TANK MATE
INCLUDES:
TOOLS REQUIRED:
3/4” WRENCH
PETCOCK TEE ASSEMBLY
8 FOOT NYLON TUBING
TEE
WV-1 DRAIN VALVE
CONRADER VALVES
**TUBING CUTTERS
** NEEDED TO CUT METAL TEE INSTALLATION LINES
AUTOMATIC DRAIN VALVE INSTALLATION KIT
STEP 1: DISCONNECT POWER/DISABLE ENGINE
IF YOUR COMPRESSOR IS ELECTRICALLY DRIVEN, (1) REMOVE THE PLUG FROM
THE WALL. IF IT IS GAS DRIVEN, (2) TURN THE
ENGINE SWITCH TO OFF.
STEP 2: BLEEDING THE SYSTEM AIR
INSTALLATION INSTRUCTIONS FOR WV-1
BLEED ANY EXISTING AIR FROM THE TANK BY FOLLOWING THE INSTRUCTIONS IN THE OWNERS
MANUAL.
STEP 3: PREPARE THE RECEIVER
(1) REMOVE THE EXISTING DRAIN PETCOCK OR DRAIN
VALVE COMPLETELY. (2) ALSO, CLEAN THE THREADS OF THE TANK OPENING TO
REMOVE ANY RESIDUE THAT MAY HAVE BUILT UP.
STEP 4: INSTALLING PETCOCK/TEE ASSEMBLY
INSTALL THE PETCOCK TEE ASSEMBLY BY SCREWING IT
INTO THE PREPARED
TANK OPENING.
1 2
OFF
21
STEP 5: INSTALLING THE DRAIN VALVE
STEP 6: INSTALLING TEE IN CONTROL LINE
THE TEE MUST NOW BE INSTALLED IN THE CORRECT UNLOADER LINE OF THE COMPRESSOR. THERE ARE THREE DIFFERENT CONFIGURATIONS DEPENDING ON THE TYPE OF COMPRESSOR. REFER TO ALL CONFIGURATIONS LISTED (A-
C), AND FOLLOW THE RELEVANT INSTRUCTIONS.
SCREW THE MALE END OF THE DRAIN VALVE INTO THE FEMALE INLET OF THE PETCOCK/TEE ASSEMBLY. THE PORT ON THE SIDE OF THE DRAIN VALVE IS PROVIDED
TO ATTACH OPTIONAL TUBING OR PIPING. WHEN SCREWING IN THE DRAIN VALVE, TRY TO POSITION THIS OPENING AS SHOWN FOR EASIER ACCESSABILITY.
A: AN ELECTRIC MOTOR COMPRESSOR WITH A PRESSURE SWITCH
TYPICAL PRESSURE
SWITCH
PRESSURE SWITCH UNLOADER LINE WHERE
THE TEE WILL BE INSTALLED
ELECTRIC COMPRESSOR
CHECK VALVE
STEP 6A: LOCATE THE PRESSURE SWITCH ON THE COMPRESSOR. THE LINE FROM THE PRESSURE SWITCH TO THE FITTING ON THE TANK IS THE PRESSURE SWITCH UNLOADER LINE. A 1/2” SECTION OF TUBING MUST BE CUT FROM THE CENTER. DEPENDING ON THE MATERIAL TYPE, SPECIAL COPPER OR OTHER METAL TUBING CUTTERS MAY BE REQUIRED.
PRESSURE SWITCH UNLOADER LINE
PRESSURE SWITCH
AFTER REMOVING THE SECTION OF THE LINE, PUSH THE ENDS INTO EITHER END OF THE TEE AND PULL BOTH SIDES TO MAKE SURE IT IS SECURE. IT SHOULD LOOK LIKE BELOW. 1/2”
B: A GAS ENGINE COMPRESSOR WITH A CONRADER BULLWHIP THROTTLE CONTROL
BULLWHIP THROTTLE
CONTROL LINE TO THE ENGINE
PILOT DEVICE
SITE OF THE TEE INSTALLATION
GAS ENGINE COMPRESSOR
STEP 6B: LOCATE THE CONRADER BULLWHIP THROTTLE CONTROL. REMOVE THE BULLWHIP FROM THE SIDE OF THE PILOT DEVICE. INSTALL THE SPECIAL THROTTLE TEE IN THE PILOT PORT WHERE THE BULLWHIP WAS LOCATED. SCREW THE BULLWHIP INTO THE OTHER END OF THE TEE.
BULLWHIP THROTTLE CONTROL
PILOT VALVE
THE END RESULT WILL LOOK LIKE BELOW.
B: A GAS ENGINE OR ELECTRIC MOTOR COMPRESSOR WITH A PILOT VALVE INTAKE UNLOADER
GAS ENGINE COMPRESSOR
LINE TO INTAKE UNLOADER
PILOT DEVICE
LINE TO INTAKE UNLOADER
WHERE THE TEE IS INSTALLED
STEP 6B: LOCATE THE PILOT VALVE ON THE COMPRESSOR. THE LINE RUNNING FROM THE PILOT VALVE TO THE COMPRESSOR’S PUMP IS THE UNLOADER LINE. A 1/2”SECTION OF THIS TUBING MUST BE CUT FROM THE CENTER OF THE LINE. SPECIAL TUBING CUTTERS MAY BE REQUIRED DEPENDING ON THE MATERIAL OF THE UNLOADER LINE.
PILOT UNLOADER LINEPUMP UNLOADER
1/2”
AFTER REMOVING THE SECTION OF THE LINE, PUSH THE ENDS INTO EITHER SIDE OF THE TEE AND PULL BOTH ENDS TO MAKE SURE IT IS SECURE. THE END RESULT WILL LOOK LIKE BELOW.
C: A GAS ENGINE COMPRESSOR WITH AN AIR LINE THROTTLE CONTROL
GAS ENGINE COMPRESSOR
THROTTLE AIR LINE WHERE THE TEE
WILL BE INSTALLED
STEP 6C:LOCATE THE AIR LINE ATTACHED TO THE PORT OF THE PILOT DEVICE RUNNING TO THE THROTTLE CONTROL MOUNTED ON THE ENGINE. A 1/2” INCH SECTION MUST BE REMOVED FROM THE CENTER OF THIS LINE.
THROTTLE AIR LINE
PILOT DEVICE
AFTER REMOVING THE SECTION OF THE LINE, PUSH THE ENDS INTO EITHER SIDE OF THE TEE AND TUG TO MAKE SURE IT IS SECURE. THE END RESULT WILL LOOK LIKE BELOW.
MOUNTED TO TANK
STEP 7: DETERMINE THE LENGTH NEEDED TO CONNECT THE PORT IN THE INSTALLEDTEE TO THE DRAIN VALVE. CUT OFF THE EXCESS AND INSTALL THE LINE BY PUSHING THE ENDS INTO BOTH PORTS. PULL TO ASSURE A SNUG FIT. IT WILL LOOK LIKE BELOW.
THE APPROPRIATE LINE THE TEE IS INSTALLED IN FROM STEP 6.
1/4” TUBING WHICH RUNS FROM THE TEE TO THE DRAIN VALVE.
YOU ARE NOW DONE!