Construction Methods for Tunnel

Embed Size (px)

Citation preview

  • 8/12/2019 Construction Methods for Tunnel

    1/11

    Construction Methods for TunnelConstruction Methods for Tunnel

    I) Drill and Blast

    II) Immersed Tube

    III) Tunnel Boring Machine (TBM)

    IV) Cut and Cover

  • 8/12/2019 Construction Methods for Tunnel

    2/11

    Existing Road Tunnels in Hong Kong

    Drill and BlastDual-10.9Discovery Bay Tunnel

    Construction MethodNo. of CarriagewaysTunnel Length (km)

    Drill and BlastDual-31.25Nam Wan Tunnel

    Drill and BlastDual-33.8Tai Lam Tunnel

    Drill and BlastDual-31.6Cheung Tsing Tunnel

    Immersed Tube + Cut and CoverDual-32Western Harbour Tunnel

    Drill and BlastDual-24Tates Cairn Tunnel

    Drill and BlastDual-20.9Tseung Kwan O Tunnel

    Drill and BlastDual-22.6Shing Mun Tunnel

    Immersed TubeDual-32.2Eastern Harbour Crossing

    Cut and CoverDual-21.3Airport Tunnel

    Drill and BlastDual-21.9Aberdeen Tunnel

    Immersed TubeDual-21.9Cross Harbour Tunnel

    Drill and BlastDual-21.4Lion Rock Tunnel

  • 8/12/2019 Construction Methods for Tunnel

    3/11

    I) Tunnel by Drill and Blast Method

    Required the tunnel to be found in

    competent rock with Grade III or better;

    Geological conditions, Grade III rock maybe very deep below ground levels

    Detailed GI

  • 8/12/2019 Construction Methods for Tunnel

    4/11

    II) Tunnel by Immersed Tube Method

    Considering the characteristics of marine mud, immersed tubetunnel is expected to be found on alluvium, for the following

    reasons:

    The top of the partially dredged mud would be heavily disturbed

    and softened to different degrees along the alignment.Subsequent placing of the tunnel box would cause unevensettlement at the different units.

    Extremely difficult to achieve a good blanket before placing the

    tunnel units, leading to permeation of clay and henceuncontrolled settlement.

    Inadequate bearing capacity from the marine mud duringconstruction when the tunnel units have to be temporarily

    supported by foundation.

  • 8/12/2019 Construction Methods for Tunnel

    5/11

    Tunnel Boring Machine (TBM)

    The Worlds Largest TBM

    (15.2m diameter) is

    required, which is being

    adopted by Shanghai

    Chongming South

    Channel Tunnel (target

    completion by 2007).

  • 8/12/2019 Construction Methods for Tunnel

    6/11

    Tunnel Boring Machine (TBM)

    Uncertainties with regard to construction practicability of

    applying the giant TBM;

    Difficult handling and logistics of such huge TBM;

    A very large working area (approximately 5 ha) for the assemblyand operation of equipment

    Substantial and extensive ground treatment in the areas of

    cavities and fault zones;

  • 8/12/2019 Construction Methods for Tunnel

    7/11

    Tunnel by Tunnel Boring Machine (TBM)

    Restriction:

    Impacts such as water quality and ecology

    Waste generated

  • 8/12/2019 Construction Methods for Tunnel

    8/11

    Cost and Programme Comparison

    with Viaduct OptionReference Projects:

    1. Groene Hart Tunnel Netherlands:

    tunnel length ~7.1km tunnel external diameter = 14.87m

    no reclamation contract period ~4.5yrs, target completion by early 2005 contract sum ~HK$ 4,300M

    2. Chongming South Channel Tunnel Shanghai:

    tunnel length ~8.9km tunnel external diameter = 15.2m

    contract period ~4yrs, target completion by 2007 contract sum ~HK$ 11,500M

  • 8/12/2019 Construction Methods for Tunnel

    9/11

    Tunnel tunnel length ~3.9km tunnel external diameter = 15.2m

    need reclamation estimated programme ~(4.5/7*5 = 3.2yrs) + ~1.5yrs for

    reclamation (require the artificial island completed first forworks area), therefore total ~4.7yrs

    estimated cost ~11500/8.9*3.9 = HKD 5,050M

    For viaduct option(reference to Shenzhen Western Corridor,

    3.3km, 2.5yrs, HKD 2,200M): length of viaduct ~3.9km estimated programme ~3yrs estimated cost ~HKD 2,600M

    Cost and Programme Comparison

    with Viaduct Option

  • 8/12/2019 Construction Methods for Tunnel

    10/11

    General Issue related to Tunnel

    Restriction:

    Restriction to dangerous goods vehicles Cat 1, 2 and 5;

    Traffic speed of tunnel to be limited to 80km/h;

    Connectivity

    No lane changing

  • 8/12/2019 Construction Methods for Tunnel

    11/11

    8914,059Viaduct over sea

    (referenced to Shenzhen

    Western Corridor)

    51418,166Drill and Blast Tunnel

    (including E&M works)

    (referenced to Nam Wan

    Tunnel)

    Annual Recurrent Cost

    (HK$/m2)

    Construction Capital

    Cost (HK$/m2)

    Cost Comparison between Tunnel and Marine Viaduct