43
LOWER BAKER UNIT 4 POWERHOUSE

Construction of Baker Powerhouse #4

Embed Size (px)

Citation preview

LOWER BAKER UNIT 4

POWERHOUSE

INTRODUCTIONS

DANNY ROBERTS FIELD ENGINEER

JASON MCLAUCHLIN PROJECT ENGINEER

PROJECT TEAM

• 32 MW Francis Turbine/Gen • 1000’ Steel Lined Power Tunnel • Subterranean Concrete Structure

and Tailrace: 7,949CY placed • Mechanical and Electrical Building

Systems • Integrated Facility Controls of

Units 3 and 4 • Upgraded Unit 3 controls and

Governor • Synchronous Bypass

THE PROJECT

• Manage In-stream Flows of the Baker and Skagit Rivers

• Restore Facility Generating Capacity Lost in 1960s landslide

• Maintain Water Supply to Lower Baker Adult Fish Trap

PROJECT GOALS

• Design-Build Delivery

• Collaborative Team Approach

• Focus on achieving PSE’s performance requirements

• Phased Design and Construction

PROJECT STRATEGY

CONSTRUCTION

PHASE I - EXCAVATION

PHASE 1 – EXCAVATION

PHASE 1 – EXCAVATION

PHASE 1 – EXCAVATION

PHASE 1 – EXCAVATION

PHASE II – TUNNELING

PHASE II - TUNNELING

• Surge Shaft Tie In

• 1000LF

• Drill and shoot

• 12’ dia steel lining

• Full Penetration Welding

• Carboline Coating

PHASE II - TUNNELING

• Unit 4 Tie-In

• Bottom of 270’ Surge Shaft

• 50LF in 22day shutdown

• Laser Scanned

PHASE II - TUNNELING

PHASE II - TUNNELING

PHASE II - TUNNELING

PHASE III – POWERHOUSE

PHASE III - POWERHOUSE

Draft Tube Elbow Liner

PHASE III - POWERHOUSE

Scrollcase and Stay Vanes

PHASE III - POWERHOUSE

Inlet Pipe lowering into position for fit up to Scroll Case

PHASE III - POWERHOUSE

Fitting Pit Liner onto Scroll Case

PHASE III - POWERHOUSE

• Structural work built concurrently with embedment of turbine components

PHASE III - POWERHOUSE

Generator Foundation Core

PHASE III - POWERHOUSE

• Removable Draft Tube Cone • Tripping Runner/Turbine Shaft

PHASE III - POWERHOUSE

Installing Wicket Gates Runner and Turbine Shaft lowered onto Bottom Ring

PHASE III - POWERHOUSE

Lowering Head Cover over the Turbine Shaft

PHASE III - POWERHOUSE

Lowering Bottom Ring into Powerhouse

PHASE III - POWERHOUSE

Lower Bearing Bracket and Stator prepped for Rotor install

PHASE III - POWERHOUSE

• “Tipping” the Rotor

• 90tons

PHASE III - POWERHOUSE • Shaft Coupling

• Lower Bearing Assembly

PHASE III - POWERHOUSE

• Installing the Slip Ring Housing

PHASE III - POWERHOUSE • Turbine Pit and Cooling

water piping systems nearing completion

PHASE III - POWERHOUSE

• Gate Guides for the Draft Tube Gate

PHASE III - POWERHOUSE

• GSU and Transmission Structures

PHASE IV – TAILRACE

PHASE IV - TAILRACE

PHASE IV - TAILRACE

PHASE IV - TAILRACE

FINISHED PRODUCT

• Tunneling Operation Extremely Accurate

• Achieved all Tolerances in Stacking Unit

• Digital Upgrade of Unit 3 Control Room and hydraulic system

• Commercially Operational 100 days ahead of schedule

• Successful Overall Design Coordination with Owner provided Unit

• No interruptions to ongoing Unit 3 generation

SUCCESSFUL PROJECT