21st NCBC Conference21st NCBC Conference
Gerald J. Kettler, PE, CCP, CPMP
COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS
ASHRAE STANDARD 202
21st National Conference on Building Commissioning
21st NCBC Conference21st NCBC Conference
AIA Quality Assurance
The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.
This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.
Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
21st NCBC Conference
21st NCBC Conference21st NCBC Conference
Presentation Description
The new ASHRAE Standard 202, The Commissioning Process for Buildings and Systems, is nearing completion and is about to be published. This standard will set the minimum requirements for the Commissioning Process. It is derived from the process in ASHRAE Guideline 0-2005. This seminar will explain the organization and contents of the standard along with its relationship to other standards and guidelines and application to construction projects.
21st NCBC Conference
21st NCBC Conference21st NCBC Conference
Understand the history and development of the commissioning process.
Understand the basics of the Commissioning Process. Recognize that Commissioning is a process and not just a
single event. Be able to apply the Commissioning Process for design and
construction of building elements and systems. Be able to utilize the commissioning process deliverable
documents. Recognize the use of the Commissioning Standard to codes
and standards in the industry.
Learning Objectives
21st NCBC Conference
21st NCBC Conference21st NCBC Conference
A quality-focused process for enhancing the delivery of a project. The process focuses upon verifying and documenting that all of the commissioned systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the Owner's Project Requirements (ASHRAE Std. 202-2013)
21st NCBC Conference
What is the Commissioning Process?
21st NCBC Conference21st NCBC Conference
History of Commissioning Documents1982 – ASHRAE forms Cx committee1989 – ASHRAE Guideline 1 first published1996 – First revision ASHRAE Guideline 12000 – ASHRAE joins with NIBS to develop
a universal process for commissioning2005 –ASHRAE/NIBS Guideline 0 published2007 – ASHRAE Guideline 1 revised2007 – Existing Building Guideline committee formed.2010 - Standard 202, The Cx Process for Buildings and Systems formed
21st NCBC Conference21st NCBC Conference
Current ASHRAE Commissioning Guideline DocumentsGuideline 0-2005, The Commissioning ProcessGuideline 1.1-2007 HVAC CommissioningGuidelines 0.2 and 1.2, Existing Buildings –
under developmentGuideline 1.3, Training of Building Staff –
under developmentGuideline 1.4, Systems Manual, under developmentGuideline 1.5, Commissioning Smoke Control Systems –published
21st NCBC Conference21st NCBC Conference
ASHRAE/ANSI/IES Standard 202 What is it?
Process Document Minimum Requirements for the
Commissioning process using ASHRAE Guideline 0-2005 as the base process
Consensus Development
21st NCBC Conference21st NCBC Conference
Standard 202 What it will NOT do? Define process for existing building projects Define qualifications of commissioning
providers List building size, type or usage or list process
variations for these List systems or assemblies requiring
commissioning Include enforcement provisions
21st NCBC Conference21st NCBC Conference
ASHRAE Standard 202 Organization Process listed as 13 functional steps and not by
project phase
Each of 13 functional steps has deliverables
The main body of the Standard has 17 chapters
There will be 16 informative annexes explaining the deliverables.
21st NCBC Conference21st NCBC Conference
Standard 202 Chapters1. Purpose2. Scope3. Definitions4. Utilization 5. Initiating the Commissioning Process6. Owner’s Project Requirements7. Commissioning Plan 8. Basis of Design9. Contractor, Supplier, and Manufacturer
Commissioning Requirements
21st NCBC Conference21st NCBC Conference
Standard 202 Chapters10. Design Review11. Commissioning Submittal Review12. Construction Observation and Testing13. Issues Documentation and Resolution14. Systems Manual15. Training16. Post Occupancy Operation 17. Commissioning Report
21st NCBC Conference21st NCBC Conference
Commissioning ProcessActivity Deliverable
• Initiate Commissioning ↓ Roles and ResponsibilitiesProcess
• Project Requirements ↓ Owner’s Project Requirements (OPR)
• Develop Commissioning ↓ Commissioning Process Plan Plan (CxP)
• Design Approach to ↓ Basis of DesignRequirements
21st NCBC Conference21st NCBC Conference
Commissioning ProcessActivity Deliverable
• Set Contractor Cx ↓ Cx Specifications Requirements
• Design Review ↓ Design ReviewReport
• Review Submittals ↓ Submittal Review Report
• Observation ↓ Construction Checklists• & Testing and Reports
21st NCBC Conference21st NCBC Conference
Commissioning ProcessActivity Deliverable
• Issues Resolution ↓ Issues and Resolution Log
• Assemble Systems Manual ↓ Systems Manual
• Conduct Training ↓ Training Plans and Records
• Post Occupancy Operation ↓ End of Warranty Cx Report
• Assemble Commissioning Commissioning Report Report
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 1
PURPOSEThe purpose is to identify theminimum acceptable Commissioning Process for Buildings and Systems.
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 2
SCOPEThis standard provides procedures, methods, and, documentation requirements for each activity for project delivery from pre-design through occupancy and operation, including:
Overview of Commissioning Process activities, Description of each process step’s minimum
activities, Minimum documentation requirements, and Acceptance requirements
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 3
DEFINITIONS 27 Updated Guideline 0-2005 Definitions 7 New Definitions
Mostly on Design Review and Documentation
Covers New and Existing Buildings for Definitions
Establishes Base for Other Documents on Commissioning
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 4
UTILIZATION Establishes Chapter format using sections for
Introduction, Requirements and Acceptance Provides Outline for Commissioning Process Establishes Minimum Activities Lists Deliverables for Each Activity
Acceptance Required for Each Activity In 202, CxA is not required to “accept” design
or construction for owner or jurisdiction.
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 5
INITIATING THE COMMISSIONING PROCESS Owner’s Responsibilities Review and Approval Select Systems and Assemblies to be
Commissioned Selecting Project CxA and
Commissioning Team “Agreement’ Required for Each Activity
and Deliverable
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 6
OWNER'S PROJECT REQUIREMENTS Base Document for Building Performance
and Commissioning Process Facility Requirements Documentation Commissioning Training
Updated as Project Evolves
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 7
COMMISSIONING PLAN Written Plan that Evolves with the Project Includes: - Project Specific Cx Process Description List of Systems and Assemblies to be
Commissioned Roles and Responsibilities Schedules for Commissioning Documentation and Checklists Process for Resolving Problems and
Deficiencies
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 8
BASIS OF DESIGN Designer’s Approach to Owner’s Project
Requirements Basic Design Information and
Assumptions Defined Platform for Review and Response
During Project Updated as Project Evolves
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 9
CONTRACTOR, SUPPLIER, and MANUFACTURER COMMISSIONING REQUIREMENTS Commissioning Included in Project as
Required Commissioning Included in
Specifications Contracts Include Commissioning Documentation Provided
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 10
DESIGN REVIEW Compliance with Owner’s Project
Requirements Include Commissioned Systems and Assemblies Complete Review Before Construction Design Team to Respond Commissioning Design Review is NOT PEER Review Code Review Regulatory Review
Approved Quality Sampling or Expert Review
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 11
COMMISSIONING SUBMITTAL REVIEW Compliance with OPR and Cx Plan Does Not Replace Designer’s Review Concurrent with Designer Review Covers Commissioned Systems and
Assemblies
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 12
CONSTRUCTION OBSERVATION AND TESTING Compliance with OPR, Cx Plan and
Construction Documents Approved Technical Procedures and
Documents for Commissioned Systems and Assemblies
Kick Off and Scoping Meeting Evaluate Equipment, Installation and
Performance Approved Sampling Process
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 13
ISSUES AND RESOLUTIONS DOCUMENTATION Written Report Documents List Issues, Dates and Responsibilities Show Resolutions when Complete Intermediate Issue Logs as Required Final Issue and Resolution Log Included in
Final Commissioning Report
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 14
SYSTEMS MANUAL Collection of Project Documents
Facility Design and Construction Systems and Assemblies Information Facility Operations Training Final Commissioning Report
Used for Operator and Maintenance Training Used for Building Operation Provides Baseline for Operation and Changes Updated as Building Evolves
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 15
TRAINING O&M Personnel and Occupants Written Plan Instructional Requirements Locations and Facilities Instructor Qualification
Commissioned Systems and Assemblies Records and Reports Retained
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 16
POST OCCUPANCY OPERATION During Warranty Period Commissioned Systems and Assemblies Delayed and Seasonal Testing Update OPR and Cx Plan Update Systems Manual Update Training
21st NCBC Conference21st NCBC Conference
Standard 202 Chapter 17
COMMISSIONING REPORT Summary of Commissioning Process Final Commissioning Plan Review Reports Commissioning Progress Reports Issue and Resolution Reports Checklists and Testing Reports Open Items Systems and Assemblies not meeting OPR and
construction Documents Requirements
21st NCBC Conference21st NCBC Conference
Annexes
I – Submittal Review and ReportJ – Construction Observation
and Testing Checklists andReports
K – Issues and Resolution Log L – Systems Manual M – Training Plans and RecordsN – End of Warranty
Commissioning O – Commissioning Report P – Commissioning Information
A – Commissioning ProcessDocumentation Matrix
B – Quality Based SamplingProcess
C – Initiating the Commissioning Process
D – Owner’s ProjectRequirements
E – Commissioning Plan F – Basis of Design G – Commissioning
Specifications H – Design Review and
Report
21st NCBC Conference
STANDARD 202 ANNEXES
21st NCBC Conference21st NCBC Conference
Informative Annex ACommissioning Process Documentation Matrix Commissioning Activity during Initiation-
Design- Construction- Operations Suggests Participants by Document for: Input ByProvided ByReviewed/Approved ByUsed ByNotes
21st NCBC Conference21st NCBC Conference
Informative Annex B
Quality Based Sampling Process Design Review Construction Review Submittal Reviews Site Visits
Complexity Factor Guidance and suggested sample ratesOwner Must Approve Sampling Process
21st NCBC Conference21st NCBC Conference
Informative Annex CInitiating the Commissioning ProcessSuggested Contract Language for Agreement to Produce:
OPR, Cx Plan, BOD CX Specs, Cx Design and Submittals Review Observation and Testing, Issue Log Systems Manual, Training End of Warranty and Final Cx Reports
21st NCBC Conference21st NCBC Conference
Informative Annex D
Owner’s Project Requirements Obtaining the Information OPR Workshop, Interviews
Suggested Contents Facility Requirements Documentation Commissioning Training Maintenance
Document Format
21st NCBC Conference21st NCBC Conference
Informative Annex ECommissioning Plan
Pre-Design, Design, Construction Contents Overview and Process Description of Cx Pre-Design Activities Design Activities Construction Activities Occupancy and Operations Activities
Schedules and Checklists Appendix List – Attached Documents Commissioning Plan Evolves into Commissioning
Report
21st NCBC Conference21st NCBC Conference
Informative Annex F
Basis of Design Process to Develop BoD Suggested Contents Format and Organization Review and Updating
21st NCBC Conference21st NCBC Conference
Informative Annex G
Commissioning Specifications Guidance for Developing Cx
Specifications Commissioning Authority Responsibilities
and Functions Commissioning Organizational Strategy for
Commissioning Team Members Commissioning Process Activities
21st NCBC Conference21st NCBC Conference
Informative Annex H
Design Review and Report Design Submissions General Review Coordination Review Field Specific Review Specification Review Design Review Reports Design Professional’s Actions
21st NCBC Conference21st NCBC Conference
Informative Annex ISubmittals Review and Report Executive Summary List of Submittals Reviewed Issues, Comments and Variances from OPR Coordination with Project Systems Conformance to Functional Requirements
and Maintainability
21st NCBC Conference21st NCBC Conference
Informative Annex JConstruction Observation and Testing Checklists and Reports Overview ant Types of Testing Performance Levels of Complexity Active and Passive Tests Checklists Reports
21st NCBC Conference21st NCBC Conference
Informative Annex JConstruction Observation and Testing Checklists and Reports Overview ant Types of Testing Performance Levels of Complexity Active and Passive Tests Checklists Reports
21st NCBC Conference21st NCBC Conference
Informative Annex K
Issues and Resolutions Log Formats Contents Resolutions Records
21st NCBC Conference21st NCBC Conference
Informative Annex LSystems Manual Use and Preparation Requirements Document Collection Contents and Format
1. Executive Summary2. Facility Design and Construction3. Building, Systems, and Assemblies
Information4. Facility Operations5. Training6. Commissioning Report
21st NCBC Conference21st NCBC Conference
Informative Annex MTraining Plans and RecordsActivities, and Roles and Responsibilities
Pre-Design Design Phase Construction Phase Occupancy and Operation
Reports and Records
21st NCBC Conference21st NCBC Conference
Informative Annex NEnd of Warranty Commissioning Commissioning Functions during
Warranty Delayed and Seasonal Testing Guidance to Operations and Owner Additional Training
Others Responsibilities Updates to OPR, Systems Manual,
Testing and Commissioning Reports
21st NCBC Conference21st NCBC Conference
Informative Annex OCommissioning Report
Summary of Commissioning Process for the Project Executive Summary
Collection of All Commissioning Documentation Final Commissioning Plan Design Review Reports Testing Reports Cx Progress Reports Issues and Resolutions Logs Open Items
Appendixes - Documents
21st NCBC Conference21st NCBC Conference
Informative Annex P
Commissioning Information
ASHRAE Commissioning Guidelines
Other Organization Resources Websites 17 Resources with Information and
Background on Commissioning.
21st NCBC Conference21st NCBC Conference
THANK [email protected]