Community Source Procurement System

Jennifer FouttyDirector of Purchasing Operations, Indiana University

Barry WalshSenior Director, eBusiness Services, Indiana University

JF

Objective

To share with you some details of what, for us, was a unique implementation of a new system

JF

Some Background

Two projects converging: Development of a new Procurement

system at Indiana University Replacing a mainframe system That system in production since 1988 We called this new system “EPIC”

Electronic Procurement & Invoicing Center

The Kuali Financial Systems Project

JF

Kuali Financial System Functional/Technical leads met Dec 2004

Scope and the data that was to be contained in the system (based primarily on existing IU FIS)

Person-years estimated to be somewhere around 60

Time allotted for project was 2.5 years March 18, 2005…$2,500,000 from Andrew

W. Mellon Foundation Development began in June, 2005

KFS Founding Partners

Started with Six Institutional Founding Partners

NACUBO and The rSmart Group are Founding Partners

On 7/8/06, a newOn 7/8/06, a newInvesting Partner joinedInvesting Partner joined

Kuali Financial System

Scope Over 700 distinct tables Over 100 distinct routable business

transactions…’eDocs’ Over 400 distinct maintenance

transactions Hundreds of inquiries, lookups, and

mandatory reports to support real-time and analytical decision making

First Module of Kuali Financial Systems

BW

Actually scheduled now

for 10/13

Convergence

Kuali Functional Council met in April 2005

KFC reviewed all functionality in EPIC KFC voted to include EPIC in the Kuali

Financial System Some enhancements were identified

JF

The EPIC Story

Two key themes: Exceptional response from users to EPIC First module of Kuali Financial System

implemented

JF

Exceptional Response

Minimal Costs Very few bugs We felt the love

JF

Minimal Costs

Approximately 2 year implementation Approximately 6 developers All procurement staff spent hours

Design Testing Training & Implementation

No external funding required

JF

Very few bugs We piloted in June 2005

Catalog shopping only Brought departments on a few at a time Defined needed workflow and set up that

workflow in the system Fully live in November 2005

No parallel activity Only major bug was in our Fax

software integration (which users didn’t see)

JF

Felt the Love

Training Mentoring Usability

JF

Training

Step-by-step documentation Town Hall meetings Hands on training

JF

Mentoring An individual Purchasing staff member met

one-on-one with each of 102 departments on the Bloomington campus

What this accomplished Probably the best “training” possible, because it

was so individualized We learned so much more about our users Our users really felt the love

JF

Usability at IU

Usability eXperience Group 5 years Early Connection with Development

Teams Accessibility issues Cross-Application Learning

Purchasing/AP; HR; Kuali

BW

Quick Demo

JF

First Module of Kuali Financial Systems

What we learned -- Best practices

Vendor data structures Reporting of diversity spend Use of Commodity Codes

Having partners we can ask “how do you do this?”

How to collaborate and compromise We pooled resources rather than

competing for them

JF

Q&A

Jennifer – [email protected][email protected]

Kuali Financial System Phase I Deliverables (Oct 2006)

Chart of Accounts Financial Transactions/General Ledger Kuali Nervous System (KNS) Kuali Enterprise Workflow (KEW)

Phase IIA Deliverables (July 2007) Accounts Payable/Purchasing…..’Kualification’ Budget Construction Labor Ledger Research Administration/Grants & Contracts

Phase IIB Deliverables (Mar 2008) Accounts Receivable Capital Assets Management System

Kuali Financial System Phase I Deliverables (Oct 2006)

Chart of Accounts Financial Transactions/General Ledger Kuali Nervous System (KNS) Kuali Enterprise Workflow (KEW)

Phase IIA Deliverables (July 2007) Accounts Payable/Purchasing…..’Kualification’ Budget Construction Labor Ledger Research Administration/Grants & Contracts

Phase IIB Deliverables (Mar 2008) Accounts Receivable Capital Assets Management System