39
Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Embed Size (px)

Citation preview

Page 1: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Construction Cost EstimatingClass #2: Concept Estimating

Prof. Ralph V. Locurcio, PE

Page 2: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

A complex process involving the collection of available information on the scope of a project, the expected resource consumption, and future changes in resource costs.

This information is synthesized in a visualization of the construction process and translated into an approximation of the final cost.

Page 3: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Extensive knowledge of: Construction processes & methods Materials & methods Contracts & work practices Construction documents & details Background business factors Design & code requirements Verbal & written communications Good common sense & judgment

Page 4: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

KickoffMeeting

WorkPlan

EstablishStandards

UpdateDatabase

PrepareEstimate

DocumentEstimate

ReviewEstimate

Adjust Estimate?

SubmitBid

ProjectExecution

ProjectCompletion

Yes

No

Revise

Lessons Learned

Feedback to improve data base

Reality C

heck Yes

No

Page 5: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Read the Plans, Specs & Contract

Conduct Site Visit

Decide Construction

MethodPrepare Schedule

Plan for Subcontracts

Plan for EquipmentMaterial Take-Offs

Estimate costs

Determine contingency

Analyze Risk Factors

Finalize Bid

Page 6: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Systematic analysis of: Project components Equipment needed Construction methods Temporary work items Support activities Externalities

Page 7: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Conceptual Used for early decisions & feasibility Rough estimate using minimal data Relies heavily on past data Level of accuracy about 70%

Detailed Used for major decisions; i.e. bids & budgets Based on final design documents Level of accuracy up to 95%

Page 8: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

% Accuracy

% D

esi

gn

0 25 50 90 100

100

90

60

30

Page 9: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Based on prior experience: Weight check… weight of equipment Cost-capacity factor- ratio of Q/$ Comparative cost of structure – $/unit

Feasibility estimates Appropriations estimates Time & location adjustments

Page 10: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Basis is cost per unit based on past experience with similar units. Compare structures of like construction, (e.g.

school: steel, concrete, quality, local labor, weather) Develop cost per unit, e.g.

A$/pupil = A Cost/A pupils Apply to new construction:

B Cost = B pupils x A$/pupil

Page 11: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Schools: $/pupil Bridges: $/feet of span Stadium: $/seat Hospital: $/beds Offices: $/ft2

Warehouses: $/ft3

Page 12: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Plant cost ratio… process plant ratiodifferentiates machine ft2 from admin ft2

Floor area… cost/ft2 … but Total horizontal area… all floors equal Finished floor area… $ based on type finish Cubic foot of volume… floor height varies

Page 13: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Used for capital budgeting Expect 80-90% accuracy Based on historical data base Methods:

Panel… hist data on “typical” panels Bay… hist data on “typical” bays Plant component… equip cost + other TPC = ET/(1-PT)

Where ET=tot equip cost/(1-% all other cost items) ET = $$$ equip/(1-70%)

Page 14: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Cost indexing Based on similar “group” of key items Compare “group” over time or location Final cost based on ratio x calculated cost:

Est Cost = T2/T1 x Calc Cost

Est Cost = (T2/T1)(L2/L1) x Calc Cost

Page 15: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

“The future ain’t what it used to be”…Yogi Berra

Need to project costs to mid-point of the construction year for budgeting

Generally average past 3-5 years cost data & project forward

Page 16: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Based on three primary factors:

A. Scope… quantitiesB. Constructability… methods

C. Risk… externalities

Page 17: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Technology in project - complexity Milestone deadlines for work - timing Material & equipment - availability Staffing needed – skill & availability Contract terms – allocation of risk Amount of competition - markets

Page 18: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Construction quality – skill required Allowable tolerances – productivity Complexity of design – learning curve Flexibility of methods – special terms

Page 19: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Unspecified material or workmanship Differing site conditions Error in bidding Changes in cost over time Subcontractor error or failures Weather & environmental issues Strikes & labor issues Utilities & support issues

Page 20: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

1. Determine project characteristics:

Scope, constructability, risk2. Examine the project design & site

3. Structure the estimate 4. Determine elements of cost 5. Calculate estimate

Page 21: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Technical specifications Referenced standards Project drawings Testing and performance Special methods or procedures Physical elements & site characteristics Errors & omissions

Page 22: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Structure often follows specification template

Ensure nothing left out Need a plan for completing the project Logical flow of resources & materials Productivity factors

Page 23: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Labor- craft & skill resources; sub-contractors; union labor; wage rates; training; “effective” labor rates; productivity factors (weather, complexity, experience, management)

Material- price, shipping, availability, storage, relation to specifications

Equipment- purchase vs. lease, single use, down time, cost of maintenance

Capital- interest rates, payment flow, retainage Time- overhead costs, required completion date,

Page 24: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Material take-off from plans1. Quantities of all construction materials2. Compare with specifications

Labor cost for construction or installation1. Effective labor rates2. Team composition & duration

Construction equipment schedule1. On hand vs. lease or purchase2. Time on job

Follow elements of cost1. Ensure all items are covered

Page 25: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Calculate the estimated cost Solution in class

Page 26: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Based on historical data Accuracy = +30% Used for planning purposes when no

design exists Used to check validity of detailed

estimate

Page 27: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Assumes cost of equipment is dominant factor in plant cost

Estimate based on % of cost allocated to equipment relative to total cost of facility

Estimated cost is proportional to known cost

Must adjust for time & location

Page 28: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Assume that the equipment portion of a chemical processing plant constructed in 2006 cost $1.2M and the total plant cost was $2.5M. Therefore the equipment portion of the total cost was 46%. Estimate the cost of a new plant with the same processes if the equipment for the new plant has been determined to cost $2.7M. Assume time and location factors are negligible in this case.

Solution:

Page 29: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Assume that the equipment portion of a chemical processing plant constructed in 2006 cost $1.2M and the total plant cost was $2.5M. Therefore the equipment portion of the total cost was 46%. Estimate the cost of a new plant with the same process if the equipment for the new plant has been determined to cost $2.4M. Assume time and location factors are negligible in this case.

Solution: C2/E2 = C1/E1 … solve for C2

C2 = [C1/E1] x E2

C2 = [$2.5M/$1.2M] x $2.4M

C2 = [2.08] x $2.7 = $5,625,000M

Page 30: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Similar to comparison of $/sf unit measure

Used when facility has differing ceiling heights

Calculate the $/cf of known facility Determine $/cf of known facility Calculate total cf of new facility Using known $/cf calculate cost of new

facility Adjust for time and location

Page 31: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Determine the cost of a new warehouse which will have 3 distinct storage areas with differing ceiling heights. Area 1 = 12’; Area 2=14’ and Area 3 = 10’. The floor area of all three areas is 4000sf. A similar warehouse was constructed earlier this year for $2.4M. In that building the floor area was 8000sf and the ceiling height was a uniform 14’. Assume time and location factors are negligible in this case.

Solution:

Page 32: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Determine the cost of a new warehouse which will have 3 distinct storage areas with differing ceiling heights. Area 1 = 12’; Area 2=14’ and Area 3 = 10’. The floor area of each area is 4000sf. A similar warehouse was constructed earlier this year for $2.4M. In that building the floor area was 8000sf and the ceiling height was a uniform 14’. Assume time and location factors are negligible in this case.

Solution: Existing Building A = 8000sf x 14’ = 112,000 cfCost/cf = $2,400,000 / 112,000 cf = $21.43/cfNew BuildingA1 = 4000sf x 12’ = 48,000 cf

A2 = 4000sf x 14’ = 56,000 cfA3 = 4000sf x 10’ = 40,000 cfTotal = 144,000 cfCost = 144,000 cf x $21.43/cf = $3,085,714

Page 33: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Prices “escalate” over time due to inflation Must adjust estimated cost to “mid-point” of

construction. Determine period of construction Determine start date of construction Determine mid-point of construction =

average cost Determine “escalation rate” = given index Multiply estimated cost by “escalation rate” Note: escalation is compounded, ie. increase is

cumulative over number of years of escalation

Page 34: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Prices differ by region of the country Must consult a reliable index to determine

“relative” cost of construction between regions RS Means Cost Data or Engineering News

Record are examples Adjustment is a simple ratio multiplied times the

estimated construction cost. So… C2/C1 = L2/L1 X Estimated Construction Cost

and C2 = C1 x L2/L1

Page 35: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

You have been asked to prepare a conceptual cost estimate for the construction of a new university dormitory at Florida Tech to open in 2010. You have 2005 RS Means data that provides a cost of $30,000/bed for similar dormitories in the northeast of the US, and a construction period of 2 years. The Means data states that construction costs escalate at 10% per year in the southeast. If the dorm is to house 200 students at Florida Tech and the Means Cost Comparison Index between the northeast and southeast is 0.80, what is the estimated cost for the new library at Florida Tech at the mid-point of construction?

Estimated Florida Tech cost:______________________

Page 36: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

1. $30,000 per bed x 200 beds = $6,000,000… in the northeast in

2005

2. In the southeast in 2005… $6,000,000 x 0.80 = $4,800,000

3. Construction start is…Occupancy – 2 years = 2010 – 2 =

2008

4. Mid-point of construction is =2008 + 1 = 2009

5. Years of escalation…2009 – 2005 = 4 yrs

Page 37: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

6. Escalation: $4,800,000 x 1.10 = $5,280,000

(2005-06) $5,280,000 x 1.10 = $5,808,000

(2006-07) $5,808,000 x 1.10 = $6,388,800

(2007-08) $6,388,800 x 1.10 = $7,027,680

(2008-09)

Page 38: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE

Therefore… the estimated cost of the new dormitory for Florida Tech at the mid-point of construction in 2009 is:

$7,027,680

Page 39: Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE