20
Kevin J. Dayton, P.E., Chief Engineer Assistant Secretary, Regional and Mega Programs Chris Christopher, P.E., State Construction Engineer Joint Transportation Committee July 20, 2017 Connecting Washington Bid Environment Roger Millar, Secretary of Transportation Keith Metcalf, Deputy Secretary of Transportation

Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Kevin J. Dayton, P.E., Chief Engineer

Assistant Secretary, Regional and Mega Programs

Chris Christopher, P.E., State Construction Engineer

Joint Transportation Committee July 20, 2017

Connecting Washington

Bid Environment

Roger Millar, Secretary of Transportation

Keith Metcalf, Deputy Secretary of Transportation

Page 2: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Current project delivery

2

Page 3: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Challenges delivering the

Nickel/TPA projects

• Escalation in global material costs during the mid-2000’s

led to an increase in project costs

• 2003 and 2005 fuel tax forecasts did not anticipate the

economic recession

• Managing the growth and decline in the size of

WSDOT’s construction workforce

• Legislative project list baselines established with limited

engineering completed

• On-going maintenance impacts of increasing the size of

the state’s transportation system

3

Page 4: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

WSDOT’s Construction Cost

Index

4

Chart from September 30, 2007 WSDOT Gray Notebook

Page 5: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

WSDOT’s Construction Cost

Forecast

5

0.00

100.00

200.00

300.00

400.00

500.00

WSDOT’s CCI Forecast

Prediction of future

construction inflation

Corrected data based on

actual construction inflation

Page 6: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

The New Challenges affecting

Connecting Washington

6

• Indicators are pointing to another period of increasing

construction costs.

• Appears to be driven by local/regional effects rather than

the global effects. For example:

– A booming Puget Sound economy

– Competition with other public Owners (Sound Transit,

Port of Seattle, City of Seattle, etc.)

– Significant private infrastructure projects

– Very low unemployment and potential labor shortages

– Shortage of subcontractors

Page 7: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Competitive bidding results

7

3.6 3.6

4.14

3.63.5

3.1

3.5

4.4

5.1

5.5

4.9

4.54.3

3.93.8

3.6

2.5 *

0

1

2

3

4

5

6

2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017

Calendar Year

Average Number of Bidders on WSDOT Contracts

* 2017 data through June 30 (56 projects)

Page 8: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Bid Prices vs. Engineers Est.

8

-15.20%

-11.71%

-9.31%

9.80%

-20.00%

-15.00%

-10.00%

-5.00%

0.00%

5.00%

10.00%

15.00%

Bid Price Percentages Above/Below Engineer's EstimateFor all bid openings in the month of March from 2014 to 2017

12

Projects

9 Projects

24

Projects

23

Projects

Ab

ove

En

gin

ee

r's

Be

low

En

gin

ee

r's

March

2014March

2015

March

2016

March

2017

Page 9: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Driven by material costs?

9

-15.20%

-11.71%-9.31%

9.80%

-60.00%

-50.00%

-40.00%

-30.00%

-20.00%

-10.00%

0.00%

10.00%

20.00%

Change in the Price of Construction CommoditiesMarch 2014 to March 2017

% In

cre

ase

in C

ost

% D

ecre

ase

in

Co

st

March

2014March

2015

March

2016March

2017

Bid Prices

Page 10: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Driven by material costs?

10

-60.00%

-50.00%

-40.00%

-30.00%

-20.00%

-10.00%

0.00%

10.00%

20.00%

Change in the Price of Construction CommoditiesMarch 2014 to March 2017

% In

cre

ase

in C

ost

% D

ecre

ase

in

Co

st

Steel Mill

Products

↓ 5.2%

March

2014March

2015

March

2016March

2017

Page 11: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Driven by material costs?

11

-60.00%

-50.00%

-40.00%

-30.00%

-20.00%

-10.00%

0.00%

10.00%

20.00%

Change in the Price of Construction CommoditiesMarch 2014 to March 2017

% In

cre

ase

in C

ost

% D

ecre

ase

in

Co

st

Diesel

Fuel

↓ 30.6%

March

2014March

2015

March

2016March

2017

Bid Prices

Page 12: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Driven by material costs?

12

Change in the Price of Construction CommoditiesMarch 2014 to March 2017

% In

cre

ase

in C

ost

% D

ecre

ase

in

Co

st

Asphalt

Binder

↓ 40.6%

March

2014March

2015

March

2016March

2017

Bid Prices

Page 13: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Driven by material costs?

13

-15.20%

-11.71%-9.31%

9.80%

-60.00%

-50.00%

-40.00%

-30.00%

-20.00%

-10.00%

0.00%

10.00%

20.00%

Change in the Price of Construction CommoditiesMarch 2014 to March 2017

% In

cre

ase

in C

ost

% D

ecre

ase

in

Co

st

Asphalt

Binder

Steel Mill

Products

Diesel

Fuel

↓ 5.2%

↓ 40.6%

↓ 30.6%

March

2014March

2015

March

2016March

2017

Bid Prices

Page 14: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

What we’re seeing

14

• Bid prices are averaging 11% above our engineer’s

estimate for January through June 2017 (55 projects

totaling $177M)

• Cost growth is exceeding what was anticipated when

Connecting Washington was passed by the Legislature

• The buying power of Connecting Washington projects

may be diminished by cost escalation

Estimate from 2015 Connecting

Washington package

Contractor Bid Price

Practical Solution Savings

Co

st

Esca

lation

Page 15: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

What we’re doing about it

15

1. Collaborating with our Contractors to fully

understand the causes of the recent escalation

2. Two broad categories:

A. Factors outside of WSDOT’s control

B. Factors within WSDOT’s control

Page 16: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Examples of Factors Outside of

WSDOT’s Control

16

1. Global economy

2. Regional economy

3. Western Washington construction market

4. Material prices

5. Contractor capacity in the Washington

market

6. Labor supply

For these, we need to ensure our estimating practices reflect the

influences these factors exert on bid prices

Page 17: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Examples of Factors Within

WSDOT’s Control

17

• Contract time

• Daily work windows

• Timing of project

advertisements

• Using full closures rather

than nightly lane closures

• How projects are

packaged

• Delivery method (Design

Bid Build vs. Design Build)

• Flexible contracting that

allows innovation

• Risk allocation

• Quantity and complexity of

Contractor reporting

requirements (e.g.

Apprenticeship, DBE)

• Cash flow constraints

• Other?

Page 18: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

But, implementation needs to

carefully consider:

18

• Impacts to the travelling public

• Long-term performance of the system

• Local community impacts and commitments

• WSDOT workforce impacts

• Environmental impacts

• Safety

• Quality

• Availability of funds

Page 19: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Next Steps:

19

• Continue to incorporate innovative practices and

practical design

• Ongoing discussion with the contracting community

• Identify factors to move forward while considering the

impacts

• Implementation in consultation with industry

• Come back with an update in January 2018

Page 20: Connecting Washington Bid Environmentleg.wa.gov/JTC/Meetings/Documents/Agendas/2017...300.00 400.00 500.00 WSDOT’s CCI Forecast Prediction of future construction inflation Corrected

Questions?

Kevin J. Dayton, PE, Chief EngineerAssistant Secretary, Regional and Mega Programs

Washington State Department of Transportation

360-705-7032

[email protected]

Chris Christopher, PEState Construction Engineer

Washington State Department of Transportation

360-705-7821

[email protected]

17