Upload
buiminh
View
215
Download
0
Embed Size (px)
Citation preview
DSR THE FIRST & BN TECH SQUAREM/s DSR BUILDERS AND DEVELOPERS
SURVEY NO. 66/2, PANMAKTHA,SERILINGAMAPALLY, RANGA REDDY DISTRICT
Conceptual PlanRESIDENTIAL AND COMMERCIAL CONSTRUCTION
PROJECT
Submitted ByM/s DSR BUILDERS AND DEVELOPERS,DSR Tranquil, Plot no 901,# 301, Ayappa Society Main Road,Madhapur, Hyderabad – 500 081Phone: +91 40 40024567
Studies & Documented ByM/s Team Labs and ConsultantsB-115 - 117 & 509,Annapurna Block, Aditya Enclave,Ameerpet, Hyderabad- 500 038Phone: 91-040-23748555/616Fax : 91-040-23748666e-mail: [email protected]
SUBMITTED TOSTATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY,
TELANGANAGOVERNMENT OF INDIA
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 1
2.0 PROJECT DESCRIPTION/CONCEPTUAL PLAN
This chapter details the need for the project, description of the proposed project andalternatives, and identifies the valued ecosystem components. The project is envisagedto provide housing to meet the growing demands for housing in the growing urban areaof Hyderabad.
2.1 THE PROJECT LOCATIONThe project will be spread over an area of 1.49 hectares in Survey no. 66/2, Panmakhta,Serilingamapally Municipality, Ranga Reddy District. The site is surrounded by openlands in all the directions except in northeast direction. An 30 m wide road in northeastdirection. The nearest railway station is the Hi-tech City railway Station at a distance of4.8 km.
2.2 PROJECT DESCRIPTION
2.2.1 DESIGN STAGEThe principles of low impact development are adopted during the design stage toensure storm water percolation, treated water reuse, energy conservation, andoptimized usage of renewable resources. The Area Statement for the proposed officebuilding is presented in table in table 2.1.
Table 2.1 Area Statement for the proposed Building
Land Use No of Floors Total No ofUnits
Total SiteArea in m2
Total Builtup area (m2)
Commercial 3C+2S+12 1570.9 18850.8Residential
3C+2S+25100
2533.959959.8
Amenities (2 stilts) 4966.2Green Area 1503.5Road Area 4791.5Open Area 3811.1Gradient up area 762.5Commercial ParkingCellar - 1 3201.8Cellar - 2 3201.8Cellar - 3 3201.8Stilt - 1 1570.9Stilt - 2 1570.9Residential ParkingCellar - 1 8497.1Cellar - 2 8494.1Cellar - 3 8494.1Total 100 14973.5 122009.3
It is proposed to develop an Residential and Commercial building has 3 Cellar floors forparking. The land allocation will be optimized to ensure compliance with the FAR
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 2
regulations of HMDA. The water requirement of the project during operation will bedrawn from HMWSSB. Sewage treatment plant will be provided to treat thewastewater. Water conservation measures will be incorporated in the plumbingdesigns. Water recycling/reuse will be adopted by way of using treated sewage fortoilet flush systems and green belt development. The treated effluent and storm waterwill be let-out into the storm water drain, which will join the drains. The required powerwill be drawn from the TRANSCO and the energy requirement will be optimized byadopting energy efficient design for lighting and for HVAC systems. Constructionmaterials will be drawn from local sources. The parking provision exceeds the guidelinesprescribed by FAR and Building policy. The layout of the project site and plan ofindividual floors is presented in fig. 2.1 and fig. 2.2.
Circulation Plan: Ground Driveway : 7.0 m No. of Cellars: 3 nos. No. of Ramps : 2 Width of Ramp : 7.3 m Slope of Ramp : 1 in 8 Cellar Driveway : 5.0 m No. of Lifts : 8 Capacity of each Lift: 10 pax. Connecting Road : 30.0 m ROW
Modified Los & Performance
RoadExistingvolume,PCU/hr
Existingvolume/Capacity
Additionalvolume
ModifiedVolume
ModifiedVolume/Capacity
ModifiedLos &performance
Gachibowli 1166 0.324 96 1262 0.351 “B” VeryGood
Mehdipatnam 962 0.267 54 1016 0.282 “B” VeryGood
Parking ProvisionIt is proposed to provide 3 cellar floors for parking. The parking provision follows theguidelines prescribed by FAR and Building policy. The number of parking spacesprovided is presented in table 2.2. The parking floor plans are presented in fig. 2.3.
Table 2.2 Parking Space Provision of the ProjectFloor 4 - Wheeler 2 - Wheeler
Commercial 216 219Residential 481 --Total 697 219
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 3
Fig 2.1 Site layout
SITE PLAN
3 BASEMENTS +2 CLUB HOUSE LEVELS+25 FLOORS
TOT-LOT931.54 Sq.M.
68.97m
TOT-LOT571.99 Sq.ft.
6.85M Lvl
19.2
0m
4.57
m6.
40m
4.57
m
102.
11m
13.0
0m
3 BASEMENTS+2STILTS+12 FLOORS
31.96m
50.0
2m
20.8
0m
9.0m
28.24m21.41m
28.02m
20.79m
19.72m
27.22m
26.96m
20.58m
21.49m
20.76m
9.01m 12.79m
12.74m
11.45m
9.02m
7.0M
WID
E D
RIV
E W
AY
7.0M
WID
E D
RIV
E W
AY7.
0M W
IDE
DR
IVE
WAY
7.0M
WID
E D
RIV
E W
AY
7.0M WIDE DRIVE WAY
5.21m
5.21m
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 4
Fig. 2.2 Typical Floor Plans
TRANSFORMERYARD
HTBREAKER
TX
ACB
BUSDUCT
CT/PT
2000kVA11KV/433V
M ETERINGENTRY
UP
UP
6.85M Lvl
10.85M LvlCLUB HOUSE Level 1
6.85M Lvl
TOT-LOT931.54 Sq.M.
7.0M WIDE DRIVE WAY
COMMERCIAL BUILDING
TOT-LOT571.99 Sq.ft.
PLO
T O
UTLI
NE
PLO
T O
UTLI
NE
PLO
T O
UTLI
NE
PLO
T O
UTLI
NE
c ente r table
0 LVL
screen
+0.750 LVL
UP
re cliner
SUNKENSLAB
p ot wash
UP
0'0" LVL
+0.750M LVL
UP
screen
wate r b ody
c ente r table
re c liner
SUNKENSLAB
SD
SD
0'0" LVL
+0.750M LVL
UP
screen
wate r b ody
p ot wash
c ente r table
re c liner
SUNKENSLAB
SD
SD
c ente r table
+0 LVL
screen
+0.750M LVL
UP
re cliner
SUNKENSLAB
p ot wash
UP
SCR EEN
BEAM
FO
R EL
EVAT
ION
PURP
OSE
OPEN TO SKY
DN
OPEN TO SKY
OPEN TO SKY
BEAM
FO
R EL
EVAT
ION
PURP
OSE
STO
RAG
E
STO
RAG
E
p ot wash
STO
RAG
E
STO
RAG
E
1
3
2
4
UP
UP
2
MASTER BEDROOM6.86 X 4.88
SERVICE LIFT2.51 x 2.36
PAS.LIFT2.51 x 1.91
1.84 WIDE BALCONY 1.84 WIDE BALCONY
s taircasepressurization shaft3.43 x 1.22
SERVICE LIFT2.51 x 2.13
FIRE
2.06
X1.52
FIRE
2.21
x 0
.91
TO ILET2.44X2.44
SUITE 24.42X3.81
DRESS2.44X1.87
P W.ROOM1 .41X2.13
DRAW ING4.38 X 4.57
LOBBY 2.06 X 2 .13
TO ILET2.13X3.05
HO METHEATRE7.51X4.27
FOYER2.13m W IDE
2.44X3.05TO ILET
DRESS2.44X2.13
SUITE 35.79X4.27
DINING4.19X4.19
KITCHEN4.46X4.72
LIVING5.91X5.183.05 X 3.05
DUCT
1 .83 X 1.22TOILET
SERVANT'S R.3 .05X 2.82
TO ILET2.44X4.15
3.46 X 4.88UTILITY
W ET KITCHEN3.05X2.28
W ALK IN CLOSET2.90X4.76
MASTER BEDROOM6.63X4.88
SITOUT3.20 X 8.34
1.98 WIDE BALCO
NY
1 .98 WIDE BALCONY 1.98 WIDE BALCONY 1.98 WIDE BALCONY
DRAW ING4.27X4.27
SUITE 13.96X4.57
TO ILET2.13X3.05
P OWDER RM.2 .13X1.41
LOBBY2.13X1.83
2.13M W IDEFOYER
DRESS2.02X2.29 TO ILET
3.05X2.29
SUITE 23.85X4.27
SITOUT3.20 X 9.56M
1.98
WID
E BA
LCO
NY1.
98M
WID
E BA
LCON
Y
DINING4.19X5.18
6.71X4.27
KITCHEN5.14X3.54
LIVING6.45X5.18
SUITE 36.17 X 3.96
HO ME THEATER
3.05X2.29
PUJA 2.74 X 1 .84
TO ILET4.17 X 2.45
DRESS3.01 X 2.29
TO ILET
W ALK IN CLOSET2 .90X4.76S ERVANT
2 .84 X 2.21
TOILET1 .41X1.83
W ET KITCHEN2 .86 x 4.80
PAS.LIFT2.51 X 1.91
1.98
m W
IDE
BALC
ONY
PAS.LIFT1.91X2.21
GARBAGEROOM
3.92 X 1.00
VRV LOBBY1.78X X 2.21
stai
rcas
epr
essu
rizat
ion
shaft
3.01
X 0
.76
1.84 WIDE BALCONY
1.98
m W
IDE
BALC
ONY
1.98
m W
IDE
BALC
ONY
1.98
m W
IDE
BALC
ONY
1.98
WID
E BA
LCO
NY
PAS.LIFT2.21 x 1.91
4.57m W IDE CO RRIDOR
2.00
m W
IDE
CORR
IDO
R
2.92
m W
IDE
CORR
IDO
R
2.00
m W
IDE
CORR
IDO
R
4 .57m W IDE CO RRIDOR
ELEC1 .20X0.76
COM1.20X0.76
GARBAGE ROOM3.43X1.00M
STAIRCASE 13.66X6.26M
STAIRCASE 24.02X7.33M
ELEC1 .91X0.76
COM1.91X0.76
V.R .V.1.52X7.01
V.R.V.1 .52X7.01
UP
UP
1.98
WID
E BA
LCO
NY1.
98 W
IDE
UTI
LITY
1.98
WID
E U
TILI
TY1.
98m
WID
E BA
LCO
NY0.254M EXPANSION JOINT
0.254M EXPANSION JOINT
0.254M EXPANSION JOINT
7.0M
WID
E D
RIVE
WAY
7.0M
WID
E D
RIVE
WAY
OPE
N TO
SKY
OPE
N TO
SKY
2.0m WIDE LOBBY
3.43m W IDE LO BBY
4.26 m WIDE LOBBY
TO ILET2.44X2.44
SUITE 24.42X3.81
DRESS2.44X1.87
P W.ROOM1 .41X2.13
DRAW ING4.38 X 4.57
LOBBY 2.06 X 2 .13
TO ILET2.13X3.05
FOYER2.13m W IDE
2.44X3.05TO ILET
DRESS2.44X2.13
SUITE 35.79X4.27
DINING4.19X4.19
KITCHEN4.46X4.72
LIVING5.91X5.183.05 X 3.05
DUCT
1 .83 X 1.22TOILET
SERVANT'S R.3 .05X 2.82
TO ILET2.44X4.15
3.46 X 4.88UTILITY
W ET KITCHEN3.05X2.28
W ALK IN CLOSET2.90X4.76
MASTER BEDROOM6.63X4.88
HO METHEATRE7.51X4.27
2.44
M C
ON
NECT
ING
CO
RRID
OR
MASTER BEDROOM6.86 X 4.88
DRAW ING4.27X4.27
SUITE 13.96X4.57
TO ILET2.13X3.05
P OWDER RM.2 .13X1.41
LOBBY2.13X1.83
2.13M W IDEFOYER
DRESS2.02X2.29 TO ILET
3.05X2.29
SUITE 23.85X4.27
DINING4.19X5.18
6.71X4.27
KITCHEN5.14X3.54
LIVING6.45X5.18
SUITE 36.17 X 3.96
HO ME THEATER
3.05X2.29
PUJA 2.74 X 1 .84
TO ILET4.17 X 2.45
DRESS3.01 X 2.29
TO ILET
W ALK IN CLOSET2 .90X4.76S ERVANT
2 .84 X 2.21
TOILET1 .41X1.83
W ET KITCHEN2 .86 x 4.80
HAND RAIL
HAND RAIL
2.0 m W IDE LOBBY
D3: 0.91X2.10
MD
:1.9
8X2.7
4
D1:1.06X2.43
D2:
.91X
2.43
D1:1.06X2.43
D1:1.06X2.43
D1: 1.06X2.43SD4: 1.67X2.43
D2: 0.91X2.43
D2: 0.91X2.43
D2:
0.9
1X2.
43
D4: 0.76X2.10
D1:
1.06
X2.43
D2:
0.9
1X2.
43
SD3:
2.4
3X2.1
0SD
: 3.6
5X2.7
4
SD1:
3.0
5X2.7
4
SD2: 2.43X2.74SD2: 2.43X2.74SD2: 2.43X2.74
PD:1.98X2.43
W2:1.52X1.52
V1:
0.9
1X2.7
4V
: 0.9
1X2.7
4
V 1: 0.91X2.74
KW1:
1.9
8X0.5
3
V 3: 0.91X0.60W4: 0.76X1.52
D3: 0.91X2.10
D2:
0.9
1X2.
43
D3: 0.91X2.10
M D: 1.98X2.74
D1:1.06X2.43
D1:1.06X2.43
D1:1.06X2.43D1:
1.06
X2.43
D1:1.06X2.43
D2:
0.9
1X2.
43
D2: 0.91X2.43
D2:
0.9
1X2.
43
D2:
0.9
1X2.
10
D2:
0.9
1X2.
43
D1:
1.06
X2.43
D3: 0.91X2.10
D2: 0.91X2.43
W: 2.43X2.60
SD1:
3.0
5X2.7
4
SD: 3
.65X
2.74
SD3:
2.4
3X2.1
0
SD2:
2.4
3X2.7
4V
: 0.9
1X2.7
4
SD: 3
.65X
2.74
SD2:
2.4
3X2.7
4
V 2:0.76X1.22
V1:
0.91
X2.74
V 2: 0.60X1.22
KW: 2
.43X
0.53
W3:
0.9
1X1.
52
PD: 1
.98X
2.43
D4: 0.76X2.10
D3: 0.91X2.10
MD
:1.9
8X2.7
4
D1:1.06X2.43
D2:
.91X
2.43
D1:1.06X2.43
D1:1.06X2.43
D1: 1.06X2.43SD4: 1.67X2.43
D2: 0.91X2.43
D2: 0.91X2.43
D2:
0.9
1X2.
43
D4: 0.76X2.10
D1:
1.06
X2.43
D2:
0.9
1X2.
43
SD3:
2.4
3X2.1
0SD
: 3.6
5X2.7
4
SD1:
3.0
5X2.7
4
M D: 1.98X2.74
D1:1.06X2.43
D1:1.06X2.43
D1:1.06X2.43D1:
1.06
X2.43
D1:1.06X2.43
D2:
0.9
1X2.
43
D2: 0.91X2.43
D2:
0.9
1X2.
43
D2:
0.9
1X2.
10
D2:
0.9
1X2.
43
D1:
1.06
X2.43
D3: 0.91X2.10
D2: 0.91X2.43
SD2: 2.43X2.74SD2: 2.43X2.74SD2: 2.43X2.74
PD:1.98X2.43
W2:1.52X1.52
W1: 2.43X2.60
V: 0
.91X
2.74
V: 0
.91X
2.74
V : 0.91X2.74
SD1:
3.0
5X2.7
4
SD: 3
.65X
2.74
SD3:
2.4
3X2.1
0
SD2:
2.4
3X2.7
4V
1: 0
.91X
2.74
SD: 3
.65X
2.74
SD2:
2.4
3X2.7
4
V 2:0.76X1.22
V1:
0.91
X2.74
V 2: 0.60X1.22
KW: 2
.43X
0.53
KW1:
1.9
8X0.5
3
V 3: 0.91X0.60
W3:
0.9
1X1.
52
W3: 0.76X1.52
PD: 1
.98X
2.43
S.D
: 1.0
X2.43
D4:
0.7
6X2.
10RA
ILIN
G
SW:0
.91X
1.52
ED: 0
.80X
2.10
CD
: 0.8
0X2.1
0
ED: 0.65X2.10
RAIL
ING
S.W
:0.9
1X1.5
2
FD: 0
.80X
2.10
S.D
: 1.0
X2.43
FD: 0
.80X
2.10
S.W
:0.9
1X1.5
2
ED: 0
.80X
2.10
CD
: 0.8
0X2.1
0
G.D
: 0.7
6X2.1
0
D4:
0.7
6X2.
10
D4:
0.7
6X2.
10
D3: 0.91X2.10
D2:
0.9
1X2.
43
D3: 0.91X2.10
D4: 0.76X2.10
W3:0.91X1.52W3:0.91X1.52
W4:0.91X1.52
W3:0.91X1.52 W3:0.91X1.52
W3:0.91X1.52
7.01m
5.21m
5.21m
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 5
Fig. 2.3 Parking Floor Plans
1:9 SLOPE
1:9 SLOPE
5.03
m W
IDE
DRIV
E W
AY5.
03m
WID
EDR
IVE
WAY
5.03
m W
IDE
DRIV
E W
AY
5.03
m W
IDE
DRIV
E W
AY
S ER VICE LIFT2.51 x 2.36
P A S .LIFT2.51 x 1.91
sta ircasepressuriza tion shaft3 .43 x 1.22
S ER VICE LIFT2.51 x 2.13
FIRE
2.06
X0.7
6
FIRE
2.21
x 0
.91
P A S .LIFT2.51 X 1.91
P A S .LIFT1.91X 2.21
GARBAGER OOM
3.92 X 1.00
V RV LOBBY1.78X X 2.21
stai
rcas
epr
essu
rizat
ion
shaf
t3.
01 X
0.7
6
P A S .LIFT2.21 x 1.91
E LEC1 .20X 0.76
COM1.20X 0.76
G ARB AGE ROOM3.43X 1.00M
S TAIRCA SE 13.66X 6.26M
S TAIRCA SE 24.02X 7.33M
E LEC1 .91X 0.76
COM1.91X 0.76
UP
UP
2 .0m W ID E LOBBY
2 .0 m W ID E LOBBY
S.D: 1
.0X2
.43
SW:0
.91X
1.52
ED: 0
.80X
2.10
CD:
0.8
0X2.1
0
ED : 0 .65X 2.10
S.W:0
.91X
1.52
S.D: 1
.0X2
.43
FD: 0
.80X
2.10
S.W:0
.91X
1.52
ED: 0
.80X
2.10
CD:
0.8
0X2.1
0
G.D
: 0.7
6X2.1
0D4
: 0.7
6X2.1
0
FD: 0
.80X
2.10
DRAIN P IT3.26 x 1.52 x 2.44
DRAIN P IT10'8"x5 '0 "x8'0"
D
B
EC
1097.76 SFT
BRIDGE
PUM P RO OM @ BASEM ENT 3 LEVEL
W IN DOW
R OLLINGS HUTTER
DRAIN P IT5 '0"x5'0"
WINDOW
R OLLINGS HUTTER
5.03
m W
IDE
DRIV
E W
AY5.
03m
WID
EDRI
VE W
AY
P UM P ROOM
C AR W ASH1 8.14x6.4
RETAINING W ALL
S TO R E ROOM5.38x7.75
M ULTI P UR PO SE R OOM4.8x5 .39
5.03m W ID E DR IVE W AY
RETAINING W ALL RETAINING W ALL
RAM P DO W N TO 2ND BASEM ENT
RAM P DO W N TO 2ND BASEM ENT
5.03m W ID E DR IVE W AY
1" GA P EX PA NS IO N JOINT
6.02m W ID E DR IVE W AY
SOIL
FIL
LING
SOIL
FIL
LING
96
12
34
56
78
910
1112
1314
1516
1718
1920
2122
2324
2526
2827
2930
3233
3435
3637
3938
5857
5351
5262
6364
6566
6768
6970
7172
7377
7879
8081
8283
8485
8687
8889
9798 95 94 93 92 91 90
`154155
152151
150149
148147
146145
144143
142141
140139
138137
136
99100
101102
103104
105106
107108
153
41 42 43 44 45 46 47 48 49
109110
111112
113114
115116
117118
119
156 157 158 159 160 161 162 163 164
133134
135
121 122 123 124 125 126 127 128 129
156A159A 160A
162A 163A
135A134A
136A137A
138A139A
140A142A
143A144A
145A149A
150A151A
152A
155A
95A
117A116A
108A107A
31
5960
6174
7576
5455
56
50
130
40
120
106A115A
132131
BRIC K W ALL
MD
D1
D2
D2
4.91m 4.91m
1.39m
2.51m
28.80m
4.00m
4.00m
4.00m
4.00
m
4.00
m
4.00m
ROLL
ING
SHUT
TER
WIN
DOW
EXH
AUST
AIR
BEL
T DR
IVE
6.10m
ROLLINGSHUTTER WINDOWWINDOW
4.00
m
4.00m
4.00
m
5.75m
3.05m
3.05
m
7.85m
2.82
m
10.68m4.57
m
13.43m4.57
m
FIRE WATER SUMP
CAPACITY:200KL
SIZE:13.43 x 4.57x 3.81
RAW WATER SUMP
CAPACITY:150KL
SIZE:10.68 x 4.57 x 3.81
SOFT
WAT
ER S
UM
PAR
EA:5
60SQ
Tx11
'0" D
EPTH
CAP
ACIT
Y:15
0KL
DRAIN PIT1.52m x 1.52m
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
2ND FLOOR
7.24M WIDE DRIVE WAY
ROAD LEVEL
SIT OUT
TOILET
DINING LOBBY BEDROOM BALCONYTOILET
COMMERCIAL BLOCK
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
SIT OUT
TOILET
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM
HOME THEATER BEDROOM
MASTER BEDROOM
HOME THEATER BEDROOM
KITCHEN LOBBY
STORE ROOM MULTIPURPOSE ROOM MULTIPURPOSE ROOM
RAMP DOWN TO BASEMENT
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
INDOOR GAMES
CAR WASH
CAR WASH
CAR WASHPUMP ROOM
GRADIENT UP 1:10
Road Lvl
3RD FLOOR
4TH FLOOR
5TH FLOOR
6TH FLOOR
7TH FLOOR
8TH FLOOR
9TH FLOOR
10TH FLOOR
11TH FLOOR
12TH FLOOR
13TH FLOOR
14TH FLOOR
15TH FLOOR
16TH FLOOR
17TH FLOOR
18TH FLOOR
19TH FLOOR
20TH FLOOR
21ST FLOOR
22ND FLOOR
23RD FLOOR
24TH FLOOR
25TH FLOOR
MASTER BEDROOM SIT OUT
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
MASTER BEDROOM LIVING
HOME THEATER TOILETBEDROOM
DINING
LOBBY BEDROOM BALCONY
TOILET
RL
SECTION AT YY
12TH FLOOR
TERRACE FLOOR
11TH FLOOR
10TH FLOOR
9TH FLOOR
8TH FLOOR
7TH FLOOR
6TH FLOOR
5TH FLOOR
4TH FLOOR
3RD FLOOR
2ND FLOOR
1ST FLOOR
STILT 2 FLOOR
STILT 1 FLOOR
BASEMENT 1 LEVEL
BASEMENT 2 LEVEL
BASEMENT 3 LEVEL
PLOT LIMIT
GLGL GFL
3.39m
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 6
2.2.1.1 Storm water drains: Storm water drains will be provided all over the site tomeet the expected increase in the runoff during rainy seasons due to the imperviousnature of the roads and other paved areas. The site is uneven and it is proposed tomaintain the levels as much as possible.
For each plot rainwater pipes shall be designed for rainfall intensity of 40mm/hour fromterrace floor to be harvested by storm water sumps adjacent to each building, excessdisposed to external storm water lateral drain running adjacent to the periphery of thecampus. The storm water drain has been worked taking into consideration the siteprofile (contour). The Rainwater Harvesting Structures is shown in fig 2.4.
The rainwater collected from the building and from the other surfaces of the plot isharvested by 1 no. of sump overflow being discharged to this municipal sewer lines.Before the storm water enters the sump I shall be passed through silt trap & grease trapfor removal of silt & oil if any. Harvested water shall be used for landscaping & fordomestic use.
Storm water drains will be provided all over the site to meet the expected increase inthe runoff during rainy seasons due to the impervious nature of the paved areas. Thesite is uneven and it is proposed to maintain the levels as much as possible, hencestorm water outlets from the site are anticipated. The expected runoff is calculated forthe design of the storm water management is presented in following table 2.3.
CALCULATION FOR STORM WATER DRAIN:Quantity of storm water:(a) With out project:Area of Catchment, ‘A’ : 1.4973 HaRun off Coefficient, ‘C’ : 0.6Maximum intensity of rainfall, ‘I’ : 40 mm/hrTherefore Q : 0.100 m3/sec
(b) With project: :Area for catchment for roof and road : 0.890 Ha
Area of Catchment, ‘A’ : 0.890 HaRun off Coefficient, ‘C’ : 0.9Maximum intensity of rainfall, ‘I’ : 40 mm/hrTherefore Q = : 0.089 m3/sec
Area for catchment for open areas : 0.608 HaRun off Coefficient, ‘C’ : 0.6Maximum intensity of rainfall, ‘I’ : 40 mm/hrTherefore Q = : 0.041 m3/secTotal Discharge : 0.129 m3/secBut, Discharge, Q = A/V :
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 7
Where, :A= Area of the Drain, :V= Max. Permissible Velocity : 6 m/sec for concrete drain
Area of drain, ‘A’ = Q/V : 0.022 m2
Taking depth of drain as 0.6 m at the startingpoint : 0.6Width of drain = Area/depth = 0.036 m 36 mm
Width of the drain is to taken 36 mm and depth varies according to the slope ofground.
Table 2.3. Storm Water CalculationLandUse
Area inHectares
Vol./hrafter
developmentC=0.8
Vol./hrbeforeDevelopmentC=0.6
Differencein
Discharges
Remarks
RoofArea
0.41 131.4 98.5 32.8Stored in 2 sumps of 20
m³ capacity and usedfor domestic utility
RoadArea 0.48 153.3 115.0 38.3 15 nos. of RWH pits are
proposed1.5m X 1.5m X 2.0 mOpen
Area 0.61 72.9* 145.9 -72.9
TOTAL 1.50 -1.8*C=0.3 after development of greenery
Rainwater Harvesting:The quantity of rainwater, which can be harvested, depends upon the annual rainfall,the area of the plot (catchment area) and soil characteristics. The amount of waterinfiltrated into soil varies with the condition of soil surface and the moisture content ofthe soil at the time of rainfall. The total amount of water infiltered depends on theinfiltration opportunity time, which depends mainly on the slope of the land and thefield structure like contour bunds, terraces and other structures, which tend to hold therunoff water over long periods on the land surface.
1. Rainwater Harvesting Pits
2. Harvesting by sumps
Roof top water shall be used for domestic purpose/landscaping after filtration &disinfection.
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 8
Fig 2.4 Rainwater Harvesting Structures
2.2.1.2 Water Availability:Water is required for the construction as well as during occupation stage as the same isan important resource. The water requirement during construction is in the order of60 cum/day with a peak demand of 100 cum/day, and during occupation stage in theorder of 145.3 KLD. The water resource available with the Municipal authorities wasstudied to identify the source and feasibility. The water resource both domestic waterand sewage is dealt by the Hyderabad Metropolitan water supply and Sewerage Board(HMWSSB) in the GHMC area. The HMWSSB has been maintaining the water supplyresources for Hyderabad along with the treatment of wastewater. The resourcesavailable with the HMWSSB are presented in table 2.4.
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 9
Table 2.4 Details of present sources of water supply to Hyderabad
Source Name River Year ImpoundmentName
Distance fromcity km
InstalledCapacity MGD
Osmansagar Musi 1920 Osmansagar 15 27Himayatsagar ESI 1927 Himayatsagar 9.6 18
Manjira Phase I Manjira 1965 Manjira barrage 58 15Manjira Phase II Manjira 1981 Manjira barrage 59 30Manjira Phase III Manjira 1991 Singur Dam 80 37Manjira Phase IV Manjira 1993 Singur Dam 80 38Krishna Phase I Krishna 2005 Nagarjuna Sagar 116 90Krishna Phase II Krishna 2008 Nagarjuna Sagar 116 90Krishna Phase III Krishna 2015 Nagarjuna Sagar 116 90Godavari Phase I Godavari 2016 Yellampally 186 172
Source: Hyderabad Metropolitan Water Supply & Sewerage Board,www.hyderabadwater.gov.in
It may be noted that the following water supply projects i.e., Krishna Phase III (Part II)with 45 MGD capacity and Godavari phase – I with 172 MGD capacity is anticipated tobe operational during 2015 and 2016 respectively. It may also be noted that thedependability of Osman sagar and Himiyath sagar is reduced to approximately 60%. 45MGD supply is available.
Domestic Water: It is proposed to draw domestic water from the HyderabadMetropolitan water supply and Sewerage Board (HMWSSB), which has beenencouraging the bulk consumers. The water shortage if any during summer season willbe drawn from ground water sources. The water requirement during construction willbe from ground water sources and the requirement is in the order of 80 cum/day. Thewater requirement of the project during occupation stage is in the order of 145.3 KLD.The water requirement for the project during the occupation stage is presented in table2.5. The Water Balance for the project is presented in table 2.7.
Table 2.5 Water Requirement of the Project
Land Use No. ofUnits
No. ofPersons/
unit
Waterrequirement per
person in l *
Total WaterRequirement
in KLDResidential 100 5 135 67.5Amenities 1 50 45 2.3Swimming pool 1 5.0Visitors 2 15 3.0Commercial 1500 45 67.5TOTAL 145.3*Water requirement as per NBC
The water requirement shall be reduced by adopting Dual plumbing system: Separatetank is provided to store the treated water; the tank shall be 1 foot below the overheadtank. Separate pipe system is provided to pump the treated water for flushing. All the
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 10
treated water pipelines shall be colored blue. Separate line in the blocks to use treatedwastewater for flushing purpose. The total saving is as follows;
Table 2.6 Water Savings Proposed
Land UseNo.of
Units
No. ofPersons/
unit
WaterRequirement/
KLD
Treatedwater
reuse/dayKlpcd
EffectiveWater
Requirementin KLD
Residential 100 5 67.5 20.0 47.5Amenities 1 50 2.3 1.0 1.3Swimming pool 1 5.0 5.0Visitors 2 3.0 1.5 1.5Commercial 1500 67.5 30.0 37.5TOTAL 145.3 52.5 92.8
Note: Treated water reuse assumed @ 20 l/head. Approximately 52.5 KL/day water willbe saved by adopting recycling of treated water in the toilet flush.
The effective water consumption is reduced by 52.5 kl/day and the requirement will bein the order of 92.8 kl/day. The water balance of the project during occupation stage istabulated in table 2.7
Table 2.7 Water Balance during occupation stageInput KL/Day Output KL/DayDomestic waterMunicipality 92.8 HVAC Chillers 59.7
Recycled water 52.5 Treated waste water for Recycle 52.5Water requirement for green beltduring non monsoon 4.0Losses approx 20% 29.1
Total 145.3 Total 145.3
The water used in the order of 145.3 KL/day would generate 116.2 KL/day ofwastewater which has to be treated for reuse and remaining unused excess treatedwater is given to municipality for roadside plantation or used for construction of otherbuildings /given to other developers.
SEWAGE TREATMENT PLANTTreatment plant for treating sewage in the project site has been proposed for a capacityof 150 m3/day. The Sewage Treatment flow chart is shown in fig 2.5.
PROCESS DESCRIPTION:The raw sewage will be collected in a collection sump and pumped to mechanical barscreen chamber for removal of large floating matter followed by grit removal in GritChamber. The raw sewage will then be collected in an equalization tank forhomogenization of hydraulic load. The tank contents will be kept in suspension by
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 11
means of course bubble serration through pipe grid. The equalization tank, with airflow indicator for continuous monitoring of air supply to the tank in order to avoidseptic conditions, will be covered from top (RCC or FRP) to avoid nuisance. Theequalized effluent will then be pumped to two Fluidized Aerobic Bio Reactors (FAB) inseries where BOD/COD reduction can be achieved by virtue of aerobic microbialactivities. The oxygen required will be supplied through coarse air bubble diffusers.The bio-solids formed in the biological process will be separated in the down streamTube Settler. The clear supernatant will gravitate to the chlorine contact tank wheresodium hypochlorite will be dosed for disinfection of treated water prior to disposal.
The biological sludge generated in the FAB and settled in the tube settlers will becollected in a sludge sump and then pumped to sludge drying bed for de watering. Thedried sludge will then be disposed off suitably as manure. The schematics of theprocess are shown. The two main components of the treatment system viz. The FABreactor and tube settler are described in the following sections.
Fluidized Aerobic Bio Reactor (FAB)Conventional effluent treatment plants are large sized, power intensive and require alot of monitoring. Scarcity of open space and rising land a power costs have forced theindustries to look our for space saving, compact and efficient treatment options. Thishas led to the development attached growth processes where the bio mass is retainedwithin the aeration tank obviating the need for recycle. These plants are not onlycompact but also user friendly. The endeavor to have a continuously operating, no-clogging biofilm reactor with no need for back washing, low head-loss and high specificbiofilm surface area culminated in the most advanced technology of aerobic biologicalfluidized bed treatment where the biofilm (biomass) grows on small carrier elementsthat move along with the water in the reactor. The movement is normally caused byaeration in the aerobic version of the reactor.The reactor combines all the advantages and best features of Trickling filters, Rotatingbiological contractors, activated sludge process and submerged fixed film reactorswhile eliminating the drawbacks of these systems. The plants are more compact andmore energy efficient.
The Fluidized Aerobic Bio Reactor (FAB) consists of a tank in any shape filled up withsmall carrier elements. The elements are made up of special grade PVC orpolypropylene of controlled density (shown in plate). For media of specific gravity 0.92-0.96 the overall density could be expected to increase up to 9.5% when full of biomasssuch that they can fluidize using an aeration device. A biofilm develops on theelements, which move along the effluent in the reactor. The movement within thereactor is generated by providing aeration with the help of diffusers placed at thebottom of the reactor. Then thin biofilm on the elements enables the bacteria to actupon the biodegradable matter in the effluent and reduce the BOD/COD content in thepresence of oxygen available from the air that is used for fluidization.
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 12
Table 2.8 Characteristics of Waste waterParameter Quantity in mg/l
PH 6 – 7Total Suspended Solids 400 – 600BOD 200 – 300COD 450 – 500
Design of the unitBasic dataFlow : 116 KLDCapacity : 150 m3
Peak factor : 3.5Peak flow Q peak : 525 m3/dayInfluent BOD : 200 mg/litInfluent Suspended Solids : 200 mg/litInfluent COD : 350 mg/litEffluent BOD : 30 mg/litEffluent COD : 200 mg/litEffluent Suspended Solids : 100 mg/lit
1. Bar Screen ChamberAverage flow : 0.0017 m3/secPeak factor : 3.5Peak flow : 0.006 m3/secVelocity at peak flow : 0.75 m/SecEffective area of screen RequiredAt average flow : 0.005 m2
At Peak flow : 0.0075 m2
Provide Effective area of screen : 0.0075 m2
Considering the bar of dia. 10 mm(w) and clear spacing of 20 mm (b)Overall area required : 0.012 m2
Considering screen depth as : 0.024 m Consider 0.5 mNumber of clear spacing : 0.3Number of bars : 1 Consider 3 Nos.Hence Provide 5 barsProvide a screen of 0.5 m X 0.5 m at an inclination of sin 600. In a screen channel of onemeter (1 m) length.
2. Grit Chamber :The flow from the bar screen chamber is let into the Grit Chamber of minimum 2 hourscapacity. This tank is provided to even out the flow variation, and to provide acontinuous feed into the secondary biological treatment units.Peak flow Q : 0.006 m3/secProviding a flow through velocity of 0.30 m/secCross sectional area of Channel (0.006/0.3) : 0.02 m2
Surface area of channel (0.006/0.013) : 0.46 m2
Assuming depth d : 0.2 m
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 13
Width of channel (0.02/0.2) : 0.1 m (say 0.2m)Length of channel (0.46/0.1) : 4. 6 m (say 4.6 m)Provide two channels each of 0.2 m wide and 4.6 m long with depth of waste water 0.2m.
3. Equalization tank:The flow from the bar screen chamber is let into the equalization tank of minimum2hours capacity. This tank is provided to even out the flow variation, and to provide acontinuous feed into the secondary biological treatment units.Average flow : 6.25 m3/hrPeak factor : 3.5Peak flow : 21.87 m3/hrHydraulic retention tank = 2 hrs at Peak flowHence required volume of the tank : 43.75 m3
Provide tank of : 43.75 m3 CapacityAssuming depth : 3 mArea : 14.58 m2
Assuming length to width ratio (1:1) ; l=blength of the tank : 3.8 mwidth of the tank : 3.8 mAir required for agitation : 0.01 m3/ m2 minTotal air required : 26.25 m3/hrAir blower required : 40 m3/hr @ 3.8 mwcEffluent transfer pump : 6.25 m3/hr @ 8 mwc
4. Fluidized Aerobic Bio Reactor (FAB):The polypropylene media have been provided with a specific surface area of 350 – 520m2 /m3. This allows micro-organisms to get attached and biomass concentration can beincreased to four folds as compared to Activated Sludge Process. This enables toconsider higher Organic loading rates.
The micro-organisms attached to media are kept in a fluid state thereby maintainingthe CSTR (continuous Stirrer tank reactor) regime as well as two tanks are provided inseries making the plug – flow system. This will enhance the efficiencies and have themerits of both CSTR and plug-flow regimes.Organic loading rate : 3.2 kg BOD/ m3 dOrganic load : 26 kg/dayVolume of the tank : 9.37 m3
Assume the depth : 3 mNo. of tanks in series : 1Size of the tank : 1.8 m dia. x 3.0 SWDSpecific gravity of media : 0.92 to 0.96Specific surface area of media : 350 – 520 m2 /m3
Media filling : 30 – 50 % of tank volumeOxygen required : 2 kg / kg BODOxygen in air : 23%Specific gravity of air @ 30 deg. : 1.65
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 14
Aeration : Coarse bubbleOxygen transfer efficiency : 12%Air required : 77.7 m3/hrAir blower required : 80 m3/hr @ 6.5 m wc
5.Tube settlerSurface loading rate : 48 m2 /m3 dSurface area required : 3.125 m2
Tank size : 3.0 m x 6.0 m x 2.7 m SWD With 55deg. hopper bottom
Tube Modules : 3.0m x 6.0 m x 0.6 m ht.Tube inclination : 60 deg.Settling area for 60 deg slope : 11 m2 /m3
Cross sectional area of tubes : 120 mm x 44 mm HexagonalHydraulic radius : 1/61 cm (1.5 cm)Shape factor : 0.6 – 0.7 for media settleable solids
6. Pre Filtration tankThe flow from the each individual settling tank i.e., the supernatant liquid is let into therespective Pre-Filtration Tank, which has a minimum 1.5 hours holding capacity. Thistank is provided to hold the treated effluent and give an even flow to the pressure sandfilter.Average flow : 6.25 m3/hrPeak factor : 2 m3/hrPeak flow : 12.5 m3/hrProvide min 1.5 hours holding capacity.Hence required volume of the tank : 18.75 m3
7. Pressure Sand Filter:Vertical down flow type with graded/sand bed under drain plate with polysterenestrains.Flow : 150 m3/dayRate of filtration assumed as : 10 m3/m2/hrRequirement of treated water for usage in 20 hrs : 7.5 m3/hrDia. of filter of 1 nos. : 980 mmProvide pressure sand filter of 980 mm dia. and 1200 mm HOS with sand as medialayer, under drain pipe, laterals face piping etc for each stream.
8. Activated Carbon Filter:Vertical down flow type with graded/sand bed under drain plate with polysterenestrains.Flow : 150 m3/dayRate of filtration assumed as : 10 m3/m2/hrRequirement of treated water for usage in 20 hrs : 7.5 m3/hrDia of filter of 1 nos. : 980 mmProvide Activated Carbon filter of 980 mm dia with granular Activated carbon as mediaand 1200 mm HOS with sand as media layer, under drain pipe, laterals face piping etc
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 15
for each stream.
9.Ultraviolet Disinfection:UV applied to low turbidity water is a highly effective means of disinfection. UV is notharmful to aquatic organisms in the receiving water. UV light kills viruses, Vegetative-and spore-forming bacteria, algae and yeasts. No chemicals are added to thewastewater to change the pH, conductivity, odor or taste to create possible toxiccompounds. UV treatment has a few moving parts to adjust or wear out.
10.Final Treated Water Holding TankIt is always preferred to provide one final holding tank of minimum one day holdingcapacity, so that the treated effluents can be stored and used back for gardening orother tertiary purposes.Capacity: 150 m3
11. Sludge Filter Press:The biomass in the aeration tank stabilizes BOD in wastewater by consuming theorganic matter in the wastewater. The metabolic activity results in growth of thebiomass population in the Fluidized Aerobic Bio Reactor (FAB). Sludge holding tank hasbeen provided with filter press for dewatering sludge. The filtrate drains off throughthe media, which is again let into equalization tank.The dewatered sludge is collected in trays, which can be used as manure in the garden.No. of plates : 24Size of plates : 600 mm X 600 mmPlate moc (material of construction) : PP (poly propline)Type of operation : HydraulicPower pack capacity : 2 HPThe biomass in the aeration tank stabilizes BOD in wastewater by consuming theorganic matter in the wastewater. The metabolic activity results in growth of thebiomass population in the Fluidized Aerobic Bio Reactor (FAB). Sludge holding tank hasbeen provided with filter press for dewatering sludge. The filtrate drains off throughthe media, which is again let into equalization tank. The dewatered sludge is collectedin trays, which can be used as manure in the garden.
Characteristics of Treated Waste waterParameter Quantity in mg/l
pH 7 – 8Total Suspended Solids 100BOD 30COD 100
Disposal of Treated Waste Water: The wastewater shall be treated and reused forflushing the toilets, on land irrigation and HVAC make up water requirement. Hence allthe recycled water is utilized completely and is considered as a zero discharge.
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 16
Fig 2.5 Sewage Treatment Flow Diagram
SEW
AG
E TR
EATM
ENT
PLA
NT
FLU
IDIZ
ED A
ERO
BIC
BIO
REA
CTO
R TE
CHN
OLO
GY
(FA
B)
Slud
geD
ewat
erin
gSy
stem
EQT
TAN
K
PSF
ACF
BarS
cree
n/ G
rit
Cham
ber
Raw
Sew
age
Ove
rflo
w
Filte
r Fee
dPu
mp
(1W
+1S)
Slud
geD
ispo
sal
SLU
DG
EH
OLD
ING
TA
NK
CLA
RIFI
EDW
ATER
TAN
K
FAB
REA
CTO
R(P
acka
ge u
nit)
TREA
TED
WAT
ERTA
NK
To R
euse
TUBE
Sett
lers UV
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 17
2.2.1.3 Solid Waste
Municipal Solid Waste CompositionIn India the biodegradable portion dominates the bulk of Municipal Solid Waste.Generally the biodegradable portion is mainly due to food and yard waste. The belowtable presents Composition of Municipal Solid Waste.
Table 2.9 Composition of Municipal Solid WasteType Composition (%) Solid waste in kg
Paper 8 62Plastics 9 70Metals 1 8Glass 1 8others 4 31Biodegradable 48 372Inerts 25 194Rags 4 31Total 100 775
Source: NSWAI - (National Solid Waste Association of India)
Design StageThe total number of people anticipated to stay in the project is in the range of 1000-2000. The anticipated solid waste/garbage is in the range of 300 g/head, and the totalgarbage will be in the order of 775 kg/day. The solid waste from the block is collectedthrough dumb waiter system and then collected at the block collection point and finallysent to the main collection point. The organic waste is treated in the waste converterand the inorganic waste is sent to the Municipal Management facility. The residents ofthe surrounding layouts are sending their solid waste through the SerilingampallyMunicipality appointed NGO for collection, which is nearer to the site. Government ofTelangana identified the Jawaharnagar Garbage disposal center for both Kukatpally andSerilingampally areas. The biodegradable garbage after segregation is composted andthe remaining waste is sent to the landfill in Jawaharnagar. The landfill site is yet toobtain clearance under Municipal solid waste rules of MoEF, GoI. The table 2.10presents the anticipated garbage quantity after occupation.
Table 2.10 Solid Waste Generation
Land Use No. ofUnits
No. of Persons/unit
Total No. ofPersons
Total Solid waste inKgs @ 0.5 kg/head
Residential 100 5 500 250Amenities 1 50 50 15Visitors 1 200 200 60Commercial 1500 1500 450
TOTAL 775
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 18
2.2.2 Construction StageThe sequence of construction operations and the approximate time requirement ispresented in the following table 2.11. The time schedule of the entire project isapproximately 18 months.
Table 2.11 Construction SequenceS.No Description of work
1 Clearing and Grubbing2 Leveling by way of cut and fill3 Foundation Excavation.4 Foundation PCC & Concrete & Plinth Beam.5 Column lifting up to GF Roof.6 1st floor slab reinforcement & shuttering & Concreting.7 Stair case slab8 1st floor column lifting up to 1st floor roof.9 1st floor roof shuttering, reinforcement & concreting.
10 Deshuttering of GF Roof & cleaning.11 Deshuttering of 1st Roof & cleaning.12 Brick work in GF floor.13 Brick work in 1st floor.14 Staircase up to terrace.15 Staircase headroom slab.
16Plumbing works (concealed works).Electrical conduit junction boxes & boardfixing.Plastering works.
a. Internal (GF & FF).
b. External (GF & FF).
17 Fixing of door & window frames.18 Plinth filling & floor PCC.19 Floor Tiling Works, bathroom, kitchen & platform works.20 Staircase stone works.21 Terrace waterproofing works.22 Parapet wall in terrace & miscellaneous works.23 Fixing of door & window shutters.24 Fixing of sanitary fittings.25 Electrical wiring & fixtures.26 Painting works.27 External development & compound wall.
The clearing and grubbing activity involves clearing of few trees and shrubs mainly asthe greenery is not disturbed in the layout plan. The cut and fill operation for the entirearea is presented in table 2.12. There is excess cut material which would be used forconstruction of roads and the purpose of aggregate for the construction purpose.
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 19
Table 2.12 Earth Work Quantities
S No Area Qty. of fill(m3)
Qty of cut(m3)
Surplus fill(m3)
Surplus cut(m3)
1 Site 14375 17968 ----- 3594
The cut material contains mainly granite stones, which is suitable for masonry works.The excess cut material in the order of 3594 m3 will be used for above purpose.
The construction of this magnitude would require huge quantities of constructionmaterials. The material requirement for the project is presented in table 2.13.
Table 2.13 Material Consumption per Total Units
Land Use BUA perunit in (m2)
ReadyMix
Concrete(m3)
Cement(bags)
Sand(m3)
Aggregate (m3)
Water(m3)
Brick(Nos) x1000
Reinforcement
steel (MT)
Total BUA 122009 50024 113469 47584 5246 29526 14153 2806Total 122009 50024 113469 47584 5246 29526 14153 2806
Thus aggregate requirement will be met from within the plant site. The lead distancefor various construction materials is presented in table 2.14.
Table 2.14 Lead Distance for Construction Materials
S.No Material Source Lead Distance(Km)
1Sand ROBOSAND and or Krishna or
Godavari river bed areaspermitted by Govt.
160 – 250
2 Aggregate With in the site 0 – 53 Cement Manufacturing units 150 – 2004 Reinforcement Steel SAIL/TATA god owns 5-105 Bricks Local suppliers/ Manufacturers 506 Plumbing Material Local suppliers 2 – 97 Electrical Material Local Suppliers 2 – 88 Sanitary Material Local suppliers 2 – 8
9 Flooring andPavement Tiles Manufacturers 50– 150
10 Paints Local Manufacturers 10 – 3011 Ready Mix Concrete Local Batch Plants 3 - 7
2.2.2.1 Water RequirementThe water required for this project is in the order of 30000 m3 for the entire projectimplementation period. The peak demand for water may be 200 m3/day, howevertypical daily consumption will be in the order of 100 m3/day. The required water will bedrawn from ground water sources. The project authorities explored the possibility ofusing treated wastewater to meet partial requirement of water and could not identify a
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 20
reliable source. The water supply and plumbing will be optimized and low waterconsuming faucets and flush tanks will be used to conserve water.
2.2.2.2 Construction DebrisThe construction debris consists of various types of materials. The construction debriswill be in both hazardous and non-hazardous categories. The hazardous debris consistsof empty containers of adhesives, thinners, paints, and petroleum products. Theseempty containers will be sold to authorized recyclers. The non hazardous wastescontain recyclable debris like iron and other metal, glass, plastics, cartons of paper,wood etc. These wastes will be sent for reuse/recycle. The waste percentage will be inthe order of 2%. Construction debris containing bricks, demolished RCC will be used forland filling in the place of sub grade.
2.2.2.3 PaintsAll the paints used in the premises will be ensured to have an albedo of at least 0.4 toincrease the reflectivity and reduce the heat dissipation and heat island effects.
2.2.2.4 Work Force:The labor/work force requirement is approximately 8000 man-days of various skilledand unskilled employees. Sufficient labor force and skilled employees are available, asHyderabad is a favorite destination of skilled employees and migrating people from therural areas. The peak labor force requirement will be in the order of 1000 people. Thelabor force will be provided with temporary toilet facilities connected to a septic tankfollowed by sewer linrs. The water requirement for the labor force will beapproximately 500 lt/day.
2.2.2.5 Material preparation and transportMost of the construction material except aggregate will be drawn from outside. Thematerial will be transported by trucks and the approximate number of truck trips are600. The material transport within the site will be facilitated by 5 no. of trippers.
2.2.3 OCCUPATION PHASEA number of facilities will be provided by M/s DSR Builders & Developers for theoccupants and the facilities are shown in table 2.15
Table 2.15 Amenities ProposedAmenity Nos. or Description
Sewage Treatment Plants 1Garbage Collection Bin 1DG Sets 3 X 1000 kVA + 2 X 500 kVAGreen area 1503.53 m2
The company shall operate the amenities like sewage treatment plant, DG sets. Themajor requirement of resource is for electricity and water. The electricity will be drawnfrom TRANSCO. Transformers will be provided to reduce voltage fluctuation and toprovide quality energy. The power requirement during operation phase is presented intable 2.16.
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 21
Table 2.16 Energy Consumption Statement
S.No DescriptionNo. ofUnits
Load inKW
TotalConnected
Load(KW)
TotalConnected
Load(kVA)
TotalMax
Demand(KVA)
1 Residential 100 6 600.0 750.0 750.02 Commercial 950 950.0 1187.5 1187.53 Street Lights 45 0.04 1.8 2.3 1.84 Amenities 100.7 125.9 100.75 STP 1 110 110.0 137.5 137.56 Lifts 8 15 120.0 150.0 150.0
TOTAL 1882.5 2353.1 2327.5Maximum demand in kw at 0.6 diversity factor 1129.5Consumption of power for 8 hours per day 9036.0Maximum demand in kw at 0.2 diversity factor 376.5Consumption of power for 16 hours per day 6024.0Total consumption of power per day 15060.0 KWTotal consumption of power per year 55.0 Lakh Units
Table 2.17 Energy Saving by using Solar Water Heater
S.No Description No. ofUnits
Powerallocated inwatts / unit
Total powerrequired in
(KW)1 Residential 80 2500 200
TOTAL 200Maximum demand in kw at 1 diversity factor 200Consumption of power for 2 hours per day 400Maximum demand in kw at 0.4 diversity factor 80Consumption of power for 2 hours per day 160Total consumption of power per day 560.0 KWTotal consumption of power per year 2.04 Lakh Units
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 22
Table 2.18 Energy Saving by using Solar Street Lights
S.No Description No. ofUnits
Powerallocated inwatts / unit
Total powerrequired in
(KW)1 Street lights 15 40 0.6
TOTAL 0.6Maximum demand in kw at 0.6 diversity factor 0.4Consumption of power for 8 hours per day 3Maximum demand in kw at full load 1Consumption of power for 4 hours per day 2Total consumption of power per day 5.3 KWTotal consumption of power per year 0.02 Lakh Unitssaving with Solar Heater and Street Lighting 2.06 Lakh Units
Table 2.19 Electrical Power savings using CFL for lighting
S.No Description Area inm2
Powerallocated inwatts / unit
Total powerrequired in
(KW)
1Residential &Commercial 78811 10 788
2 Common & Utilities 4966 2.5 12TOTAL 801
Maximum demand in kw at 0.9 diversity factor 720Consumption of power for 12 hours per day 8646Total consumption of power per day 8645.6 KWTotal consumption of power per year 31.56 Lakh UnitsSavings in power using CFL 9.47 Lakh Units
Table 2.20 Savings in Electrical Power Consumption – SUMMARY
S.No Description WithCFL/LED
With SolarHeater and
StreetLighting
TotalConsumptionin lakh units
Total Saving
1 Savings in lakhkwh units
9.47 2.0654.97
11.53
2 Savings inpercentage (%)
17.22 3.75 21.0
2.2.3.1 Domestic WaterThe domestic water will be drawn from HMWSSB and during non-availability Groundwater will be drawn and used to augment the supplies. The wastewater will be treatedand reused for gardening and flush tanks. Dual plumbing system is adopted to reuse thetreated wastewater for flushing. Dual plumbing system: Separate tank is provided tostore the treated water, the tank is at least 1 foot below the level of other tanks and a
DSR The First & BN Tech Square Environmental Impact Statement
Team Labs and Consultants2 - 23
distance of minimum 2 feet from the other water pipelines. Separate pipe system isprovided to pump the treated water for flushing. All the lines providing treated waterwill be colored blue. The excess treated water will be let out into the storm waterdrains.
2.2.3.2 Solid WasteThe solid wastes anticipated during occupation stage include garbage, sludge from STP,hazardous waste of used oils, and batteries from generators. The quantity of wastes ispresented in table 2.21.
Table 2.21 Solid Waste Generated during Occupation PhaseS.No Type of Waste Quantity Collection/storage Disposal
1 Garbage 775 kg/day
Segregation at source intobio-degradable, non bio-degradable and DomesticHazardous wastes. Disposalof recyclable waste toAuthorized Waste Pickers /Authorized Recyclers.Balance segregated wastegiven to Authorized Agencyof Local Body.
Municipalsolid wastedisposal
2SewageTreatmentPlant Sludge
7.5kg/day Stored in HDPE bags.
Used asmanure andor given tofarmers.
3 Used Batteries 8 nos. year
Sent toAuthorizedrecyclers orreturned toseller
4 Used Lubricant 175 l/year Stored in HDPE CarboySold toauthorizedrecyclers
5 TransformerOil 220 l/year Stored in HDPE Drum
Sold toTRANSCOauthorizedcontractors
6 e-waste Stored in go downs e-parisara
DSR THE FIRST & BN TECH SQUAREM/s DSR BUILDERS AND DEVELOPERS
SURVEY NO. 66/2, PANMAKTHA,SERILINGAMAPALLY, RANGA REDDY DISTRICT
Studies and Documentation by:M/s Team Labs and ConsultantsB-115 to 117 & 509, Annapurna Block,Aditya Enclave, Ameerpet,Hyderabad- 500 038Phone: 91-040-23748555/616Fax : 91-040-23748666e-mail: [email protected]