COMPUTOS METRICOS SEDE DE CADECO 1. PLANTA 1 1.1 ZAPATAS 1.1.1 EDIFICIO CADECO ZAPATAS a b c = d e f v1 v2 V Total SIMPLES m m m m m m3 m3 m3 ZAPATA C1 0.25 0.3 0.5 2.5 2.5 1.563 0.775 2.338 ZAPATA C2 0.25 0.4 0.5 2.8 2.8 1.960 1.265 3.225 ZAPATA C3 0.25 0.2 0.5 2.1 2.1 1.103 0.381 1.483 ZAPATA C4 0.25 0.35 0.5 2.7 2.7 1.823 1.037 2.860 ZAPATA C5 0.25 0.65 0.5 4 4 4.000 3.954 7.954 ZAPATA C6 0.25 0.45 0.5 3 3 2.250 1.613 3.863 ZAPATA C11 0.25 0.35 0.5 2.6 2.6 1.690 0.970 2.660 SUBTOTAL ZAPATAS SIMPL24.382 m3 ZAPATAS a b c d e f v1 v2 V Total LATERALES m m m m m m m3 m3 m3 ZAPATA C28 0.25 0.15 0.4 0.35 1.8 0.9 0.405 0.112 0.517 ZAPATA C29 0.25 0.05 0.4 0.35 0.9 0.65 0.146 0.017 0.163 SUBTOTAL ZAPATAS LATERALES = 0.680 ZAPATAS a b c d e f v1 v2 V Total COMBINADAS m m m m m m m3 m3 m3 ZAPATA C7-C10 0.25 0.6 3.3 0.5 6.55 3.7 6.059 6.442 12.500 ZAPATA C8-C9 0.25 0.3 3.5 0.4 5.55 2.4 3.330 1.904 5.234 ZAPATA C12-C13-C17 0.25 0.35 0.73 2.3 2.95 4.5 3.319 2.295 5.614 ZAPATA C14-C15-C16 0.25 0.35 0.73 2.3 2.85 4.4 3.135 2.194 5.329 ZAPATA DE ASCENSOR 0.25 0.35 2.2 2.2 4.35 4.4 4.785 3.921 8.706 SUBTOTAL ZAPATAS LATERALES = 37.383 TOTAL VOLUMEN DE ZAPATA = 62.445 1.1.2AUDITORIO ZAPATAS a b c = d e f v1 v2 V Total m m m m m m3 m3 m3 ZAPATA C18 0.25 0.05 0.5 1.5 1.5 0.563 0.054 0.617 ZAPATA C19 0.25 0.05 0.5 1.5 1.5 0.563 0.054 0.617 ZAPATA C20-C21-C26-C27 0.25 0.1 2.1 2.6 2.6 1.690 0.554 2.244 ZAPATA C22-C22-C24-C25 0.25 0.1 2.1 2.65 2.65 1.756 0.567 2.322 TOTAL VOLUMEN DE ZAPATA = 5.800 m3 1.1.3 BAÑOS EXTERIORES ZAPATAS a b c d e f v1 v2 V Total m m m m m m m3 m3 m3

Computos Metricos Obra Gruesa

Embed Size (px)

DESCRIPTION

COMPUTOS PARA QUE PUEDAS HACERLOS

Citation preview

Page 1: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 1. PLANTA 1 1.1 ZAPATAS 1.1.1 EDIFICIO CADECO

ZAPATAS a b c = d e f v1 v2 V TotalSIMPLES m m m m m m3 m3 m3

ZAPATA C1 0.25 0.3 0.5 2.5 2.5 1.563 0.775 2.338ZAPATA C2 0.25 0.4 0.5 2.8 2.8 1.960 1.265 3.225ZAPATA C3 0.25 0.2 0.5 2.1 2.1 1.103 0.381 1.483ZAPATA C4 0.25 0.35 0.5 2.7 2.7 1.823 1.037 2.860ZAPATA C5 0.25 0.65 0.5 4 4 4.000 3.954 7.954ZAPATA C6 0.25 0.45 0.5 3 3 2.250 1.613 3.863

ZAPATA C11 0.25 0.35 0.5 2.6 2.6 1.690 0.969 2.660 SUBTOTAL ZAPATAS SIMPLES = 24.382 m3

ZAPATAS a b c d e f v1 v2 V TotalLATERALES m m m m m m m3 m3 m3ZAPATA C28 0.25 0.15 0.4 0.35 1.8 0.9 0.405 0.112 0.517ZAPATA C29 0.25 0.05 0.4 0.35 0.9 0.65 0.146 0.017 0.163

SUBTOTAL ZAPATAS LATERALES = 0.680 m3ZAPATAS a b c d e f v1 v2 V Total

COMBINADAS m m m m m m m3 m3 m3ZAPATA C7-C10 0.25 0.6 3.3 0.5 6.55 3.7 6.059 6.442 12.500ZAPATA C8-C9 0.25 0.3 3.5 0.4 5.55 2.4 3.330 1.904 5.234

ZAPATA C12-C13-C17 0.25 0.35 0.73 2.3 2.95 4.5 3.319 2.295 5.614ZAPATA C14-C15-C16 0.25 0.35 0.73 2.3 2.85 4.4 3.135 2.194 5.329ZAPATA DE ASCENSOR 0.25 0.35 2.2 2.2 4.35 4.4 4.785 3.921 8.706

SUBTOTAL ZAPATAS LATERALES = 37.383 m3TOTAL VOLUMEN DE ZAPATA = 62.445 m3

1.1.2AUDITORIO

ZAPATAS a b c = d e f v1 v2 V Totalm m m m m m3 m3 m3

ZAPATA C18 0.25 0.05 0.5 1.5 1.5 0.563 0.054 0.617ZAPATA C19 0.25 0.05 0.5 1.5 1.5 0.563 0.054 0.617

ZAPATA C20-C21-C26-C27 0.25 0.1 2.1 2.6 2.6 1.690 0.554 2.244ZAPATA C22-C22-C24-C25 0.25 0.1 2.1 2.65 2.65 1.756 0.567 2.322

TOTAL VOLUMEN DE ZAPATA = 5.800 m3

1.1.3 BAÑOS EXTERIORES

ZAPATAS a b c d e f v1 v2 V Totalm m m m m m m3 m3 m3

Page 2: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO

1.2 COLUMNAS1.2.1 EDIFICIO CADECO

COLUMNAS a b c V Totalm m m m3

COLUMNA 1 0.4 0.3 5.94 0.713COLUMNA 2 0.3 0.4 5.94 0.713COLUMNA 3 0.4 0.3 5.94 0.713COLUMNA 4 0.3 0.4 5.94 0.713COLUMNA 5 0.4 0.4 5.94 0.950COLUMNA 6 0.4 0.3 5.94 0.713COLUMNA 7 0.4 0.4 5.94 0.950COLUMNA 8 0.4 0.3 5.94 0.713COLUMNA 9 0.4 0.3 5.94 0.713

COLUMNA 10 0.4 0.4 5.94 0.950COLUMNA 11 0.3 0.4 5.94 0.713COLUMNA 12 0.3 0.4 5.94 0.713COLUMNA 13 0.3 0.4 5.94 0.713COLUMNA 14 0.3 0.4 5.94 0.713COLUMNA 15 0.3 0.3 5.94 0.535COLUMNA 28 0.3 0.3 5.94 0.535COLUMNA 29 0.3 0.3 5.94 0.535

TOTAL VOLUMEN DE C 12.296 m31.2.2 AUDITORIO

COLUMNAS a b c V Totalm m m m3

COLUMNA 16 0.3 0.4 7.28 0.874COLUMNA 17 0.3 0.4 7.28 0.874COLUMNA 18 0.4 0.3 7.28 0.874COLUMNA 19 0.4 0.3 7.28 0.874COLUMNA 20 0.3 0.4 7.28 0.874COLUMNA 21 0.4 0.3 7.28 0.874COLUMNA 22 0.4 0.3 7.28 0.874COLUMNA 23 0.3 0.4 7.28 0.874COLUMNA 24 0.3 0.3 7.28 0.655COLUMNA 25 0.3 0.3 7.28 0.655COLUMNA 26 0.3 0.3 7.28 0.655COLUMNA 27 0.3 0.3 7.28 0.655

TOTAL VOLUMEN DE C 9.610 m31.2.3 BAÑOS ESTERIORES

COLUMNAS a b c V Totalm m m m3

Page 3: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO

1.3 VIGAS

1.3.1 EDIFICIO CADECO

PORTICOS a b c d e f g h i V Totalm m m m m m m m m m3

PORTICOS 1 0.15 0.3 0.6 0.027PORTICOS 2 0.15 0.3 0.6 0.027PORTICOS 3 0.15 0.3 5.25 0.23625PORTICOS 4 0.15 0.3 3.01 0.13545PORTICOS 5 0.15 0.3 12 0.54PORTICOS 6 0.4 0.3 5.6 0.672PORTICOS 7 0.4 0.3 9.71 1.1652PORTICOS 8 0.2 0.5 1.9 0.19PORTICOS 9 0.15 0.3 2.97 0.13365

PORTICOS 10 0.15 0.3 1.1 0.0495PORTICOS 11 0.4 0.3 3.21 0.3852PORTICOS 12 0.15 0.3 1.09 0.04905PORTICOS 13 0.4 0.3 14.99 1.7988PORTICOS 14 0.15 0.3 2.41 0.10845PORTICOS 15 0.15 0.3 0.8 0.036PORTICOS 16 0.15 0.3 1.09 0.04905PORTICOS 17 0.2 0.5 5.59 0.15 0.3 2.31 0.66295PORTICOS 18 0.2 0.5 3.25 0.15 0.3 0.95 0.36775PORTICOS 19 0.2 0.5 2.1 0.21PORTICOS 20 0.2 0.5 3 0.3PORTICOS 21 0.2 0.5 6.61 0.661PORTICOS 22 0.15 0.3 0.8 0.036PORTICOS 23 0.15 0.3 2.6 0.117PORTICOS 24 0.2 0.5 10.3 0.15 0.3 1.87 1.11415PORTICOS 25 0.15 0.3 0.82 0.0369PORTICOS 26 0.4 0.3 5.4 0.2 0.5 4.9 0.15 0.3 1.86 1.2217PORTICOS 27 0.15 0.3 1.5 0.0675PORTICOS 28 0.2 0.5 0.5 0.05PORTICOS 29 0.15 0.3 0.71 0.03195PORTICOS 30 0.4 0.3 8.6 1.032PORTICOS 31 0.2 0.5 0.5 0.05

Page 4: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO PORTICOS 32 0.4 0.3 10.5 1.26PORTICOS 33 0.15 0.3 3.69 0.16605PORTICOS 34 0.15 0.3 0.5 0.0225PORTICOS 35 0.15 0.3 1.1 0.0495PORTICOS 36 0.15 0.3 1.4 0.063PORTICOS 37 0.15 0.3 1.31 0.05895PORTICOS 38 0.15 0.3 3.3 0.1485PORTICOS 39 0.2 0.5 7.65 0.765PORTICOS 40 0.15 0.3 2 0.09PORTICOS 41 0.15 0.3 12.5 0.5625

TOTAL VOLUMEN DE VIGAS = 14.7475 m31.3.2 AUDITORIO

PORTICOS a b c d e f g h i V Totalm m m m m m m m m m3

PORTICOS 1 0.2 0.4 1.4 0.112PORTICOS 2 0.45 0.35 11.01 1.73408PORTICOS 3 0.2 0.4 1.4 0.112PORTICOS 4 0.2 0.4 1.39 0.1112PORTICOS 5 0.45 0.35 11.01 1.73408PORTICOS 6 0.2 0.4 1.4 0.112PORTICOS 7 0.2 0.4 2 0.16PORTICOS 8 0.2 0.4 10.5 0.84

TOTAL VOLUMEN DE VIGAS = 4.91535 m31.3.3 BAÑOS EXTERIORES

PORTICOS a b c d e f g h i V Totalm m m m m m m m m m3

1.4 LOSA ENCACETONADA

Page 5: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO

LOSAS a b A Totalm m m2

LOSA 1 4.9 5 24.500LOSA 2 5.05 4.5 22.725LOSA 3 5.15 0.85 4.378LOSA 4 0.3 0.5 0.150LOSA 5 0.3 1.2 0.360LOSA 6 2.55 4.7 11.985LOSA 6 0.85 0.3 0.255 12.240LOSA 7 2.6 0.7 1.820LOSA 8 5.4 4.65 25.110LOSA 8 2.35 0.3 0.705 25.815LOSA 9 5.4 2.8 15.120LOSA 9 3.7 0.75 2.775 17.895LOSA 10 3.7 0.85 3.145LOSA 11 1.5 0.85 1.275LOSA 12 0.55 6.35 3.493LOSA 12 0.95 2.8 2.660LOSA 12 0.9 1.85 1.665LOSA 12 2.75 0.7 1.925 9.743LOSA 13 1.35 1.8 2.430LOSA 14 1.95 2.2 4.290LOSA 14 1.95 5 9.750 14.040LOSA 15 2.3 0.7 1.610

TOTAL DE LOSAS= 142.1 m2

1.5. CAJON DE ASCENSORMURO a b c V Total

m m m m3MURO 1 0.2 0.5 5.94 0.594MURO 2 1.7 0.2 5.94 2.0196MURO 3 0.2 2.1 5.94 2.4948MURO 4 1.7 0.2 5.94 2.0196MURO 5 0.2 0.5 5.94 0.594

TOTAL VOLUMEN CAJON DE ASCENSOR= 7.7 m3

1.6 MURO PERIMETRALMURO a b A Total

m m m3MURO 1 50 2.5 125MURO 2 16 2.5 40MURO 3 50 2.5 125

TOTAL MURO PERIMETRAL= 290 m2

Page 6: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO

1.7 MURO LADRILLO 6 HUECOS e=15cm 1.7.1 EDIFICIO CADECO

DESCRIPCION a b A Totalm m m2

CIRCULACION Y ESTARES 45.8 3.4 155.72GERENCIA GENERAL 7.5 3.4 25.500HALL DE INGRESO 8.5 3.4 28.900

210.12 m2

1.7.2 AUDITORIODESCRIPCION a b A Total

m m m2MURO SIN VENTANAS 4.36 4 17.44MURO CON VENTANA 10.32 6.28 64.81

82.25 m21.7.3 BAÑOS EXTERIORES

DESCRIPCION a b A Totalm m m2

MURO SIN VENTANAS 7.5 2.82 21.15MURO CON VENTANA 5.86 2.82 16.53

37.68 m2

1.8 MURO LADRILLO 6 HUECOS e=10cm 1.8.1 EDIFICIO CADECO

DESCRIPCION a b A Totalm m m2

BAÑOS 4.7 3.4 15.980COCINETA 3.8 3.4 12.920

SALA DE REUNION 9.8 3.4 33.32062.22 m2

1.8.2 AUDITORIODESCRIPCION a b A Total

m m m2MURO SIN VENTANAS 2.8 4.5 12.60MURO CON VENTANA 0.00

12.60 m21.8.3 BAÑOS EXTERIORES

DESCRIPCION a b A Totalm m m2

MURO SIN VENTANAS 10.6 2.82 29.89MURO CON VENTANA 0.00

29.89 m2

1.9 CIMIENTO CORRIDO DE HORMIGON ARMADO 1.9.1 EDIFICIO CADECO

DESCRIPCION a b c V Totalm m m m3

CIMIENTO 117.9 0.2 0.4 9.432

Page 7: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 9.43 m3

1.9.2 AUDITORIO

DESCRIPCION a b c V Totalm m m m3

CIMIENTO 50.1 0.2 0.4 4.0084.01 m2

1.9.3 BAÑOS EXTERIORES

DESCRIPCION a b c V Totalm m m m3

CIMIENTO 34.2 0.2 0.4 2.7362.74 m2

Page 8: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 2. PLANTA 22.1 COLUMNAS

COLUMNAS a b c V Totalm m m m3

COLUMNA 1 0.4 0.3 3.4 0.408COLUMNA 2 0.3 0.4 3.4 0.408COLUMNA 3 0.4 0.3 3.4 0.408COLUMNA 4 0.3 0.4 3.4 0.408COLUMNA 5 0.4 0.3 3.4 0.408COLUMNA 6 0.4 0.3 3.4 0.408COLUMNA 7 0.4 0.3 3.4 0.408COLUMNA 8 0.4 0.3 3.4 0.408COLUMNA 9 0.4 0.3 3.4 0.408

COLUMNA 10 0.3 0.4 3.4 0.408COLUMNA 11 0.3 0.4 3.4 0.408COLUMNA 12 0.3 0.4 3.4 0.408COLUMNA 13 0.3 0.4 3.4 0.408COLUMNA 14 0.3 0.4 3.4 0.408COLUMNA 15 0.3 0.3 3.4 0.306

TOTAL VOLUMEN DE COLUMNA = 6.018 m3

2.2 VIGAS

PORTICOS a b c d e f g h i V Totalm m m m m m m m m m3

PORTICOS 1 0.15 0.3 0.6 0.027PORTICOS 2 0.15 0.3 0.6 0.027PORTICOS 3 0.15 0.3 5.45 0.24525PORTICOS 4 0.15 0.3 3.01 0.13545PORTICOS 5 0.15 0.3 12 0.54PORTICOS 6 0.4 0.3 5.6 0.672PORTICOS 7 0.15 0.3 0.56 0.0252PORTICOS 8 0.3 0.4 9.71 1.1652PORTICOS 9 0.2 0.5 1.9 0.19

PORTICOS 10 0.4 0.3 3.21 0.3852PORTICOS 11 0.15 0.3 0.56 0.0252PORTICOS 12 0.4 0.3 19.7 2.364PORTICOS 13 0.15 0.3 2.4 0.108PORTICOS 14 0.15 0.3 0.8 0.036PORTICOS 15 0.2 0.5 5.59 0.15 0.3 0.81 0.59545PORTICOS 16 0.2 0.5 3.25 0.15 0.3 0.95 0.36775

Page 9: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO PORTICOS 17 0.2 0.5 2.1 0.21PORTICOS 18 0.2 0.5 3 0.3PORTICOS 19 0.2 0.5 6.61 0.661PORTICOS 20 0.15 0.3 0.8 0.036PORTICOS 21 0.2 0.5 10.3 0.15 0.3 1.87 1.11415PORTICOS 22 0.15 0.3 0.82 0.0369PORTICOS 23 0.4 0.3 5.4 0.2 0.5 4.9 0.15 0.3 1.86 1.2217PORTICOS 24 0.15 0.3 1.5 0.0675PORTICOS 25 0.2 0.5 0.5 0.05PORTICOS 26 0.15 0.3 0.71 0.03195PORTICOS 27 0.4 0.3 8.6 1.032PORTICOS 28 0.2 0.5 0.5 0.05PORTICOS 29 0.4 0.3 10.5 1.26PORTICOS 30 0.15 0.3 0.5 0.0225PORTICOS 31 0.2 0.5 7.65 0.765PORTICOS 32 0.15 0.3 2 0.09PORTICOS 33 0.15 0.3 5.3 0.2385PORTICOS 34 0.15 0.3 0.6 0.027PORTICOS 35 0.15 0.3 0.6 0.027

TOTAL VOLUMEN DE VIGAS = 14.15 m3

2.3 LOSA ENCACETONADA

LOSAS a b A Totalm m m2

LOSA 1 4.9 5 24.500LOSA 2 5.05 4.5 22.725LOSA 3 5.15 0.85 4.378LOSA 4 0.3 0.5 0.150LOSA 5 0.3 1.2 0.360LOSA 6 2.55 4.7 11.985LOSA 6 0.85 0.3 0.255 12.240LOSA 7 2.6 0.7 1.820

Page 10: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO LOSA 8 5.4 4.65 25.110LOSA 8 2.35 0.3 0.705 25.815LOSA 9 5.4 2.8 15.120LOSA 9 3.7 0.75 2.775 17.895LOSA 10 3.7 0.85 3.145LOSA 11 5.15 4 20.600LOSA 11 0.65 1.7 1.105 21.705LOSA 12 5.15 3.5 18.025LOSA 13 5.15 0.85 4.378LOSA 14 1.5 5 7.500

TOTAL DE LOSAS = 164.6 m2

2.4. CAJON DE ASCENSOR

MURO a b c V Totalm m m m3

MURO 1 0.2 0.5 3.4 0.34MURO 2 1.7 0.2 3.4 1.156MURO 3 0.2 2.1 3.4 1.428MURO 4 1.7 0.2 3.4 1.156MURO 5 0.2 0.5 3.4 0.34

TOTAL VOLUMEN CAJON DE ASCENSOR= 4.4 m3

2.5 MURO LADRILLO 6 HUECOS e=15cm

DESCRIPCION a b A Totalm m m2

PRESIDENCIA 2.7 3.4 9.18SALA DE REUNION 23.3 3.4 79.22

COCINETA Y BAÑOS 12.2 3.4 41.48CIRCULARION Y ESTARES 23.5 3.4 79.90

209.78 m2

2.6 MURO LADRILLO 6 HUECOS e=10cm

DESCRIPCION a b A Totalm m m2

BAÑOS Y COCINETA 9.4 3.4 31.96PRESIDENCIA 21.9 3.4 74.46

106.42 m2

2.7 ESCALERAESCALERA a b c V Total

m m m m3LOSA 0.3 1.25 2.6 0.975

LOSA DE GRADAS 0.3 3.5 1.15 1.0510 GRADAS 0.3 0.17 1.15 0.255

LOSA DE GRADAS 0.3 3.5 1.15 1.0510 GRADAS 0.3 0.17 1.15 0.255

TOTAL VOLUMEN ESCALERA= 2.28 m3

Page 11: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 3. PLANTA 33.1 COLUMNAS

COLUMNAS a b c V Totalm m m m3

COLUMNA 1 0.3 0.3 3.4 0.306COLUMNA 2 0.3 0.3 3.4 0.306COLUMNA 3 0.3 0.3 3.4 0.306COLUMNA 4 0.3 0.4 3.4 0.408COLUMNA 5 0.3 0.3 3.4 0.306COLUMNA 6 0.3 0.3 3.4 0.306COLUMNA 7 0.3 0.3 3.4 0.306COLUMNA 8 0.3 0.3 3.4 0.306COLUMNA 9 0.3 0.3 3.4 0.306

COLUMNA 10 0.3 0.3 3.4 0.306COLUMNA 11 0.3 0.3 3.4 0.306COLUMNA 12 0.3 0.3 3.4 0.306COLUMNA 13 0.3 0.3 3.4 0.306COLUMNA 14 0.3 0.3 3.4 0.306COLUMNA 15 0.3 0.3 3.4 0.306

TOTAL VOLUMEN DE COLUMNA = 4.692 m3

3.2 VIGAS

PORTICOS a b c d e f g h i V Totalm m m m m m m m m m3

PORTICOS 1 0.15 0.3 0.6 0.027PORTICOS 2 0.15 0.3 0.6 0.027PORTICOS 3 0.15 0.3 5.45 0.24525PORTICOS 4 0.15 0.3 3.01 0.13545PORTICOS 5 0.15 0.3 1.4 0.063PORTICOS 6 0.15 0.3 3.11 0.13995PORTICOS 7 0.4 0.3 5.15 0.618PORTICOS 8 0.15 0.3 1.1 0.0495PORTICOS 9 0.15 0.3 1.19 0.05355

PORTICOS 10 0.4 0.3 10.31 1.2372PORTICOS 11 0.2 0.5 1.9 0.19PORTICOS 12 0.15 0.3 1.01 0.04545PORTICOS 13 0.4 0.3 3.21 0.3852PORTICOS 14 0.4 0.3 14.15 0.2 0.5 5.54 2.252PORTICOS 15 0.15 0.3 1.01 0.04545PORTICOS 16 0.2 0.5 5.64 0.15 0.3 0.76 0.5982

Page 12: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO PORTICOS 17 0.2 0.5 3.25 0.15 0.3 0.95 0.36775PORTICOS 18 0.2 0.5 2.1 0.21PORTICOS 19 0.2 0.5 3 0.3PORTICOS 20 0.2 0.5 6.61 0.661PORTICOS 21 0.15 0.3 0.8 0.036PORTICOS 22 0.2 0.5 10.35 0.15 0.3 1.82 1.1169PORTICOS 23 0.15 0.3 0.82 0.0369PORTICOS 24 0.4 0.3 5.35 0.2 0.5 5 0.15 0.3 1.81 1.22345PORTICOS 25 0.15 0.3 1.5 0.0675PORTICOS 26 0.2 0.5 0.5 0.05PORTICOS 27 0.15 0.3 0.71 0.03195PORTICOS 28 0.4 0.3 8.6 1.032PORTICOS 29 0.2 0.5 0.5 0.05PORTICOS 30 0.15 0.3 0.35 0.01575PORTICOS 31 0.15 0.3 0.35 0.01575PORTICOS 32 0.4 0.3 10.5 1.26PORTICOS 33 0.15 0.3 0.5 0.0225PORTICOS 34 0.15 0.3 0.5 0.0225PORTICOS 35 0.4 0.3 8.5 1.02PORTICOS 36 0.15 0.3 2 0.09PORTICOS 37 0.15 0.3 2 0.09

TOTAL VOLUMEN DE VIGAS = 13.83 m3

3.3 LOSA ENCACETONADA

LOSAS a b A Totalm m m2

LOSA 1 4.9 5 24.500LOSA 2 5.1 4.5 22.950LOSA 3 5.15 0.85 4.378LOSA 4 0.3 0.52 0.156LOSA 5 0.3 1.2 0.360

Page 13: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO LOSA 6 0.91 0.3 0.273LOSA 6 2.61 4.7 12.267 12.540LOSA 7 2.71 0.71 1.924LOSA 8 2.4 0.3 0.720LOSA 8 5.4 4.7 25.380 26.100LOSA 9 5.4 2.8 15.120LOSA 9 3.71 0.7 2.597 17.717LOSA 10 3.71 0.65 2.412LOSA 10 0.85 0.2 0.170LOSA 10 1.75 0.2 0.350 2.932LOSA 11 4.99 4 19.960LOSA 12 4.99 3.5 17.465LOSA 13 0.64 0.2 0.128LOSA 14 0.46 1.7 0.782LOSA 15 0.46 1.45 0.667

TOTAL DE LOSAS = 152.6 m2

3.4. CAJON DE ASCENSOR

MURO a b c V Totalm m m m3

MURO 1 0.2 0.5 3.4 0.34MURO 2 1.7 0.2 3.4 1.156MURO 3 0.2 2.1 3.4 1.428MURO 4 1.7 0.2 3.4 1.156MURO 5 0.2 0.5 3.4 0.34

TOTAL VOLUMEN CAJON DE ASCENSOR= 4.4 m3

3.5 MURO LADRILLO 6 HUECOS e=15cm

DESCRIPCION a b A Totalm m m2

PLANTA LIBRE 61.3 3.4 208.42BAÑO Y COCINETA 11.5 3.4 39.10

247.52 m2

3.6 MURO LADRILLO 6 HUECOS e=10cm

DESCRIPCION a b A Totalm m m2

BAÑOS Y COCINETA 10.5 3.4 35.70PLANTA LIBRE 3.4 0.00

35.70 m2

3.7 ESCALERAESCALERA a b c V Total

m m m m3LOSA 0.3 1.25 2.6 0.975

LOSA DE GRADAS 0.3 3.5 1.15 1.0510 GRADAS 0.3 0.17 1.15 0.255

LOSA DE GRADAS 0.3 3.5 1.15 1.0510 GRADAS 0.3 0.17 1.15 0.255

Page 14: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO TOTAL VOLUMEN ESCALERA= 2.28 m3

Page 15: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 4. PLANTA 44.1 COLUMNAS

COLUMNAS a b c V Totalm m m m3

COLUMNA 1 0.3 0.3 4.9 0.441COLUMNA 2 0.3 0.3 4.9 0.441COLUMNA 3 0.3 0.3 4.9 0.441COLUMNA 4 0.3 0.3 6.6 0.594COLUMNA 5 0.3 0.3 6.6 0.594COLUMNA 6 0.3 0.3 6.6 0.594COLUMNA 7 0.3 0.3 6.6 0.594COLUMNA 8 0.3 0.3 6.6 0.594COLUMNA 9 0.3 0.3 4.9 0.441

COLUMNA 10 0.3 0.3 3.4 0.306COLUMNA 11 0.3 0.3 4.9 0.441COLUMNA 12 0.3 0.3 4.9 0.441COLUMNA 13 0.3 0.3 4.9 0.441COLUMNA 14 0.3 0.3 4.9 0.441COLUMNA 15 0.3 0.3 4.9 0.441COLUMNA 30 0.3 0.3 3.2 0.288

TOTAL VOLUMEN DE COLUMNA = 7.533 m3

4.2 VIGAS

4.2.1 VIGAS LOSA CUBIERTA 1PORTICOS a b c d e f g h i V Total

m m m m m m m m m m3PORTICOS 1 0.15 0.25 5.9 0.22125PORTICOS 2 0.15 0.25 3.01 0.11287PORTICOS 3 0.15 0.25 5.26 0.19725PORTICOS 4 0.4 0.25 10.31 1.031PORTICOS 5 0.4 0.25 5.6 0.56PORTICOS 6 0.2 0.5 1.9 0.19PORTICOS 7 0.15 0.25 1.01 0.03788PORTICOS 8 0.4 0.25 19.69 1.969PORTICOS 9 0.15 0.25 1.01 0.03788

PORTICOS 10 0.2 0.5 5.64 0.15 0.25 0.76 0.5925PORTICOS 11 0.2 0.4 2.1 0.168PORTICOS 12 0.2 0.4 6.61 0.5288PORTICOS 13 0.2 0.4 6.05 0.15 0.25 0.95 0.51963PORTICOS 14 0.2 0.4 10.35 0.15 0.2 1.85 0.8835PORTICOS 15 0.4 0.25 5.35 0.2 0.5 5 0.15 0.25 0.46 1.05225

Page 16: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO PORTICOS 16 0.15 0.25 1.54 0.05775PORTICOS 17 0.2 0.4 0.5 0.04PORTICOS 18 0.15 0.25 0.51 0.01913PORTICOS 19 0.4 0.25 8.6 0.86PORTICOS 20 0.4 0.25 7.88 0.4 0.3 2.62 1.1024PORTICOS 21 0.15 0.25 1.2 0.045PORTICOS 22 0.15 0.25 1.4 0.0525PORTICOS 23 0.4 0.25 8.5 0.85PORTICOS 24 0.15 0.25 3.25 0.12188PORTICOS 25 0.15 0.25 3.25 0.12188

SUBTOTAL VOLUMEN DE VIGAS CUBIERTA 1 = 11.37 m34.2.2 VIGAS LOSA CUBIERTA 2

PORTICOS a b c d e f g h i V Totalm m m m m m m m m m3

PORTICOS 1 0.15 0.25 1.1 0.04125PORTICOS 2 0.2 0.4 6.1 0.488PORTICOS 3 0.2 0.4 6.2 0.496PORTICOS 4 0.2 0.4 6.05 0.15 0.25 0.95 0.51963PORTICOS 5 0.2 0.4 6.05 0.15 0.25 0.95 0.51963PORTICOS 6 0.2 0.4 10.5 0.84PORTICOS 7 0.2 0.4 10.5 0.84PORTICOS 8 0.15 0.25 10.5 0.39375

SUBTOTAL VOLUMEN DE VIGAS CUBIERTA 2 = 4.14 m3 TOTAL VOLUMEN DE VIGAS = 15.51 m3

4.3 LOSA ALIVIANADA 1 DIRECCION

4.3.1 LOSA CUBIERTA 1

LOSAS a b A Totalm m m2

LOSA 1 4.9 5 24.500LOSA 2 5.1 4.5 22.950LOSA 3 5.15 0.31 1.597

Page 17: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO LOSA 3 5.6 1.24 6.944 8.541LOSA 4 0.91 0.3 0.273LOSA 4 2.61 4.7 12.267 12.540LOSA 5 2.61 5.06 13.207LOSA 6 5.4 5 27.000LOSA 9 3.71 0.85 3.153

LOSA 10 0.65 0.85 0.553LOSA 11 4.99 4 19.960LOSA 12 4.99 3.5 17.465LOSA 13 0.65 0.85 0.553LOSA 14 0.46 2.95 1.357LOSA 15 0.46 2.7 1.242

SUBTOTAL DE LOSAS CUBIERTA 1 = 153.0 m24.3.2 LOSA CUBIERTA 2

LOSAS a b A Totalm m m2

LOSA 16 5.8 5 29.000LOSA 17 5.8 3.7 21.460LOSA 18 5.7 1 5.700LOSA 19 0.65 5.05 3.283LOSA 20 0.65 4.15 2.6975LOSA 20 0.75 0.85 0.638 3.335

SUBTOTAL DE LOSAS CUBIERTA 2 = 62.8 m2

TOTAL DE LOSAS = 215.8 m2

4.4 LOSA LLENALOSAS a b A Total

m m m2LOSA 7 5.4 2.8 15.120LOSA 7 3.71 0.7 2.597 17.717LOSA 8 1.7 1.7 2.890

TOTAL DE LOSAS = 20.6 m2

4.5. CAJON DE ASCENSOR

MURO a b c V Totalm m m m3

MURO 1 0.2 0.5 3.4 0.34MURO 2 1.7 0.2 3.4 1.156MURO 3 0.2 2.1 3.4 1.428MURO 4 1.7 0.2 3.4 1.156MURO 5 0.2 0.5 3.4 0.34

TOTAL VOLUMEN CAJON DE ASCENSOR= 4.4 m3

4.6 MURO LADRILLO 6 HUECOS e=15cm

DESCRIPCION a b A Totalm m m2

PLANTA LIBRE 51.8 3.4 176.12BAÑO Y COCINETA 11.5 3.4 39.10

Page 18: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 215.22 m2

4.7 MURO LADRILLO 6 HUECOS e=10cm

DESCRIPCION a b A Totalm m m2

BAÑOS Y COCINETA 10.5 3.4 35.70PLANTA LIBRE 4.5 3.4 15.30

51.00 m2

Page 19: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 1. PLANTA 1 1.1 PISO PORCELANATO1.1.1 EDIFICIO CADECO

DESCRIPCION a b A Totalm m m2

SALA DE REUNION 5.1 3 15.30COCINETA 2.1 2.8 5.88

BAÑOS 2.5 3.7 9.25CUARTO DE SONIDO 2.2 1.9 4.18

CIRCULARION Y ESTARES 2 4 8.00CIRCULARION Y ESTARES 4.6 1.5 6.90CIRCULARION Y ESTARES 3.6 1.3 4.68CIRCULARION Y ESTARES 2.1 6.2 13.02CIRCULARION Y ESTARES 4.7 2.5 11.75CIRCULARION Y ESTARES 2.6 3.5 9.10CIRCULARION Y ESTARES 4.8 5.2 24.96CIRCULARION Y ESTARES 0.8 2.2 1.76CIRCULARION Y ESTARES 1.5 3.5 5.25 85.42

HALL DE INGRESO AL 2° Y 3° PISO 3.1 2.6 8.06HALL DE INGRESO AL 2° Y 3° PISO 0.7 2.5 1.75HALL DE INGRESO AL 2° Y 3° PISO 1.5 2.2 3.3HALL DE INGRESO AL 2° Y 3° PISO 1.5 1.3 1.95 15.06

GRADAS PB AL 1° PISO 1.5 1.3 1.95GRADAS PB AL 1° PISO 1.2 2.1 2.52GRADAS PB AL 1° PISO 3.9 1.2 4.68GRADAS PB AL 1° PISO 3.9 1.2 4.68GRADAS PB AL 1° PISO 1.2 0.3 0.36GRADAS PB AL 1° PISO 2.3 1.2 2.76 16.95

TOTAL AREA DE PORCELANA = 152.04 m2

1.1.2 AUDITORIO

DESCRIPCION a b A Totalm m m2

AUDITORIO 10.8 9.5 102.60AUDITORIO 0.5 6.5 3.25

TOTAL AREA DE PORCELANA = 105.85 m2

1.1.3 BAÑOS EXTERIORES

DESCRIPCION a b A Totalm m m2

BAÑO MUJERES 6.3 1.6 10.08BAÑO MUJERES 4.5 0.7 3.15 13.23BAÑO HOMBRES 6.3 1.6 10.08BAÑO HOMBRES 4.5 0.7 3.15 13.23

Page 20: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO TOTAL AREA DE PORCELANA = 23.31 m2

1.2 PISO ENTABLONADO DE MADERA

DESCRIPCION a b A Totalm m m2

GERENCIA 3.2 4.5 14.40GERENCIA 0.5 1 0.50GERENCIA 0.5 2.1 1.05 15.95

ESCENARIO AUDITORIO 2.4 6 14.40ESCENARIO AUDITORIO 0.4 6 2.40 16.80

TOTAL AREA DE ENTABLONADO DE MADERA = 32.75 m2

1.3 PISO DE MOSAICO GRANITICO

DESCRIPCION a b A Totalm m m2

ACCESO PRINCIPAL 3.6 2.3 8.28ACCESO PRINCIPAL 2.5 1 2.50ACCESO PRINCIPAL 0.7 1 0.70ACCESO PRINCIPAL 2.5 0.9 2.25ACCESO PRINCIPAL 1 1.3 1.30ACCESO PRINCIPAL 2.5 1.4 3.50ACCESO PRINCIPAL 0.7 0.7 0.49 19.02

RAMPA 2.8 1 2.80RAMPA 1 1.7 1.70 4.50

RECORRIDOS EXTERIORES 10 1.9 19.00RECORRIDOS EXTERIORES 11.4 1.3 14.82RECORRIDOS EXTERIORES 3.9 0.3 1.17RECORRIDOS EXTERIORES 7.1 1.6 11.36RECORRIDOS EXTERIORES 0.5 1 0.50RECORRIDOS EXTERIORES 2 6.9 13.80RECORRIDOS EXTERIORES 1.7 6.5 11.05 71.70

TOTAL AREA DE MOSAICO GRANITICO = 95.22 m2

1.4 ZOCALO DE PORCELANA 1.4.1 EDIFICIO CADECO

DESCRIPCION a Totalm ml

CUARTO DE SONIDO 7.4 7.40CIRCULACION Y ESTARES 53.9 53.90

SALA DE REUNION 15.7 15.70HALL INGRESO AL 2° Y 3° PISO 16.3 16.30

TOTAL ML DE ZOCALO DE PORCELANA = 93.30 ml

1.4.2 AUDITORIO

Page 21: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO

DESCRIPCION a Totalm ml

AUDITORIO 13.3 13.30 TOTAL ML DE ZOCALO DE PORCELANA = 13.30 ml

1.5 ZOCALO DE MADERA

DESCRIPCION a Totalm ml

GERENCIA 12.8 12.80ESCENARIO DE AUDITORIO 9.5 9.50

TOTAL ML DE ZOCALO DE MADERA = 22.30 ml

1.6 REVOQUE INTERIOR DE YESO1.6.1 EDIFICIO CADECO

DESCRIPCION a b A Totalm m m2

ESCENARIO DE AUDITORIO 13.5 3.4 45.90PUERTAS 2 -2.2 -4.40

ESCENARIO DE AUDITORIO 41.50CUARTO DE SONIDO 8.2 4.5 36.90

PUERTAS 1 -2.2 -2.20VENTANAS 4 -0.6 -2.40

CUARTO DE SONIDO 32.30CIRCULACION Y ESTARES 56.8 3.4 193.12

PUERTAS 4 -2.2 -8.8VENTANAS 1.4 -2.2 -3.08VENTANAS 3 -3.1 -9.3VENTANAS 3 -2.6 -7.8VENTANAS 0.5 -2.6 -1.3PUERTAS 0.6 -2.2 -1.32

VENTANAS 1 -2.2 -2.2CIRCULACION Y ESTARES 159.32

SALA DE REUNIONES 16.4 3.4 55.76PUERTAS 1 -2.2 -2.2

VENTANAS 1.5 -2.4 -3.6SALA DE REUNIONES 49.96

HALL INGRESO AL 2° Y 3° PISO 16.5 3.4 56.1PUERTA Y VENTANA 2.6 -3.1 -8.06

HALL INGRESO AL 2° Y 3° PISO 48.04GERENCIA 13.7 3.4 46.58PUERTAS 1 -2.2 -2.2

VENTANAS 1 -2.6 -2.6GERENCIA 41.78

TOTAL AREA DE REVOQUE INTERIOR = 372.90 m2

Page 22: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO

1.6.2 AUDITORIO

DESCRIPCION a b A Totalm m m2

AUDITORIO 39.9 4.5 179.55ESCENARIO 6 -3.05 -18.30

PUERTAS 3 -2.5 -7.50PUERTAS 4 -4.5 -18.00

VENTANAS 3 -1.5 -4.50VENTANAS 8 -4.2 -33.60VENTANAS 1 -2.5 -2.50VENTANAS 8 -4 -32.00AUDITORIO 0.00

TOTAL AREA DE REVOQUE INTERIOR = 63.15 m2

1.7 REVOQUE INTERIOR IMPERMEABLE1.7.1 EDIFICIO CADECO

DESCRIPCION a b A Totalm m m2

COCINETA 10.1 3.4 34.34PUERTAS 1 -2.2 -2.20

VENTANAS 0.6 -2 -1.20COCINETA 30.94

BAÑOS 23.8 3.4 80.92PUERTA 2.4 -2.2 -5.28

VENTANAS 1.2 -2 -2.40BAÑOS 73.24

TOTAL AREA DE REVOQUE INTERIOR = 104.18 m2

1.7.2 BAÑOS EXTERIORES

DESCRIPCION a b A Totalm m m2

BAÑO VARONES 16.9 3.12 52.73MURO 4.8 2.5 12.00

PUERTAS 2.4 -2.5 -6.00VENTANAS 1 -0.6 -0.60

BAÑO VARONES 58.13BAÑO MUJERES 16.9 3.12 52.73

MURO 4.8 2.5 12.00PUERTAS 2.4 -2.5 -6.00

VENTANAS 6 -0.3 -1.80VENTANAS 1 -0.6 -0.60

BAÑO MUJERES 56.33 TOTAL AREA DE REVOQUE IMPERMEABLE = 114.46 m2

Page 23: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO

1.8 REVOQUE EXTERIOR BLANCO

DESCRIPCION a b A Totalm m m2

ELEVACION ESTE 1.2 17.8 21.36ELEVACION ESTE 9.5 3.4 32.30ELEVACION ESTE 12.5 0.6 7.50ELEVACION ESTE 4.8 0.6 2.88ELEVACION ESTE 3.2 0.6 1.92ELEVACION ESTE 3.5 0.5 1.75ELEVACION ESTE 7 0.5 3.50ELEVACION ESTE 2 2.5 5.00ELEVACION ESTE 3.5 0.25 0.88ELEVACION ESTE 0.6 3.5 2.10ELEVACION ESTE 79.18

ELEVACION OESTE 10.5 1.8 18.90ELEVACION OESTE 10.5 1.2 12.60ELEVACION OESTE 3.6 5 18.00ELEVACION OESTE 49.50ELEVACION NORTE 14 5.5 77.00ELEVACION NORTE 8 9.5 76.00ELEVACION NORTE 3.2 4 12.80ELEVACION NORTE 2.5 3.5 8.75ELEVACION NORTE 5.5 4 22.00ELEVACION NORTE 11.5 6.2 71.30ELEVACION NORTE 6.2 1 6.20

VENTANAS Y PUERTAS 7.7 -0.6 -4.62VENTANAS Y PUERTAS 0.9 -6 -5.40VENTANAS Y PUERTAS 2.7 -3.1 -8.37VENTANAS Y PUERTAS 2.4 -2 -4.80VENTANAS Y PUERTAS 1.5 -4.3 -6.45VENTANAS Y PUERTAS 4 -4 -16.00VENTANAS Y PUERTAS 0.6 -2.5 -1.50VENTANAS Y PUERTAS 4 -3.7 -14.80

ELEVACION NORTE 212.11ELEVACION SUD 7 18 126.00ELEVACION SUD 11.5 6.1 70.15ELEVACION SUD 6.1 1 6.10ELEVACION SUD 1.5 5.5 8.25ELEVACION SUD 1 1.5 1.50

VENTANAS Y PUERTAS 2.8 -13 -36.40VENTANAS Y PUERTAS 1.5 -3.8 -5.70VENTANAS Y PUERTAS 3.8 -3.8 -14.44VENTANAS Y PUERTAS 0.5 -2.5 -1.25

Page 24: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO VENTANAS Y PUERTAS 3.8 -3.6 -13.68

ELEVACION SUD 140.53VOLUMEN BAÑOS EXTERIORES 3.7 0.7 2.59VOLUMEN BAÑOS EXTERIORES 7.6 0.75 5.70VOLUMEN BAÑOS EXTERIORES 8 0.8 6.40VOLUMEN BAÑOS EXTERIORES 1.5 3.1 4.65VOLUMEN BAÑOS EXTERIORES 19.34

TOTAL AREA DE REVOQUE EXTERIOR = 500.67 m2

1.9 REVESTIMIENTO CERAMICO1.9.1 EDIFICIO CADECO

DESCRIPCION a b A Totalm m m2

COCINETA 10.1 3.4 34.34PUERTAS 1 -2.2 -2.20

VENTANAS 0.6 -2 -1.20COCINETA 30.94

BAÑOS 23.8 3.4 80.92PUERTA 2.4 -2.2 -5.28

VENTANAS 1.2 -2 -2.40BAÑOS 73.24

TOTAL AREA DE REVESTIMIENTO CERAMICO = 104.18 m2

1.9.2 BAÑOS EXTERIORES

DESCRIPCION a b A Totalm m m2

BAÑO VARONES 16.9 3.12 52.73MURO 4.8 2.5 12.00

PUERTAS 2.4 -2.5 -6.00VENTANAS 1 -0.6 -0.60

BAÑO VARONES 58.13BAÑO MUJERES 16.9 3.12 52.73

MURO 4.8 2.5 12.00PUERTAS 2.4 -2.5 -6.00

VENTANAS 6 -0.3 -1.80VENTANAS 1 -0.6 -0.60

BAÑO MUJERES 56.33 TOTAL AREA DE REVESTIMIENTO CERAMICO = 114.46 m2

1.9 REVESTIMIENTO ENCHAPADO DE MADERA

DESCRIPCION a b A Totalm m m2

GRADA PRINCIPAL 2.1 3.3 6.93

Page 25: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO GRADA PRINCIPAL 4.2 2 8.40GRADA PRINCIPAL 0.5 1.5 0.75GRADA PRINCIPAL 1.4 3.3 4.62

TOTAL AREA DE REVESTIMIENTO CERAMICO = 20.70 m2

1.10 TABLON DE MADERA

DESCRIPCION a Totalm ml

HUELLA 40.53 40.53 TOTAL ML TABLON DE MADERA = 40.53 ml

1.11 REVESTIMIENTO EXTERIOR DE ALUCOBOND

DESCRIPCION a b A Totalm m m2

ELEVACION ESTE 2 11.8 23.60ELEVACION ESTE 1.7 1.6 2.72ELEVACION ESTE 1.7 1.6 2.72ELEVACION ESTE 2 7 14.00ELEVACION ESTE 2 3.4 6.80ELEVACION ESTE 1.5 13 19.50ELEVACION ESTE 69.34

ELEVACION OESTE 12 10.1 121.20ELEVACION OESTE 1.5 2.8 4.20

VENTANAS 2.5 -5.5 -13.75VENTANAS 1 -5.5 -5.50

ELEVACION OESTE 106.15ELEVACION NORTE 5.3 7 37.10ELEVACION NORTE 6 13 78.00

VENTANAS 0.5 -21.9 -10.95VENTANAS 4.8 -10 -48.00

ELEVACION NORTE 56.15ELEVACION SUD 6.7 16.5 110.55ELEVACION SUD 5.3 15.5 82.15

VENTANAS 0.5 -39.6 -19.80VENTANAS 0.7 -1.2 -0.84VENTANAS 0.5 -2 -1.00VENTANAS 3 -3 -9.00VENTANAS 0.5 -31.5 -15.75

ELEVACION SUD 146.31VOLUMEN BAÑOS EXTERIORES 6.3 5 31.50

VENTANAS 0.3 -6 -1.80VOLUMEN BAÑOS EXTERIORES 29.70

VOLUMEN AZUL INGRESO PRINCIPAL Y LATERAL 2.8 2.5 7.00

Page 26: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO

VOLUMEN AZUL INGRESO PRINCIPAL Y LATERAL 0.5 4.2 2.10

VOLUMEN AZUL INGRESO PRINCIPAL Y LATERAL 1 3 3.00

VOLUMEN AZUL INGRESO PRINCIPAL Y LATERAL 0.5 5 2.50

VOLUMEN AZUL INGRESO PRINCIPAL Y LATERAL 2.8 1 2.80

VOLUMEN AZUL INGRESO PRINCIPAL Y LATERAL 17.40

TOTAL AREA DE REVESTIMIENTO EXTERIOR DE ALUCOBOND = 425.05 m2

1.12 CIELO RASO BAJO LOSA1.12.1 EDIFICIO CADECO

DESCRIPCION a b A Totalm m m2

SALA DE REUNION 5.1 3 15.30CUARTO DE SONIDO 2.2 1.9 4.18

CIRCULARION Y ESTARES 2 4 8.00CIRCULARION Y ESTARES 4.6 1.5 6.90CIRCULARION Y ESTARES 3.6 1.3 4.68CIRCULARION Y ESTARES 2.1 6.2 13.02CIRCULARION Y ESTARES 4.7 2.5 11.75CIRCULARION Y ESTARES 2.6 3.5 9.10CIRCULARION Y ESTARES 4.8 5.2 24.96CIRCULARION Y ESTARES 0.8 2.2 1.76CIRCULARION Y ESTARES 1.5 3.5 5.25 85.42

HALL DE INGRESO AL 2° Y 3° PISO 1.7 3.2 5.44HALL DE INGRESO AL 2° Y 3° PISO 2.7 1.4 3.78 9.22

GERENCIA 3.2 4.5 14.40GERENCIA 0.5 1 0.50GERENCIA 0.5 2.1 1.05 15.95

TOTAL AREA DE CIELO RASO BAJO LOSA = 130.07 m2

1.12.2 BAÑOS EXTERIORES

DESCRIPCION a b A Totalm m m2

BAÑO MUJERES 6.3 1.6 10.08BAÑO MUJERES 4.5 0.7 3.15 13.23BAÑO HOMBRES 6.3 1.6 10.08BAÑO HOMBRES 4.5 0.7 3.15 13.23

TOTAL AREA DE CIELO RASO BAJO LOSA = 23.31 m2

1.13 CIELO FALSO1.13.1 EDIFICIO CADECO

DESCRIPCION a b A Totalm m m2

COCINETA 2.1 2.8 5.88BAÑOS 2.5 3.7 9.25

Page 27: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO ESCENARIO AUDITORIO 2.4 6 14.40ESCENARIO AUDITORIO 0.4 6 2.40 16.80

TOTAL AREA DE CIELO FALSO = 31.93 m2

1.13.2 AUDITORIO

DESCRIPCION a b A Totalm m m2

AUDITORIO 10.8 9.5 102.60AUDITORIO 0.5 6.5 3.25 105.85

TOTAL AREA DE CIELO FALSO = 105.85 m2

1.14 PUERTAS DE VIDRIO TEMPLADO 10 MM

DESCRIPCION a b A Totalm m m2

INGR. LADO ESTE BALCON PUENTE 2 2.2 4.40INGR. LADO ESTE BALCON PUENTE 2 2.2 4.40 8.80

INGRESO LADO OESTE 6.5 2.55 16.58INGRESO LADO NORTE BALCON 1 2.2 2.20INGRESO LADO NORTE BALCON 1.4 2.6 3.64 5.84

INGRESO LADO SUD 1.4 2.6 3.64 TOTAL AREA PUERTA DE VIDRIO = 34.86 m2

1.15 PUERTAS DE TABLERO DE MADERA1.15.1 EDIFICIO CADECO

DESCRIPCION a b A Totalm m m2

PLANTA BAJA 7 2.2 15.40PLANTA BAJA 2.8 2.2 6.16 21.56

TOTAL AREA PUERTA DE MADERA = 21.56 m2

1.15.2 BAÑOS EXTERIORES

DESCRIPCION a b A Totalm m m2

BAÑOS MUJERES 2.7 2.2 5.94BAÑOS VARONES 2.7 2.2 5.94 11.88

TOTAL AREA PUERTA DE MADERA = 11.88 m2

1.16 PANEL DE VIDRIO REFLETIVO

DESCRIPCION a b A Totalm m m2

ELEVACION ESTE 2 3 6.00ELEVACION ESTE 2 3 6.00ELEVACION ESTE 2 2.2 4.40ELEVACION ESTE 4.2 3.3 13.86

Page 28: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO ELEVACION ESTE 2.2 4.8 10.56ELEVACION ESTE 4.5 5.2 23.40ELEVACION ESTE 1 1 1.00ELEVACION ESTE 65.22

ELEVACION OESTE 6.5 2.05 13.33ELEVACION OESTE 2.5 5.5 13.75ELEVACION OESTE 1 5.5 5.50ELEVACION OESTE 32.58ELEVACION NORTE 5 3 15.00ELEVACION NORTE 0.5 21.5 10.75ELEVACION NORTE 0.8 6 4.80ELEVACION NORTE 2.5 3 7.50ELEVACION NORTE 4.5 9.9 44.55ELEVACION NORTE 0.5 8 4.00ELEVACION NORTE 4 3.9 15.60ELEVACION NORTE 4 3.7 14.80ELEVACION NORTE 1.5 1.5 2.25

PUERTA 1.2 -2.5 -3.00ELEVACION NORTE 116.25

ELEVACION SUD 0.5 38.5 19.25ELEVACION SUD 3 13.3 39.90ELEVACION SUD 1.5 13.4 20.10ELEVACION SUD 0.5 2 1.00ELEVACION SUD 0.3 18.9 5.67ELEVACION SUD 4 4 16.00ELEVACION SUD 4 3.8 15.20ELEVACION SUD 1.5 1.5 2.25ELEVACION SUD 3 3 9.00ELEVACION SUD 128.37

VOLUMEN BAÑOS EXTERIORES 0.3 6 1.80 TOTAL AREA VIDRIO REFLECTIVO= 344.22 m2

1.17 VIDRIO TEMPLADO 10 MM

DESCRIPCION a b A Totalm m m2

GERENCIA 0.5 3.4 1.70GERENCIA 0.5 3.4 1.70 3.40

TOTAL AREA DE VIDRIO = 3.40 m2

1.18 BARANDA DE VIDRIO TEMPLADO 10 MM

DESCRIPCION a Totalm ml

GRADAS PRINCIPALES 5 5.00GRADAS PRINCIPALES 0.5 0.50

Page 29: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO TOTAL DE VIDRIO = 5.50 ml

1.19 BARANDA METALICA

DESCRIPCION a Totalm ml

GRADAS 7.5 7.50RAMPLA 9 9.00

TOTAL DE VIDRIO = 16.50 ml

1.20 CAJONERIA COCINETA

DESCRIPCION a Totalm ml

CAJONERIA 4.5 4.50 TOTAL CAJONERIA = 4.50 ml1.21 MESON DE GRANITO COCINETA

DESCRIPCION a b A Totalm m m2

COCINETA 2.8 0.6 1.68COCINETA 1.5 0.55 0.83

TOTAL AREA DE MESON = 2.51 m2

1.22 PINTURA OLEO INTERIOR1.22.1 EDIFICIO CADECO

DESCRIPCION a b A Totalm m m2

ESCENARIO DE AUDITORIO 13.5 3.4 45.90PUERTAS 2 -2.2 -4.40

ESCENARIO DE AUDITORIO 41.50CUARTO DE SONIDO 8.2 4.5 36.90

PUERTAS 1 -2.2 -2.20VENTANAS 4 -0.6 -2.40

CUARTO DE SONIDO 32.30CIRCULACION Y ESTARES 56.8 3.4 193.12

PUERTAS 4 -2.2 -8.8VENTANAS 1.4 -2.2 -3.08VENTANAS 3 -3.1 -9.3VENTANAS 3 -2.6 -7.8VENTANAS 0.5 -2.6 -1.3PUERTAS 0.6 -2.2 -1.32

VENTANAS 1 -2.2 -2.2CIRCULACION Y ESTARES 159.32

SALA DE REUNIONES 16.4 3.4 55.76PUERTAS 1 -2.2 -2.2

VENTANAS 1.5 -2.4 -3.6

Page 30: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO SALA DE REUNIONES 49.96

HALL INGRESO AL 2° Y 3° PISO 16.5 3.4 56.1PUERTA Y VENTANA 2.6 -3.1 -8.06

HALL INGRESO AL 2° Y 3° PISO 48.04GERENCIA 13.7 3.4 46.58PUERTAS 1 -2.2 -2.2

VENTANAS 1 -2.6 -2.6GERENCIA 41.78

TOTAL AREA DE PINTURA DE OLEO = 372.90 m2

1.22.2 AUDITORIO

DESCRIPCION a b A Totalm m m2

AUDITORIO 39.9 4.5 179.55ESCENARIO 6 -3.05 -18.30

PUERTAS 3 -2.5 -7.50PUERTAS 4 -4.5 -18.00

VENTANAS 3 -1.5 -4.50VENTANAS 8 -4.2 -33.60VENTANAS 1 -2.5 -2.50VENTANAS 8 -4 -32.00AUDITORIO 0.00

TOTAL AREA DE PINTURA DE OLEO = 63.15 m2

1.23 PINTURA EXTERIOR VOLUMEN BLANCO

DESCRIPCION a b A Totalm m m2

ELEVACION ESTE 1.2 17.8 21.36ELEVACION ESTE 9.5 3.4 32.30ELEVACION ESTE 12.5 0.6 7.50ELEVACION ESTE 4.8 0.6 2.88ELEVACION ESTE 3.2 0.6 1.92ELEVACION ESTE 3.5 0.5 1.75ELEVACION ESTE 7 0.5 3.50ELEVACION ESTE 2 2.5 5.00ELEVACION ESTE 3.5 0.25 0.88ELEVACION ESTE 0.6 3.5 2.10ELEVACION ESTE 79.18

ELEVACION OESTE 10.5 1.8 18.90ELEVACION OESTE 10.5 1.2 12.60ELEVACION OESTE 3.6 5 18.00

Page 31: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO ELEVACION OESTE 49.50ELEVACION NORTE 14 5.5 77.00ELEVACION NORTE 8 9.5 76.00ELEVACION NORTE 3.2 4 12.80ELEVACION NORTE 2.5 3.5 8.75ELEVACION NORTE 5.5 4 22.00ELEVACION NORTE 11.5 6.2 71.30ELEVACION NORTE 6.2 1 6.20

VENTANAS Y PUERTAS 7.7 -0.6 -4.62VENTANAS Y PUERTAS 0.9 -6 -5.40VENTANAS Y PUERTAS 2.7 -3.1 -8.37VENTANAS Y PUERTAS 2.4 -2 -4.80VENTANAS Y PUERTAS 1.5 -4.3 -6.45VENTANAS Y PUERTAS 4 -4 -16.00VENTANAS Y PUERTAS 0.6 -2.5 -1.50VENTANAS Y PUERTAS 4 -3.7 -14.80

ELEVACION NORTE 212.11ELEVACION SUD 7 18 126.00ELEVACION SUD 11.5 6.1 70.15ELEVACION SUD 6.1 1 6.10ELEVACION SUD 1.5 5.5 8.25ELEVACION SUD 1 1.5 1.50

VENTANAS Y PUERTAS 2.8 -13 -36.40VENTANAS Y PUERTAS 1.5 -3.8 -5.70VENTANAS Y PUERTAS 3.8 -3.8 -14.44VENTANAS Y PUERTAS 0.5 -2.5 -1.25VENTANAS Y PUERTAS 3.8 -3.6 -13.68

ELEVACION SUD 140.53VOLUMEN BAÑOS EXTERIORES 3.7 0.7 2.59VOLUMEN BAÑOS EXTERIORES 7.6 0.75 5.70VOLUMEN BAÑOS EXTERIORES 8 0.8 6.40VOLUMEN BAÑOS EXTERIORES 1.5 3.1 4.65VOLUMEN BAÑOS EXTERIORES 19.34

TOTAL AREA DE PINTURA = 500.67 m2

1.24 IMPERMEABILIZACION LAMINA ASFALTICA SIKA CON ALUMINIO

DESCRIPCION a b A Totalm m m2

JARDIN INTERIOR 1.6 0.5 0.80JARDIN INTERIOR 1.6 2 3.20JARDIN INTERIOR 0.5 2 1.00JARDIN INTERIOR 2.5 0.6 1.50

Page 32: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO JARDIN INTERIOR 2.5 2 5.00JARDIN INTERIOR 0.6 2 1.20JARDIN INTERIOR 1 0.5 0.50JARDIN INTERIOR 7 1 7.00JARDIN INTERIOR 4.5 1.5 6.75JARDIN INTERIOR 2.2 0.7 1.54JARDIN INTERIOR 3.8 0.5 1.90JARDIN INTERIOR 1 2 2.00

TOTAL AREA DE IMPERMEABILIZACION = 32.39 m2

1.25 AREA VERDE EN JARDINES

DESCRIPCION a b A Totalm m m2

JARDIN INTERIOR 1.6 0.5 0.80JARDIN INTERIOR 1.6 2 3.20JARDIN INTERIOR 0.5 2 1.00JARDIN INTERIOR 2.5 0.6 1.50JARDIN INTERIOR 2.5 2 5.00JARDIN INTERIOR 0.6 2 1.20JARDIN INTERIOR 1 0.5 0.50JARDIN INTERIOR 7 1 7.00JARDIN INTERIOR 4.5 1.5 6.75JARDIN INTERIOR 2.2 0.7 1.54JARDIN INTERIOR 3.8 0.5 1.90JARDIN INTERIOR 1 2 2.00JARDIN INTERIOR 32.39JARDIN EXTERNO 6.5 1.5 9.75JARDIN EXTERNO 5 4.5 22.50JARDIN EXTERNO 2 0.7 1.40JARDIN EXTERNO 1 1 1.00JARDIN EXTERNO 3 0.5 1.50JARDIN EXTERNO 8.5 2 17.00JARDIN EXTERNO 14.3 0.6 8.58JARDIN EXTERNO 3.2 1 3.20JARDIN EXTERNO 3.4 0.5 1.70JARDIN EXTERNO 2 2 4.00JARDIN EXTERNO 70.63

TOTAL AREA DE JARDINES = 103.02 m2

1.26 REJA METALICA DE PROTTECION DE FRONTIS

DESCRIPCION a b A Totalm m m2

REJA LADO ESTE 8.2 2 16.40

Page 33: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO REJA LADO ESTE 2.5 2 5.00REJA LADO ESTE 3.3 2 6.60

TOTAL AREA DE REJA= 28.00 m2

1.27 TUBO REDONDO 4" NIQUELADO

DESCRIPCION a b A Totalm ml

LADO ESTE 7 3 21.00 TOTAL DE TUBO= 21.00 ml

1.28 TUBO REDONDO 8"

DESCRIPCION a b A Totalm ml

PLANTA BAJA 5.4 1 5.40PLANTA BAJA 5.8 1 5.80

BAÑOS EXTERIORES 3.7 2 7.40 TOTAL DE TUBO= 18.60 ml

1.29 TUBO RECTANGULAR 4"X 2"

DESCRIPCION a b A Totalm ml

LADO NORTE 4.5 26 117.00LADO NORTE 5.1 7 35.70

LADO SUD 3.1 18 55.80LADO SUD 1.6 18 28.80

TOTAL DE TUBO= 237.30 ml

Page 34: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 2. PLANTA 22.1 PISO PORCELANATO

DESCRIPCION a b A Totalm m m2

SALA DE REUNION 5.1 7.15 36.46COCINETA 2.35 2.5 5.88

BAÑOS 2.6 2.6 6.76PUENTE Y BALCON 2.9 1.3 3.77PUENTE Y BALCON 1.7 4.2 7.14 10.91

CIRCULARION Y ESTARES 5.3 1.3 6.89CIRCULARION Y ESTARES 8.6 4.7 40.42CIRCULARION Y ESTARES 1 0.3 0.30CIRCULARION Y ESTARES 2.6 0.3 0.78 48.39

HALL DE ASCENSOR-GRADAS 1.7 3.2 5.44HALL DE ASCENSOR-GRADAS 2.7 1.4 3.78 9.22GRADAS 1° PISO AL 2° PISO 1.2 2.7 3.24GRADAS 1° PISO AL 2° PISO 2.6 1.2 3.12GRADAS 1° PISO AL 2° PISO 1.2 2.7 3.24GRADAS 1° PISO AL 2° PISO 3.2 1.2 3.84 13.44

TOTAL AREA DE PORCELANA = 131.06 m2

2.2 PISO ENTABLONADO DE MADERA

DESCRIPCION a b A Totalm m m2

PRESIDENCIA 4.3 5 21.50PRESIDENCIA 0.45 2.5 1.13PRESIDENCIA 1 4.1 4.10PRESIDENCIA 1 2.3 2.30

TOTAL AREA DE ENTABLONADO DE MADERA = 29.03 m2

2.3 ZOCALO DE PORCELANA

DESCRIPCION a Totalm ml

CIRCULACION Y ESTARES 28.1 28.10SALA DE REUNION 19.1 19.10

HALL DE ASCENSOR-GRADAS 8.8 8.80 TOTAL ML DE ZOCALO DE PORCELANA = 56.00 ml

2.4 ZOCALO DE MADERA

DESCRIPCION a Totalm ml

PRESIDENCIA 12.5 12.50 TOTAL ML DE ZOCALO DE MADERA = 12.50 ml

Page 35: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO

2.5 REVOQUE INTERIOR DE YESO

DESCRIPCION a b A Totalm m m2

CIRCULACION Y ESTARES 40.2 3.4 136.68VENTANAS 2.4 -3.4 -8.16VENTANAS 0.5 -3.4 -1.70VENTANAS 3 -3.4 -10.20VENTANAS 1.5 -3.4 -5.10VENTANAS 1 -0.5 -0.50VENTANAS 2.6 -2.5 -6.50SIN MURO 2.7 -2.4 -6.48PUERTAS 3 -2.2 -6.6PUERTAS 1.4 -2.2 -3.08

CIRCULACION Y ESTARES 88.36SALA DE REUNIONES 25.4 3.4 86.36

VENTANAS 4.6 -3.4 -15.64VENTANAS 2.5 -0.5 -1.25PUERTAS 1 -2.2 -2.2

SALA DE REUNIONES 67.27HALL DE ASCENSOR-GRADAS 8.65 3.4 29.41

PUERTA Y VENTANA 3 -3 -9HALL DE ASCENSOR-GRADAS 0 20.41

PRESIDENCIA 13.8 3.4 46.92VENTANAS 1.8 -0.5 -0.9VENTANAS 1 -2.2 -2.2

PRESIDENCIA 43.82GRADAS INGRESO AL 2° Y 3° PISO 14 3.4 47.6

PUERTA Y VENTANA 5.5 -3 -16.5VENTANAS 2.75 -3.4 -9.35

GRADAS INGRESO AL 2° Y 3° PISO 0 21.75 TOTAL AREA DE REVOQUE INTERIOR = 241.61 m2

2.6 REVOQUE INTERIOR IMPERMEABLEDESCRIPCION a b A Total

m m m2COCINETA 9.6 3.4 32.64PUERTAS 1 -2.2 -2.20

VENTANAS 2.7 -0.3 -0.81COCINETA 29.63

BAÑOS 18.4 3.4 62.56PUERTA 2.4 -2.2 -5.28

VENTANAS 3.6 -0.3 -1.08

Page 36: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO BAÑOS 56.20 28.1

TOTAL AREA DE REVOQUE IMPERMEABLE = 85.83 m2

2.7 REVESTIMIENTO CERAMICO

DESCRIPCION a b A Totalm m m2

COCINETA 9.6 3.4 32.64PUERTAS 1 -2.2 -2.20

VENTANAS 2.7 -0.3 -0.81COCINETA 29.63

BAÑOS 18.4 3.4 62.56PUERTA 2.4 -2.2 -5.28

VENTANAS 3.6 -0.3 -1.08BAÑOS 56.20 28.1

TOTAL AREA DE REVESTIMIENTO CERAMICO = 85.83 m2

2.8 CIELO RASO BAJO LOSA

DESCRIPCION a b A Totalm m m2

SALA DE REUNION 5.1 7.15 36.46PUENTE Y BALCON 2.9 1.3 3.77PUENTE Y BALCON 1.7 4.2 7.14 10.91

CIRCULARION Y ESTARES 5.3 1.3 6.89CIRCULARION Y ESTARES 8.6 4.7 40.42CIRCULARION Y ESTARES 1 0.3 0.30CIRCULARION Y ESTARES 2.6 0.3 0.78 48.39

HALL DE ASCENSOR-GRADAS 1.7 3.2 5.44HALL DE ASCENSOR-GRADAS 2.7 1.4 3.78 9.22

PRESIDENCIA 4.3 5 21.50PRESIDENCIA 0.45 2.5 1.13PRESIDENCIA 1 4.1 4.10PRESIDENCIA 1 2.3 2.30 29.03

TOTAL AREA DE CIELO RASO BAJO LOSA = 134.01 m2

2.9 CIELO RASO BAJO LOSA

DESCRIPCION a b A Totalm m m2

COCINETA 2.35 2.5 5.88BAÑOS 2.6 2.6 6.76

TOTAL AREA DE CIELO FALSO = 12.64 m2

2.10 PUERTAS DE TABLERO DE MADERA

DESCRIPCION a b A Total

Page 37: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO DESCRIPCION m m m2

PRIMER PISO 4 2.2 8.80PRIMER PISO 2.8 2.2 6.16 14.96

TOTAL AREA PUERTA DE MADERA = 14.96 m2

2.11 VIDRIO TEMPLADO 10 MM

DESCRIPCION a b A Totalm m m2

PRESIDENCIA 8 3.4 27.20HALL DE ASCENSOR-GRADAS 3 3.4 10.20HALL DE ASCENSOR-GRADAS 2.2 2.5 5.50

TOTAL AREA DE VIDRIO = 42.90 m2

2.12 BARANDA DE VIDRIO TEMPLADO 10 MM

DESCRIPCION a Totalm ml

PUENTE 5.6 5.60BALCON 7.6 7.60

TOTAL DE VIDRIO = 13.20 ml

2.13 BARANDA METALICA

DESCRIPCION a Totalm ml

GRADAS 6 6.00 TOTAL DE VIDRIO = 6.00 ml

2.14 CAJONERIA COCINETA

DESCRIPCION a Totalm ml

CAJONERIA 4.5 4.50 TOTAL CAJONERIA = 4.50 ml2.15 MESON DE GRANITO COCINETA

DESCRIPCION a b A Totalm m m2

COCINETA 2.5 0.6 1.50COCINETA 1.6 0.6 0.96

TOTAL AREA DE MESON = 2.46 m2

2.16 PINTURA OLEO INTERIOR

DESCRIPCION a b A Totalm m m2

CIRCULACION Y ESTARES 40.2 3.4 136.68VENTANAS 2.4 -3.4 -8.16

Page 38: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO VENTANAS 0.5 -3.4 -1.70VENTANAS 3 -3.4 -10.20VENTANAS 1.5 -3.4 -5.10VENTANAS 1 -0.5 -0.50VENTANAS 2.6 -2.5 -6.50SIN MURO 2.7 -2.4 -6.48PUERTAS 3 -2.2 -6.6PUERTAS 1.4 -2.2 -3.08

CIRCULACION Y ESTARES 88.36SALA DE REUNIONES 25.4 3.4 86.36

VENTANAS 4.6 -3.4 -15.64VENTANAS 2.5 -0.5 -1.25PUERTAS 1 -2.2 -2.2

SALA DE REUNIONES 67.27HALL DE ASCENSOR-GRADAS 8.65 3.4 29.41

PUERTA Y VENTANA 3 -3 -9HALL DE ASCENSOR-GRADAS 0 20.41

PRESIDENCIA 13.8 3.4 46.92VENTANAS 1.8 -0.5 -0.9VENTANAS 1 -2.2 -2.2

PRESIDENCIA 43.82GRADAS INGRESO AL 2° Y 3° PISO 14 3.4 47.6

PUERTA Y VENTANA 5.5 -3 -16.5VENTANAS 2.75 -3.4 -9.35

GRADAS INGRESO AL 2° Y 3° PISO 0 21.75 TOTAL AREA DE PINTURA DE OLEO = 241.61 m2

Page 39: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 3. PLANTA 33.1 PISO PORCELANATO

DESCRIPCION a b A Totalm m m2

COCINETA 2.3 2.7 6.21BAÑOS 2.7 2.7 7.29

PLANTA LIBRE 5.1 8.3 42.33PLANTA LIBRE 1 0.3 0.30PLANTA LIBRE 2.6 0.3 0.78PLANTA LIBRE 8.5 0.7 5.95PLANTA LIBRE 14.5 4 58.00PLANTA LIBRE 0.3 1.6 0.48PLANTA LIBRE 9 4.1 36.90PLANTA LIBRE 0.3 1.6 0.48PLANTA LIBRE 3.8 1 3.80PLANTA LIBRE 0.4 1.4 0.56 149.58

HALL DE ASCENSOR-GRADAS 1.7 3.2 5.44HALL DE ASCENSOR-GRADAS 2.7 1.5 4.05 9.49GRADAS 1° PISO AL 2° PISO 1.2 2.7 3.24GRADAS 1° PISO AL 2° PISO 2.6 1.2 3.12GRADAS 1° PISO AL 2° PISO 1.2 2.7 3.24GRADAS 1° PISO AL 2° PISO 3.2 1.2 3.84 13.44

TOTAL AREA DE PORCELANA = 186.01 m2

3.2 ZOCALO DE PORCELANA

DESCRIPCION a Totalm ml

PLANTA LIBRE 55.3 55.30HALL DE ASCENSOR-GRADAS 8.2 8.20

TOTAL ML DE ZOCALO DE PORCELANA = 63.50 ml

3.3 REVOQUE INTERIOR DE YESO

DESCRIPCION a b A Totalm m m2

PLANTA LIBRE 73.15 3.4 248.71VENTANAS 3.5 -2.4 -8.40VENTANAS 4.7 -3.4 -15.98VENTANAS 2.6 -3 -7.80VENTANAS 1.8 -2.3 -4.14VENTANAS 0.5 -1.5 -0.75VENTANAS 1.5 -3.4 -5.10VENTANAS 4.5 -3.4 -15.30

PLANTA LIBRE 191.24HALL DE ASCENSOR-GRADAS 8.65 3.4 29.41

Page 40: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO PUERTA Y VENTANA 3 -3 -9

HALL DE ASCENSOR-GRADAS 0 20.41GRADAS INGRESO AL 2° Y 3° PISO 14 3.4 47.6

PUERTA Y VENTANA 5.5 -3 -16.5VENTANAS 2.75 -3.4 -9.35

GRADAS INGRESO AL 2° Y 3° PISO 21.75 TOTAL AREA DE REVOQUE INTERIOR = 233.40 m2

3.4 REVOQUE INTERIOR IMPERMEABLE

DESCRIPCION a b A Totalm m m2

COCINETA 10 3.4 34.00PUERTAS 1 -2.2 -2.20

VENTANAS 2.7 -0.3 -0.81COCINETA 30.99

BAÑOS 19.2 3.4 65.28PUERTA 2.4 -2.2 -5.28

VENTANAS 3.6 -0.3 -1.08BAÑOS 58.92 29.46

TOTAL AREA DE REVOQUE IMPERMEABLE = 89.91 m2

3.5 REVESTIMIENTO CERAMICO

DESCRIPCION a b A Totalm m m2

COCINETA 10 3.4 34.00PUERTAS 1 -2.2 -2.20

VENTANAS 2.7 -0.3 -0.81COCINETA 30.99

BAÑOS 19.2 3.4 65.28PUERTA 2.4 -2.2 -5.28

VENTANAS 3.6 -0.3 -1.08BAÑOS 58.92 29.46

TOTAL AREA DE REVESTIMIENTO CERAMICO = 89.91 m2

3.6 CIELO RASO BAJO LOSA

DESCRIPCION a b A Totalm m m2

PLANTA LIBRE 5.1 8.3 42.33PLANTA LIBRE 1 0.3 0.30PLANTA LIBRE 2.6 0.3 0.78PLANTA LIBRE 8.5 0.7 5.95PLANTA LIBRE 14.5 4 58.00PLANTA LIBRE 0.3 1.6 0.48PLANTA LIBRE 9 4.1 36.90

Page 41: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO PLANTA LIBRE 0.3 1.6 0.48PLANTA LIBRE 3.8 1 3.80PLANTA LIBRE 0.4 1.4 0.56 149.58

HALL DE ASCENSOR-GRADAS 1.7 3.2 5.44HALL DE ASCENSOR-GRADAS 2.7 1.5 4.05 9.49

TOTAL AREA DE CIELO RASO BAJO LOSA = 159.07 m2

3.7 CIELO RASO BAJO LOSA

DESCRIPCION a b A Totalm m m2

COCINETA 2.3 2.7 6.21BAÑOS 2.7 2.7 7.29

TOTAL AREA DE CIELO FALSO = 13.50 m2

3.8 PUERTAS DE TABLERO DE MADERA

DESCRIPCION a b A Totalm m m2

PRIMER PISO 3 2.2 6.60PRIMER PISO 2.8 2.2 6.16 12.76

TOTAL AREA PUERTA DE MADERA = 12.76 m2

3.9 VIDRIO TEMPLADO 10 MM

DESCRIPCION a b A Totalm m m2

HALL DE ASCENSOR-GRADAS 2.7 3.4 9.18HALL DE ASCENSOR-GRADAS 1.5 2.2 3.30

TOTAL AREA DE VIDRIO = 12.48 m2

3.10 BARANDA METALICA

DESCRIPCION a Totalm ml

GRADAS 6 6.00 TOTAL DE VIDRIO = 6.00 ml

3.11 CAJONERIA COCINETA

DESCRIPCION a Totalm ml

CAJONERIA 5 5.00 TOTAL CAJONERIA = 5.00 ml3.12 MESON DE GRANITO COCINETA

DESCRIPCION a b A Totalm m m2

COCINETA 2.7 0.6 1.62COCINETA 1.7 0.6 1.02

Page 42: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO TOTAL AREA DE MESON = 2.64 m2

3.13 PINTURA OLEO INTERIOR

DESCRIPCION a b A Totalm m m2

PLANTA LIBRE 73.15 3.4 248.71VENTANAS 3.5 -2.4 -8.40VENTANAS 4.7 -3.4 -15.98VENTANAS 2.6 -3 -7.80VENTANAS 1.8 -2.3 -4.14VENTANAS 0.5 -1.5 -0.75VENTANAS 1.5 -3.4 -5.10VENTANAS 4.5 -3.4 -15.30

PLANTA LIBRE 191.24HALL DE ASCENSOR-GRADAS 8.65 3.4 29.41

PUERTA Y VENTANA 3 -3 -9HALL DE ASCENSOR-GRADAS 0 20.41

GRADAS INGRESO AL 2° Y 3° PISO 14 3.4 47.6PUERTA Y VENTANA 5.5 -3 -16.5

VENTANAS 2.75 -3.4 -9.35GRADAS INGRESO AL 2° Y 3° PISO 21.75

TOTAL AREA DE PINTURA DE OLEO = 233.40 m2

Page 43: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 4. PLANTA 44.1 PISO PORCELANATO

DESCRIPCION a b A Totalm m m2

COCINETA 2.3 2.7 6.21BAÑOS 2.7 2.7 7.29

PLANTA LIBRE Y BALCON 4.7 1 4.70PLANTA LIBRE Y BALCON 5.1 7.3 37.23PLANTA LIBRE Y BALCON 1 0.3 0.30PLANTA LIBRE Y BALCON 2.6 0.3 0.78PLANTA LIBRE Y BALCON 8.5 0.7 5.95PLANTA LIBRE Y BALCON 14.5 4.05 58.72PLANTA LIBRE Y BALCON 0.3 1.6 0.48PLANTA LIBRE Y BALCON 9 4.1 36.90PLANTA LIBRE Y BALCON 0.3 1.6 0.48PLANTA LIBRE Y BALCON 3.8 1.05 3.99PLANTA LIBRE Y BALCON 0.4 1.4 0.56 150.10

HALL DE ASCENSOR-GRADAS 1.7 3.2 5.44HALL DE ASCENSOR-GRADAS 2.7 1.5 4.05 9.49

TOTAL AREA DE PORCELANA = 173.09 m2

4.2 ZOCALO DE PORCELANA

DESCRIPCION a Totalm ml

PLANTA LIBRE 52 52.00HALL DE ASCENSOR-GRADAS 8.2 8.20

TOTAL ML DE ZOCALO DE PORCELANA = 60.20 ml

4.3 REVOQUE INTERIOR DE YESO

DESCRIPCION a b A Totalm m m2

PLANTA LIBRE Y BALCON 71.55 3.4 243.27VENTANAS 3.5 -2.4 -8.40VENTANAS 4.7 -3.4 -15.98VENTANAS 2.6 -3 -7.80VENTANAS 1.8 -2.3 -4.14VENTANAS 0.5 -1.5 -0.75VENTANAS 1.5 -3.4 -5.10VENTANAS 4.5 -3.4 -15.30VENTANAS 0.8 -3.4 -2.72VENTANAS 6.4 -0.5 -3.20

PLANTA LIBRE Y BALCON 179.88HALL DE ASCENSOR-GRADAS 8.65 3.4 29.41

PUERTA Y VENTANA 3 -3 -9

Page 44: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO HALL DE ASCENSOR-GRADAS 0 20.41

GRADAS INGRESO AL 2° Y 3° PISO 14 3.4 47.6PUERTA Y VENTANA 5.5 -3 -16.5

VENTANAS 2.75 -3.4 -9.35GRADAS INGRESO AL 2° Y 3° PISO 21.75

TOTAL AREA DE REVOQUE INTERIOR = 222.04 m2

4.4 REVOQUE INTERIOR IMPERMEABLE

DESCRIPCION a b A Totalm m m2

COCINETA 10 3.4 34.00PUERTAS 1 -2.2 -2.20

VENTANAS 2.7 -0.3 -0.81COCINETA 30.99

BAÑOS 19.2 3.4 65.28PUERTA 2.4 -2.2 -5.28

VENTANAS 3.6 -0.3 -1.08BAÑOS 58.92 29.46

TOTAL AREA DE REVOQUE IMPERMEABLE = 89.91 m2

4.5 REVESTIMIENTO CERAMICO

DESCRIPCION a b A Totalm m m2

COCINETA 10 3.4 34.00PUERTAS 1 -2.2 -2.20

VENTANAS 2.7 -0.3 -0.81COCINETA 30.99

BAÑOS 19.2 3.4 65.28PUERTA 2.4 -2.2 -5.28

VENTANAS 3.6 -0.3 -1.08BAÑOS 58.92 29.46

TOTAL AREA DE REVESTIMIENTO CERAMICO = 89.91 m2

4.6 CIELO RASO BAJO LOSA

DESCRIPCION a b A Totalm m m2

PLANTA LIBRE Y BALCON 4.7 1 4.70PLANTA LIBRE Y BALCON 5.1 7.3 37.23PLANTA LIBRE Y BALCON 1 0.3 0.30PLANTA LIBRE Y BALCON 2.6 0.3 0.78PLANTA LIBRE Y BALCON 8.5 0.7 5.95PLANTA LIBRE Y BALCON 14.5 4.05 58.72PLANTA LIBRE Y BALCON 0.3 1.6 0.48PLANTA LIBRE Y BALCON 9 4.1 36.90

Page 45: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO PLANTA LIBRE Y BALCON 0.3 1.6 0.48PLANTA LIBRE Y BALCON 3.8 1.05 3.99PLANTA LIBRE Y BALCON 0.4 1.4 0.56 150.10

HALL DE ASCENSOR-GRADAS 1.7 3.2 5.44HALL DE ASCENSOR-GRADAS 2.7 1.5 4.05 9.49

AREA DE GRADAS 2.6 3.9 10.14 TOTAL AREA DE CIELO RASO BAJO LOSA = 169.73 m2

4.7 CIELO RASO BAJO LOSA

DESCRIPCION a b A Totalm m m2

COCINETA 2.3 2.7 6.21BAÑOS 2.7 2.7 7.29

TOTAL AREA DE CIELO FALSO = 13.50

4.8 PUERTAS DE TABLERO DE MADERA

DESCRIPCION a b A Totalm m m2

PRIMER PISO 3 2.2 6.60PRIMER PISO 2.8 2.2 6.16 12.76

TOTAL AREA PUERTA DE MADERA = 12.76 m2

4.9 VIDRIO TEMPLADO 10 MM

DESCRIPCION a b A Totalm m m2

HALL DE ASCENSOR-GRADAS 2.7 3.4 9.18HALL DE ASCENSOR-GRADAS 1.5 2.2 3.30

TOTAL AREA DE VIDRIO = 12.48 m2

4.10 BARANDA DE VIDRIO TEMPLADO 10 MM

DESCRIPCION a Totalm ml

BALCON 4.7 4.70 TOTAL DE VIDRIO = 4.70 ml

4.11 CAJONERIA COCINETA

DESCRIPCION a Totalm ml

CAJONERIA 5 5.00 TOTAL CAJONERIA = 5.00 ml4.12 MESON DE GRANITO COCINETA

DESCRIPCION a b A Totalm m m2

COCINETA 2.7 0.6 1.62

Page 46: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO COCINETA 1.7 0.6 1.02

TOTAL AREA DE MESON = 2.64 m2

4.13 PINTURA OLEO INTERIOR

DESCRIPCION a b A Totalm m m2

PLANTA LIBRE Y BALCON 71.55 3.4 243.27VENTANAS 3.5 -2.4 -8.40VENTANAS 4.7 -3.4 -15.98VENTANAS 2.6 -3 -7.80VENTANAS 1.8 -2.3 -4.14VENTANAS 0.5 -1.5 -0.75VENTANAS 1.5 -3.4 -5.10VENTANAS 4.5 -3.4 -15.30VENTANAS 0.8 -3.4 -2.72VENTANAS 6.4 -0.5 -3.20

PLANTA LIBRE Y BALCON 179.88HALL DE ASCENSOR-GRADAS 8.65 3.4 29.41

PUERTA Y VENTANA 3 -3 -9HALL DE ASCENSOR-GRADAS 0 20.41

GRADAS INGRESO AL 2° Y 3° PISO 14 3.4 47.6PUERTA Y VENTANA 5.5 -3 -16.5

VENTANAS 2.75 -3.4 -9.35GRADAS INGRESO AL 2° Y 3° PISO 21.75

TOTAL AREA DE PINTURA DE OLEO = 222.04 m2

Page 47: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 1. PLANTA 1 1.1. EDIFICIO CADECO

# ITEM UNIDAD CONSULTORIA COMPUTOS DIFERENCIA PORCENTAJEMETRICOS

OBRA GRUESA1 ZAPATAS M3 61.91 62.445 0.535 0.86%2 COLUMNA M3 11.83 12.296 0.466 3.79%3 VIGAS M3 13.92 14.748 0.828 5.61%4 LOSA ENCASETONADA M2 142.57 142.1 0.47 0.33%5 CAJON DE ASCENSOR M3 11.64 7.7 3.94 33.85%6 MURO PERIMETRAL M2 290 290 0 0.00%7 MURO LADRILLO 6 HUECOS e=15cm M2 221.44 210.12 11.32 5.11%8 MURO LADRILLO 6 HUECOS e=10cm M2 48.53 62.22 13.69 22.00%9 CIMIENTO CORRIDO M3 9.15 9.43 0.28 2.97%

OBRA FINA1 PISO PORCELANATO M2 151.98 152.04 0.06 0.04%2 PISO ENTABLONADO DE MADERA M2 32.8 32.75 0.05 0.15%3 PISO MOSAICO GRANITICO M2 95.17 95.22 0.05 0.05%4 ZOCALO DE PORCELANA ML 93.36 93.3 0.06 0.06%5 ZOCALO DE MADERA ML 22.16 22.3 0.14 0.63%6 REVOQUE INTERIOR DE YESO M2 371.97 372.9 0.93 0.25%7 REVOQUE INTERIOR IMPERMEABLE M2 104.32 104.18 0.14 0.13%8 REVOQUE EXTERIOR BLANCO M2 515.71 500.67 15.04 2.92%9 REVESTIMIENTO CERAMICO M2 104.32 104.18 0.14 0.13%

10 TABLON DE MADERA ML 40.56 40.53 0.03 0.07%11 REVESTIMIENTO EXTERIOR DE ALUCOBOND M2 425.11 425.05 0.06 0.01%12 CIELO RASO BAJO LOSA M2 127.94 130.07 2.13 1.64%13 CIELO FALSO M2 32.31 31.93 0.38 1.18%14 PUERTA DE VIDRIO TEMPLADO M2 34.76 34.86 0.1 0.29%15 PUERTA DE TABLERO DE MADERA M2 29.7 21.56 8.14 27.41%16 PANEL DE VIDRIO REFLECTIVO M2 345.34 344.22 1.12 0.32%17 VIDRIO TEMPLADO M2 3.4 3.4 0 0.00%18 BARANDA VIDRIO TEMPLADO ML 4.93 5.5 0.57 10.36%19 BARANDA METALICA ML 19.26 16.5 2.76 14.33%20 CAJONERIA COCINETA ML 4.72 4.5 0.22 4.66%21 MESON DE GRANITO M2 2.5 2.51 0.01 0.40%22 PINTURA OLEO INTERIOR M2 371.97 372.9 0.93 0.25%23 PINTURA EXTERIOR VOLUMEN BLANCO M2 515.71 500.67 15.04 2.92%24 IMPERMEABILIZACION LAMINA ASFALTICA M2 32.36 32.39 0.03 0.09%25 AREA VERDE JARDINES M2 102.73 103.02 0.29 0.28%26 REJA METALICA DE PROTECCION FRONTIS M2 27.88 28 0.12 0.43%27 TUBO REDONDO 4" ML 21 21 0 0.00%28 TUBO REDONDO 8" ML 18.69 18.6 0.09 0.48%29 TUBO RECTANGULAR 4"X2" ML 237.72 237.3 0.42 0.18%

Page 48: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 1. PLANTA 1 1.2. AUDITORIO

# ITEM UNIDAD CONSULTORIA COMPUTOS DIFERENCIA PORCENTAJEMETRICOS

OBRA GRUESA1 ZAPATAS M3 5.84 5.8 0.04 0.68%2 COLUMNA M3 9.84 9.61 0.23 2.34%3 VIGAS M3 5.08 4.91 0.17 3.35%7 MURO LADRILLO 6 HUECOS e=15cm M2 62.9 82.25 19.35 23.53%8 MURO LADRILLO 6 HUECOS e=10cm M2 73.71 12.6 61.11 82.91%9 CIMIENTO CORRIDO M3 6.12 4.01 2.11 34.48%

OBRA FINA1 PISO PORCELANATO M2 105.62 105.85 0.23 0.22%4 ZOCALO DE PORCELANA ML 13.26 13.3 0.04 0.30%6 REVOQUE INTERIOR DE YESO M2 62.9 63.15 0.25 0.40%

13 CIELO FALSO M2 105.62 105.85 0.23 0.22%22 PINTURA OLEO INTERIOR M2 62.9 63.15 0.25 0.40%

1.3. BAÑOS EXTERIORES# ITEM UNIDAD CONSULTORIA COMPUTOS DIFERENCIA PORCENTAJE

METRICOSOBRA GRUESA

7 MURO LADRILLO 6 HUECOS e=15cm M2 29.79 37.68 7.89 20.94%8 MURO LADRILLO 6 HUECOS e=10cm M2 32.76 29.89 2.87 8.76%9 CIMIENTO CORRIDO M3 1.61 2.74 1.13 41.24%

OBRA FINA1 PISO PORCELANATO M2 26.38 23.31 3.07 11.64%7 REVOQUE INTERIOR IMPERMEABLE M2 114.46 114.46 0 0.00%9 REVESTIMIENTO CERAMICO M2 114.46 114.46 0 0.00%

12 CIELO RASO BAJO LOSA M2 26.38 23.31 3.07 11.64%15 PUERTA DE TABLERO DE MADERA M2 11.88 11.88 0 0.00%

Page 49: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 2. PLANTA 2

# ITEM UNIDAD CONSULTORIA COMPUTOS DIFERENCIA PORCENTAJEMETRICOS

OBRA GRUESA2 COLUMNA M3 5.55 6.018 0.468 7.78%3 VIGAS M3 13.33 14.15 0.82 5.80%4 LOSA ENCASETONADA M2 165.85 164.6 1.25 0.75%5 CAJON DE ASCENSOR M3 2.57 4.4 1.83 41.59%7 MURO LADRILLO 6 HUECOS e=15cm M2 209.42 209.78 0.36 0.17%8 MURO LADRILLO 6 HUECOS e=10cm M2 103.5 106.42 2.92 2.74%

10 ESCALERA M3 2.66 2.28 0.38 14.29%OBRA FINA

1 PISO PORCELANATO M2 130.94 131.06 0.12 0.09%2 PISO ENTABLONADO DE MADERA M2 28.99 29.03 0.04 0.14%4 ZOCALO DE PORCELANA ML 55.93 56 0.07 0.13%5 ZOCALO DE MADERA ML 12.52 12.5 0.02 0.16%6 REVOQUE INTERIOR DE YESO M2 241.53 241.61 0.08 0.03%7 REVOQUE INTERIOR IMPERMEABLE M2 85.79 85.83 0.04 0.05%9 REVESTIMIENTO CERAMICO M2 85.79 85.83 0.04 0.05%

12 CIELO RASO BAJO LOSA M2 162.77 134.01 28.76 17.67%13 CIELO FALSO M2 12.34 12.64 0.3 2.37%15 PUERTA DE TABLERO DE MADERA M2 21.34 14.96 6.38 29.90%17 VIDRIO TEMPLADO M2 43.12 42.9 0.22 0.51%18 BARANDA VIDRIO TEMPLADO ML 13.09 13.2 0.11 0.83%19 BARANDA METALICA ML 6.6 6 0.6 9.09%20 CAJONERIA COCINETA ML 4.79 4.5 0.29 6.05%21 MESON DE GRANITO M2 2.52 2.46 0.06 2.38%22 PINTURA OLEO INTERIOR M2 241.53 241.61 0.08 0.03%

Page 50: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 3. PLANTA 3

# ITEM UNIDAD CONSULTORIA COMPUTOS DIFERENCIA PORCENTAJEMETRICOS

OBRA GRUESA2 COLUMNA M3 4.35 4.692 0.342 7.29%3 VIGAS M3 13.03 13.83 0.8 5.78%4 LOSA ENCASETONADA M2 153.36 152.6 0.76 0.50%5 CAJON DE ASCENSOR M3 5.26 4.4 0.86 16.35%7 MURO LADRILLO 6 HUECOS e=15cm M2 272.25 247.52 24.73 9.08%8 MURO LADRILLO 6 HUECOS e=10cm M2 139.59 35.7 103.89 74.43%

10 ESCALERA M3 2.66 2.28 0.38 14.29%OBRA FINA

1 PISO PORCELANATO M2 186 186.01 0.01 0.01%4 ZOCALO DE PORCELANA ML 63.41 63.5 0.09 0.14%6 REVOQUE INTERIOR DE YESO M2 237.12 233.4 3.72 1.57%7 REVOQUE INTERIOR IMPERMEABLE M2 89.91 89.91 0 0.00%9 REVESTIMIENTO CERAMICO M2 89.91 89.91 0 0.00%

12 CIELO RASO BAJO LOSA M2 159.17 159.07 0.1 0.06%13 CIELO FALSO M2 13.35 13.5 0.15 1.11%15 PUERTA DE TABLERO DE MADERA M2 12.54 12.76 0.22 1.72%17 VIDRIO TEMPLADO M2 12.55 12.48 0.07 0.56%19 BARANDA METALICA ML 6.6 6 0.6 9.09%20 CAJONERIA COCINETA ML 5 5 0 0.00%21 MESON DE GRANITO M2 2.65 2.64 0.01 0.38%22 PINTURA OLEO INTERIOR M2 237.12 233.4 3.72 1.57%

Page 51: Computos Metricos Obra Gruesa

COMPUTOS METRICOS SEDE DE CADECO 4. PLANTA 4

# ITEM UNIDAD CONSULTORIA COMPUTOS DIFERENCIA PORCENTAJEMETRICOS

OBRA GRUESA2 COLUMNA M3 6.79 7.533 0.743 9.86%3 VIGAS M3 14.95 15.51 0.56 3.61%4 LOSA ALIVIANADA M2 215.57 215.8 0.23 0.11%5 LOSA LLENA M2 21.7 20.6 1.1 5.07%6 CAJON DE ASCENSOR M3 5.26 4.4 0.86 16.35%7 MURO LADRILLO 6 HUECOS e=15cm M2 251.3 215.22 36.08 14.36%8 MURO LADRILLO 6 HUECOS e=10cm M2 118.91 51 67.91 57.11%

OBRA FINA1 PISO PORCELANATO M2 173.04 173.09 0.05 0.03%4 ZOCALO DE PORCELANA ML 60.17 60.2 0.03 0.05%6 REVOQUE INTERIOR DE YESO M2 222 222.04 0.04 0.02%7 REVOQUE INTERIOR IMPERMEABLE M2 89.91 89.91 0 0.00%9 REVESTIMIENTO CERAMICO M2 89.91 89.91 0 0.00%

12 CIELO RASO BAJO LOSA M2 169.84 169.73 0.11 0.06%13 CIELO FALSO M2 13.35 13.5 0.15 1.11%15 PUERTA DE TABLERO DE MADERA M2 12.54 12.76 0.22 1.72%17 VIDRIO TEMPLADO M2 12.55 12.48 0.07 0.56%19 BARANDA DE VIDRIO ML 4.7 4.7 0 0.00%20 CAJONERIA COCINETA ML 5 5 0 0.00%21 MESON DE GRANITO M2 2.65 2.64 0.01 0.38%22 PINTURA OLEO INTERIOR M2 222 222.04 0.04 0.02%