Community Consultative Committee August 2016

Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

Community Consultative Committee

August 2016

Page 2: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

2

Agenda item 3 - Correspondence

� Issued 2015 AEMR to department of planning

� Environment Protection Licence – Annual return paperwork received

Page 3: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

3

Agenda item 4 – Operations

� Maintain zero harm

� Completed the site improvement works – walkways, parts storage etc

� Overburden works ceased

� Maintain processing performance

� Continue to develop preventative maintenance scheme further

Page 4: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

4

Agenda item 5 – OH&S Performance

� No loss time injuries

Page 5: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

5

Agenda Item 6 - Environmental Performance

Incidents (EPL period June 2014 – July 2015)

June - overflow of oil separator during east coast low

Page 6: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

6

Agenda item 6 – Environmental Performance

Complaints

2 noise notifications in line with monitoring

Page 7: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

7

Agenda item 6 – Environmental Performance

Air

Annual Average goal of 4gm2/month

Not In compliance at Site 1 (5.22 ) and 3 (4.04)

0.00

5.00

10.00

15.00

20.00

25.00

mg

/m3

Month

Insoluble solids (EPL 2015-2016)

site 1 Insoluble solids site 2 Insoluble solids site 3 Insoluble solids Insoluble solid goal

Page 8: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

8

Agenda item 6 – Environmental Performance

Air

Annual Average goal of 4gm2/month

In compliance

0

2

4

6

8

10

12

14

Jul-2015 Aug-2015

Sep-2015

Oct-2015

Nov-2015

Dec-2015

Jan-2016

Feb-2016

Mar-2016

Apr-2016

May-2016

Jun-2016

Annualaverage

g/m

2/m

on

th

Month

Peppertree Quarry Deposited Dust 2015 - 2016 683 Marulan South Road

Insoluble solids Ash soluble solids Ins Sol Goal

Page 9: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

9

Agenda item 6 – Environmental Performance

Air

Annual Average goal of 4gm2/month

Not In compliance due to dust recorded in July and October 2015. However of the insoluble solids Ash content is nearly 50%.

0

2

4

6

8

10

12

14

Jul-2015

Aug-2015

Sep-2015

Oct-2015

Nov-2015

Dec-2015

Jan-2016

Feb-2016

Mar-2016

Apr-2016

May-2016

Jun-2016

Annualaverage

g/m

2/m

on

th

Month

Peppertree Quarry Deposited Dust 2015-2016 Onsite (NW boundary)

Insoluble solids Ash soluble solids Ins Sol Goal

Page 10: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

10

Agenda item 6 – Environmental Performance

Air

Annual Average goal of 4gm2/month

Not in compliance – westerly winds and over burden activities

0

2

4

6

8

10

12

14

Jul-2015 Aug-2015

Sep-2015

Oct-2015 Nov-2015

Dec-2015

Jan-2016Feb-2016Mar-2016Apr-2016 May-2016

Jun-2016 Annualaverage

g/m

2/m

on

th

Month

Peppertree Quarry Deposited Dust 2015-2016432 Long Point Road, Tallong

Insoluble solids Ash soluble solids Ins Sol Goal

Page 11: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

11

Agenda item 6 – Environmental Performance

Air – Particulate Matter <10 microns

(EPL period July 2015 – July 2016)

PM10 below annual average goal

0

20

40

60

80

100

120

140

160

180

PM10 (ug/m

3)

sampling date

Peppertree Quarry PM10 (EPL 2015-2016)

PM10

PM10 24 hour goal

PM10 annual average goal

Page 12: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

12

Agenda item 6 – Environmental Performance

Air - Total Suspended Particulates

(EPL period July 2015 – July 2016)

TSP below Annual average goal

0

20

40

60

80

100

120

140

TSP (ug/m

3)

sampling date

Peppertree Quarry TSP (EPL 2015-2016)

TSP

TSP annual average goal

Page 13: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

13

Agenda item 6 – Environmental Performance

Noise - quarterly noise monitoring April 2016

All sensitive receiver sites monitored In compliance – daytime

Receiver Date

Predicted Site Noise Level

Contribution Operational Criteria (dB(A))

EPL ID Name LAeq, 15 minute (dB(A)) daytime

16 Pace10th May 2016 30 41

6 Bartolo10th May 2016 31 35

2 Ordasi10th May 2016 31

39

5 Cooper10th May 2016 26 35

16 Pace10th May 2016 23 41

6 Bartolo11th May 2016 33 35

2 Ordasi11th May 2016 28 39

5 Cooper11th May 2016 25 35

16 Pace11th May 2016 23 41

6 Bartolo11th May 2016 32 35

2 Ordasi11th May 2016 23 39

5 Cooper11th May 2016 26 35

16 Pace11th May 2016 20 41

Page 14: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

14

Agenda item 6 – Environmental Performance

Noise - quarterly noise monitoring April 2016

All sensitive receiver sites monitored In compliance - evening

Receiver Date Site Noise Level Contribution

Operational Criteria

(dB(A))

EPL ID Name Leq, 15 minute (dB(A)) evening

2 Ordasi

11th may 2016

28 35

16 Pace

11th may 2016

24 35

5 Cooper

12th May 2016

26 35

6 Bartolo

12th May 2016

30 35

5 Cooper

12th May 2016

26 35

Page 15: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

15

Agenda item 6 – Environmental Performance

Noise - quarterly noise monitoring April 2016

All sensitive receiver sites monitored In compliance – evening 1min

Receiver Date Site Noise Level Contribution Operational Criteria (dB(A))

EPL ID Name LA1, 1 minute (dB(A)) evening

2 Ordasi

12th May 2016 28

45

5 Cooper

12th May 2016 24

45

5 Cooper

12th May 2016

30

45

16 Pace

12th May 2016

26

45

6 Bartolo

12th May 2016

26

45

Page 16: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

16

Agenda item 6 – Environmental Performance

Blast monitoring (EPL 2015-2016)

All in compliance

0

20

40

60

80

100

120

140

26

-Ma

y-2

01

5

15

-Ju

l-2

01

5

3-S

ep

-20

15

23

-Oct

-20

15

12

-De

c-2

01

5

31

-Ja

n-2

01

6

21

-Ma

r-2

01

6

10

-Ma

y-2

01

6

29

-Ju

n-2

01

6

18

-Au

g-2

01

6

Overpressure

north west boundary

north east boundary

683 Marulan sth road

Pace

criteria 5%

criteria 100%

Page 17: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

17

Agenda item 6 – Environmental Performance

Blast monitoring (EPL 2015-2016)

All in compliance

0

2

4

6

8

10

12

26

-Ma

y-2

01

5

15

-Ju

l-2

01

5

3-S

ep

-20

15

23

-Oct

-20

15

12

-De

c-2

01

5

31

-Ja

n-2

01

6

21

-Ma

r-2

01

6

10

-Ma

y-2

01

6

29

-Ju

n-2

01

6

18

-Au

g-2

01

6

ppv

date

vibration

north west boundary

north east boundary

683 Marulan sth road

Pace

criteria 5%

criteria 100%

Page 18: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

18

Agenda item 6 – Environmental Performance

Heritage

� All salvage work ceased for 12 months

� 96 000 artefacts salvaged

� Management plan currently being reviewed

Page 19: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

19

Agenda item 6 – Environmental Performance

Ecology

� Rehab maintenance work ongoing

� Wildlife management – Boris the bat

Page 20: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

20

Agenda item 6 – Stakeholder Engagement

� HASP project

� CVA schools program

Page 21: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

21

Agenda item 7 – Plans for the next three months

Page 22: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

22

Agenda item 8 – General Business

� Annual Environmental Management report 2015

- issued

� Weather station update

- Review of data provided for the last 12 months

� Peppertree Modifications

- Advised that conditions are being drafted for approval

� Marulan South Limestone update

- Still being prepared

� Next meeting dates – November 2016

Page 23: Community Consultative Committee August 2016 · August 2016. 2 Agenda item 3 - Correspondence Issued 2015 AEMR to department of planning ... Insoluble solids (EPL 2015-2016) ... Microsoft

23

END