Commissioning Procedure for System Engineer power plant

Embed Size (px)

Citation preview

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    1/24

    PROCESS FOR AN COMMISSIONING

    ACTIVITIES :-

    Prepared by

    Chethan Kumar.G

    COTMAC

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    2/24

    STEP TO BE TAKEN IN COMMISSIOINING TIME PERIOD

    :-

    Planning/Preparation for an Site Visit.

    Safety Materials.Discussion with the Project Team.

    Plan to Pay Your Kind Attention Towards Your Project.

    Initial Supervision of Dcs System After Reaching Site & Plan for

    Dcs System Power-On.

    Supervision in field for Erection Activities.

    Loop Test.Drive Checking.

    Closed Loop & Open Loop Checking.

    Pid Tuning.

    Take Backup in a Regular Intervals.

    Try to Maintain Official Relationship with Customer.

    Maintain Your Documents.

    Conduct SAT with Customer & Handover the system to

    customer.

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    3/24

    1. PLANNING/PREPARATION FOR AN SITE VISIT :-

    Whenever engineer Plans to move from an site Visit. He have to carry

    certain Necessary Materials with him. Which is Related Document to thatProjects. Doc. Are Like :-

    Project I/O List.

    BOM Copy Stands for Bill Of Material.

    HDM Copy Stands for Hardware Design Manual.

    SDM Copy Stands for Software Design Manual.

    FAT Doc. Copy Stands for Factory Acceptance TestReport.

    KOM Copy Stands for Kick Off Meeting Copy.

    FAT MOM Copy Stands for FAT Minutes of Meeting

    Copy.

    System Architecture Copy.

    System Integration Datasheet Copy.

    Power-On Checklist.

    SAT Document Copy.

    CLCS Loop Protocol Stands for Closed Loop Protocol.

    http://localhost/var/www/apps/conversion/tmp/Doc's/IO_LIST.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/BOM.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/HDM.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/SDM.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/SIGNED_FAT_DOC.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/SIGNED_FAT_DOC.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/FAT_MOM.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/FAT_MOM.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/SYSTEM_INTEGRATION_DATASHEET.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/POWER_ON_CHECKLIST.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/SAT.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/CLCS_PROTOCOL.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/CLCS_PROTOCOL.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/CLCS_PROTOCOL.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/SAT.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/SAT.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/POWER_ON_CHECKLIST.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/POWER_ON_CHECKLIST.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/POWER_ON_CHECKLIST.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/POWER_ON_CHECKLIST.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/SYSTEM_INTEGRATION_DATASHEET.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/SYSTEM_INTEGRATION_DATASHEET.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/FAT_MOM.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/FAT_MOM.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/FAT_MOM.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/SIGNED_FAT_DOC.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/SIGNED_FAT_DOC.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/SIGNED_FAT_DOC.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/SDM.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/SDM.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/HDM.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/HDM.pdfhttp://localhost/var/www/apps/conversion/tmp/Doc's/BOM.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/BOM.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/IO_LIST.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/IO_LIST.xls
  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    4/24

    1. PLANNING/PREPARATION FOR AN SITE VISIT :-

    DRIVE Protocol Copy.

    Instrument Protocol Copy.Commissioning Status Loop wise Protocol Copy.

    Weekly Progress Report Copy.

    Timesheet Copy.

    HSE Report Copy.

    The above mentioned doc are necessary to bring at site

    for a commissioning Activities. This doc. Can tell the realstate what exactly happened during Fat Time Period. This

    will be proof for us. So, In case customer are trying to

    demand something from us. We can show this doc. So, this

    is necessity for all Engineer to bring doc. With them to Site.

    http://localhost/var/www/apps/conversion/tmp/Doc's/DRIVE%20PROTOCOL.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/INST_PROTOCOL.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/Orn.XXXXXXXX_Commisoning%20status%20Loop%20wise.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/Weekly%20Progress%20Report%200n%2008-10-2012%20to%2013-10-2012.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/June_month_Expenses%20(1).xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/June_month_Expenses%20(1).xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/June_month_Expenses%20(1).xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/Weekly%20Progress%20Report%200n%2008-10-2012%20to%2013-10-2012.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/Weekly%20Progress%20Report%200n%2008-10-2012%20to%2013-10-2012.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/Orn.XXXXXXXX_Commisoning%20status%20Loop%20wise.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/Orn.XXXXXXXX_Commisoning%20status%20Loop%20wise.xlshttp://localhost/var/www/apps/conversion/tmp/Doc's/INST_PROTOCOL.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/INST_PROTOCOL.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/DRIVE%20PROTOCOL.dochttp://localhost/var/www/apps/conversion/tmp/Doc's/DRIVE%20PROTOCOL.doc
  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    5/24

    2. SAFETY MATERIALS :-

    It is must and clear to all the engineer who is working in automation Field

    must have to carry certain Safety materials with him to protect Themselvesfrom accidents. Those Materials are :-

    Safety Helmet

    Safety Shoes

    Safety Goggle

    Safety Glues

    Ear-Plugs

    This are all the small Safety Materials which can save Your Life From

    Unpredictable Accident. So, Always work with Safety and go with Green.

    Maintain Honeywell Hse Report Properly. Try to get work from Our sub-

    contractor with Safety. Conduct meeting in a regular interval with sub-

    contractor and check there safety status.

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    6/24

    3. Discussion with Project Team :-

    Before Planning to visit for commissioning. Let u discuss with your

    particular Project Team. (Lead Engineer, Engineer Manager, Project

    Manager Exceptional case u can discuss have few discussion with

    Operational Manager in Honeywell also).

    Get backup from the lead-engineer, Cross-check those Backup which

    you received from the lead. Try to get there Number/Mail Id in case if any

    queries or clarification requires You can call and get Solution from them.

    Cross-check the backup which You have received from the Lead. Discuss

    with team regarding your role in commissioning. Also discuss about loop

    hole of Honeywell Dcs system which Honeywell was hided in front of

    customer.

    Get the Customer details Ex Reporting Person (Name, Phone No, Mail

    Id)

    Discuss with team regarding your role in commissioning.

    Get the Sub-contractor details Supervisor (Name, Phone No, Mail Id)

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    7/24

    4. Plan to Pay Your Kind Attention Towards Your Project. :-

    First of all get details about customer from Honeywell they might have

    experienced with customer during the time period of pre-fat and fat.

    Get the details about Reporting Time and Relieving Time from Site.

    Make Yourself Prepared on the same Manner.

    Plan to present Yourself in a well dressed Manner.

    Whenever you will plan to visit for a site. Plan according to keep entireproject related doc with You.

    Plan to pay Official Hours at site premises. And also try to avoid taking

    unwanted leaves.

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    8/24

    5. Initial Supervision of Dcs System After Reaching Site :-

    At the Initial supervision of Dcs system. Check the room temperature.

    Whether room temperature is well maintained. Alternatively check for dust-free in control Room. And check for falls sealing and flooring system

    readiness. If this three points are well-Maintained/Prepared then we can

    start Proceeding remaining Process.

    Check the panel internal Design . Whether system has been prepared

    as per the HDM copy.

    Check the grounding system. Whether entire grounding has done

    properly in Panel (SG, FG)

    Locate / Allign the System, Panels, Printers, Third-Party Devices as Per

    Complexity diagram.

    Check entire System & Marshalling Cabinets Dressing in all Panels, if itsnot well dressed then supervise the dressing. And make it done Before

    Planning for a system Power-on

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    9/24

    Check entire Devices Ferruling/Tagging are given Properly if Not then

    supervise the Tagging Activities. And make it done Before Planning for a

    system Power-on

    Cross verify the Ups incomer Voltage and current as per our Power-on

    Checklist. Also Check the PDB Incomer Voltage and current. EX - Vpn,

    Vne, Vpe.

    Connect the Fte, Fta, Internal Power-loop Connections (Tubes, Fans,

    FTA cards Supply, BPS, Pmio Power Supply, Controller Supply (DBK), Wet

    Contact Relay Supplies as per System Integration, Hdm copy and cross-

    verify its tagging and ferruling .

    Cross-verify the grounding system. Check whether signal & Frame

    Ground are given properly as per HDM copy In Panel. Connect signal &

    frame grounding cable to panel bus-bar (individual bus bar already

    allocated for each panel). Also Cross-verify every signal grounds are loop

    internally, check the continuity for signal ground. As same like signal

    grounds frame ground has to have to same continuity with each other.

    Note :- Frame & Signal should not have continuity with each other. This is

    Very Important checkpoint has to be taken care before planning for a

    power-on

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    10/24

    Check the preparation of earth pit whether customer/sub-contractor has

    made/prepared as per Honeywell standard. If its made then start to

    megger resistance with that pit. As per Honeywell standards SG-

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    11/24

    6. Initial Supervision of Dcs System After Reaching Site :-

    Plan to supervise field with Sub-contractor supervisor at initial stage and

    get planned from him about allocation of Man Power, Completion Date,

    Etc.,

    Cross- check Honeywell Materials which is received by Customer (Cross

    check with BOM).

    Plan to supervise status of the field activities with Sub-contractor

    supervisor at initial stage.

    Plant to do the in parallel. Try to allocate manpower in parallel areas.

    Work has to show progress in all areas. Guide technically to all Electrician.

    Try to Supervise there work. If any problems it can be solved on the

    instant.

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    12/24

    7. Loop Test :-

    Normally in Dcs there are two types of loop checking system are there.

    They are :-

    Cold-Loop Checking

    Hot-Loop Checking

    Hot-Loop Check :-

    During the Hot-Loop Checking the signals will be checked from field (JB-

    Junction Box, Mcc- Electrical Feeder) to dcs. Through the way of checking

    connectivity/ By the way of checking cores in a cable.

    Cold-Loop Check :-

    During the Cold-Loop Checking the signals will be checked from TB

    Terminals Block to the system. It can be checked by the way of loopingcable in TB and observing bit changeover in Dcs system.

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    13/24

    Before starting to take trail of all drives, closed Loop, system. The Loops

    signals should clear from field to avoid time loss during trail time period. It

    is mandatory to check the Loop signals from field to Dcs after System

    Power-on.

    The signals which have to be loop tested from Field (JB- Junction Box,Mcc- Electrical Feeders to Dcs. They are :-

    Digital Input signals.

    Digital Output Signals. ( Pfc, Wet contact 230v ).

    Thermocouple Signals

    Rtd Signals

    Analog Input Signals. (2 Wire system (24v) , 4- Wire system(Pfc) ).

    Once the signals will be loop tested from field to Dcs then the Dcs

    system will be ready to take trail.

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    14/24

    8. Drive / Motors / Pumps Checking :-

    For drive checking initially the logics shall be checked with customer.

    Before Proceeding for taking trail certain things also needed to check from

    our end like Contacts of relay. Whether feeder requires (Pfc, 230v WetContact Relay ). As per the demand we can provide relay contact. Same

    inform You can get from Electrical Mcc Diagrams. Once logics & Relay

    Contact will be checked then we can proceed for taking trial a feeder

    (Meant to say Motor/drive) through Dcs.

    Hardly drives have two types :-

    AC DrivesDC Drives

    Drives are mainly used for controlling the speed of a motor. Like rolling

    of a kiln roller. we can control the roller by varying its speed (Analog Output

    from dcs (4-20 MA)

    For Motors & Pumps Checking :-

    For Motor and Pump, it will be same as like drive initially you can

    cross-verify logics with customer. Once logic will be finalized. Then you can

    go-ahead to take trial from Mcc feeder. For Motor and Pumps different

    application available as per process. Like :-

    1. Conveyor

    2. Fans3. Motors

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    15/24

    Normally in automation Sector certain Motors/Pumps are used based on

    application. Based on Application the Specification for particular machine

    will vary.

    Initially whenever you are planning to take trial from Mcc Feeder

    Requested the concern Electrical Engineer to Switch off the Power Circuit.

    Once Power Circuit if Off. We can take trail From Dcs through control

    circuit. Supply will not reach till to field. But, feeder will be running. By this

    way we can take trial of a feeder.

    There are two classification of motor are available in Power Sector :-

    LT Motor Low Torque Motor.

    HT Motor - High Torque Motor.

    This classification between motors applies for application. Based on

    Application the Motors are classified.

    LT Motor :-

    LT Motor stands for Low Torque Motor. To start this motor it requires

    less initial torque. (Ex :- Conveyors)

    HT Motor :-

    HT Motor stands form High Torque Motor. It requires High Initial

    Torque to start. (Ex :- ID Fan)

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    16/24

    9. Closed Loop & Open Loop Checking :-

    Closed Loop :-

    Example for an closed Loop Is PID Loop.

    Pid stand for Proportional + Integral + Derivative Loop Control

    Pid can be loop tested through Dcs by applying (4-20 ma) from

    Dcs. By the way of varying o-100 Command. And parley we have to cross

    check with its position feedback which is an analog input will tells the

    Control valve opening/closing status. So as per the command we need to

    get the position feedback from field.

    Once this Loop tune finishes we can make Pid in auto mode.

    And we can vary set point as per process. Pv-sp = op based on thisphilosophy the controller will control the Pid loop.

    In power sector certain Process applies Closed Loops Like :-

    1. Drum level Control.

    2. Combustion Control.

    3. Atemperator Control. ( Temperature, Pressure )

    4. Hot well Level Control.

    5. Deaerator Level Control.This are all certain Parameters in a Power Plant which will be controlled by

    Pid Loop.

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    17/24

    Open Loop :-

    Example for an Open Loop Is Damper Control.

    Open loop can be tested through Dcs by applying (4-20 ma) from Dcs. By

    the way of varying o-100 % Command. And parley we have to cross check

    with its position feedback which is an analog input, tells the Control valveopening/closing status. So as per the command we need to get the

    position feedback from field.

    In power sector certain Process applies Open Loops. They are :

    1. ID Fan Damper Control.

    2. FD Fan Damper Control.

    These are all certain Parameters in a Power Plant which will be controlled

    by Open Loop.

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    18/24

    10. PID Tuning :-

    PID Tuning :-

    Example for an closed Loop Is PID Loop.

    Pid stand for Proportional + Integral + Derivative Loop Control

    Please refer. The attached above Picture which is clearly mentioned how

    the Pid works. Pid is basically an closed loop circuit.

    Set point (SP) :- Set point is an parameters (Temperature, Flow, Pressure,

    Level). Operator use to feed this set point to maintain the process

    parameter.Process Value (PV) :- Process Value / Control Value Is an parameter

    reading which comes from field (Transmitter) it can be either (Temperature,

    Flow, Pressure, Level).

    Output (OP) :- Pid Controller Output In the form of 0-100 % / 4-20 ma.

    Which operates the Control Value By using I2P Convertor / Positiner

    OP = PV-SPERROR

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    19/24

    10. PID Tuning :-

    PID Tuning :-

    For Pid Tuning mainly 3 terms are used. They are :-

    1. Proportional .2. Integral.

    3. Derivative.

    Proportional :- (Gain Factor) :- Proportional is a gain factor for a Pid

    control which control the control valve stock length speed. Default it will be

    1. If stock will be fast then this gain factor can be reduce. By reducing thisgain factor the control stock length can be controlled.

    Integral :- (Offset Time) :- Integral is an Offset Time for a Pid control

    which control the offset time between process value with set point. By

    Increasing/decreasing this offset time Pid sp = Pv Equalization can be

    done soon.

    Derivative :- (Unstable Condition) :- Derivative is an Unstable Condition

    for a Pid control which makes the normal Pid in unstable condition.Before Tuning a Pid Control set the op Limit

    (Lower, Higher Limit). Which can save the plant

    from the unwanted trip.

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    20/24

    11. Take Backup in a Regular Intervals. :-

    Try to backup in a regular Intervals. If some unexpected things we can

    be in a safe zone. It is a good way to take backup daily and even it will

    secure for us. In Honeywell system certain system backup can be taken

    on site on daily basis. They are :-Erdb

    Emdb

    Host Files

    Exported Files

    Checkpoint

    Qdb

    Graphics

    Log Report

    Exported Assets

    Alarm Groups

    R400

    Menu & Toolbars.

    Station File.

    How to take backup in Honeywell System

    http://localhost/var/www/apps/conversion/tmp/Doc's/Honeywell%20Backup%20HOW%20TO%20TAKE.xlsxhttp://localhost/var/www/apps/conversion/tmp/Doc's/Honeywell%20Backup%20HOW%20TO%20TAKE.xlsx
  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    21/24

    12. Try to Maintain Official Relationship with Customer. :-

    Try to Maintain Official Relationship with Customer :-

    Represent Yourself in a good Manner.

    Try to avoid speaking regional language with Customer. If You will speak

    in a regional they may demand to do some Extra Work Not in an officialmanner in a Personal way. So, Always try to make Conversation in English

    with Customer.

    Try to follow the company Timing on Site.

    Dont do any extra activities which is not known by your Team.

    Dont commit anything by verbal Communication. Whatever,

    Commitment You will give to Customer do it in Official Manager By the way

    of giving a detailed mail to entire Team Members.

    Dont take any big discussion by your oneself. Let you give a mail to

    company. Let them take a discussion and give you confirmation. Then you

    can proceed for that.

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    22/24

    13. Maintain Your Documents :-

    Maintain Your Documents :-

    Always give much priority for documentation works. Only

    documentation can tell how much activities u have done on site. In

    Honeywell We have certain Doc. Which need to be taken signed fromcustomer after completion of particular activities. Those doc. are :-

    Weekly Progress Report

    Time-sheet

    Power-on Checklist

    Drive Protocol

    Instrument Protocol

    Closed Loop Protocol

    HSE Report

    Commissioning status Protocol

    Mom Copies

    SAT Procedure Copies.

    Site Change Report (Honeywell SCR Report)

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    23/24

    14. Conduct SAT with Customer & Handover the system to

    customer :-

    Conduct SAT with Customer & Handover the System to Customer :-

    After Finishing the entire Commissioning activities. Request

    Customer to give permission for Conducting SAT Procedure at Site. Before

    conducting sat in front of Customer. Let u check our system first whether

    entire redundancy system is ok (Pre-sat) If You will get Satisfaction then

    declare a day for conduct sat at site. Conduct sat in front of Customer and

    show them the redundancy of Dcs system and other check-up which is

    cleared mentioned in sat procedure. After completion of this procedure, sit

    with customer and make a final mom and get signed from customer in satand mom copies.

  • 7/29/2019 Commissioning Procedure for System Engineer power plant

    24/24

    THANK YOU

    Thank you all to spend your precious time for mypresentation