COMMISSIONING: REDUCING THE CARBON FOOTPRINT(…and Maintenance Costs) (…and Operating Costs)
Existing Building Commissioning
What is Commissioning?Existing Building Commissioning is defined as:
An organized process whereby the performance of selected building systems are verified and documented in order to identify energy and operational cost reduction opportunities and to improve overall building performance.
Typical Commissioned Systems:• Mechanical
• HVAC• Controls
• Electrical• Emergency Power Equipment
• Fire & Life Safety• Fire Alarm System
Existing Building Commissioning
Purpose & Goals of EB-Commissioning:• Identifying Potential Energy Savings• Improving Indoor Air Quality (IAQ)• Improving Guest Comfort• Eliminating Known Issues• Meeting the Demands of a Change• Reducing Maintenance Costs• Improving Systems/Equipment Documentation
Existing Building Commissioning
Procedures of EB-Commissioning:• Owner Interview
• Project’s History & Future• Document Review
• Site Investigation• Data Collection• Observation of Performance• Trending• Current Energy Bills
• Analysis• Data from Trends• Energy Bills• Maintenance Records
• Findings Report• Investigation Findings• Recommendations
• Implementation
Existing Building Commissioning
Typical Commissioning Findings:• Equipment Issues
• Equipment not functioning correctly• Equipment not functioning at all• Older equipment with poor efficiency ratings
• Controls Issues• Sensors out of calibration• Programming errors (or emissions)• Wiring or connection issues
• Maintenance Issues• Poor maintenance• Improper maintenance
Existing Building Commissioning
Commissioning Costs & ROI:• Typical Costs of EB-Commissioning
• $0.10 - $0.25/Square Foot, based on type of systems• Contract by Scope
• Investigation Phase• Implementation Phase
• Typical Return On Investment• 0 to 4 months for most (low hanging fruit)• 6 months to 2 years (equipment replacement)
Existing Building Commissioning Item
BuildingMeasure Description Cost Savings Simple Payback
1 Extended Surface Filters $10,700 $18,000 0.6 years2 HVAC Scheduling & Flow
Settings $35,000 $86,800 0.4 years3 Excessive simultaneous
heating and cooling $17,300 $23,000 0.75 years
4 Hospital Pump Impellers $6,700 $6,700 1 year
5 By-Pass Timers $3,500 $65,800 0.05 years6 Supply Air Temperature
Setpoints $700 $5,000 0.14 years
7 Long Term Care Facility
Enable Economizer Controls $3,600 $4,700 0.8 years
8 Scheduling Equipment and Lights $0 $66,400 Immediate
9 Economizer Settings $0 $17,000 Immediate10 Static Pressure Reset $0 $7,500 Immediate
11 Oregon Office EMS Control of Duct Heaters $0 $3,700 Immediate
12 Colorado Retail EMS Night Purge and Optimum Stop/Start Strategies $0 $5,000 Immediate
13 Tennessee Office Chilled Water Pump VFD, Piping System Leaks, and By-Passes $9,300 $24,300 0.3 years
14 Massachusetts Retail
Battery Charging Schedule Changes $0 $3,700 Immediate
Totals $86,800 $337,600 0.26 years
High Tech
Coronor's Office
Corporate Office
* Based on case studies performed by Portland Energy Conservation Inc. (PECI), 2000
Existing Building Commissioning
Benefits of Commissioning:• Reduction in Energy Costs
• Better efficiency equals lower operating costs• Reduction in Maintenance Costs
• Fine tuning eliminates emergency repairs and allows for scheduled preventive maintenance
• Improved IAQ• Optimum operating systems create a healthy environment
with verified and documented OSA • Improved Guest Comfort
• Proper operating systems create a healthy environment• Verification of functioning systems reduces occupant
complaints
Existing Building Commissioning
EB-Cx Questions
Existing Building Commissioning
Thank You