Upload
others
View
14
Download
1
Embed Size (px)
Citation preview
Appendix 7.2
Construction and Demolition
Materials Management Plan
(C&DMMP) for Central
Kowloon Route
Highways Department
Agreement No. CE 43/2010 (HY)
Central Kowloon Route –
Design and Construction
Updated Construction and Demolition
Material Management Plan (C&DMMP)
217722-REP-023-01
Issue 4 August 2012
Arup-Mott MacDonald Joint Venture
Level 5 Festival Walk
80 Tat Chee Avenue
Kowloon Tong
Kowloon
Hong Kong
www.arup.com
This report takes into account the particular instructions
and requirements of our client.
It is not intended for and should not be relied upon by
any third party and no responsibility is undertaken to any
third party.
ArupArupArupArup----Mott MacDonald Mott MacDonald Mott MacDonald Mott MacDonald
Joint VentureJoint VentureJoint VentureJoint Venture
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF
Contents
Page
1 Introduction 1
1.1 Background 1
1.2 Scope of Project Works 1
2 Purpose and Objective of this Construction & Demolition Material Management Plan (C&DMMP) 3
2.1 Purpose and Objective of the C&DMMP 3
2.2 Implementation Programme and Works Packaging 4
3 Development Constraints 5
3.1 Constraints 5
3.2 Alignment Constraint and Trunk Road Connections 5
3.3 Slip Road Connections 5
3.4 Existing Buildings 5
3.5 Existing Railway Lines 6
3.6 Adjacent Major Infrastructures 6
3.7 Kowloon City PTI 7
3.8 Ma Tau Kok Public Pier 7
3.9 HKCG Ma Tau Kok Gas Work Plant 7
3.10 Geological Constraint in Bored Tunnel Section 8
3.11 Traffic Impact 8
3.12 Environmental Issues 8
3.13 Demolition and Reprovisioning 8
4 Alignment Development 10
4.1 Alignment Review 10
4.2 Preferred Alignment and Construction Scheme 10
4.3 Construction Methodologies 11
5 Management of C&D Materials 13
5.1 Generation of C&D Materials 13
5.2 Demolition Materials from CKR 14
5.3 Excavated C&D Materials from CKR 14
5.4 Minimizing C&D Materials Generation in CKR 14
5.5 Maximizing Reuse of Inert C&D Material on Site 15
5.6 Maximizing Reuse of Inert C&D Material for Temporary Reclamation 16
5.7 Estimated Quantity of C&D Materials in CKR 17
5.8 Concurrent Projects 18
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF
5.9 Barging Points 19
6 Conclusion 19
6.1 The Key Concerns in CKR C&DMMP 19
7 Recommendation 21
Appendix A
An Overview of the CKR Alignment and Location Plan of Possible TSA
Appendix B
C&D Material Quantity Estimation for CKR
Appendix C
Tentative Construction Programme and Time Chainage Diagram
Appendix D
Correspondence
Appendix E
Response to Comments on CEDD/ PFC memo dated 15 May 2012
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 1
1 Introduction
1.1 Background
1.1.1 Central Kowloon Route (CKR) is a proposed dual 3-lane trunk road across central Kowloon linking the West Kowloon in the west and the proposed Kai Tak Development (KTD) in the east. It will connect the West Kowloon Highway at Yau Ma Tei Interchange with the road network at Kowloon Bay and the future Trunk Road T2 at KTD which will connect to the future Tseung Kwan O – Lam Tin Tunnel (TKO-LTT).
1.1.2 On 30 June 2011, Highways Department (HyD) of the Government of the Hong Kong Special Administrative Region appointed the Arup – Mott MacDonald Joint Venture (AMMJV) under Agreement No. CE43/2010(HY) to provide consultancy services in respect of Central Kowloon Route – Design and Construction (this hereafter called CKR project).
1.1.3 In I&PD consultancy, a C&DMMP was prepared and submitted by Mott Connell- Meinhardt – Hyder Joint Venture in Dec 2008.
1.1.4 After the design review of CKR under current consultancy, the land use, road layout and extent, and the construction programme have been revised from I&PD stage. The alignment has been revised and fine tuned in accordance with the review findings. The review will be completed in early 2012.
1.1.5 In Dec 2011, the Consultants proceed with the advancement of EIA study in order to provide necessary information for the subsequent public consultation in May 2012. The commencement of gazette process is scheduled in August 2012. According to the brief, the CKR construction contract commencement is scheduled in early 2015 while the CKR commissioning is scheduled in year 2020.
1.2 Scope of Project Works
1.2.1 Based on the latest design development, the Project comprises of the followings:-
(a) A dual 3-lane east-west trunk road about 4.7km long with about 3.9km in tunnel connecting West Kowloon with the proposed KTD;
(b) Connection with Yau Ma Tei Interchange of the West Kowloon Highway and associated road network in West Kowloon;
(c) Connection to future Trunk Road T2 and associated road network in Kowloon Bay and KTD;
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 2
(d) A landscaped deck at the west portal and the structure of landscaped decks above the depressed road at east end;
(e) Demolition and/or reprovisioning of Government and other facilities affected by CKR;
(f) Reprovisioning of the section of Gascoigne Road Flyover affected by CKR;
(g) Conservation of the Yau Ma Tei Police Station;
(h) Enhancement works at Yau Ma Tei and Ma Tau Kok;
(i) Tunnel ventilation system and air purification system, and associated ventilation buildings, adits and shafts;
(j) Administration buildings, tunnel management system and operator facilities for the management and operation of the tunnel;
(k) Traffic Control and Surveillance System (TCSS) for CKR, and associated interface with TCSS for other Route 6 projects and CBL, and control centres;
(l) Associated environmental, geotechnical, marine, landscape, utility, drainage, traffic engineering, fire services, electrical and mechanical works, and road works and modification works; and
(m) All other works associated with the construction or future operation of CKR.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 3
2 Purpose and Objective of this Construction & Demolition Material Management Plan (C&DMMP)
2.1 Purpose and Objective of the C&DMMP
2.1.1 This updated Construction & Demolition Materials Management Plan (C&DMMP) is prepared with reference to the guidelines and requirements given in Chapter 4 section 4.1.3 of Project Administravtion Handbook (PAH) – ‘Management of Construction and Demolition Materials including rock’ and HyD Technical circular No.7/2003. The main purposes of this update reports are to:
• draw up a Construction and Demolition Material Management Plan
(C&DMMP) at an early design stage to minimize C&D material
generation and encourage proper management of such material.
• vetting of the C&DMMP prior to upgrading of the project to
Category A in the Public Works Programme;
• provide the future contractor with information from the C&DMMP
in order to facilitate him in the preparation of the Waste
Management Plan (WMP) and to minimize C&D material
generation during construction.
• enable classification and estimation the quantities of C&D
materials generated and their time of generation and disposal
method;
• recommend ways to minimise the generation and to maximise the
benefical reuse of inert C&D materials;
• investigate the arrangement for the delivery of excavated C&D
materials and review possible barging point.
• enable the Vetting Committee to scrutinize and endorse the
C&DMMP and monitoring of its implementation;
• provide the information for management of C&D materials in the
EIA report for this “Designated Project” under the EIA Ordinance.
2.1.2 As required by the Chapter 4 section 4.1.3 of PAH, a C&DMMP at the feasibility study or preliminary design stage for each project which generates more than 50,000m
3 of C&D material including rock or that
requiring imported fill in excess of 50,000m3 shall be prepared. The
CKR project would fall within this category.
2.1.3 The objective of this C&DMMP is to present the estimation of C&D materials. Another objective is to ensure that options are considered in
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 4
the planning and design of the development in order to reduce the generation of C&D material and encourage the reuse of the C&D material generated. The C&DMMP also provides basis for the monitoring and management of the C&D material and imported material throughout the construction period of the Project. The main principle for the management and planning of C&D material includes:
• reduce the generation of C&D materials at source;
• maximise the reuse of C&D materials; and
• maximise the recycling of C&D materials.
2.1.4 This C&DMMP covers the sections of the CKR as shown in Figures CKR/F/01/0001 in Appendix A. This report covers only the CKR C&D materials which excluding the marine sediment, contaminated materials.
2.2 Implementation Programme and Works Packaging
2.2.1 According to the brief, the tentative commencement date for construction is 2015 and the commissioning date of CKR is 2020.
2.2.2 The works implemented by HyD will be divided into different package. Details of works packaging and possible entrustment works (if any) will be updated together later with key dates.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 5
3 Development Constraints
3.1 Constraints
3.1.1 The CKR cut-and-cover and bored tunnelling will involve excavation of soil (fill) materials, therefore, generation of considerable amount of excavated soils and filling materials will result. Inert excavated materials will be properly segregated and either be reused on site, delivered to quarry and reused for concrete aggregate, or disposed of at designated public fill areas in accordance with the guidance from the Fill Management Division (FMD) of the Civil Engineering and Development Department (CEDD).
3.1.2 This section provides an insight into the development constraints of the proposed development areas and infrastructure leading to the choice of preferred option.
3.2 Alignment Constraint and Trunk Road Connections
3.2.1 The derivation of CKR Trunk Road alignments is constrained by the mainline connections at either end to existing Yau Ma Tei West Kowloon Area and the committed road alignments at Kai Tak Area (i.e. T2). The proposed CKR alignment will fall within centre of the Kowloon peninsula, where it has been densely developed with high-rise buildings and public facilities.
3.3 Slip Road Connections
3.3.1 The review of the preliminary design identified an issue with the alignment of Hoi Wang Road in that the vertical alignment at the junction with the Lai Cheung Road did not match the existing road alignment. A modification of the profile of Hoi Wang Road was therefore necessitated. This in turn affected the alignment of the CKR depressed road section under Hoi Wang Road.
3.4 Existing Buildings
3.4.1 Due to the potential impacts on private sectors, the alignment aims at minimising the adverse effect in terms of physical impact during construction and future redevelopment potential impact. In order to achieve that, the adopted alignment will affect the least number of private land lots, buildings and units.
3.4.2 Western Section of CKR is located at the residential area of Yau Ma Tei. At the section between Ferry Street and Nathan Road, the existing buildings that may be affected by the project are the buildings of Yau Ma Tei Police Station, CLP substation, Tak Cheong Building and Tak On Building. At the section between Ferry Street and Yau Ma Tei Interchange, the existing structures may be affected by CKR are the
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 6
MTR tunnels (AEL, TCL, XRL and KSL), XRL ventilation builidng, the new YMT Police Station Building and the new residental site at Hoi Wang Road. It is important to ensure sufficient protection measures to protect these buildings against the possible tilting or settlement. The use of diaphragm wall construction is anticipated to provide a water sealed wall with minimum water pumping with the high stiffness wall to control settlement.
3.4.3 CKR bored tunnel will run underneath the existing YMT multi-storey car park building. As the tunnel tubes are too close to the foundation of the building, the stability of the building will be affected and need to be removed. Before demolition of the building, it is required to decant the Yau Ma Tei Public Library and the other government offices in the building.
3.4.4 In the Central portion, to avoid disturbance and significant building demolishment, the CKR Trunk road at the middle portion must be underground by bored tunnel method. The trunk road must be deep enough to avoid encoarching into existing building foundation.
3.5 Existing Railway Lines
3.5.1 The proposed CKR alignment will be constructed underneath a number of existing or commited railway line which include MTR Tsuen Wan Line, future Kwun Tong Line Extension, East Rail Line, future Shatin Central lane, future Express Rail Line.
3.5.2 5.5% gradient of CKR between the Yau Ma Tei Interchange and Nathan Road is necessary in order to provide sufficient clearance under the MTRC Kwun Tong Line Extension (KTE) and to connect with the existing elevated roads at the West Kowloon interchange.
3.6 Adjacent Major Infrastructures
3.6.1 The alignment of CKR will run underneath the existing Ferry Street Flyover. A section of the flyover (Deck B and C) is therefore required to be underpinned. In detailed design stage, it is required to establish a safe underpinning scheme for the flyover.
3.6.2 In Eastern Portion, The existing submarine gas mains in Kowloon Bay conflicts with the Kowloon Bay section alignment of CKR. The pipeline diversion works will be completed in the 4th quarter of 2013. A disused aviation fuel pipe is known to run north-south between the dolphin in Kowloon Bay and the former Kai Tak airport runway. The disused pipe decommissioning works, undertaken by CEDD, will be completed in the 4th quarter of 2012.
3.6.3 In association with the proposed KTD project, the Kai Tak Nullah Modification Works and construction of the Multi-Purpose Stadium Complex (MPSC) are scheduled. Adequate liaison between CKR and KTD will be needed to ensure smooth interfacing of the projects, in particular where the MPSC is concerned as the proposed alignment of the CKR depressed road lies immediately south of the MPSC building footprint.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 7
3.7 Kowloon City PTI
3.7.1 The existing Kowloon City PTI requires re-provisioning for the duration of CKR east end construction activities to provide working and construction space. The temporary PTI will remain in the same vicinity as the existing PTI shifting slightly towards the southern San Ma Tau Street, preserving all existing routes and parking stands. The re-provisioning of the PTI is proposed to be carried out over the course of 4 stages accommodating the advanced construction works including the diaphragm wall installation and demolition of the Ma Tau Kok Public Pier. Sufficient planning and foresight is crucial to ensure that the re-provisioning and advanced works do not inhibit the operation of the Kowloon City PTI which will remain in operation throughout.
3.8 Ma Tau Kok Public Pier
3.8.1 The existing Ma Tau Kok Public Pier requires demolishing to facilitate CKR construction works. Subject to the layout of the approved Kowloon City re-provisioned PTI and the future contractor’s proposed method and sequence of construction works, decking over of the cut and cover tunnel at the east end may be needed to preserve pedestrian means of access to the Kowloon City Ferry Pier.
3.9 HKCG Ma Tau Kok Gas Work Plant
3.9.1 The cut and cover tunnel lies nearby the Hong Kong and China Gas Company Ltd. (HKCG) owned Ma Tau Kok Gas Works Plant which is classified as a potentially hazardous installation for which a 300m consultation boundary is applied. In association with the Gas Plant there are several existing pipelines running from the plant to an existing pigging station and storage tank located between the residential development Grand Waterfront and the Kowloon Bay seawall. The pigging station is used to transfer liquid gas naphtha which is delivered by barge to the Ma Tau Kok Gas Works Plant. Although the alignment of this existing pipeline does not conflict with CKR works, extreme care shall be taken to ensure sufficient excavation clearance is provided and that ground movements are monitored closely.
3.9.2 An existing 400mm HKCG owned pipeline currently runs between the Kapok Industrial building and the Kowloon City PTI. Although the pipeline does not conflict with proposed CKR excavation works, extremely care shall be taken to ensure that ground movement is mitigated and monitored closely.
3.9.3 HKCG owned pigging station and storage facility in Ma Tau Kok currently receives shipments of naphtha gas via barge delivery. To maintain the shipment off-loading operation, close proximity by the temporary reclamation are proposed in 2 phases under CKR. In addition, maintenance dredging shall be considered to ensure that sufficient draft is provided for the delivery vessel to navigate an alternative route around the proposed Stage 2 temporary reclamation.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 8
Communication between HKCG and CKR will be critical in the lead up to the Stage 2 temporary reclamation; care should be taken to ensure that the delivery vessel staff/pilots are well briefed on the revised operational arrangements.
3.10 Geological Constraint in Bored Tunnel Section
3.10.1 From geological consideration, the rockhead level along the adopted alignment is generally high. In specific, the main trunk road can pass through strong Grade II rock with sufficient bedrock cover to the bored tunnel aim at gaining sufficient bedrock cover to tunnel can increase the excavation stability and reduce the geotechnical risk by drill and blast method. However, local weak seam and rockhead depression may still exist and impose fine adjustment of tunnel vertical profile.
3.11 Traffic Impact
3.11.1 The works of CKR will affect some major roads including Gascoigne Road, Ferry Street, Kansu Street, Battery Street, Reclamation Street, Canton Road, Ho Man Tin and To Kwa Wan Area. All those roads shall be maintained operation during the construction stage.
3.11.2 In the design stage, it is necessary to establish a traffic deck system to temporary support the existing roads at the period after diaphragm wall construction in cut and cover section. The system shall also be used to temporarily support/protect the existing utilities.
3.11.3 The petrol stations along the south side of Kai Fuk Road will remain operation during the construction stage. The designed works should not encroach into the area. To ensure the petrol stations are accessible during construction stage, the existing access should be maintained unless with an alternative route as agreed by the operators of the petrol stations and other government departments.
3.12 Environmental Issues
3.12.1 Landscaped deck will be constructed at the tunnel portals so that the vehicular entrance and exit will be moved further away from the residential buildings. This arrangement will also provide additional greening to the area.
3.12.2 The ventilation buildings will be relocated from the previously proposed location near Ferry Street to the Yau Ma Tei Interchange of the West Kowloon Highway. This new location will maximise the separation and better dispersion of tunnel exhaust so as to reduce air quality impact on existing dwellings close to the portal.
3.13 Demolition and Reprovisioning
3.13.1 During the ground preparatory works, demolition and re-provisioning of existing structures such as lavatory, public library, refuse collection points, box culverts, multi-storey carpark building, public pier and
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 9
methadone clinic is needed. Tourist-areas such as the Jade Market will need to be re-located. The AA Club area and Ma Tau Kok Public Pier will also be entirely demolished and required disposal.
3.13.2 The cut and cover tunnel of CKR will be constructed underneath the building of YMT Police Station. The police station needs to be decanted for the CKR construction works. A new police station building will be built beside Yau Cheung Road. After the tunnelling works of CKR, the existing police station will be revitalize for other purpose.
3.13.3 The existing Special Clinic Extension Building (SCEB) at Battery Street is also required to be demolished for the construction of CKR. A new building will be constructed in Queen Elizabeth Hospital to house the special clinic.
3.13.4 The existing Methadone Clinic at the ground floor of SCEB will be relocated to a new clinic building within the area of the adjacent Jockey Club Polyclinic Building. The works is included in the scope of CKR.
3.13.5 The existing single storey buildings for Jade Markets at Battery Street are located on the alignment of CKR. The buildings also need to be removed for the constuction of cut and cover tunnel. A temporary building will be built on the existing Kausu Street Rest Garden on the south side of multi-storey car park building to house the affected hawkers of the Jade Markets. After completion of the cut and cover tunnel, the temporary building will be removed and the hawkers will be decanted to the new buildings located at the original Jade Market position.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 10
4 Alignment Development
4.1 Alignment Review
4.1.1 During the course of design development in I&PD Stage and review phase of Detailed Design Stage, various alignments and construction schemes have been considered and reviewed together with the connectivity and constraints in Section 3. The latest preferred scheme and corresponding alignment are discussed and presented in this section. It should be noted that the preferred scheme adopted may be subject to fine tuning change by the Detailed Design Consultants.
4.2 Preferred Alignment and Construction Scheme
4.2.1 In the preferred alignment, the west end of CKR will connect to the existing Yau Ma Tei Interchange of the West Kowloon Highway. It will be a side-by-side tunnel running along Kansu Street (with the portal at Hoi Wang Road), entering into a twin-bored tunnel underneath Nathan Road, and passes below MTR KTE Line. The bored tunnel then runs under Ho Man Tin, before passing through a relatively short submarine tunnel under the harbour at Ma Tau Kok and emerging at KTD.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 11
4.3 Construction Methodologies
4.3.1 In view of the topography and geology of constraints on the CKR, the anticipated construction methods are summarized in the table below:-
Chainage Portion Assumed Construction Scheme
West Kowloon
Interchange -
1050
Depressed Road and
Connecting Roads to West
Kowloon Interchange
The connecting road and depressed approach road will
comprise of at grade roads, viaduct structures and
depress link road by open cut method which link to the
West Portal.
1050 – 1440 West Cut & Cover Tunnel The trunk road will be formed inside reinforced concrete
cut and cover tunnel boxes. The concrete box will be
constructed by top-down excavation method with
diaphragm perimeter walls.
1440 – 4230 Mined Tunnel The mined tunnel section will be mainly excavated by
Drill & Blast. Temporary rock support measures will be
installed before the completion of permanent horseshoe
shape concrete lining and trunk road slab.
4230 – 4330 East Cut & Cover Tunnel The road will be formed inside reinforced concrete cut
and cover tunnel boxes. The concrete box will be
constructed by bottom up excavation method with
diaphragm perimeter walls.
4330 – 4700
East Cut & Cover Tunnel
(underwater)
Temporary reclamation by two phases will be carried out
before the construction of the underwater cut and cover
section. The underwater tunnel box structure is to be cast
insitu as per these two stages and once completed would
be joined together by breaking through the interfacing
diaphragm walls.
4700-Kai Tak
Interchange &
future T2
Depressed Road and
Connecting Roads to Kai Tak
Interchange and future T2
Trunk road
The connecting road and depressed approach road will
comprise of at grade roads, viaduct structures and
depress link road by open cut method which link to the
East Portal.
4.3.2 Drill and Blast Tunnel Method
4.3.2.1 The mined tunnel will be constructed by the Drill and Blast (D&B) method. This is commonly used for excavation of hard rock tunnels which is small in size and short in length. It is an economical way and less restricted by site condition for equipment set-up, where tunnelling by TBM is not possible given the large diameters involved and the extreme wear and tear expected due to the hard rock strata. However,
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 12
non-blasting mechanical excavation will be adopted in difficult geological condition or vibration sensitive area.
4.3.3 Underwater Tunnel
4.3.3.1 Different construction methodologies for the underwater tunnel have been discussed in I&PD stage prior to the recommendation of the cut and cover construction method with temporary reclamation. Those construction methodologies include the use of Bored Tunnel (or mined tunnel), Tunnel Boring Machine (TBM), Immersed Tube Tunnel (IMT) and Full Flyover. Based on the preliminary review on the feasibility of using these alternatives, it is considered that the use of cut and cover construction with temporary reclamation is still the most appropriate method for the construction of the underwater tunnel in term of constructability, engineering feasibility and safety concerns.
4.3.4 Cut-and-cover Tunnel
4.3.4.1 Cut-and-cover is a common method of construction for relatively shallow tunnels where a trench is excavated and roofed over. In order to reduce impacts on the environment and existing traffic, diaphragm wall with top-down construction will be adopted for cut-and-cover tunnels. A shallow excavation is made to allow the tunnel roof to be constructed. Once the tunnel roof is completed, the ground surface is reinstated. This allows early reinstatement of the roads, the disturbance to public will be therefore minimised. Further excavation and construction of lower part of the tunnel will be carried out under the completed tunnel roof away from direct impact on the public.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 13
5 Management of C&D Materials
5.1 Generation of C&D Materials
5.1.1 C&D materials (divided into two types - inert and non-inert) would be generated from the demolition of the existing building, bridges, excavation works in the cut and cover tunnel construction, mined tunnel construction, shaft construction and removal of temporary reclamation within underwater tunnel.
5.1.2 C&D materials do NOT include the dredged marine sediment, wet soil with moisture content over 25% and contaminated soil. In particular, the seabed near Kai Tak would be temporarily backfilled during underwater tunnel construction. Those backfill will be excavated or dredged after the cut & cover box formation.
5.1.3 The inert material comprises of rock, soils, debris, rubble, bitumen materials and broken concrete that can be used as fill materials for reclamation and earth filling projects. The C&D material generated would be considered to be reused in the subsequent stage of temporary reclamation, cut & cover tunnel backfilling, site formation works for buildings if appropriate.
5.1.4 The non-inert portion of construction waste comprises timber, metal, glass, steel, packaging waste, organic materials and plastic. Some non-inert construction waste can be reused or recycled prior to disposal of at landfill. Recyclables include mainly of metals, paper/ cardboard packaging and plastic (plastic bottles/ containers, plastic sheets/ foam from packaging materials). Non-recyclable materials are treated as general refuse requiring landfilling.
5.1.5 A breakdown of C&D materials by type and volume expected from construction of the CKR and the schedule of quantities generated and required are presented in Appendix B.
5.1.6 A summary of breakdown of C&D material generation and demand is presented in Table B1. The summaries of quantities of C&D material generated and fill material required at each portion are shown in Table B2 and Table B3 respectively.
5.1.7 Soil type excavated materials will mainly arise from the excavation works of the east and west cut and cover tunnels. Those will take place upon completion of the diaphragm walls at the Ma Tau Kok East Portal (including underwater tunnel) and Yau Ma Tei West Portal.
5.1.8 Rock type excavated material will be created by central bored tunnel excavation by drill and blast. The retrieval quantity of rocks material from the bored tunnel has been estimated and splitted into (a) YMT west portal (b) HMT central shaft and (c) MTK east portal.
5.1.9 The schedule of quantities of inert C&D material at YMT west portal, HMT central shaft and MTK east portal generated and required are presented in Table B4, Table B5 and Table B6 respectively.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 14
5.1.10 The schedules of overall quantities of C&D materials generation and demand are also shown in Table B7 and Table B8. Besides, the overall schedules of bulked quantities of C&D materials generation is shown in Table B9. The schedule of quantities of fill material required in CKR is presented in Table B10.
5.1.11 Tentative construction programme & Time-Chainage diagram are presented in Appendix C.
5.2 Demolition Materials from CKR
5.2.1 Based on the latest design of the Project, demolition material will be generated from the removal of existing flyover, the demolition of buildings in Yau Ma Tei Area and Ma Tau Wei Area, site clearance and modification of West Kowloon Interchange.
5.2.2 C&D material generated from the demolition works will be sorted on-site into public fill (which should be re-used on-site as far as possible) and C&D waste (which will require disposal to landfill). C&D material arising from the demolition of highway structures will comprise primarily concrete. It is assumed that approximately 85% of the C&D material will be public fill and the rest will be C&D waste.
5.3 Excavated C&D Materials from CKR
5.3.1 In view that the volume of grade I/II rock generation from CKR would be quite substantial, it is proposed to manage the possible recycling of the surplus rock by local quarries (e.g. Lam Tei Quarry). The detail arrangement to be discussed with Mines/Quarry division. Correspondence from Mines Division of CEDD regarding proposed disposal of surplus rock is presented in Appendix D. Continue liaison with Mines Division of CEDD and exploration of other alternative disposal sites for surplus rock will be made. It is anticipated that part of the rock material can be exported to Mainland China for reuse purpose. In the CKR contract, flexibility in the contractual arrangement for transporting rock to alternative disposal sites would be allowed.
5.3.2 It is proposed that rock crusher plants should be adopted in CKR central tunnel. It aims at controling the mucking out, transportation (potential vertical conveyor) and standard requirements in public fill site (250mm down) and quarry and the re-use of selected public fill on site. The maximum size of imported rock should be agreed between the CKR contractor and the quarry contractor.
5.4 Minimizing C&D Materials Generation in CKR
5.4.1 In order to minimize the generation of CKR C&D materials, the future Contractor should plan the construction methods to minimize the generation of C&D materials and to incorporate a Waste Management System into the WMP for effective management and control of C&D materials to avoid, reduce, minimize the generation of C&D materials during construction.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 15
5.4.2 These include but not limited to the following key consideration:- (a) Good site management to minimize over ordering; (b) Better programming of works to minimise stockpiling and maximise reuse opportunity; (c) Use of reusable steel formwork (e.g steel shutter for tunnel lining); (d) On site material sorting or in designated sorting area and separate C&D materials into public fill and C&D waste and sorting of C&D materials by category to facilitate reuse / recycling; (e) On site rock crushing to control the size of excavated rock from tunnel; (f) Use of excavated soft materials for landscaping works as far as possible; (g) Use of pre-cast construction method for elevated structures to minimise the amount of C&D materials generated on site (h) Reuse or recycle construction/ demolition waste with recyclable values such as reinforcement bars, steel mesh etc. These wastes should either be reused on site or collected by outside licensed waste recycling agents.
5.4.3 Under the contract, the contractor will also be required to minimize the generation of C&D materials and reuse it on site by complying with the following guidelines and documents:
•••• Works Bureau Technical Circular No 06/2002 & 6/2002A, Enhanced Specification for Site Cleanliness and Tidiness, Works Bureau;
•••• Works Bureau Technical Circular No 22/2003A, Additional Measures to Improve Site Cleanliness and Control Mosquito Breeding on Construction Sites, Works Bureau;
•••• Chapter 4 Section 4.1.3 of PAH, Construction and Demolition Materials, Project Adminstrative Handbook for Civil Engineering Works
•••• Works Bureau Technical Circular No 6/2010, Trip Ticket System for Disposal of Construction & Demolition Materials, Works Bureau;
•••• Works Bureau Technical Circular No 19/2005, Environment Management on Construction Sites, Works Bureau;
•••• Practice Note for Authorised Persons and Registered Structural Engineers
5.5 Maximizing Reuse of Inert C&D Material on Site
5.5.1 The C&D material generated from the excavation works will be re-
used as far as practicable.
5.5.2 As described in Section 5.2, demolition materials will be generated
from the removal of infrastructures. C&D materials generated from
the demolition will be sorted into public fill and C&D waste. On site
sorting will be implemented by employment of appropriate sequential
demolition to facilitate recovering all reusable and recycle material.
5.5.3 As described in Section 5.3.2, rock crusher plants should be
established. The maximum size of imported rock should be agreed
between the CKR contractor and the quarry contractor.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 16
5.6 Maximizing Reuse of Inert C&D Material for Temporary Reclamation
5.6.1 The use of inert C&D material has been further explored and
maximized as far as practicable. The use of selected public fill
material (below grade 200) for the temporary reclamation and
backfilling seabed has been considered.
5.6.2 The programme constraint of the overall development and in
particular the required handover dates for the CKR is an important
factor in deciding the reclamation method.
5.6.3 Temporaray reclamation works could use selected public fill material
with no oversize (below grade 200), otherwise it would cause
obstructions for the subsequent diaphragm wall construction. Apart
from the selected public fill generated from site, selected public fill
can also be obtained from fill banks at Tseung Kwan O and Tuen
Mun.
5.6.4 For the use of public fill material of Grade 200, further liaision with
CEDD/ Fill Management Division on the details of the proposed
arrangement is required.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 17
5.7 Estimated Quantity of C&D Materials in CKR
5.7.1 The total volume of C&D material generated from both demolition work and excavation works are summarised in Table 5.1 below:-
Table 5.1 – Summary of C&D Material Excavated & Generated (million cubic metre Mm3)
Grade II or
above Rock
(Granite)
Grade III or
below Rock
(Granite)
Inert Soft
C&D
Materials
Broken
Concrete
Reclaimed
Asphalt
Pavement
(RAP)
Bentonite
Slurry
C&D
Waste
Volume
(Mm3)
West YMT
Portion
0 0.135 0.716 0.084 0.014 0.050 0.012 1.011
Central HMT
Tunnel
0.880 0.077 0.019 0 0 0.002 0 0.978
East MTK
Portion
0 0.019 1.327 0.007 0.012 0.102 0.002 1.469
Total Excavated
Volume
0.880 0.231 2.062 0.091 0.026 0.154 0.014 3.458
Adopted Bulk
Factors
x 1.8 x 1.3 x 1.3 x 1.3 x 1.3 x 1.3 x 1.3 -
Total Generated
(Bulk) Volume
1.584 0.300 2.680 0.119 0.033 0.201 0.017 4.934
5.7.2 Public fill is required from either CKR project or from Tsueng Kwan O and /or Tuen Mun Fill Bank which will depend on the availability of temporary stockpile area (TSA) and the programme or interacting activities. For the temporary reclamation works in underwater tunnel, selected public fill is necessary for the cut and cover box construction and reclamation filling.
5.7.3 Wet public fill from diaphragm walls, tunnel construction and temporary reclamation will temporarily stockpile on TSA Those will then deliver to the fill bank when moisture content less than 25%. Althernatively, wet public fill will be mixed with cement before tranporting to the fill bank.
5.7.4 Reclaimed asphalt pavement will not be mixed with other C&D materials when delivered to public fill reception facilities.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 18
5.7.5 The amount of selected public fill materials required in the projects is given in Table 5.2.
Table 5.2 – Summary of Fill Material Required (million cubic metre Mm3)
Material East MTK Portion
Central
HMT Tunnel
West YMT Portion
Total
Selected Public Fill 0.752 0 0.207 0.959
5.7.6 Based on the current design development, the availibility for TSA is very limited. However, the possible land allocation of TSA for GLA-TK389 and Housing Authority Mock Up Centre are under study and a location plan is attached in Appendix A. Other possible TSA will be explored. In case of no TSA is available, the inert and non-inert C&D material will be disposed directly to public fill reception facilities and landfills respectively. The schedule of C&D material generated is given in table 5.3
Table 5.3 – Schedule of C&D Material Generated (in bulk volume) (half year) Grade II or
above (Granite)
Grade III or below (Granite)
Inert soft C&D
material
Broken Concrete
RAP Bentonite Slurry
C&D Waste
Jan - Jun 0 0.117 0 0 0 0 0.007 2015
Jul - Dec 0.010 0.071 0.460 0.013 0.008 0.043 0.007
Jan - Jun 0.089 0.043 0.114 0.011 0.003 0.006 0 2016
Jul - Dec 0.273 0.040 0.619 0.043 0.008 0.055 0.001
Jan - Jun 0.416 0.026 0.359 0.041 0.008 0.020 0.001 2017
Jul - Dec 0.416 0.002 0.278 0.010 0.003 0.013 0.001
Jan - Jun 0.294 0.001 0.147 0 0.001 0.010 0 2018
Jul - Dec 0.086 0 0.405 0 0.001 0.037 0
Jan - Jun 0 0 0.192 0.001 0.001 0.016 0 2019
Jul - Dec 0 0 0.106 0 0 0.001 0
Jan - Jun 0 0 0 0 0 0 0 2020 Jul - Dec 0 0 0 0 0 0 0
Sub -Total 1.584 0.300 2.680 0.119 0.033 0.201 0.017 Total 4.934
5.8 Concurrent Projects
5.8.1 A number of concurrent projects is identified which will potentially have major public fill demand during the CKR construction period (i.e. 2015 to 2020). Those potential projects with major fill demands include (a) Third Runway of Hong Kong International Airport; (b) Shatin Central Link Cross Harbour Section; and (c) Other potential CEDD reclamation project in study stage.
5.8.2 One of the potential major projects is the New Third Runway of Airport Authority. Based on item 5.68 of HKIA Master Plan 2030
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 19
Technical Report, the estimated required quantity of rockfill and rock armour will be 15 million cubic metres. The expected time frame should be overlapped with CKR construction period based on the latest information. Airport Authority Hong Kong will be consulted to seek the possibility to absorb the CKR fill materials.
5.9 Barging Points
5.9.1 It is recommended that C&D material should be transported off-site by barge wherever possible to reduce impacts from road transport.
5.9.2 There are four numbers of existing or planned temporary barging points in the Kowloon peninsula for the MTR projects. They are (a) Nam Chong XRL Temporary Barging Point, (b) West Kowloon XRL Temporary Barging Point, (c) Hung Hom Finger Pier KTE Temporary Barging Point and (d) Kai Tai SCL Barging Point.
5.9.3 However, based on the latest information from Planning Department, the existing Nam Chong XRL barging point at Cheung Sha Wan Wholesale Food Market cannot be allocated to CKR project as the site will be used for other purposes. Similar situation applies to the rest of the temporary barging points listed above.
5.9.4 There is the other potential barging point (being used by XRL project) at Kwai Chung underneath Cheung Tsing Bridge. DLO/TW&KT has allocated the site until August 2015 to RDO/HyD. Close liaison with DLO/TW&KT will be needed for the possibility of taking over the site for CKR. The correspondence from DLO/TW&KT is presented in Appendix D. Continue liaison with DLO and other relevant offices on any possible barging points will be needed.
6 Conclusion
6.1 The Key Concerns in CKR C&DMMP
6.1.1 To maximise the reuse of inert C&D materials, materials generated from tunnel excavation shall be sorted and temporarily stockpiled if a Temporary Stockpile Area is available.
6.1.2 To minimise the generation of C&D material, in particular C&D waste, the requirement for drawing up a Waste Management Plan for the implementation of the waste management and reduction measures will be incorporated in all works contracts for the project.
6.1.3 The estimated quantities of various types of C&D materials produced and the fill material required in the reclamation and tunnel backfilling works, their respective volume are summarized in Tables 6.1 and 6.2 below:
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 20
Table 6.1 – Summary of C&D Materials and Waste Generated (million cubic metre Mm3)
Material Grade II or above Rock
(Granite)
Grade III or below Rock
(Granite)
Inert Soft C&D
Material
Broken Concrete
Reclaimed Asphalt Pavement (RAP)
Bentonite Slurry
C&D Waste
West YMT Portion
0 0.135 (0.176)
0.716 (0.930)
0.084 (0.109)
0.014 (0.018)
0.050 (0.065)
0.012 (0.015)
Central HMT Tunnel
0.880 (1.584)
0.077 (0.100)
0.019 (0.024)
0 0 0.002 (0.003)
0
East MTK Portion
0 0.019 (0.025)
1.327 (1.726)
0.007 (0.010)
0.012 (0.015)
0.102 (0.133)
0.002 (0.002)
Total Quantity Generated
0.880 (1.584)
0.231 (0.300)
2.062 (2.680)
0.091 (0.119)
0.026 (0.033)
0.154 (0.201)
0.014 (0.017)
Quantity to be re-used on site
0 0 0.959 (1.247)
0 0 0 N.A.
Notes (i) : For those figures in brackets, they are bulk volume. The bulk factors of soft material and rock are 1.3 and 1.8 respectively.
(ii) : Continue liaison with CEDD/ Mines Division and exploration on other other alternative projects such as export to Mainland China and other construction projects in Hong Kong are required
Table 6.2 – Summary of Fill Material Requirement (million cubic metre Mm3)
Material East MTK Portion
Central HMT Tunnel
West YMT Portion
Total
Selected Public Fill 0.752
(0.978)
0 0.207
(0.269)
0.959
(1.247)
Total Volume Required (in-situ)
Total Volume Required (bulk)
0.959
1.247
Notes (i): For those figures in brackets, they are bulk volume. The bulk factors of soft material and rock are 1.3 and 1.8 respectively.
Highways Department Agreement No. CE 43/2010 (HY) Central Kowloon Route - Design and Construction
Updated Construction and Demolition Material Management Plan
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 21
(ii): Tentative sources of selected imported public fill is proposed to be from Fill Banks and/ or other alternative sources, liaison with CEDD/ Fill Management Division on the details of the proposed arrangement is required
7 Recommendation
7.1.1 To identify the management of excavated rock material to CEDD rock quarry site and Mainland China. CEDD/Mines division supports the proposal of importing good quality rock generated from CKR project to their quarries for beneficial reuse of the surplus rock. Continue liaison with CEDD/ Mines Division and exploration of other alternative disposal sites such as export to Mainland China and other construction projects in Hong Kong are required.
7.1.2 To explore the feasibility of using the inert C&D materials in products with recycled aggregates such as concrete or paving blocks in the project.
7.1.3 To take over potential temporary barging point for CKR project, Continue liasion with DLO/TW&KT is required for the possible taking over for barging a barging point at Kwai Chung underneath Cheung Tsing Bridge. Continue liaison with DLO and other relevant offices on any possible barging points will be needed.
7.1.4 Continue exploration of possible TSA is needed so as to re-use the public fill on site as far as possible.
7.1.5 Continue to liaise with potential concurrent project is needed so as to re-use in other construction projects in Hong Kong.
7.1.6 This C&DMMP shall be regularly reviewed and updated during the detailed design as well as construction stage. The construction works on site should also be closely monitored.
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 22
Appendix A
An Overview of the CKR Alignment and Location Plan of Possible TSA
¥›
¥›
¥›
¥›¥x¡]⁄U…
¥›
fið¯
Ø¿
¥›
¥›¥x¡]⁄U…hƒ
¥›¥›¥x¡]⁄U…hƒ
‹Ý
¥›
Podium
Podium
Podiu
m
RCP
Podium (Car Park under)
PP
P
P
P
Podium
TS
Podiu
m
Podium (Multi-storey Car Park under)TS
Podium (Multi-storey Car Park under)
Podium
Stand
Podiu
m
¶fi§Q…
›» · ä ⁄‰ ›»·ä¤‹
‚ô …w•|
“À° ˇ
†̃ ⁄ '—«˛'e›†˜⁄
†̃ ⁄
†̃ ⁄
†̃ ¥
'—
«˛'e›
⁄嘡]¢Ñ
⁄å¶ †̃ ⁄¡]¢Ò
⁄åÙ¡]¢—
⁄唡]¢ˇ
ƒò
¥œµ
ó
ƒó⁄套‹
⁄å•
¡]¢Ú
›{–K
⁄å•
¡]¢Ù
§g¶
–d
¥
«Ø¥
„¯
¥
´§¥ƒó⁄套
Auxiliary Medical Service Headquarters
Ellery
Terra
ce
The Open University
of Hong Kong
Hong Kong Football
AssociationBloc
k 1Martha B
oss
Community
Centre L
uthera
n Chu
rch
-Hon
g Ko
ng S
ynod
Block 1
Housing AuthorityHeadquarters Building
Block 3
Block 2
Housin
g
Authority
Headquarters
Block 4
Man Lan House
(Block C)
Block 3
Man Hor House
(Block D)
Man Pan House
(Block B)
Man Fuk House
(Block A)
Fat K
wong Street
Sports
Centre
Ho Man TinGovernment Offices
Man Shui House
(Block L)
Carmel Secondary School
Man Oi House
(Block K)
Carmel On The Hill
Hong
Man
House
Kin Man House
Kar
Man
House
Lai Man House
Ho Man TinSports Centre
38
55
3089
80
83
93
33
101
18
88
7
9
“Y„
„C…
‚t⁄‰•|‰†
˜x†
›{–K§ł ⁄Ñ¥D–—»
„C…
ƒó⁄套
ƒó⁄套ƒŁ›
„C…
›»·ä'e›…—•˙…ÒÀÀ
˜x† ¤‹†
˜x†ƒó⁄å¥
¡]ƒa⁄U°
Cascades
Playground
Sheng Kung HuiTsoi Kung Po
Secondary School
Bas
ketball C
ourt
ESS
Carmel VillageStreet Garden
Playground
Ling To CatholicPrimary School
Ho Man Tin Ambulance Depot
RCP
Ho Man Tin West Fresh Water Service Reservoir
Playground
Housing AuthorityMock-up Centre
ESS RCP
Football FieldBasketballCourt
BasketballCourt Ho Man Tin Park
(Car Park under)
CUL
CUL
CUL
F
31.430.7
30.8
35.1
46.3
35.2
20.1
26.8 35.1
38.757.8
27.0
35.731.9
39.136.8
34.2
38.4
35.8
38.5
38.5
38.5
38.4
44.5
38.5
44.9
48.0
43.1
47.0
42.0
43.1
42.5
42.4
46.7
51.6
43.0
68.1
68.3
68.2
68.359.7
59.8
68.2 60.0
60.8
68.2
68.3
59.9
68.343.6 68.2
61.5
62.368.3
62.8
62.5
62.8
36.663.8
65.165.1
48.3
68.168.2
68.566.3
66.6
68.2
68.3
68.2
68.1
46.8
50.3
68.368.3
68.536.5
68.2
68.4
68.268.3
68.3
53.2
68.2
51.9
46.8
36.4
61.1
53.9 65.554.2
53.5
L
L
L
L
H
LL L
L
H
H LL
H
L L
L
H
L
L L
H
LH L
L
H
LL
LLH
L
LH
LL
HH
L
LL
L
L
L L
HL
L
H
L
L LHL
H
L
LH
HL L
L
L
L
L
L H
LL
L
L
H
L
L
L
L
H
LL
L
L
FAT
KW
ON
G STREET
SHE
UN
G F
OO STREET
CH
UN
GH
AU
ST
REET
GO
OD
SH
EP
HE
RD
ST
RE
ET
CAR
MEL
VIL
LAGE STREET
HAUMAN
STREET
–‘·
'¾§
““•
›{
–K
„D
„D
„D
„D
„D
Ra
mp
EW
EW
Road
Road
Road
Road
Road
Road
FP
Oi Man Shopping Centre
•R¥`
¥›
¡]⁄U…h°
¥›
¡]⁄U…h°
¥›¥x¡]⁄U…
P
Podium
(Car P
ark
under)
�»¿¾
HO MAN TIN ESTATE
P
Podium
(Car Pa
rk unde
r)
Podium
(Car Pa
rk unde
r)
P
RCP
TS
P
PH
P
TS
TS
TS
P
PH
P
“ö ⁄
ƒó⁄å¥
” ö ⁄
¶h⁄
«ï ⁄
¶fi⁄
¾A⁄
ÀR⁄
“Y⁄
«a¿
» ï •
° “•
†˜⁄
Choi Man
House
Homantin Plaza
Yee Man
House
Yat Ma
n Hous
e
Tim Man
House
Nga Man
House
Sik Man
House
Ching Man
House
Yan Ma
n Hous
e
Kwun Hei
Court
Ming Fa
i House
Ko Fai
House
Block 8
68
3
1
–̆ †
¤àµ
£„
„C…
„C…
¤à µ£„
x̃†
x̃†
«a¿
–‘…Ö µ
„C… „C…«a•
–‘…Ö µó “ƶØ
¤‹†
“Fƒó⁄套°t
¤‹†
„C…
„C…
“ł´
Volleyba
ll
Court
Child
ren’s
Pla
yground
Playground
Playgro
und
Children’s
Playgro
und
RCP
Football FieldBas
ketball
Court
Basketb
all
Court
Kwun Hei
Court
Sheung Lok StreetGarden
Playgrou
nd
Playground
Kwun Fai
Court
Sheung Lok Street Garden (Stage II)
Football Field
Ho Man Tin East Service Reservoir Playground
Football Field
Pla
yground
Playground
CUL
CUL
CUL
CULCUL
CUL
CUL
CULCUL
CULCUL
CUL
CUL
CUL
CUL
105.0
105.8
72.1
44.0
46.0
46.0
100.7
45.9
57.8
46.0
45.9
74.2
106.8
45.9
43.1
43.7
46.0
62.643.5
46.0
43.8 47.2
44.574.2
93.2
47.0
48.7
51.8
50.554.3
53.1
46.257.8
52.4
73.976.4
47.4
51.7
63.7
51.8
75.154.4
73.4
49.9
54.254.3
54.351.9
72.471.5
63.2
51.8
51.554.251.8
74.3
59.2
53.5
70.4
69.2
55.2 54.3
52.254.3
70.3
53.5
53.6
68.4
59.4
70.0
60.863.3
60.7
66.1 55.266.8
61.3
64.6
59.5
60.3
68.7
61.1
68.5
67.2
62.0
61.8
68.4
68.3
61.4
68.6
60.6
26.3
67.5
66.3
68.4
67.6
68.7
60.2
68.5
55.722.1
65.8
59.868.5
69.465.7
87.4
68.3
25.1
23.1
52.3
26.0
52.7
18.048.8
48.5
L
L
L LH
L
L
L
H
L
LH
H
L
L
L
H
LL
HH
L
L
L
H L
L
L
H
L
L
L
H
H
L
L L
L
L
LH
L LLL
H H
LH
LL
H
L
L
L
L
L
LL
H
L
L
L
L
H
L
LH
L
L
H
L
SH
EU
NG
LO
K
ST
RE
ET
SHEUNG LOK S
TREET
FA
T
KW
ON
G
ST
RE
ET
–‘…
ƒò
¥
–‘…
–×
„D
° “‹[
CW
CW
CW
EW
Ramp
EW
CW
CW
CW
Road
ElevatedRoa
d
EW
FPF
P
¥›¥x„¡]⁄
U…h
¥› ¡]⁄U…hƒh…
(Co
mmercial C
om
plex under)
Podiu
m
A
ARCH
FP
Road
†˜⁄
†˜⁄Block 7
Block 6
48.6
47.952.3
L LH
L
Pipeline
¾É
Pipeline
¾É
“ł¤
F
flï“
K
LAI CHI KOK ROAD
WATE
RLOO
ROAD
BOUNDARY STREET‹É›
PRINCE EDW
ARD ROAD
WEST
⁄Ó⁄l
¤¨‹Ò
ARGYLE
STREET
ƒò ¥
°¤À
Y
KOWL
OON CIT
Y R
OAD ⁄
g¥
˚
TO
KWA W
AN
ROAD
⁄EÀs
CHAT
HAM R
OAD N
ORTH
”£«
w
MA
TAU W
AI
ROAD
ƒı·
JORDAN ROAD
À–
·NATHAN ROAD
GASCOIGNE ROAD
¥⁄'„
”«„
«
°¶•
WAI YIP STREET
˘[¶
SALISB
URY R
OAD
“° ¤·
KING’S
ROAD
›^‹
PRIN
CE
SS
MA
RG
ARET R
OA
D
CHAT
HAM
RO
AD
SOUT
H
QUEEN’S
DES VOEUX ROAD
CENTRAL
ISLA
ND
EAS
TERN COR
RIDOR
⁄¥
„
CROSS HARBOUR TUNNEL
fiü'‡
1
1
1
3
3
“F°
ˇfiü
ƒŁ°
ˇfiü
WEST
ERN H
ARBO
UR
CROSSI
NG
5
5
5
5
5
2
4
4
fiÞ⁄
h⁄
FAT KWONG STREET
CONNAUGHT
ROAD
CENTRAL
…s
“
CANTON ROAD
KAI TAK TUNNEL–Ò…w
ƒŁ⁄
EÀ
WEST KOWLOON CORRIDOR
WEST
KOWLOON
HIGHWAY
˘[¶í
KWUN TONG BYPASS
⁄EÀ
Ko
wlo
on
Ba
y
Mei
Shek Kip
⁄Ó
Prin
ce
Ed
war
d
'ô
Mo
ng
Ko
k
“o‡
Ya
u
Ma
Tei
ƒı
Jor
da
n
¶łOly
mpic
Ko
wlo
on
⁄ßÀNgau Tau Kok
ƒy
¤
Tsim
Sha
Ts
ui
Sheung Wan
⁄W
ܦ
¥
¥_
North
Point
�o‡
Quarry Bay
⁄Ó
Tai Koo
⁄E
Fortress
Hill
«nN
am
Cheong
–N›x
flþ˘
'¤
“
Mo
ng
Ko
k
East
EA
ST
RAI
L
“F¯
WEST RAIL
LINE
ƒŁ̄
ƒy
East T
sim
Sha
Tsui
†‘⁄
Sha
m Shui P
o
›»Hong Kong
“FflTUNG CHUNG LINE
TS
UE
N
WA
N
LI
NE
AI
RP
OR
T
EXP
RESS
¾÷
§Ö
‹_⁄
Austin
Railway under construction
KW
UN
TO
NG
LI
NE
KWUN TONG
⁄g¥
WANTO KWA
⁄ßÀ
KOKNGAU TAU
‹ıHUNG HOM
⁄EÀKOWLOON CITY
⁄EÀKOWLOON BAY
…ÖµØ
Estate
Lok Wah North
°¤ÀMA TAU KOK
⁄ßÀY¤
⁄EÀ
Rock
Kowloon
fiü¶hLaguna Verde
“Y”aJubilant Place
⁄g¥˚˘W
Typhoon Shelter
To Kwa Wan
˜R·„
Gardens
Richland
˘[¶í`
Typhoon Shelter
Kwun Tong
CROCODILE HILL
¤˚⁄KING’S PARK
•R¥
Estate
Oi Man
fia”
Chuen
Ka Wai
…Ö¥`
Tung Estate
Tai Hang
⁄j¤TAI KOK TSUI
«n'
Estate
Nam Cheong
°¤ÀMA TAU WAI
˜Rƒ
Estate
Lai On
Estate
Lai Kok
'ôMONG KOK
‹f·
¥bfiq
Peninsula
Royal
”ß·
Harbourview
Island
”y⁄
“o‡YAU MA TEI
•s“o‡´ƒ
Typhoon Shelter
New Yau Ma Tei
SHAM SHUI PO
«ÒfixMajestic Park
Garden
Charming
·I”a
°¤ÀY
Estate
Ma Tau Wai
¶ÀfiHWhampoa Garden
ƒó⁄
HO MAN TIN«T¥
Court
Chun Man
�o‡QUARRY BAY˜_°
BRAEMAR HILL
˜_°¤⁄Pacific Palisades
⁄Ó¥Taikoo Shing
¥_NORTH POINT
˘W
⁄j¥
PAU MAI
TAI
⁄WSHEUNG WAN
ƒy¤
TSIM SHA TSUI
⁄⁄CENTRAL DISTRICT
»É˘r˘W
Typhoon Shelter
Causeway Bay
Court
Yee Ching
´@µo
Garden
Prosperous
fiü·
–m`
⁄ƒfi‡
Garden
Tanner
…Ò‰
”
Ĥ
¤·
⁄EKOWLOON
–‘…
Estate
Sheung Lok
V
I
C T O
R I A
H A R B O
U R
«Ò‹fCentral Park
«Òfi
Villa
King’s Park
¤˚⁄h
Hill
King’s Park
Sun Chuen
Lok Man
Avenue
Park
Hoi Fu Court
·I'
Estate
Fu Cheong†‘⁄
ėڌ
Estate
Ho Man Tin
⁄S⁄
TSUENYAU YAT
·ä·
Towers
Victoria
À”⁄ÑSorrento
‡˝ƒ
PlaceHampton
·ä˘WMetro Harbour View
¶˘¶Sky Tower
–Òfi
Court
Kai Tai
–Ò•
Estate
Kai Yip
EstateModel Housing
§g`{The Harbourside
⁄EÀ
KOWLOON BAY‹ıŒ
Estate
Hung Hom
…w”Ö
Gardens
Telford
ƒˆ⁄ô‡
Treatment Works
Sewage
§gÀParc Palais
fiö…
BeachThe Long
…Ö¶Lok Nga Court⁄ßÀY¤
‡˝–The Arch
`ɃŁ·
Braemar Hill Mansions
GreenHarbour
§gœ
⁄@‚„One SilverSea
µ¾ÀGrand Waterfront
“ƶØGarden Estate
fið¶
StationMeteorological
Mei Chuen
Chun Seen
fluµ‰
°•–
Village
Healthy
ƒŁ⁄EÀs⁄åWEST KOWLOON CULTURAL DISTRICT
¤fi
⁄U…h
under
Railway Depot
fiüÀØ
Place
Harbour
–m‹
Estate
Choi Ying
Estate
Ngau Tau Kok
Upper
Estate
Ngau Tau Kok
Lower
¥b⁄s
Heights
Celestial
–m”
Estate
Choi Fook
–m…
Estate
Choi Tak
¿‡«Ø⁄⁄⁄§
under Construction
Cruise Terminal
Choi Ha Estate
The Waterfront
ڄThe Cullinan
'_⁄
ISLAND
KELLETT
–ÒKAI TAK
`‘
°“‡t
¿‡«Ø
under Construction
Link Terminus
Express Rail
°t⁄Ser Res
°t⁄Ser Res
°t⁄
°t⁄Ser Res
°t⁄Ser Res
°t⁄Ser Res
°t⁄Ser Res
°t⁄Ser Res
°t⁄Ser Res
°t⁄Ser Res
°t⁄Ser Res
°t⁄Ser Res
›»·ä†z
°˘›„«~§
MarketWholesale Food
⁄⁄°Œ«¨
TerminalChina Ferry
·ç‰üFerry Pier
·ç‰üFerry Pier
`A–Lookout
·ç‰üFerry Piers
“aSw P
·ç‰üFerry Piers
Sw P
“aSw P
¥ì§Q¤F
HospitalQueen Elizabeth
⁄EÀsKowloon Park
⁄EÀs
HospitalKowloon
“a
·ç‰üFerry Piers
›»·ä¯
·ä¿D«¨
Ferry TerminalHK - Macau
“aSw P
“aSw P
⁄Ó“Space Museum⁄å⁄˘
CentreCultural
fiü „B
Ocean
Termin
al
›»·ä¾ð
`A–Lookout
⁄Ñ⁄HK Observatory
˜`Clock Tower
·ç‰üFerry Piers
‡‰ˆþ§å
MarketWholesale Fish
'ô¤⁄⁄
StadiumMong Kok
UniversityHK Shue Yan
UniversityThe HK Polytechnic
‹ì¾Science Museum
¾œ¥v‡
History
Museum of
HK Coliseum
`A–Lookout
›»·ä⁄‰The Open University of HK
·ç‰üFerry Pier
⁄⁄
°Œ»Ú
Exhibition Centre
Trade and
International
“a
Jordan Valley Park
ˆÀ‡Museum of Art
⁄å“
°“⁄s
TheatreKo Shan
200
200
100
88
‹ıŒ'
Station
Hung Hom
Àô†y¶T
Centre
Commerce
International
›xBarracks
DISTRICT
CENTRAL
VICTORIA HARBOUR
TSIM SHA TSUI
HUNG HOM
NORTH POINT
KEY PLAN N.T.S.
TO KWA WAN
YAU MA TEI
MONG KOK
KOWLOON CITY
KOWLOON BAY
Filena
me :
J:\
28
77
86-
CK
R\
SK
ET
CH\
10\
CK
R_
SK_
10_
0009.d
gn
24/5/2
012
Printed by :
Rev.
Status
Rev DateByDescription
Drawn
Drawing no.
Date Checked
Drawing title
Scale
COPYRIGHT RESERVED
Project title
Consultant
Approved
Design and Construction
Central Kowloon Route -
/Agreement No. CE 43 2010 (HY)
Joint Venture
HL
PRELIMINARY
EC
A
09/11
1:1000 @ A1
03/12JLA FIRST ISSUE
A.LIE
0 20 403010 50m
1 : 2000 (A3)
1 : 1000 (A1) SCALE BAR
819 400 N
819 600 N
836 600 E
836 800 E
CKR/SK/10/0009
LEGEND:
837 000 E
819 200 N
TGLA
GLA-TK 389
GLA-TK 389
POSSIBLE TSA
NN
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 23
Appendix B
C&D Material Quantity Estimation for CKR
Project: Arup-Mott MacDonald Joint VentureArup-Mott MacDonald Joint VentureArup-Mott MacDonald Joint VentureArup-Mott MacDonald Joint Venture
AGREEMENT NO. CE 43/2010 (HY)
CENTRAL KOWLOON ROUTE - DESIGN AND CONSTRUCTION Div/Dept Job Ref 287786
HKT
Calculation for: Calculated by: Date: Page:
CY 31-May-12
C&D material for C&DMMP Checked by: Date: 1
RC 31-May-12
Table B1. Summary of Breakdown of C&D Material Generation and Demand:
(All Quantities are in-situ volume, cu.m)
C&C Tunnel
Underwater
Tunnel
Depressed
Road Shaft (1)
Demolish
Structures
Cross-
passage Bored Tunnel
Shaft (1)
&
Bldg.
C&C
Tunnel
Depressed
Road Shaft (1)
Demolish
Structures Total
C&D Material Generation
A) Inert C&D Material
1) Grade II or above Rock 0 0 0 0 0 20800 849657 9659 0 0 0 0 880116
2) Grade III or below rock 0 0 0 18500 0 1600 74600 450 0 0 135000 0 230150
3) Inert Soft C&D Material 241875 684688 145680 140000 115340 0 0 19013 504400 101430 0 110283 2062709
4) Broken Concrete 0 0 0 0 7242 0 0 0 0 0 0 84155 91397
5) Reclaimed Asphalt Pavement (RAP) 1750 0 3640 0 6100 0 0 0 4900 2450 0 6856 25696
6) Bentonite Slurry 23625 55013 19320 0 4393 0 0 2138 33300 16380 0 406 154575
Sub-total for Inert C&D Material (cu.m) 267250 739701 168640 158500 133075 22400 924257 31260 542600 120260 135000 201700 3444643
Sub-total for Inert C&D Material (M cu.m) 0.267 0.740 0.169 0.159 0.133 0.022 0.924 0.031 0.543 0.120 0.135 0.202 3.444
B) Non-Inert C&D Material
Non-inert C&D Waste 2000 0 0 0 0 0 0 0 2000 2000 8000 0 14000
Sub-total for Non-inert material (cu.m) 2000 0 0 0 0 0 0 0 2000 2000 8000 0
Sub-total for Non-Inert C&D Material (M cu.m) 0.002 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.002 0.002 0.008 0.000 0.014
Total C&D Material Generated 3.458
Fill Material Required
Selected Public Fill 120000 619900 12000 0 0 0 0 0 207200 0 0 0 959100
Sub-total for Fill Material (M cu.m) 0.120 0.620 0.012 0.000 0.000 0.000 0.000 0.000 0.207 0.000 0.000 0.000 0.959
Table B2. Summary of Quantities of C&D Material at Each Portion
(All quantities are in-situ volume, cu.m)
Total
Inert C&D Material Generation (cu.m) (M cu.m) (cu.m) (M cu.m) (cu.m) (M cu.m) (M.cu.m)
1) Grade II or above Rock 0 0.000 880116 0.880 0 0.000 0.880
2) Grade III or below Rock 18500 0.019 76650 0.077 135000 0.135 0.231
3) Inert Soft C&D Material 1327582 1.327 19013 0.019 716113 0.716 2.062
4) Broken Concrete 7242 0.007 0 0.000 84155 0.084 0.091
5) Reclaimed Asphalt Pavement (RAP) 11490 0.012 0 0.000 14206 0.014 0.026
6) Bentonite Slurry 102351 0.102 2138 0.002 50086 0.050 0.154
Sub-total for Inert C&D Material (M cu.m) 1.467 0.978 0.999 3.444
Non-inert C&D Waste
Sub-total for Non-inert material (cu.m) 2000 0.002 0 0.000 12000 0.012 0.014
Total C&D Generation 1.469 0.978 1.011 3.458
Table B3. Summary of Quantities of Fill Material Required at Each Portion
(All quantities are in-situ volume, cu.m)
Total
Fill Material Required (cu.m) (M cu.m) (cu.m) (M cu.m) (cu.m) (M cu.m) (M.cu.m)
Inert C&D Material (Selected Public Fill) 751900 0.752 0 0.000 207200 0.207 0.959
Sub-total for Non-Inert Material (M cu.m) 0.752 0.000 0.207 0.959
Notes:
1. Shaft refers to an underground vertical tunnel from top down which provides vertical passage for tunnel construction and mucking out
Central HMT Portion West YMT Portion
East MTK Portion Central HMT Portion West YMT Portion
East MTK Portion
East MTK Portion Central HMT Portion West YMT Portion
Table B4 - Schedule of quantities of Inert C&D material generated and required at West YMT Portion (All quantities are in-situ volume, cu.m)
Total
Rock III or below 135000
Inert Soft C&D Material 716113
Broken Concrete 84155
Reclaimed Asphalt Pavement (RAP) 14206
Bentonite Slurry 50086
Selected Public Fill Demand 207200
Table B5 - Schedule of quantities of Inert C&D material generated at Central HMT Portion (All quantities are in-situ volume, cu.m)
Total
Rock II or above 880116
Rock III or below 76650
Inert Soft C&D Material 19013
Bentonite Slurry 2138
Table B6 - Schdeule of quantities of Inert C&D material generated and required at East MTW Portion (All quantities are in-situ volume)
Total
Rock III or below 18500
Inert Soft C&D Material 1327582
Broken Concrete 7242
Reclaimed Asphalt Pavement (RAP) 11490
Bentonite Slurry 102351
Selected Public Fill Demand 751900
Table B7 - Schedule of overall quantities of C&D material generated and required (All quantities are in-situ volume, cu.m)
Total
Rock II or above 880116
Rock III or below 230150
Inert Soft C&D Material 2062709
Broken Concrete 91397
Reclaimed Asphalt Pavement (RAP) 25696
Bentonite Slurry 154574
C&D Waste 14000
Selected Public Fill Demand 959100
Table B8 - Schedule of overall quantities of C&D material generated (All quantities are in-situ volume (M cu.m))
Total
Rock II or above 0.880
Rock III or below 0.231
Inert Soft C&D Material 2.062
Broken Concrete 0.091
Reclaimed Asphalt Pavement (RAP) 0.026
Bentonite Slurry 0.154C&D Waste 0.014
Total C&D Material Generated 3.458
Notes: Inert Soft C&D Material will be generated by the excavation of depressed roads and C&C tunnels, mined tunnel construction, construction of bridge footings, demolition of structures and TTM implementation
Rock (Grade I/II) will be generated by mined tunnel construction
Non-inert C&D Waste will be generated by the general site clearance and demolition of structures
Table B9 - Schedule of overall quantities of C&D material generated (All quantities are "bulked" volume (M cu.m))
Total
Rock II or above 1.584
Rock III or below 0.300
Inert Soft C&D Material 2.680
Broken Concrete 0.119
Reclaimed Asphalt Pavement (RAP) 0.033
Bentonite Slurry 0.201
C&D Waste 0.017
Total C&D Material Generated 4.934
Remarks: The bulk factor of rock and soil is 1.8 and 1.3 respectively
Table B10 - Schedule of quantities of fill material required (All quantities are in-situ volume (M cu.m))
Total
Selected Public Fill Demand 0.959
Total Fill Demand 0.959
Notes: Selected Public Fill will be required for backfill C&C tunnel, temporary reclamation works and the transition between underwater tunnel & depressed road
0.000 0.000 0.000 0.0000.026 0.002 0.001 0.0000.117 0.071 0.043 0.040
0.000 0.000 0.000 0.0000.020 0.001 0.001 0.0010.090 0.054 0.033 0.031
0 0 0 090450 54250 33392 30741
0.0000.405 0.192 0.106 0.0000.000 0.460 0.114 0.619 0.359 0.278 0.147
0.0000.001 0.001 0.000 0.000
0.416 0.416
0.007 0.007 0.000 0.001
0.294 0.0860.000 0.010 0.089 0.273
Jan - Jun Jul - Dec Jan - Jun Jul - Dec
2019 2020
Jan - Jun Jul - Dec Jan - Jun Jul - Dec Jan - Jun Jul - Dec Jan - Jun Jul - Dec
2015 2016 2017 2018
0 0 0 01811 0 0 00 1810 1810 1811
0.000 0.000 0.000 0.000
0.000 0.0000.000
119196 68000
0 16500
Jan - Jun Jul - DecJan - Jun Jul - Dec
0 0108086 1080860 0 0 81428
0 7951 6477 31232
Jan - Jun Jul - Dec
151756 140657
Jan - Jun Jul - DecJan - Jun Jul - Dec
108086 18014
2015 2016 2017 2018
Jan - Jun Jul - Dec Jan - Jun Jul - Dec
2019 2020
0 200532 40106 64350 0 0
Jan - Jun Jul - Dec
0 354210 88115 393073
Jan - Jun Jul - Dec Jan - Jun Jul - DecJan - Jun Jul - Dec Jan - Jun Jul - Dec
2015 2016 2017 2018 2019 2020
163395 47779 0 0 0 0
0
0 5795 49087 151598 231231 231231
Jan - Jun Jul - DecJan - Jun Jul - Dec
5185 5185 5185 2593
Jan - Jun Jul - Dec Jan - Jun Jul - Dec
2015 2016 2017 2018 2019 2020
0 0
Jan - Jun Jul - Dec Jan - Jun Jul - Dec
0 0
148192 82364 0 00 354210 88115 475366 276139 213842 113271 311211
231231 231231 163395 47779
20227 436 436 218
0 5795 49087 151598
Jan - Jun Jul - Dec
0 00 0
Jan - Jun Jul - DecJan - Jun Jul - Dec Jan - Jun Jul - Dec Jan - Jun Jul - Dec Jan - Jun Jul - Dec
2015 2016 2017 2018 2019 2020
450 0 24142 30741 20227 436 436 218 0
51558 319347 86000 0 58000 121247 99248 0 0 0
2482
10301
0
1050
7719
333
1050
28521
0 0
0 33399 4318 42492
31604
6345
15281
7702
29793 7702 0 333 667 0 0 0
58000 121247 99248 051558 319347 86000 0 0 223700 0 0
Jan - Jun Jul - Dec Jan - Jun Jul - Dec
2019 2020
Jan - Jun Jul - Dec Jan - Jun Jul - Dec Jan - Jun Jul - Dec Jan - Jun Jul - Dec
2015 2016 2017 2018
0.000 0.006 0.049 0.152 0.231 0.231 0.163 0.048 0.000 0.000 0.000 0.000
0.052 0.319 0.086 0.000 0.058 0.121 0.099 0.000 0.000 0.224 0.000 0.000
0.000 0.354 0.088 0.476 0.276 0.214 0.113 0.311 0.148 0.082 0.000 0.000
0.006 0.005 0.000 0.001 0.001 0.001 0.000 0.000 0.000 0.000 0.000 0.000
5333 4667 0 769 1137 736 429 429 429 71 0 0
0 0583 583 583 2920 0 0 97
0 5783 2132 2050 1525 0 0 0 0 0
0
0
9761
5783
8287
2132
33043
5629
0 0 0 0 0 0 0 0 0 207200 0 0
2015 2016 2017 2018 2019 2020Jan - Jun Jul - Dec Jan - Jun Jul - Dec Jan - Jun Jul - Dec Jan - Jun Jul - Dec Jan - Jun Jul - Dec Jan - Jun Jul - Dec
0 33399 4318 35939 3383 0 0 21094 4218 0 0 0
0
0
0
0
0
0
3579
6456
4820
11315
2482
9718
1050
7136
1050
7136
1050
7136 1189
175 0
00
0
667
1050
11354
0
175
1189
0
0
0
0
0
0
0.000
0.000
0.000
0.009
0.006
0.033
0.008
0.002
0.004
0.033
0.006
0.042
0.032
0.006
0.015
0.008
0.003
0.010
0.000
0.001
0.008
0.000
0.001
0.029
0.001
0.001
0.012
0.000
0.000
0.001
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.013
0.008
0.043
0.011
0.003
0.006
0.043
0.008
0.055
0.041
0.008
0.020
0.010
0.003
0.013
0.000
0.001
0.010
0.000
0.001
0.037
0.001
0.001
0.016
0.000
0.000
0.001
0.000 0.000
0.000
0.000
0.000
0.000
90000 45000 0 0 0 0 0 0 0 0 0 0
0 9250 9250 0 0 0 0 0 0 0 0 0
0 0 0 865 0 0 0 0
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 24
Appendix C
Tentative Construction Programme and Time Chainage Diagram
Figure C1 - CKR: Tentative Programme for the C&D Material Generation and Fill Material Demand (In-situ) (m3)
Activities Grade II Grade III Inert soft C&D Material Broken Concrete RAP Bentonite Slurry C&D Waste Filling Volume Duration
or above rock or below rock Start Finish (month) 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
WEST PORTION
Depressed Road - Excavation 101430 0 2450 16380 2000 08-2016 08-2017 13 ## ## ##
TTM implementation, Building Basement & Demolish Bridges 110283 48148 6856 406 08-2016 08-2017 13 ## ## ##
Demolish Multistory Carpark - Stage 1 0 13252 10-2015 02-2016 5 0 0
Demolish Multistory Carpark - Stage 2 0 9466 09-2016 03-2017 7 0 0
Demolish YMT Specialist Clinic Extension 0 5249 09-2016 02-2017 6 0 0
Demolish the Existing Flyover 0 2040 08-2016 10-2016 3 0
Demolish Ferry Street Subway 0 1000 12-2018 02-2019 3 0 0
C & C Tunnel - Excavation 504400 0 4900 33300 2000 04-2017 07-2019 28 ## ## ## ## ## ##
C & C Tunnel - Backfill 207200 08-2019 11-2019 4 ##
Foundation Excavation for Bridge Construction 5000 03-2016 07-2017 17 0 0 0 0
Assess Shaft - Excavation 135000 8000 01-2015 09-2015 9 0 0
CENTRAL PORTION
Non-blast tunnelling -Mined Tunnel (1440-1600) 59370 01-2017 06-2017 18 ## ## ##
Drill and Blast Tunnelling (1600-3200) 520075 05-2016 04-2018 23 ## ## ## ## ##
Excavation of Shaft (Rock Grade III or below) 450 01-2015 06-2015 6 ##
Excavation of Shaft (Rock Grade I/II) 9659 07-2015 04-2016 10 ## ##
Drilling and Blast Tunnelling (3200-4180) 329582 12-2016 09-2018 22 ## ## ## ## ##
Non-blast tunnelling - Mined tunnel (4180-4230) 15229 05-2016 11-2016 7 ## ##
Cross Passage (26 Nos.) & Pump Sumps 20800 12-2016 09-2018 22 ## ## ## ## ##
Cross Passage (2 Nos.) & Ventilaton Bldg Basement Construction 1600 2138 19013 12-2016 09-2018 22 73 ## ## ## ##
EAST PORTION
C & C Tunnel - Phase 1 Excavation 168975 1225 16200 2000 08-2015 12-2015 5 ##
C & C Tunnel - Phase 1 Backfill 84000 04-2016 05-2016 2 ##
C & C Tunnel - Phase 2 Excavation 72900 525 7425 09-2016 11-2016 3 ##
C & C Tunnel - Phase 2 BackfilI 36000 02-2017 03-2017 2 ##
Underwater Tunnel - Stage 1 Reclamation (Selected Public Fill) 360905 06-2015 12-2015 7 ## ## ##
Underwater Tunnel - Stage 1 Excavation 277700 29700 07-2016 01-2017 6.5 ## ##
Underwater Tunnel - Stage 1 Backfill seabed (Selected Public Fill) 44000 06-2017 07-2017 2 ## ##
Underwater Tunnel - Stage 1 Removal and Restore Reclamation 102000 06-2017 08-2017 3 ## ##
Underwater Tunnel - Stage 2 Reclamation (Selected Public Fill) 198495 11-2017 02-2018 4 ## ##
Underwater Tunnel - Stage 2 Excavation 240638 25313 08-2018 01-2019 6 ## ##
Underwater Tunnel - Stage 2 Backfill seabed (Selected Public Fill) 16500 07-2019 08-2019 2 ##
Underwater Tunnel - Stage 2 Removal and Restore Reclamation 64350 07-2019 10-2019 3 ##
Depressed Road - Excavation 145680 3640 19320 08-2015 01-2016 6 ## ##
Backfill for Transition at C & C Tunnel & Depressed Road 12000 08-2015 01-2016 6 ##
Foundation Excavation for Bridges / Underpass Construction 140000 07-2015 06-2017 24 ## ## ## ##
Demolition of Structures 115340 7242 6100 4394 07-2015 06-2017 24 ## ## ## ##
Ventilation Shaft - Excavation 18500 07-2015 06-2016 12 0 0
20202018 2019Duration 2015 2016 2017
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 25
Appendix D
Correspondence
217722-REP-023-01 | Issue 4 | August 2012
217722-REP-023-01 REV 4.RTF Page 26
Appendix E
Response to Comments on CEDD/ PFC memo dated 15 May 2012
Agreement No. CE 43/2010 (HY) Construction and Demolition Material Management Plan (C&DMMP)
Central Kowloon Route (CKR) – Design and Construction Response to Comments
P:\Hong Kong\BRI\287786 CKR D&C\07 Documents\Deliverables\21 Updated C&DMMP\15 RtC on PFC (15 May 2012)\RtC - CEDD_PFC_HyD comment.doc
Page 1
Comments received: Responses:
PFC, CEDD
Ref : (0SQ54-01) in FM PF/CDM/00
Date : 15 May 2012
(i)
CEDD/ PFC’s Comments on 15 May 2012
Para.2.1.4 – In para. 5.1.2, it stated that the
backfill excavated / dredged from the
temporary reclamation near Kai Tak will not
be covered by this C&DMMP and the relevant
excavation/ dredging proposal for the backfill
will be submitted separately to Marine Fill
Committee and the Environmental Protection
Department. In this connection, please amend
the last sentence of this paragraph as “This
report covers only the CKR C&D materials
which excluding the marine sediment,
contaminated materials and the excavated/
dredged public fill from the temporary
reclamation near Kai Tak.”
Removal of public fill from temporary reclamation is
included in the C&DMMP. The last sentence in para.
5.1.2 is deleted instead.
(ii) Para.5.1.5 – This paragraph stated that a
breakdown of estimated volume of C&D
materials to be reused was provided but was
found missing.
Noted and the para. 5.1.5 was duplicated to para.5.1.6.
para. 5.1.5 was deleted accordingly.
(iii) Para.5.3.1 – It is noted that Mines Division of
CEDD advised that it is unlikely to accept the
rock generated from CKR under the current
contracts, and importing of rock from CKR to
Lam Tei Quarry (LTQ) could only be
materialized if the quarry operation of LTQ is
to continue beyond 2015 under a new contract.
As the disposal site of rock is not secured yet,
please continue to liaise with Mines Division
and also explore other alternative disposal sites
such as export to Mainland China and other
construction projects in Hong Kong. Please
include the details and progress of the liaison
of exporting rock to Mainland China.
We will closely liaise with CEDD/ Mines Division and
explore other alternative disposal sites such as the Third
Runway of Hong Kong International Airport and other
construction projects in Hong Kong. We will also
include contract provisions for alternative disposal sites
arrangement in the contract.
The para. 5.3.1 was amended accordingly.
(iv) Para.5.3.2 – Please be reminded that disposal
of rock to public fill reception facilities should
be considered as the last resort.
Noted. The selected public fill will be re-used on site as
far as possible and disposal of rock to public fill
reception facilities will be considered as the last resort.
The para. 5.3.2 was amended accordingly.
(v) Para.5.6.3 – Public fill of grade 200 available
at the fill banks is of limited amount, please
liaise with Fill Management Division on the
details of the proposed arrangement.
Noted and we will closely liaise with Fill Management
Division on the details of proposed arrangement. Para.
5.6.4 in the report is added accordingly.
(vi) Para.5.7.5 – Please provide a location plan for
the possible temporary stockpile area (TSA).
We would like to reiterate that disposal of
public fill to public fill reception facilities
should be considered as the last resort. Please
continue to explore possible TSA so as to re-
The possible land allocation of TSA is Housing
Authority Mock Up Centre and the location is attached
in Appendix A for your information. Further exploration
of possible TSA will be carried out.
Agreement No. CE 43/2010 (HY) Construction and Demolition Material Management Plan (C&DMMP)
Central Kowloon Route (CKR) – Design and Construction Response to Comments
P:\Hong Kong\BRI\287786 CKR D&C\07 Documents\Deliverables\21 Updated C&DMMP\15 RtC on PFC (15 May 2012)\RtC - CEDD_PFC_HyD comment.doc
Page 2
Comments received: Responses:
use the public fill on site as far as possible.
(vii) Para.5.9.4 – Please continue to liaise with
DLO and other relevant offices on any
possible barging points.
Noted and we will continue to liaise with DLO and
relevant offices on the possible barging point location.
The para. 5.9.4 was amended accordingly.
(viii) Table 5.1 – According to PAH Appendix 4.9,
please breakdown the C&D materials into
different types of materials (e.g. Inert soft
C&D materials, Grade II of above rock
(granite or volcanic or others), Grade III or
below rock, C&D waste, etc.).
The breakdown of C&D materials in Table 5.1 was
amended in accordance with the PAH Appendix 4.9.
(ix) Table 5.3 – Please follow the classification of
C&D material in item (viii) above
The breakdown of C&D materials in Table 5.3 was
amended in accordance with the PAH Appendix 4.9.
(x) Table 6.1 – Please note item (viii) above. For
each type of C&D material, please provide a
breakdown of (a) total quantity generated, (b)
quantity to be re-used on site, (c) quantity to
be re-use in other projects, (d) quantity to be
delivered to mainland and (e) quantity to be
delivered to public fill reception facilities/
landfills.
Table 6.1 was amended. We will closely liaise with
CEDD/Mines Division and explore other alternative
disposal sites. The quantities of items c, d and e will be
provided.
(xi) Table 6.2 – Please include the source of public
fill imported.
Noted and the source of public fill imported was
included in the table 6.2.
(xii) Para.7.1.1 – this paragraph did not adequately
reflect Mines Division’s comments provided
via their memo ref. MQ 2A/13/39 dated 30
January 2012. As pointed out in item (ii)
above, disposal site of rock from CKR is not
secured and the project office is requested to
continue the liaison with Mine Division and
also explore other alternative disposal sites.
Para. 7.1.1 was amended. We will closely liaise with
CEDD/Mines Division and explore other alternative
disposal sites.
(xiii) Para.7.1.3 – What are the reasonable measures
to minimize the generation of C&D materials
and to maximize the use/ reuse of C&D
materials? Details of the proposed measure
such as exploration of TSA, liaison with
potential concurrent projects, etc. should be
clearly stated as the way forward in the
Recommendation Section.
Paras. 7.1.2, 7.1.3 and 7.1.4 were amended accordingly.