23
1 BROOKHAVEN SCIENCE ASSOCIATES Commissioning Plans F. Willeke 9 th ASAC Meeting for NSLS-II Project February 1-2, 2012

Commissioning Plans

  • Upload
    krikor

  • View
    61

  • Download
    0

Embed Size (px)

DESCRIPTION

Commissioning Plans. F. Willeke 9 th ASAC Meeting for NSLS-II Project February 1-2, 2012. Outline. Status of Preparations for LINAC Commissioning Status of Booster Commissioning Preparations Preparations for Storage Ring Commissioning Commissioning Database - PowerPoint PPT Presentation

Citation preview

Page 1: Commissioning Plans

1 BROOKHAVEN SCIENCE ASSOCIATES

Commissioning Plans

F. Willeke

9th ASAC Meeting for NSLS-II Project

February 1-2, 2012

Page 2: Commissioning Plans

2 BROOKHAVEN SCIENCE ASSOCIATES

Outline

• Status of Preparations for LINAC Commissioning

• Status of Booster Commissioning Preparations

• Preparations for Storage Ring Commissioning

• Commissioning Database

• High Level Application Development for Commissioning

• Commissioning Retreat

• Summary

Page 3: Commissioning Plans

3 BROOKHAVEN SCIENCE ASSOCIATES

Timeline

LINAC Commissioning: April’12 - June ‘12 (BL: Sep ‘12)

Booster Commissioning: Feb’13 - June ‘13 (BL: July ‘13)

Storage Ring Commissioning without ID: June’13 - Nov ‘13 (BL: Nov ‘13)

Storage Ring Commissioning with ID: Feb ’14 - April ‘14 (BL: Feb ‘14)

Page 4: Commissioning Plans

4 BROOKHAVEN SCIENCE ASSOCIATES

Procedure

LINACLINAC

BoosterBooster

Page 5: Commissioning Plans

5 BROOKHAVEN SCIENCE ASSOCIATES

Accelerator Commissioning and Operation Authorization

Storage RingStorage Ring BoosterBooster

LINACLINAC

Page 6: Commissioning Plans

6 BROOKHAVEN SCIENCE ASSOCIATES

Status of Preparations for LINAC Commissioning

• LINAC installation nearly complete

• Component Testing in Progress

Modulators have been tested successfully

• Instrument Readiness Review Committee (internal) appointed (chaired by R. Heese) which is certifying technical readiness

• ARR committee appointed

• ARR Date fixed (27-29 Febr. 2012)

Page 7: Commissioning Plans

7 BROOKHAVEN SCIENCE ASSOCIATES

Status of Documentation for LINAC Commissioning

• LINAC Commissioning Authorization Base approved by BSHO in May 2011.

• Last missing requirement is the technical and organizational readiness certified by a successful Accelerator Readiness Review (ARR) . The LINAC ARR schedule for February 27-29 2012.

• Most of the Documentation which forms the Authorization Base in place or is being circulated for final signatures

Page 8: Commissioning Plans

8 BROOKHAVEN SCIENCE ASSOCIATES

Status of Documentation for LINAC Commissioning

Page 9: Commissioning Plans

9 BROOKHAVEN SCIENCE ASSOCIATES

LINAC Commissioning Sequence

Excerpt from LINAC Commissioning Plan

Page 10: Commissioning Plans

10 BROOKHAVEN SCIENCE ASSOCIATES

LINAC Commissioning Sequence

Page 11: Commissioning Plans

11 BROOKHAVEN SCIENCE ASSOCIATES

LINAC Commissioning Sequence

Page 12: Commissioning Plans

12 BROOKHAVEN SCIENCE ASSOCIATES

LINAC Commissioning

• RI is responsible for LINAC commissioning and demonstrating the specified performance

• Commissioning safety is in the responsibility of Photon Sciences. NSLS-II scientist will always be present during commissioning

• A trainee from the Operations Group will attend LINAC commissioning Shifts to assure a smooth transition from commissioning to operations

• LINAC commissioning will be performed form the injector control room in the injector service building

• A token systems is being prepared which allows to handover the LINAC operations to the NSLS control room for routing operations such as vacuum and RF conditioning. This token will make sure that there is always only one well defined control center which carries the responsibility for operational safety.

Page 13: Commissioning Plans

13 BROOKHAVEN SCIENCE ASSOCIATES

After in the tunnel checkout has been done, and once beam is available in the linac, the following beam-based checkout will be done. This list assumes that all magnets have had their fields fully standardized, a reasonable quality electron beam is available from the injector, some rough beam steering and linac RF phasing has been accomplished, and any beam obstruction issues have been solved.

• Generate betatron oscillations in each plane, using well calibrated steering coils, to verify BPM polarities, local focusing optics, and possible BPM scaling errors.

• Using well-calibrated steering coils, verify the scaling of all profile monitors (OTR, YAG), by verifying the proper induced centroid shifts in each plane.

• Repeat above, but for BPMs and profile monitors at high dispersion points (e.g., energy slit, VF2), using reasonably well known RF phase or amplitude changes.

• BPM and other charge readings (such as ICT, FCT and Faraday cup) should be uniformly calibrated based on a well known reference.

• After the checkout, the electron beam measurements and corrections can be done in the transport line.

Preparation for LTB commissioning

Page 14: Commissioning Plans

14 BROOKHAVEN SCIENCE ASSOCIATES

LTB operation panelhttp://code.nsls2.bnl.gov/hg/opis/boy

Page 15: Commissioning Plans

15 BROOKHAVEN SCIENCE ASSOCIATES

PS

Page 16: Commissioning Plans

16 BROOKHAVEN SCIENCE ASSOCIATES

Preparation of Booster Commissioning

The lab safety committee has approved the Booster SAD and ASE. Build-up of the Booster Commissioning Authorization Base is progress.

Page 17: Commissioning Plans

17 BROOKHAVEN SCIENCE ASSOCIATES

Commissioning Control Room

* Control room: top view

Located in the NSLS-II injector service building. Is close to injector, RF, and computer room hardware. Will be used for LINAC, Booster, Transferline and initial storage ring commissioning

Page 18: Commissioning Plans

18 BROOKHAVEN SCIENCE ASSOCIATES

Commissioning Staff

LINAC Commissioning Coordinator: Ray Fliller, Commissioning staff: RI personnel, members of the RF group; members of the operations group

Transfer-line Commissioning: Prepared by Gui-Mei Wang

Booster Commissioning Coordinator: Timur ShaftanCommissioning staff: BINP personnel, members of the accelerator physics group; members of the operations group

Storage Ring Commissioning Coordinator: Sam Krinsky

Page 19: Commissioning Plans

19 BROOKHAVEN SCIENCE ASSOCIATES

High Level Applications for Commissioning

• High level component data management and control: 100% finished (it includes the mapping from lattice-element-name-based control to low level EPICS channel access, element/family/lattice read, write and save) quick prototyping of controls and specific applications for problem solving

• Linear lattice measurement package: (lattice function measurement and correction, orbit response matrix measurement, beam based alignment, orbit correction, local c.o. bump) 90% finished

• Diagnostics display and analysis package• On-line Lattice modeling: (Python binding of the Tracy code; useable as online or offline simulator;

includes Linear Optics matching; 70% complete• Other tools specific for commissioning are in progress.• Documentation for all HLA libraries are 70% finished/published. Including training tutorial and

examples.

Accelerator Physics Taskforce on High Level Applications in place and very active to provide in close collaboration with the controls group software for commissioning:

Page 20: Commissioning Plans

20 BROOKHAVEN SCIENCE ASSOCIATES

Software Repository

A website has been created with info, tutorials, Software depository access

Page 21: Commissioning Plans

21 BROOKHAVEN SCIENCE ASSOCIATES

Commissioning Data Base

- First Pass of evaluation which data to make available for database completed- Switched to a more pragmatic approach to make sure all relevant data are available for

commissioning- Tools have been created and implemented to import various information stored in convenient

format (MS-excel, text, ) into the IRMIS Database- IRMIS Data-base is being populated with data relevant for commissioning:

• Lattice data, • survey data, • magnet calibration data, • multipole data, • magnet-girder alignment data

Page 22: Commissioning Plans

22 BROOKHAVEN SCIENCE ASSOCIATES

Process Data Collection for Commissioning and Analysis

Page 23: Commissioning Plans

23 BROOKHAVEN SCIENCE ASSOCIATES

Summary

• LINAC commissioning preparations is nearing completions, commissioning expected top start in March’12

• Transfer line commissioning well prepared and commissioning tools in place• Booster Authorization base was supported by lab safety committee and approved by

BSHO• Storage ring commissioning preparations continue, commissioning document being

updated, ASE and SAD documents under development, capturing of relevant data in IRMIS database in progress, commissioning software being implemented and tested.