Upload
ngoquynh
View
225
Download
1
Embed Size (px)
Citation preview
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-1
4-1
Lesson 4
CONSTRUCTIONDOCUMENTS
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-2
4-2
Learning Outcomes
• Locate Plan Sheet Details Related to Drilled Shafts
• Calculate REC % and RQD
• Identify key elements of the Drilled Shaft Installation Plan
• Identify & interpret applicable 455 Specifications
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-3
4-3
Standard Specifications
Supplemental Specifications
Developmental Specifications
Design Standards
Plans (including revisions)
TechnicalSpecial Provisions
SpecialProvisions
Project Document Governing Order
Must know this governing order. The Coordination of Contract Documents is set forth in section 5-2 of the Standard Specifications for Road and Bridge Construction. Governing order
• • Special Provisions – Specific clauses adding to or revising the Standard
Specification, setting forth conditions varying from or additional to the Standard Specifications, for a specific project.
• Technical Special Provisions – Specifications prepared, signed and sealed by an Engineer registered in the State of Florida other than the State Specifications Engineer, or his designee, which are made part of the Contract as an attachment to the Specifications Package.
• Plans – The approved plans, including reproductions thereof, showing the location, character, dimensions and details of the work to be done.
• Design Standards – Are FDOT standard design sheets for common items and are typically included in Plan sets. An example of this type of sheet is the “Notes and Details for Square Prestressed Concrete Piles”, Index No. 20600.
• Developmental Standards – A specification developed around a new process, procedure, or material and designated as a developmental specification.
• Supplemental Specifications – Approved additions and revisions to the Standard Specifications.
• Standard Specifications – The directions, provisions and requirements contained herein, together with all stipulations contained in the plans or in the contract documents, setting out or relating to the method and manner of performing the work, or to the quantities and qualities of materials and labor to be furnished under the contract.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-4
4-4
Definition of the Engineer
Engineer: Director, Office of Construction, acting directly or through
his duly designated representatives
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-5
4-5
PLANS ANDDOCUMENTSCHECKLIST
Plans & Specification Checklist
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-6
4-6
• Approved Drilled Shaft Installation Plan
• Complete set of Project Plans with Pay Items
• Minutes of Previous Meetings
• Special Provisions
• Technical Special provisions for project
• Standard Specifications
• Supplemental Specifications
• Design Standards
•Project Geotechnical Report
Inspector References
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-7
4-7
• Key Sheet
• Summary of Pay Items
• Plan and profile
• Special Provisions
• Structural Plans:
•General Notes
•Report of Core Borings
•Foundation Layout Plans
•Bridge Hydraulic Sheet
•Drilled Shaft Details
•Bent/Pier Plans
• Design Standards (17743 and 17502)
Important Plans and Drawings
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-8
4-8
Plans Review
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-9
4-9
Plan Set- Sheet 1 (Key Sheet)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-10
4-10
Plan Set- Sheet 1 (Key Sheet)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-11
4-11
Plan Set- Sheet 1 (Key Sheet)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-12
4-12
Plan Set- Sheet 1 (Key Sheet)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-13
4-13
Plan Set- Sheet 1 (Key Sheet)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-14
4-14
Plan Set- Sheet 1 (Key Sheet)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-15
4-15
Plan Set- Sheet 2 (Summary of Pay Items)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-16
4-16
Plan Set- Sheet 2 (Summary of Pay Items)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-17
4-17
Plan Set- Sheet 3 (Plan & Elevation)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-18
4-18
Plan Set- Sheet 3 (Plan & Elevation)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-19
4-19
Plan Set- Sheet 4 (Report of Core Borings)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-20
4-20
Plan Set- Sheet 4 (Report of Core Borings)
This notes section explains other symbols that may be used in this plan and special information that may be relevant to the drilled shaft construction. For example, the contractor is advised that artesian water was observed or expected at certain elevation and how high the water reached. WOH: means weight of hammer in the Standard Penetration Test. This is means a very loose or a very soft material or maybe even a void was encountered. We will cover later on what is a Standard Penetration test, or SPT. 50=2”: This means that during the SPT test the hammer reached 50 blows and only advanced 2 “. This in the industry of soil boring is considered refusal. In general, every time an SPT sampler requires 50 blows or more and advancing less than 6” is considered refusal. Note also the symbols for casing used. This refers to the casing used during the execution of the soil boring. If the soil testing firm needed to use casing during the soil borings, this will typically indicate the presence of permeable soils and formations. Water and drilling fluids are required to maintained cool the drilling tools. If these get lost through the soil or rock formations the drilling will need to use casing to hold the drilling
fluid or water.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-21
4-21
Plan Set- Sheet 4 (Report of Core Borings)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-22
4-22
Plan Set- Sheet 4 (Report of Core Borings)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-23
4-23
Plan Set- Sheet 4 (Report of Core Borings)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-24
4-24
Plan Set- Sheet 4 (Report of Core Borings)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-25
4-25
Plan Set- Sheet 4 (Report of Core Borings)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-26
4-26
Plan Set- Sheet 4 (Report of Core Borings)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-27
4-27
Plan Set- Sheet 5 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-28
4-28
Plan Set- Sheet 5 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-29
4-29
Plan Set- Sheet 5 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-30
4-30
Plan Set- Sheet 5 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-31
4-31
Plan Set- Sheet 5 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-32
4-32
Plan Set- Sheet 5 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-33
4-33
Plan Set- Sheet 6 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-34
4-34
Plan Set- Sheet 6 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-35
4-35
Plan Set- Sheet 7 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-36
4-36
Plan Set- Sheet 7 (Foundation Layout)
In bridge projects the geotechnical engineer will produce a drilled shaft length letter detailing the required production tip elevations which are based on load tests and soil borings called pilot holes. These production tip elevations may be different from whatever elevations were anticipated tip elevations were presented in the plans. If there are no load testing nor any pilot holes or any other field testing to verify these tip elevations, the tip elevations indicated in the plans will be the ones to construct the shafts to. Note 6 mentions the rock socket. Rock socket is the portion of the shaft that will be in contact with rock. The drilled shaft length letter may contain a revision of the required rock socket lengths. If there are no field testing at all, the rock sockets indicated in the plans will be ones the must be met. Note 7 indicates what type of material should be considered good enough to be considered part of the rock socket. Drilled shafts must meet both: the required tip elevations (indicated in the plans or revised by the drilled shaft length letter) and the rock socket lengths (indicated in the plans or revised by the drilled shaft length letter).
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-37
4-37
Plan Set- Sheet 7 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-38
4-38
Plan Set- Sheet 7 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-39
4-39
Plan Set- Sheet 7 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-40
4-40
Plan Set- Sheet 7 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-41
4-41
Plan Set- Sheet 7 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-42
4-42
Plan Set- Sheet 7 (Foundation Layout)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-43
4-43
Scour
AbutmentScour
Scour
AbutmentScour
Clear-watercontraction scour
Long-term degradationLive-bed contraction scour
Short-term scour
Drilled Shafts
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-44
4-44
Scour
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-45
4-45
Scour
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-46
4-46
Scour
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-47
4-47
Plan Set- Sheet 8 (Hydraulic Sheet)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-48
4-48
Plan Set- Sheet 8 (Hydraulic Sheet)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-49
4-49
Plan Set- Sheet 9 (Drilled Shaft Details)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-50
4-50
Plan Set- Sheet 9 (Drilled Shaft Details)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-51
4-51
Plan Set- Sheet 9 (Drilled Shaft Details)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-52
4-52
Plan Set- Sheet 9 (Drilled Shaft Details)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-53
4-53
Plan Set- Sheet 10 (Bent/Pier Plan)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-54
4-54
Plan Set- Sheet 10 (Bent/Pier Plan)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-55
4-55
Plan Set- Sheet 10 (Bent/Pier Plan)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-56
4-56
Rock Socket
Rock socket:Portion of shaftIn contact with Rock.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-57
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-58
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-59
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-60
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-61
455-15.6.1 Pilot Hole: When pilot holes are shown in theplans core a pilot hole, prior to shaft excavation, inaccordance with ASTM D 2113 Standard Practice forDiamond Core Drilling for Site Excavation and theDepartment’s Soils & Foundations Handbook using adouble or triple wall core barrel through part or all of theshaft, to a depth of 3 times the diameter of the drilled shaftbelow the tip elevation shown in the plans, as directed bythe Engineer. The Engineer may require the Contractor tocut any core to a total depth below the bottom of the drilledshaft excavation of up to 5 times the diameter of the drilledshaft.
4-61
455-15.6.1- Pilot Hole
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-62
4-62
• Drilled Shafts are not part of CQC
• Department responsible for maintaining log ofPilot Hole, Coring and Shaft Excavation
CPAM 10.5.5
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-63
4-63
455-15.6.2- Cores
455-15.6.2 Cores: Take cores when shown in the plansor directed by the Engineer to determine the character ofthe material directly below the shaft excavation. Provideequipment to retrieve the core from a depth of 5 times thediameter of the drilled shaft below the bottom of the drilledshaft excavation in accordance with ASTM D 2113Standard Practice for Diamond Core Drilling for SiteExcavation. Cut the cores with an approved core barrel toa minimum depth of 3 times the diameter of the drilledshaft below the bottom of the drilled shaft excavation aftercompleting the shaft excavation, as directed by theEngineer. ….
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-64
4-64
455-15.6.2- Cores
455-15.6.2 Cores:Continued
… The Engineer may require the Contractor to cut anycore to a total depth below the bottom of the drilledshaft excavation of up to 5 times the diameter of thedrilled shaft.
For cores or pilot holes, use only a double ortriple wall core barrel designed:
(a) to cut a core sample from 4 to 6 inches indiameter, at least 5 feet in length, and,(b) so that the sample of material cored can beremoved from the shaft excavation and the corebarrel in an undisturbed state, and
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-65
4-65
455-15.6.2 Cores: Continued
… The Engineer will inspect the cores and determine thedepth of required excavation. When considerednecessary by the Engineer, take additional cores. Placethe core samples in suitable containers, identified by shaftlocation, elevation from and to, and job number, anddeliver to the Department within 48 hours after cutting.When called for in the plans, substitute StandardPenetration Tests (SPT) for coring. In such cases, supplythese tests at no additional cost per foot to theDepartment above that bid for core (shaft excavation).
455-15.6.2- Cores
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-66
455-15.6.2 Cores:Continued
…Provide areas for the disposal of unsuitable materialsand excess materials as defined in 120-5 that areremoved from shaft excavations, and dispose of them ina manner meeting all requirements pertaining topollution….
4-66
455-15.6.2- Cores
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-67
4-67
Standard Penetration Test Borings
140 lb.Hammerfree-falling30”Anvil
Split-BarrelDrive sampler
Drill Rod
Seating Spoon6”
Second Increment 6”
SPT Resistance(N-value) is total number of blows to drive sampler the 2nd
and 3rd 6 inch increments
Third Increment 6”
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-68
4-68
• Disassemble spoon, avoiding disturbance to sample
• Note length of sample recovered
• Describe the sample and anychange in material (stratumbreak)
• Carefully place representativeportion(s) in waterproof container
• Properly label, store & transport
Standard Penetration Test Borings
After the sampler has been removed from the borehole and detached from the drill rods, the sampling spoon can be disassembled and the soil in the sampling spoon can be examined. If there is soil within the sampler, the soil boring inspector will record the length of the sample recovered or the percent recovery, describe the soil and record the SPT results. Then the inspector will note the location of each stratum with respect to the bottom of the sampler barrel. The inspector will then place a representative portion of each stratum into a waterproof container (jar) and properly label, store and transport the samples to the laboratory facility. In the report of core borings, the N values will be presented at the left side of each boring.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-69
4-69
• Core runs are generally 5 feet in length
• Most common size is 4 in.
• In accordance with ASTM D 2113
Rock Cores
Core drilling is used to obtain intact samples of rock for testing purposes and for assessing rock quality and structure. Rock coring may be required during the execution of pilot holes, prior to construct production drilled shafts or after the excavation of the shaft to verify the conditions of the rock underneath the shaft bottom. The rock coring is performed usually in segments, called runs, that are typically 5 ft in length. Even though for soil exploration purposes smaller sizes are typically used, in our specifications we require core diameters of 4 to 6”.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-70
4-70
Conventional Rock Coring
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-71
4-71
Core Barrels
Double-tube Core Barrel
Here is a picture of a double tube core barrel. Core barrels may be single-tube, double-tube, or triple-tube. Single barrels are not acceptable in our specifications.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-72
4-72
Rock Coring Video
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-73
4-73
Core Barrel Components
Double tubeCore Barrel
Inner barrelshoe assembly
Diamond bit w/ carbide reaming shell
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-74
4-74
• Fluids
• Pressures and Rates
• Procedural items
Core Drilling Observations
.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-75
4-75
• Amount of water injected versus amount returned
• Losses of fluids
• Color change
Fluids
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-76
4-76
• Hydraulic down pressure
• Water pressure
• Drilling Action (smooth, rough, etc.)
• Changes in drilling rates, revolutions
• Rod drops (depth from and to)
• Loss of circulation
• Drilling Rate (time in Minutes per 1 ft.)
Pressures & Rates
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-77
4-77
• Size and type of core barrel and bit
• Casing size, type, depth
• Core run data
Procedural Items
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-78
4-78
Drilled Shaft Rock Core Log
Form # 700-010-86
http://www2.dot.state.fl.us/proceduraldocuments/forms/ByNumber.asp?index=7
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-79
4-79
Drilled Shaft Rock Core Log
Form # 700-010-86(Cont’d)
http://www2.dot.state.fl.us/proceduraldocuments/forms/ByNumber.asp?index=7
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-80
4-80
Pilot Hole Log
Pilot Hole Log Form #700-010-35
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-81
4-81
Core Handling & Preservation
Core
Tray
Extruded intoa tray
Or
Into core box
Left (Top of Run) Right (Bottom of Run)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-82
4-82
Recovered Rock Cores
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-83
4-83
Recovery %
REC % is defined as the length of core recovereddivided by the length of core run and is expressedand reported as a percentage.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-84
4-84
% REC = Length of Core Recovered
Length of Core Run(100)
EXAMPLE PROBLEM
Length of Run = 5.0’
Recovered 39”
REC =
Can REC be greaterthan 100%?
5.0’ = (100)
Recovery %
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-85
4-85
RQD is defined as the sum of all recovered pieces ofrock core greater than 4” in length divided by the lengthof core run and is expressed and reported as apercentage.
Ref: ASTM 6032
Rock Quality Designation (RQD)
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-86
4-86
(RQD)**DESCRIPTION OF
ROCK QUALITY
0 – 25 Very Poor
25 – 50 Poor
50 – 75 Fair
75 – 90 Good
90 – 100 Excellent
Rock Quality Designation (RQD)
* from Federal Highway Administration
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-87
4-87
Measuring of Core Pieces
CoreDia.
Centerlineof core
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-88
4-88
% RQD = Sum of Pieces >4”Length of Core Run
(100)
Can RQD be greaterthan REC?
PROBLEM
Length ofRun = 5.0’ = 60”
6”
Recovered pieces
9”
14”
7”
Can RQD be greaterthan 100%?
RQD =
%”60”
(100) =
Rock Quality Designation (RQD)
3.5”
3”
2.5”
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-89
4-89
What is that?I don’t know butI’m not going totouch it!
Material Identification
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-90
4-90
SANDS
CLAYS
ROCK
The Inspector needs torecord the materials comingout of the hole.
Material Identification
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-91
4-91
ROCK
Material Identification
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-92
4-92
In its naturalstate maylook like this.
Material Identification
Coming out ofthe hole maylook like this.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-93
4-93
What is Soil ?
Naturally occurring mineral particles that are readily separated into small pieces.
What is Rock ?
Naturally occurring material composed of mineralparticles so firmly bonded together that significanteffort is required to separate the particles.
Material Identification
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-94
4-94
Granular Soils: Sands and Gravel
Fine-grained Soils: Silts and Clays
Organic Soils: Peat, Organic Soils
Soil Type
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-95
4-95
In Florida Drilled Shaft projects: Limestone, Sandstone
Rock
The rock type most encountered in our drilled shaft projects will be limestone, though some sandstones are possible. These type of rocks belong to the sedimentary rocks group. Sedimentary rocks are formed by the cementation of sedimented soils or precipitated materials. Limestone for example is mostly formed by precipitation of calcite, aragonite and typically includes accumulation of shells, corals and fossilized organisms. Our limestone is frequently vuggy and very porous. Parts of the state are known for their sinkhole activity. Even where sinkhole activity is relatively unlikely, the limestone can still be very porous. The relative hardness of the limestone varies widely and can occur over short distances.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-96
4-96
FIELD IDENTIFICATION OF SOILS/ROCKSOILS
Soil Type
Squeezed in Hand & Pressure Released
Visual Appearance
Rolled BetweenThumb & Finger
when MoistW hen Air Dry W hen Moist
SAND Individual grain sizes can be detected. It is free-flowing when in a dry condition.
W ill not form a cast & will fall apart when pressure is released
Forms a cast which will crumble when lightly touched
Can not be ribboned
SILT Contains +80% silt particles with very little fine sand & clay. When dry, it may be cloddy, readily pulverizes to a powder with a soft flour-like feel. Washes off easily.
Forms a cast which can be handled without breaking, but can easily be broken into powdery form by hand
Forms a cast which can freely be handled. When wet, it readily puddles.
Has a tendency to ribbonwith a broken appearance; crumbles easily, feels smooth
CLAY Fine texture- breaks into hard lumps when dry. Difficult to pulverize into a soft flour-like powder when dry. ID based on cohesive properties of moist soil.
Forms a cast which can be handled without breaking
Forms long, thin flexible ribbons. Can be worked into a dense, compact mass.
Forms a cast which can be handled without breaking
ROCK(Terms to describe rock hardness)
Description Field Observations (Characteristics)
Friable
Low Hardness
Moderately Hard
REMEMBER: Rock formations are tough to classify. If it’s hard (+50 blow count on Boring Log Report) and you are not sure what it is-- call it Rock. Collect cuttings whenever recovery is not possible.
Example Descriptions of the Soil ComponentsType Description
REMEMBER- Don’t come home until you answered all your questions… To late after the shaft is installed.
Hard
Very Hard
Easily crumbled by hand, pulverized or reduced to powder and is too soft to be cutwith a pocket knife.
Can be gouged deeply or carved with a pocket knife.
Can be readily scratched by a knife blade; scratch leaves a heavy trace of dust andscratch is readily visible after the powder has been blown away.Can be readily scratched with difficulty; scratch produces little powder and is oftenfaintly visible; traces of the knife steel may be visible
Cannot be scratched with a pocket knife. Leaves knife steel marks on surface.
Sand Describes a sample that consists of both fine and coarse sand particles.Gravel Describes a sample that consists of both fine and coarse gravel particles.Silty Fine Sand Major component fine sand, with non-plastic finesSandy Gravel Major component gravel size, with fine and coarse sand. May contain small amount of
finesGravelly Sand Major component sand, with gravel. May contain small amount of fines.Gravelly Sand, Silty Major component sand, with gravel and non-plastic fines.Gravelly Sand, Clayey Major component sand, with gravel and plastic fines.Sandy Gravel, Silty Major component gravel size, with sand and non-plastic fines.Sandy Gravel, Clayey Major component gravel size, with sand and plastic finesSilty Gravel Major component gravel size, with non-plastic fines. May contain sand.Clayey Gravel Major component gravel size, with plastic fines. May contain sand and silt.Clayey Silt Major component silt size, with sufficient clay to impart plasticity and considerable
strength when dry.Silty Clay Major component clay, with silt size. Higher degree of plasticity and higher dry strength
than clayey silt.
Field Identification of Materials
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-97
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-98
REQUIRED ON ALL FDOTPROJECTS WITH DRILLED
SHAFT FOUNDATIONS
Drilled Shaft Installation Plan
4-98
The Drilled Shaft Installation Plan is a shop drawing describing in detail the Contractor's tools and methods of constructing the drilled shafts. Section 455-15-1.2, Drilled Shaft Installation Plan describes the minimum requirements of the Drilled Shaft Installation Plan. The intent behind having the Contractor submit this item is to cause him to put thought and planning into the project. Normally, contractors want to take a "wait and see" attitude. For most Contractors, that is the extent of their pre-job planning; desiring to rely on flexibility to adjust once on site and the job begins to develop. There are so many unknowns when dealing with subsurface conditions, that the Contractor could benefit himself to pay closer attention to details regarding methods of installation and equipment ahead of time, thereby minimizing some of the unknown factors. A smooth and successful start will usually be carried all the way through the job. As a Drilled Shaft Inspector you must receive a copy of the Contractor's approved Drilled Shaft Installation Plan. You should be familiar with the installation plan well in advance of the start of shaft construction.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-99
4-99
Contractor prepares DrilledShaft Installation Plan
Submits to Engineer, for Reviewat Preconstruction Conference
Changes to Contractorwithin 20 days of receipt
Contractor resubmits toEngineer
Engineer ApprovesPlan
No changes may be madewithout the Engineers approval
Test Shaft
Construction of Shafts
Eng.Review
Review7 Days
Changes Changes
ApprovalApproval
Drilled Shaft Installation Plan
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-100
4-100
455-15.1.2 Drilled Shaft Installation Plan: Atthe preconstruction conference submit a drilledshaft installation plan for review by theEngineer. Final approval will be subject tosatisfactory performance. Include in this planthe following details:
455-15.1.2- Drilled Shaft Install. Plan
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-101
4-101
455-15.1.2 Drilled Shaft Installation Plan: Continued
1. Name and experience record of drilled shaftsuperintendent or foreman in responsible charge of drilledshaft operations. Ensure the drilled shaft superintendentor foreman in responsible charge of the drilled shaftoperations has a minimum of one year of experience ofinstalling drilled shafts of the size and depth shown in theplans and a minimum of three years experience in theconstruction of drilled shafts using the following methods:
a. Mineral slurry,b. Casings up to the length shown in the plans,c. Shaft drilling operations on water under conditions asshown in the plans.
455-15.1.2- Drilled Shaft Install. Plan
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-102
455-15.1.2 Drilled Shaft Installation Plan: Continued
2. List and size of proposed equipment, includingcranes, drills, augers, bailing buckets, final cleaningequipment, desanding equipment, slurry pumps, coresampling equipment, tremies or concrete pumps,casings, etc.
3. Details of sequence of construction operations andsequence of shaft construction in bents or shaft groups.
4. Details of shaft excavation methods.
4-102
455-15.1.2- Drilled Shaft Install. Plan
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-103
List of Equipment
4-103
Note:
Rig
Augers
Core Barrels
Buckets
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-104
455-15.1.2 Drilled Shaft Installation Plan: Continued
5. Details of slurry, including proposed methods to mix,circulate, desand, test methods, and proposed testinglaboratory to document test results.
6. Details of proposed methods to clean shaft after initialexcavation.
7. Details of shaft reinforcement, including methods toensure centering/required cover, cage integrity duringplacement, placement procedures, cage support,and tie downs.
4-104
455-15.1.2- Drilled Shaft Install. Plan
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-105
455-15.1.2 Drilled Shaft Installation Plan: Continued
8. Details of concrete placement, including elapsedconcrete placement times and proposed operationalprocedures for concrete tremie or pump, including initialplacement, raising during placement, and overfilling ofthe shaft concrete. Provide provisions to ensure properfinal shaft cutoff elevation.
9. Details of casing removal when removal is required,including minimum concrete head in casing duringremoval.
4-105
455-15.1.2- Drilled Shaft Install. Plan
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-106
Details of Concrete Placement
Note:
Methods
Tremie
4-106
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-107
4-107
455-15.1.2- Drilled Shaft Install. Plan
455-15.1.2 Drilled Shaft Installation Plan: Continued
10. Required submittals, including shop drawing andconcrete design mixes.
11. Details of any required load tests, including equipmentand procedures, and recent calibrations for any jacks orload cells.
12. Proposed CSL Specialty Engineer to perform, loganalyze, and report the test results.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-108
4-108
455-15.1.2- Drilled Shaft Install. Plan
455-15.1.2 Drilled Shaft Installation Plan: Continued
13. Methods and equipment proposed to prevent displacementof casing and/or shafts during placement and compaction of fill.
14. Provide the make and model of the shaft inspection device,if applicable.
15. Details of environmental control procedures used to preventloss of slurry or concrete into waterways or other protectedareas.
16. Proposed schedule for test shaft installation, load tests andproduction shaft installation.
17. Other information shown in the plans or requested by theEngineer.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-109
4-109
455-15.1.2 Drilled Shaft Installation Plan: Continued
18. For drilled shafts for miscellaneous structuresconstructed using polymer slurry, identify the polymerslurry meeting the requirements of Section 455-15.8.2, thepH and viscosity ranges recommended by themanufacturer for the materials to be excavated and adescription of the mixing method to be used. Submit theMaterial Safety Data Sheets (MSDS) for the product, andcertifications that the polymer slurry and components meetthe requirements of Section 455-15.8.2. Submit the contactinformation for the manufacturer’s representative availablefor immediate contact during shaft construction and therepresentative’s schedule of availability.
455-15.1.2- Drilled Shaft Install. Plan
18. For drilled shafts for miscellaneous structures constructed using polymer slurry, identify the polymer slurry meeting the requirements of Section 455-15.8.2, the pH and viscosity ranges recommended by the manufacturer for the materials to be excavated and a description of the mixing method to be used. Submit the Material Safety Data Sheets (MSDS) for the product, and certifications that the polymer slurry and components meet the requirements of Section 455-15.8.2. Submit the contact information for the manufacturer’s representative available for immediate contact during shaft construction and the representative’s schedule of availability.
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-110
455-15.1.2 Drilled Shaft Installation Plan: Continued
The Engineer will evaluate the drilled shaft installationplan for conformance with the Contract Documents.Within 20 days after receipt of the plan, the Engineerwill notify the Contractor of any additional informationrequired and/or changes that may be necessary in theopinion of the Engineer to satisfy the ContractDocuments. The Engineer will reject any part of the planthat is unacceptable. Submit changes agreed upon forreevaluation. The Engineer will notify the Contractorwithin seven days after receipt of proposed changes oftheir acceptance or rejection. All equipment andprocedures are subject to trial and satisfactoryperformance in the field. 4-110
455-15.1.2- Drilled Shaft Install. Plan
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-111
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-112
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-113
4-113
Learning Outcomes
• Locate Plan Sheet Details Related to Drilled Shafts
• Calculate REC % and RQD
• Identify key elements of the Drilled Shaft Installation Plan
• Identify & interpret applicable 455 Specifications
Student’s Guide Lesson 4-Construction Documents
Version1 -1/15 4-114
4-114
Questions?
4-115
4-116
4-117
4-118
4-119
PLAN EXAMPLES
4-120
4-121
4-122
4-123
4-124
4-125
4-126
4-127
4-128
4-129
4-130
4-131
4-132
4-133
4-134
4-135
4-136
4-137
4-138
4-139
4-140
4-141
4-142
4-143
4-144
4-145
4-146
4-147
4-148
4-149
4-150
4-151
4-152
4-153
4-154
4-155
4-156
4-157
4-158
4-159
4-160
4-161
4-162
4-163
4-164
4-165
4-166