Condition Monitoring of Power Plant Equipment

Embed Size (px)

Citation preview

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    1/44

    Condition Monitoring of Power

    Plant Equipment

    Presented by

    S Bhattacharya, K R Bairwa,P Kukde

    The Tata Power Co Ltd, Mumbai

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    2/44

    CONTENT

    Concept of Condition Monitoring Condition Based Maintenance

    Management System at Trombay

    Case Studies

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    3/44

    Need of Condition Monitoring

    Safety of Man and Machine

    Plant availability Reliability

    Operation at Best Efficiency

    Minimization of Maintenance Cost

    Health assessment & Minimizing the failures

    Equipment Life Assessment

    Input for developing Maintenance Strategy

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    4/44

    Safety of Man and Machine

    Modern Power Plant Equipment are High Cost

    Capital assets

    Fire Hazards Fuel, Lubricating Oils, Electrical, etc

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    5/44

    Reliability

    High reliability

    Electricity is life line of the modern civilization Local

    Trains, Hospitals, Industrial requirement, Domesticrequirements, sanitation, basic amenities, etc

    Maximize reliability by performing plannedmaintenance based on condition monitoring.

    Machinery in large power plant is desired to have high reliability.As maintenance has a large cost impact on the total operation, it

    is however essential to only perform maintenance when it is

    really required.

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    6/44

    Plant Availability

    Shift form breakdown to condition based

    maintenance

    Machine health input for scheduling inspection &

    maintenance

    To guarantee the machine availability, avoid major breakdown &

    to schedule inspection & maintenance, the condition of the

    machines need to be monitored accurately, so that right

    maintenance decisions can be taken

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    7/44

    Objectives of Condition Monitoring

    Protect machines against major breakdowns

    Machine health assessment.

    Maximize operation efficiency.

    Troubleshooting

    Minimize maintenance cost

    This is the basis for formulating maintenance strategy

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    8/44

    Machine Health Assessment

    Parameter Identification

    OEM guidelines

    Operating Experience

    Improved Diagnostic Analysis

    Monitoring System

    On line monitoring

    Off line monitoring

    Trends

    Raw data monitoring

    Data analysis and monitoring of derived parameters

    Defined range of operation - Normal/Alarm/Trip value

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    9/44

    Machine Health Assessment

    Feed back from Machine Operating History

    Machine operating characteristics

    History of past problems and its remedy

    Residual Life Analysis

    Comprehensive Equipment Health Survey

    Pre-overhaul survey

    Input from OEM and other plants

    Residual life study

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    10/44

    Condition Based Maintenance Management

    System at Trombay

    Online monitoring of Critical Parameters

    Periodic Data Collection and Trending Analysis

    Inputs from equipment history, pre-overhaul survey

    and past experiences

    RLA

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    11/44

    Monitoring Parameters for Main Turbine

    Mechanical Parameters

    Vibration of Shaft and pedestal

    Bearing metal temperature

    Turbine Expansions

    Axial shift,

    Turbine metal temperature

    Functional Parameters

    Steam pressures and temperatures

    Vacuum

    Feed Water Parameters

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    12/44

    Limit Values of Operating Parameters

    OEM recommendation

    Steady state running parameters

    Revise limit values based on condition monitoring

    This forms the basis for deciding alarm & trip values

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    13/44

    Pre-overhaul survey of Main Turbine

    Objective

    Ascertain present running behavior Identify problem areas

    Planning for high value insurance spares

    Define scope of Quality overhaul Planned preparation

    Focused approach to minimize outage duration

    Decision making for future overhauls

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    14/44

    Pre-overhaul survey of Main Turbine

    Studies to be conducted during Pre-Overhaul Survey

    Running hours

    Reports of all previous overhauls along with therepairs carried out and spares consumed

    Discussions on Past / present problems

    RLA reports Present vibration behavior/scan

    Thermo-scan

    Study of past and present operating data Heat balance diagram and reports of periodic

    enthalpy drop tests

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    15/44

    Pre-overhaul survey of Main Turbine

    Example:

    High IP exhaust steam temperature in Unit 5

    Possible causes: Steam leak through parting plane.

    Inlet steam passing into exhaust directly through

    angle seal rings Steam leakage through angle sealing rings of steam

    extractions

    Faulty RTD

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    16/44

    Pre-overhaul survey of Main Turbine

    Analysis and Action Taken:

    Machine EOH > 1.5 Lakh hours.

    Parting plane fasteners replacement planned.

    No history of steam leak through angle seal rings.

    During turbine fact finding inspection no sign of

    leakage observed. Also clearances were within

    design limits.

    RTD

    Problem identified with data acquisition and transfer.

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    17/44

    Pre-overhaul survey of Main Turbine

    Strategic decision based on past experience:

    HP front shaft high vibration problem persisted for 4years.

    Problem resolved by carrying out slow speed dynamic

    balancing at site.

    This practice is being followed for all rigid rotors at

    Trombay. All rotors balanced till date have hadsubstantial mass imbalance.

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    18/44

    Vibration analysis

    Vibration is one of the most significant parameter for

    interpreting machine-health and indication for problems

    at incipient stage.

    For machine health monitoring, the simplest method of

    detecting any abnormality with the machine is to look for

    the change in vibration pattern and level.

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    19/44

    Guidelines for Vibration Analysis

    Gradual rise in vibration are due to:

    Bearing deterioration/ wearDeterioration of base frame/ grouting

    Wear, corrosion, deposition on rotating

    componentsSettling of foundations

    Deterioration in alignment

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    20/44

    Guidelines for Vibration Analysis

    Abrupt change in vibration could be due to:

    Change in operating parameters like flow,

    pressure, temperature, etcModification / maintenance deficiency ( e,g

    bearing misalignment) if it increases just after

    maintenance.Operating shocks resulting in machine

    deterioration / damage

    Hot misalignmentBearing lubrication problem

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    21/44

    Guidelines for Vibration Analysis

    Very high vibrations can be attributed to:

    Resonance

    Imbalance of rotating parts

    Expansion restrictions/ Piping strains

    Foundation problem/ Foundation loading

    Loading of bearings

    Lubrication problems

    Improper dimensional tolerances

    Machine performance does not meet withrequired performance, hydraulic forces,aerodynamic forces-design problem.

    Equipment damage e.g rubbing, rotor bent,

    gear mismatch, etc

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    22/44

    Guidelines for Vibration Analysis

    Vibration spectrums analysis indicative of thefollowing problems:

    Unbalance

    Bent shaftMisalignment of couplings, bearings and gears

    Looseness

    RubbingEccentricity of rotating components

    Resonance

    Journal bearing problems oil whip, oil whirl

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    23/44

    Guidelines for Vibration AnalysisSalient Points for vibration analysis:

    Shaft is the source of energy in rotating machinery.

    Shaft could get its energy from: process medium, imbalance, restrictions,variation of design settings, expansion problem, rubbing, electrical problem,inconsistency of oil film, etc

    Energy of shaft shows through bearing, casing, foundation, pipe, etc Acceptable energy/ vibration of shaft may show unacceptable vibration in

    bearing due to problem in bearing, foundation, casing , pipe pulls, etc

    Latent design defects/deficiencies surfacing at a later date can be source of

    vibrations. e.g foundation, pipe pull, resonance, etc. Recognize the focal point of vibrations

    Look for temperature effect on vibrations

    Look for effect on vibration behavior due to loading of machine

    Study the recent maintenance carried out if any. Look for change in operating parameters if any

    Look into the history of vibrations of the machine

    Look for abrupt change/ trend of vibration

    Look for change in running parameters of the machine like bearingtemperatures, etc.

    Look for change in lubrication, oil quality, etc

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    24/44

    Main Turbine Unit # 5 LP free

    standing blade failure.

    Case Study 1

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    25/44

    Main Turbine Unit # 5 LP free standing blade failure.

    Background

    LP turbine free standing blade failure occured on running machine,which lead to catastrophic failure of the machine. Being the first incident

    of this nature and our unit being the oldest 500MW unit in India, the

    study of blade failure detection was undertaken in collaboration with

    BARC, Mumbai.

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    26/44

    Observations and analysis:

    Blade vibrations were recorded twice, before & after shutdown.

    1. During vacuum drop many peaks of vibration corresponding to

    natural frequency of LP II & LP III observed. These were

    not seen during normal steady state operation.

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    27/44

    Observations and analysis:

    2. Drastic variation in amplitude is seen in BPF component of LP

    II & LP III during excitation. Normally, the amplitude are

    steady unless the blades are disturbed and set into vibration.

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    28/44

    Observations and analysis:

    3. Side band harmonics are seen on both sides of the BPF. The

    harmonics are 20 Hz on either side of the BPF. The presence of

    the side bands indicates problem with the blades. Theseharmonics vanished after replacement of the cracked blades.

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    29/44

    Observations and analysis:

    4. The Amplitude of the BPF have drastically reduced after

    replacement of the cracked blades.

    This technique of detecting cracks in freestanding blades may be very

    useful for monitoring the health of the machine and thereby detecting

    blade cracks at the incipient stage.

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    30/44

    Control Fluid Pump CurrentHunting

    Case Study 2

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    31/44

    Pump Specification

    Make : KSB, Germany

    Type : WKVM 100/2+3

    LP Discharge : From 2nd Stage

    HP Discharge : From 5

    th

    stage Rated Pressure : LP - 13.6 Bar

    HP - 40 Bar

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    32/44

    Pump Layout

    Pump 1Pump 2

    LP Circuit

    HP CircuitNRV

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    33/44

    Problem

    Motor Current of CF Pump 2 hunting from 152 192

    Amps.

    No pressure hunting in LP Circuit.

    HP circuit pressure hunting around 1 bar

    (CF system is provided with accumulators to take

    care of pressure fluctuations)

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    34/44

    Cause Effect DiagramOperational Hydraulic

    Pump flow variation Loss of suction

    System fluctuations Obstruction at suction

    Load / Freq variation Blockage

    Accumulators Detached suction pipe

    Bladder failure Fluid foaming

    Isolation from circuit change in air release property

    Control system contaminationGovernor hunting air ingress

    Fluid properties

    Viscosity / Temperature

    Contamination

    Internal clearances

    Increase in clearances beyond limits Damage to internals

    Wear Impeller / Diffuser

    Rubbing

    Axial float setting

    Setting during assembly

    Pump operating in unstable zone Rotor faultInterstage leakages Design

    Gasket failure Change due to internal damage Measurement error

    Looseness

    Mechanical Electrical

    Pump charecteristics

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    35/44

    Possible Causes

    Electrical fault

    Rotor fault Motor of pump #2 swapped with motor of pump #1

    Measurement error

    RPM measurements carried out Power measurements carried out

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    36/44

    Possible Causes

    Hydraulic problems

    Obstruction in pump suction

    During unit outage the Control Fluid was transferred

    to another tank for tank inspection and no

    abnormality found

    Fluid foaming

    No foaming observed and CF sample tested OK

    Change in fluid viscosity

    Operating temperature normal and no contaminationof fluid

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    37/44

    Possible Causes

    Operational Problem

    - Pump flow variation

    No System fluctuation , accumulators found

    healthy, and no hunting in governing system.

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    38/44

    Possible Causes

    Mechanical Problems

    - Increase in internal clearances

    - Problem with Axial float setting- Damage to internals

    Pump overhauled and performance tested at OEM

    facility (partial test with LP stage blocked).No damage observed on internals, gasket failure or

    looseness in the pump

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    39/44

    Possible Causes

    Mechanical Problems

    - Pump characteristics

    In-situ pump flow measurements carried out. Flowhunting observed in HP circuit.

    2

    1

    Pump

    39-41

    41

    LP Flow(m3/hr)

    10 15

    24.5 25

    HP Flow(m3/hr)

    152-192

    167 -172

    Current(Amp)

    P Ch t i ti

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    40/44

    0

    50

    100

    150

    200

    250

    300

    350

    400

    0 20 40 60 80 100 120 140

    Flow

    Head(m)

    Unit 6 CF Pump 2 Char Modified hyd char

    Pump Characteristics

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    41/44

    Corrective action

    HP Impeller modification

    It was observed that the pump operating point is in

    unstable zone

    Diameter increased by 10 mm to change the pump

    hydraulics

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    42/44

    Pump behavior after modification

    174170Current

    (Amps)

    40.539.6HP Pressure

    (Bar)

    13.513.6LP Pressure

    (Bar)

    21Pump

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    43/44

    Operational Hydraulic

    Pump flow variation Loss of suction

    System fluctuations Obstruction at suction

    Load / Freq variation Blockage

    Accumulators Detached suction pipe

    Bladder failure Fluid foaming

    Isolation from circuit change in air release property

    Control system contaminationGovernor hunting air ingress

    Fluid properties

    Viscosity / Temperature

    Contamination

    Internal clearancesIncrease in clearances beyond limits Damage to internals

    Wear Impeller / Diffuser

    Rubbing

    Axial float setting

    Setting during assembly

    Pump operating in unstable zone Rotor fault

    Interstage leakages Design

    Gasket failure Change due to internal damage Measurement error

    Looseness

    Mechanical Electrical

    Pump charecteristics

  • 8/8/2019 Condition Monitoring of Power Plant Equipment

    44/44

    THANK YOU