTS

  • 7/28/2019 commissioning of hydro.ppt

    40/59

    To check the output of the unit with an agreedaccuracy.

    To check the unit for instability, vibration orcavitations in the range of guaranteed loads.

    To check the functioning of governor andregulating devices, as well as that of the entireunit.

    To determine the momentary pressure and speedvariations of the unit and to find their extremevalues. To adjust the closing times of the wicketgates, needle valves and deflectors to minimizeover speeding of the unit within the permissiblelimit of pressure variation

    To permit testing of the operation of otherhydraulic and electrical equipment, includingprotection and other automatic devices.

    PURPOSES:

    LOAD REJECTION TESTS

    LOAD RUN ANDLOAD REJECTION TESTS

  • 7/28/2019 commissioning of hydro.ppt

    41/59

    PROCEDURE:

    The load shall be increased in steps and load rejection test made at

    successively higher loads up to the maximum expected to be placedon the unit. For example: rejections may be made at 25%, 50%, 75%and 100% of the rated load as well as from the maximum load thatmay be agreed upon.

    Two rejections shall be made at each load. One rejection is made

    under governor control to no load gate or needle opening, the othermay be an emergency shutdown by stop solenoid.

    If specified, load rejection tests shall be made by means of theemergency valve or by any other emergency device.

    After the completion of each load rejection test, the pressure rise andturbine speed rise data shall be analyzed to ensure that the specifiedsafe limits will not be exceeded during the next higher load rejectiontest.

    LOAD REJECTION TESTS

    LOAD RUN ANDLOAD REJECTION TESTS

  • 7/28/2019 commissioning of hydro.ppt

    42/59

    Observations, Measurements and Recordings:

    LOAD REJECTION TESTS

    Head and tail water level

    Generator output.

    Wicket gate or needle opening (where applicable)

    Pressure at turbine inlet and outlet

    Pressures and levels in oil pressure systems

    Operating times of oil pressure pumps.

    Temperatures in bearings.

    Noise levels, if values are specified in thecontract.

    Abnormal noises if any.

    Vibration and other displacement of rotating andfixed parts.

    Action of air-admission devices if any.

    Applicablefor SteadyState

    Operation:

    LOAD RUN ANDLOAD REJECTION TESTS

  • 7/28/2019 commissioning of hydro.ppt

    43/59

    Observations, Measurements and Recordings:

    LOAD REJECTION TESTS

    Head and tail water levels Generator output

    Strokes and closing times of wicket gates orneedles where applicable.

    Pressure at the turbine inlet and outlet.

    Level variations at intake and surge tanks

    Pressure drop in the oil pressure system in theprocess of governing, and variation of level inthe oil pressure reservoir.

    Noise levels, if values are specified in thecontract.

    Abnormal noises, if any.

    Vibration and other displacement of rotating andfixed parts.

    Action of braking jets in case of Pelton turbine.

    Load

    rejectionand

    subsequenttests:

    COMMERCIAL RUN

  • 7/28/2019 commissioning of hydro.ppt

    44/59

    COMMERCIAL RUN

    After meeting all the

    contractual requirements of

    operation, the machine canbe declared ready for

    Commercial Run.

  • 7/28/2019 commissioning of hydro.ppt

    45/59

    ILLUSTRATIVE

    PHOTOGRAPHS

    Generator Barrel & Turbine Pit

  • 7/28/2019 commissioning of hydro.ppt

    46/59

  • 7/28/2019 commissioning of hydro.ppt

    47/59

  • 7/28/2019 commissioning of hydro.ppt

    48/59

    STATOR SECTION

  • 7/28/2019 commissioning of hydro.ppt

    49/59

    GENERATOR

    ROTOR

    LOWERING OF ROTOR

  • 7/28/2019 commissioning of hydro.ppt

    50/59

  • 7/28/2019 commissioning of hydro.ppt

    51/59

    DRAFT TUBE

    ERECTION

  • 7/28/2019 commissioning of hydro.ppt

    52/59

    STAY RING

    SPIRAL CASING

  • 7/28/2019 commissioning of hydro.ppt

    53/59

    HYDROSTATIC

    TESTING

    TURBINE RUNNER

  • 7/28/2019 commissioning of hydro.ppt

    54/59

    TURBINESHAFT

  • 7/28/2019 commissioning of hydro.ppt

    55/59

    TOP COVER & TURBINEASSEMBLY

  • 7/28/2019 commissioning of hydro.ppt

    56/59

    ASSEMBLY

    LOWER BRACKET

  • 7/28/2019 commissioning of hydro.ppt

    57/59

    LOWER BRACKET

    ASSEMBLY OF MIV

  • 7/28/2019 commissioning of hydro.ppt

    58/59

    BUTTERFLY TYPE SPHERICAL TYPE

  • 7/28/2019 commissioning of hydro.ppt

    59/59