Construction Phase Plan

Embed Size (px)

Citation preview

  • 8/11/2019 Construction Phase Plan

    1/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 1

    CCOONNSSTTRRUUCCTTIIOONNPPHHAASSEEPPLLAANN

    ((DDEEMMOOLLIITTIIOONN))

    Demolition and Site Clearance ofDawson House, Public Library and

    Community Centre, Redcar

    REVISION HISTORY

    REVISION DATE REVISION DETAILS

    HSE Literature reproduced under the terms of the Click Use Licence.

    9 March 2011

    A Buckler (Haulage) Ltd24-28 Marsh Road Garage

    Middlesbrough

    TS1 5LD

  • 8/11/2019 Construction Phase Plan

    2/175

  • 8/11/2019 Construction Phase Plan

    3/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 3

    Al though every at tempt is made to make this Health and Safety Phase Plan si te specif ic , somesections of this document will be generic and not necessarily applicable to this pro ject.

    SECTION1 DESCRIPTION OF THE PROJECT

    Introduction

    This Construction Phase Plan (Demolition) is prepared under Regulation 23(1) & (2) of the Construction(Design and Management) Regulations 2007 (in line with the recommendations made in the ApprovedCodes of Practice (ACOPs) L144.

    This Construction Phase Plan (Demolition) describes the specific arrangements and duties relating toHealth and Safety for this project. It includes factors relevant under the Health and Safety at Work Act1974, the Construction (Design and Management) Regulations 2007, and the Management of Healthand Safety at Work Regulations 1999.

    NB: Prior to any work commencing on this project a copy of this document must be forwardedonto the Client/CDM Co-ordinator for approval under Regulation 16(a) (b) of the CDM Regulations2007.

    A Buckler (Haulage) Ltd has the right to amend the Demolition Phase Plan/Method Statement ifnecessary; details will be forwarded to the Client/CDM Co-ordinator for approval.

    Description of Project

    Demolition and Site Clearance of Dawson House, Public Library and Community Centre, Redcar

    Project Site Plan

    LIBRARY

    COUNCILOFFICES

    SINGLESTOREYBUILDING

  • 8/11/2019 Construction Phase Plan

    4/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 4

    Contract Details

    Site Address: Dawson HouseRidley StreetRedcarTS10 1RG

    Programme

    Est. Start Date:

    Est. Duration of Work:

    14/3/11

    16 Weeks

    Hours of Work and Delivery of Materials:-

    Delivery of materials to be arranged to ensure no disturbance to local residents.

    Weekend working to be agreed with Client

    *Abnormal loads will be accompanied by a support vehicle whilst in transit.

    Monday to Fridays 8.00 hrs 17.00 hrs

    Saturdays 8.00 hrs 12.00 hrs

    *Comments

  • 8/11/2019 Construction Phase Plan

    5/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 5

    Details of Project Team

    Client

    Contact::Address:

    Tel:Email:

    Alan LoganRedcar & Cleveland Borough CouncilRegeneration Services DirectorateRedcar & Cleveland HouseKirkleatham StreetRedcarTS10 1RT01642 444 [email protected]

    CDM Co-ordinator

    Contact::Address:

    Tel:Email:

    CDM CoordinatorChris DixonTurner & Townsend Project ManagementVictoria HousePearson Way

    ThornabyTS17 6PT01642 611 [email protected]

    Principal Contractor

    Contact::Company Name:Address:

    Tel:Email:

    Mark Love/Martin LoveA Buckler (Haulage) Ltd24/28 Marsh Road GarageMiddlesbroughTS1 5LD01642 [email protected]

    ContractorContact::Company Name:Address:

    Tel:Email:

    Other Members of the Project Team

    Contact::Address:

    Tel:Email:

    Project ManagersBen Hughes/Paul DensonDeloitte LLP

    5 New York StreetManchesterM1 4JB0161 455 [email protected]@djdeloitte.co.uk

  • 8/11/2019 Construction Phase Plan

    6/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 6

    Safety Adviser

    Tel:Email:

    Northern Safety Ltd109B Allison AveTeesside Industrial EstateThornabyStockton-on-TeesTS27 9LY01642 754 880les/@northernsafeltyltd.co.uk

    H & S Executive

    Address:

    Tel:

    Arden HouseRegent CentreRegent Farm RoadGosforthNewcastle-upon-TyneNE3 3JN0191 202 6200

    Local Accident & Emergency Hospital

    Address:

    Tel:

    James Cooke University HospitalMarton RoadMiddlesbrough

    01642 850850

    Extent and Location of Existing Records and Plans

    Existing Drawings/ Site Sketches

    Refurbishment orDemolition AsbestosSurvey

    Is an Asbestos Survey required for this Project Yes

    An Asbestos survey is in progress at the time of preparing thisdocument

    Is there an Asbestos Survey in place Yes No

    Types of Non-Licensed Asbestos left in building

    Cement Asbestos - Roof/Wall Sheets

    Cement Asbestos - Gutters/Down-comers

    Cement Asbestos - Flues

    Textured Coating *

    Floor Tiles

    Toilet Cisterns

    Sink Pads

    Flash Pads

    (See Statement of Cleanliness after Textured Coating Removal pro-forma included in the appendix)

    Ecological Survey

    Has a Bat Survey been carried out?Yes

    No

    Has a Tree Survey been carried out?Yes

    No

    Other?Yes

    No

  • 8/11/2019 Construction Phase Plan

    7/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 7

    Description of Site and Redundant Building/s

    Building Identification No. 1 Dawson House

    Former Use Council Offices Condition Good

    Wall Structure Concrete Roof Structure

    Floor StructureGround

    Concrete Floor StructureFirst Floor etc

    No of Floors Two HighlightedProblems

    Lean-to Canopy withboundary wall

    Other Details

    Building Identification No. 2

    Former Use Library Building Condition Fair

    Wall Structure Brick and metal cladding Roof Structure Metal claddingFloor StructureGround

    Concrete Floor StructureFirst Floor etc

    Concrete

    No of Floors Two HighlightedProblems

    Known to have aBasement

    Other Details

    Building Identification No. 3Former Use Single Storey Building Condition Good

    Wall Structure Brick Roof Structure Tiles

    Floor StructureGround

    Concrete Floor StructureFirst Floor etc

    No of Floors One HighlightedProblems

    Adjacent footpath andparking meter

    Other Details

  • 8/11/2019 Construction Phase Plan

    8/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 8

    SECTION 2 COMMUNICATION AND MANAGEMENT OF THE PROJECT.

    The responsibility of the Principal Contractor involves the day to day running of the site, site safety andthe organisational aspects of the Demolition Phase Plan. They will also communicate and liaise with theCDM Co-ordinator or Client when necessary. All employees will be encouraged to take reasonablepersonal care and co-operate where necessary to prevent harm to themselves or others.

    Organisation and Arrangements for Liaison

    Management Structure

    Contracts Manager

    Name:

    Contact No:

    Mark Love/Martin Love

    01642 243399

    Visiting Contracts Manager.

    Responsible for overseeing project to ensure work is carried out safely in the first instance and toschedule, in accordance with documentation and best practice.

    Site Supervisor

    Name:

    Contact No:

    Terry Collett

    07867 786198

    Full time Supervisor.

    Responsible for day to day running of project and ensuring all work is completed in a safe manner.Responsibilities include maintaining and updating the health and safety on site.

    First Aider

    Name:

    Contact No:

    Elliot Love

    07876 591065

    First Aid Facilities

    A qualified First Aider/ Appointed Person (depending on the size of the site) will be on site at all times.First aid boxes will be provided and checked regularly by the First Aider or Appointed Person. The siteFirst Aider/ Appointed Person will be identified during the site induction and information posters placedon the site notice board

  • 8/11/2019 Construction Phase Plan

    9/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 9

    Arrangements for Managing, Monitoring and Review

    The Health and Safety Goals:

    The objective is to complete the works within the contract timescale, having due regard to the welfare ofall those employed on the project, without putting at significant risk their health and safety, and that of

    any others who may be affected by the project.

    The Management of A Buckler (Haulage) Ltd recognises that, as employers, they and their employeeshave duties placed upon them by the Health and Safety at Work Act 1974.

    A Buckler (Haulage) Ltd will conduct its activities such that it complies with all relevant statutorylegislation, approved codes of practice and general guidelines.

    It is the Policy of the Management to:-

    Provide a place of work that is safe and without risk to health and welfare of all its; employees,independent contractors, members of associated companies, customers and the general public so

    far as is reasonably practicable. Make safety an integral part of the Management of the Company.

    Prevent accidents/incidents occurring on site.

    Monitor the performance of activities against this Demolition Phase Plan.

    Provide appropriate training for employees and others where necessary.

    Seek to continually improve safety, health and welfare performance.

    Regularly review the Demolition Phase Plan, introducing improvements where possible.

    Consult with employees to ascertain measures required to increase awareness of health and safetyand to ensure that all necessary measures are taken to make this Plan effective.

    Monitoring and Review of Health and Safety Issues

    Health and safety will be an item on the agenda of all project meetings. A report/minutes will be kept onany health and safety issues that have arisen since any previous meetings and subsequent actions. Asa minimum, these will include:-

    Time lost due to accidents Hazard spotting statistics (number, type and action) Safety inspections and audits (key issues, actions) HSE visits (observations, enforcement notices, actions) Implications of developing design issues and changes Safety goals for the project and arrangements for monitoring and review

    Monitoring and Review of Health and Safety Performances

    At various times during the demolition, A Buckler (Haulage) Ltd will carry out health and safetyinspections of the work on site. The purpose of these inspections is to ensure that they are not in breachof their own statutory obligations. All employees, sub-contractors and their employees will be expectedto co-operate and assist with these inspections and to act on any reasonable suggestions that areoffered. As requested by A Buckler (Haulage) Ltd an independent safety officer will visit site to carryout inspections, action taking immediately on their recommendations followed by a detailed report.

  • 8/11/2019 Construction Phase Plan

    10/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 10

    Arrangements

    Liaison between Parties on Site

    A Buckler (Haulage) Ltd will ensure contractors attend meetings held on site to maintain up to datecontact and exchange of any safety relevant information. Alterations to working methods or personnel

    involved in the project will be detailed and relayed to the A Buckler (Haulage) Ltd and others that itmay affect.

    Any other information arising that may have an affect upon other personnel working on site will benotified at the earliest opportunity.

    Consultation with the Workforce

    Each morning before work commences the Site Manager/Supervisor will discuss the days workprogramme with the operatives on site. All hazards associated with the work will be highlighted to therelevant personnel. In addition, periodic safety talks on subjects relevant to the work being carried outwill be given by the Site Manager/Supervisor or the visiting Safety Adviser. The Operatives are

    encouraged to participate in these talks and bring to light any problems, hazards or safety issuesencountered on the project. Attendance records are kept of these talks. A Buckler (Haulage) Ltdoperates an open door policy where personnel are encouraged to participate in the meetings and alsobring to light any concerns, hazards or safety issues encountered during the project.

    The Selection and Control of Contractors

    A Buckler (Haulage) Ltd employ a system of assessing potential sub-contractors competency whichincludes a health and safety questionnaire. All accepted contractors are reviewed to determinecontinued suitability/competency. The assessment/review will consider all aspects of the contractorsmanagement and all operatives relevant technical capabilities. The Contractors policies, practices, risk

    assessments and safe working procedures and miscellaneous safety matters will be explored in depthalong with relevant recent experience. The information collected during the assessment/review will bekept updated as necessary to aid future reviews. The information obtained during this review mayinclude the following:

    Company Safety Policy Statement Site Safety Responsibilities Risk and CoSHH Assessments Method Statements Competency, Training Records and Qualifications Provision of Protective Clothing Site Accommodation Provision of Toilet and Washing Facilities Monitoring of Safe Systems of Work Safety performance and inspection reports Accidents Statistics HSE Actions

  • 8/11/2019 Construction Phase Plan

    11/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 11

    Site Security, Access and Egress Arrangements

    A Buckler (Haulage) Ltdwill erect a perimeter fence around the site where required and warning signsbearing the company name will be placed along the fence at suitable locations to ensure personsapproaching are aware of the demolition site, exclusion zone and the dangers therein.

    All visitors to the site will enter through the main entrance gate and report to the site supervisor/manager.

    They will be required to sign in and out to ensure the site management are aware how many people areon site in the event of an emergency. Visitors will be required to undergo site induction, wear safetyequipment i.e. safety helmet, hi-visibility attire, safety footwear and will be accompanied by arepresentative on site at all times.

    The perimeter fence will be checked on a daily basis to ensure that it is maintained in good condition andremains secure. Gates into the site will be secure at all times and the keys positioned adjacent to themto allow demolition personnel safe, swift escape in an emergency. When wagons enter and leave thesite they will be aided by a banks man who will open and close the gates.

    If the exclusion zone (hazardous area) extends close to or beyond the site boundary for any period oftime standby men will be deployed to ensure that any unauthorised personnel, i.e. public, are directed

    away from the area.

    All mobile plant left overnight will be parked safely and locked to prevent anyone tampering with them.The keys for the machines will kept secured or removed from site by the Site Supervisor or nominatedresponsible person.

    Where agreed overnight or out of hours security will be engaged to maintain site secure.

    Site Induction

    Before attending site everyone must attend the site induction, the induction will identify information on:-

    Site specific instructions,

    Site rules, Welfare facilities

    Emergency procedure

    First aid facilities and provisions

    Refer to the Site Induction which is to be completed by the Supervisor/Manager on site.

    NB: Site Induction proforma available in appendix if required.

    Personnel and Training

    The work will be carried out by experienced competent, demolition operatives supervised by an

    experienced Site Supervisor/Manager.

    Onsite training will take the form of initial inductions and periodic tool box talks given by the SiteManager/Supervisor or Safety Advisers. Attendance records are kept of these safety talks and will beavailable for inspection on site.

  • 8/11/2019 Construction Phase Plan

    12/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 12

    Welfare Facilities and First Aid

    A Buckler (Haulage) Ltd will provide welfare facilities for their employees. Site cabins and/or suitablerooms will be made available for breaks and when bad weather stops work. They will be equipped withheating, tables and chairs, a means of heating food and boiling water, wash basins, showers, drying andtoilet facilities. These facilities will be conveniently located with good access, lighting and ventilation.They will be properly maintained and kept clean.

    A qualified First Aider/ Emergency First Aid at Work Person (depending on the size of the site) will be onsite at all times. First aid boxes will be provided and checked regularly by a nominated person. The siteFirst Aider/ Emergency First Aid at Work Person will be identified during the site induction andinformation posters placed on the site notice board.

    Emergency Procedures

    Local emergency services will be summoned in the event of an accident or incident. Nominated accessroutes will be kept clear of obstruction at all times to ensure safe access for emergency vehicles.

    Operatives will be informed during their site induction (see induction format enclosed) and subsequentsafety talks, that in the event of an emergency they must go directly to the nearest muster point andawait further instruction.

    A daily log will be kept to record the personnel on site at any one time and the area that each person isworking in if appropriate, to provide essential information in the event of an emergency.

    Accident Reporting and Investigation

    An accident book will be kept on site to record all accidents. In accordance with Health and SafetyRegulations incidents, diseases or injuries classified under the Reporting of Injuries, Diseases andDangerous Occurrences Regulations`(RIDDOR) will be notified to the Health and Safety Executive

    (HSE) by the employees employer within the specified timescale and copied to the Principal Contractorif applicable.

    Accidents to non employees arising from activities on the site will be will be reported to and managed bythe Principal Contractor.

    In the event of an accident or incident (near miss) the Site Manager will be notified immediately who willin turn notify their Safety Adviser. The scene of the accident/incident will be visited and inspected by theSite Manager and Safety Adviser, the injured person(s) and witnesses will be questioned. The SiteManager and Safety Adviser will report on the findings of the investigation including the underlyingcause(s) of the accident/incident and all actions to be implemented to prevent a recurrence. This reportwill be forwarded to the Managing Director of A Buckler (Haulage) Ltdwho will forward this information

    to the Principal Contractor, CDM Co-ordinator and Client.

    Production and Approval of Risk Assessments and Written Systems of Work

    A Buckler (Haulage) Ltdwill ensure that risk assessments are carried out for all demolition activitiesand the findings incorporated into safe systems of work. The risk assessments must be reviewedregularly and revised as necessary. A Buckler (Haulage) Ltd site manager will approve all riskassessments and safe methods of work before the work is carried out.When agreed methods/procedures have been produced these will be adhered to by all employees. Anydeviation or alteration will only be allowed on receipt of appropriate authorisation from seniormanagement and followed up with immediate written changes to the method statement. The only

    possible exception to this rule will be where an emergency situation arises which requires immediateaction.

  • 8/11/2019 Construction Phase Plan

    13/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 13

    Site Rules

    All operatives on site will undergo induction training by the site manager/supervisor before commencingwork covering all aspects of safety and hazards associated with the site including an explanation of ABuckler (Haulage) Ltdsmethod statement and emergency procedures.

    Site Rules

    The site will be secured from unauthorised entry by perimeter fencing, with appropriate warningsigns, any access or created openings must be secured immediately.

    At the end of the working day all means of access, e.g. steps, ladders left in position must besecured to prevent unauthorised persons (especially children) accessing the site and hazardousareas.

    All personnel on the site must be inducted as to the site nature and specific hazards. All plant, equipment used on site must be compliant with the Provision and Use of Work Equipment

    Regulations 1998 (PUWER), maintenance and relevant certificates must be kept on site.

    All substances to be used or handled on site must have the CoSHH assessment available on site foroperatives to consult.

    Smoking may be prohibited on site or only allowed in specified areas, and the possession or use ofalcohol and drugs is prohibited on site.

    Operatives must maintain the site welfare facilities in a tidy safe condition for the duration of theworks.

    Operatives must wear the standard personal protective equipment (PPE) required on site at all timesand additional appropriate RPE where necessary for the tasks they are performing.

    Operatives are not to be allowed to use audio equipment on site. Operatives must comply with the Demolition Phase Plan, work to their safety method statements and

    abide by all safety signs at all times.

    All operatives and contractors on site must co-operate in the interest of health and safety. All operatives on site must conduct themselves and perform their duties of work on site in a safe

    manner. Operatives must check their plant and equipment prior to use, reporting defects or problems to their

    supervisor, removing the plant or equipment from use where necessary.

    All work areas must have clear, well maintained signage as to the works being carried out. Operatives must have the designated firefighting equipment on hand to cover hot works carried out

    on site; if necessary a hot work permit must be available.

    Prior to excavation work being carried out the Operative/Contractor must, have a permit to work,check for underground services and deploy designated side supports and edge protection measures.

    Protection and guarding that is removed to allow work to be carried out must be immediatelyreplaced once the work is complete. Protection and guarding must not be removed if it creates anunsafe working area.

    All waste materials must be collected and removed from site at regular intervals.

    No burning of rubbish is allowed on site. Acts of threat or violence will not be tolerated and any offender will be removed and permanently

    excluded from the site.

    These rules may be updated as the nature of the work proceeds.

  • 8/11/2019 Construction Phase Plan

    14/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 14

    Fire and Emergency Procedures

    Site Specific Emergencies and Procedures

    Emergency procedures are the responsibility of the A Buckler (Haulage) LtdSite Manager who willensure that all personnel under their control will attend site inductions where they will be informed of the

    emergency procedures.

    Emergency procedures must be site specific and will form part of the site induction (site induction formincluding in document)

    Fire Prevention on Demolition Sites

    All A Buckler (Haulage) Ltdemployees are aware of the hazards of fire on demolition sites and thus aretrained and vigilant in ensuring sites are kept clear of unnecessary flammable materials and fireextinguishers are readily available. Supervisors who control demolition sites will ensure that all sourcesof ignition are controlled such as burning activities, electrical equipment, smoking and fires. They willensure that:

    Where applicable a hot work permit will be issued

    That all burning equipment is in working order and that operatives are suitably trained.

    Water hoses or extinguishers or both will be available during hot work procedures.

    Before burning activities take place all combustible materials will be removed and stored safely

    Burning activities will cease at least one hour before the end of the working day and followed byan inspection to ensure that all flames have been extinguished and that no hot spots are evident.Where applicable hot spots will be dampened.

    Flammable waste materials will not be allowed to build up and controlled by continual removal.

    That all electrical equipment is suitable for the task and suitably maintained.

    There will be no fires on site

    Smoking will be prohibited or restricted to safe areas identified by the site supervisor Before leaving site all flammables used in demolition activities such as diesel or petrol will be

    stored safely.

    The site at the end of each working day will be made secure to stop unauthorised access

  • 8/11/2019 Construction Phase Plan

    15/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 15

    SECTION 3 ARRANGEMENTS FOR CONTROLLING SIGNIFICANT RISKS

    Traffic Management Plan

    Access to the site will be via The site areas are located within Redcar and Cleveland town centreand are accessed of the A174, A1042 (Kirkleatham Lane) and locally via Kirkleatham Street andCoatham Road,*Project Site Plan refer to section 1.1.1

    Fire and emergency access routes will be kept free from obstruction at all times. Agreed access and egress routes on the site will be observed at all times. Footpaths and roads will always be kept clear of obstructions, including parked cars. Footpaths and roads will be protected and maintained in a condition suitable for vehicular and

    pedestrian traffic.

    Materials will not be stored on or near roadways, paths or other areas where they may constitute ahazard.

    Traffic control and warning lights will be made available for use where thoroughfares are obstructed. Banksmen will be employed to assist in traffic movements on and off the demolition site with

    consideration for other road users and pedestrians.

    In the event of an emergency a nominated person will meet the emergency services at the entrance

    to the site and guide them to the emergency. Upon arrival to site a banksman will take control of plant. Safe routes to separate pedestrians from plant and vehicles will be established on site as soon as

    practicable.

    Wherever possible, traffic will enter the site in forward gear and, after unloading/loading, drive roundand leave the site without the need to reverse.

    Where necessary a separate reversing area will be set up excluding all pedestrians. Vehicles not fitted with an audible reversing alarm/flashing beacon will have a banksman present

    when reversing or carrying out difficult manoeuvres on site.

    Banksmen will always wear high visibility clothing. A safe parking area will be established and personnel will be made aware. Delivery vehicle movement will be controlled on site and will follow the site rules. Safety signs will be clearly posted to make personnel on site aware of traffic hazards. Operatives must not drive or interfere with any vehicle unless authorised and trained to do so. The use of mobile phones whilst driving or operating plant is forbidden. Acts of threat or violence will not be tolerated and any offender will be removed and permanently

    excluded from the site.

    Drivers must obey the site traffic management system including speed restrictions. The above measures will be monitored during safety audits and personnel will be made aware of the

    control measures at the induction and tool box talks.

    Ensure,so far as is reasonably practicable, demolition sites under control are organised in such away that pedestrians and vehicles can move safely.

    Designated traffic routes will be suitable for the persons or vehicles using them, sufficient in number,

    suitably positioned and of sufficient size. Suitable steps will be taken to ensure that vehicles can use traffic routes without causing danger to

    the health or safety of persons nearby.

    Pedestrian accesses which lead onto a traffic route will be sufficiently separated to enable them tosee approaching plant and vehicles, from a place of safety.

    Adequate separation between vehicles and pedestrians will be established to ensure safety or,where not reasonably practicable, other means of protecting pedestrians and effective arrangementsfor warning, person/s liable to be crushed or trapped by a vehicle, of its approach.

    Every traffic route, where necessary for reasons of health or safety, will be clearly indicated bysuitable signs regularly checked and properly maintained.

    Traffic routes will be kept free from obstruction and have sufficient clearance for its use, so far as isreasonably practicable.

  • 8/11/2019 Construction Phase Plan

    16/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 16

    Location of Existing Services see plan reference *Isolated

    Electricity Client/ Principal Contractor to affirm

    Gas Client/ Principal Contractor to affirm

    Telephone Client/ Principal Contractor to affirm

    Water Client/ Principal Contractor to affirm

    Public Sewers Client/ Principal Contractor to affirm

    Drainage Client/ Principal Contractor to affirm

    Others Client/ Principal Contractor to affirm

    The A Buckler (Haulage) Ltd will ensure all above services are isolated and letter ofconfirmation received prior to any work commencing.

    NB *The isolated tick box is to be completed by the site supervisor prior to any workcommencing.

    Services on Site NOT Isolated (This FULL Section to be completed by the Site Supervisor)

    Electricity

    GasTelephone

    Water

    Public Sewers

    Drainage

    Others

    Reason why no isolation:

    Precautions taken to ensure safe working if any services are left live:-

    Are all Supervisors, operatives and any sub-contractors aware of any live services: (see ToolBox Talk Register below)

  • 8/11/2019 Construction Phase Plan

    17/175

  • 8/11/2019 Construction Phase Plan

    18/175

  • 8/11/2019 Construction Phase Plan

    19/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 19

    Access to work above ground level will be attained by:-

    Existing ladders, walkways, landings and platforms

    Scaffolding, tube/clip or patent system, erected by a competent Sub-contractor,

    Tower Scaffold.

    MEWPs Boom/ Scissor lift type of machines.

    Other means

    Comments:

    Where possible the need for working at heights will be avoided, if unavoidable an assessment will becarried out to identify the safest overall means of completing the work. A safe working platform andcollective safety measures will take priority over personnel protective equipment.

    All personnel will be fully trained in safety and safe working procedures when working at height, thistraining will be carried out through external health and safety training along with site induction's and toolbox talks.

    Controlling Lifting Operations

    All lifting operations will be carried out by competent personnel working to agreed procedures andregulations, and utilising properly designed, manufactured, tested and maintained equipment. All craneswill have been tested and examined before being put to use on site. Copies of test certificates,examinations and inspections will be available for inspection when required.

    All ropes, chains, slings and other lifting gear will be clearly marked with their safe working load (SWL)and an identification mark. They will be examinedevery six months and a record of the examination

    maintained.

    A Buckler (Haulage) Ltd must ensure that an appointed person is established and a lift supervisor isavailable on site to supervise the lift. There is a clear system of communication established and agreedbetween the person in charge, the Crane Driver(s), the banksmen and the riggers handling the load.The Crane is set up in the agreed location as per the design drawing.

    The Maintenance of Plant and Equipment

    A Buckler (Haulage) Ltd will ensure that all plant and equipment brought onto site for use byemployees will be maintained tested and certified to the appropriate standards.

    Documentation of the above will be requested from any sub-contractor or Hire Company and filed on siteprior to the use of the plant and equipment

    Upon arrival on site the equipment/plant will be inspected to ensure it is in good condition and thatadequate operating instructions are available where appropriate, including any Safe Working Load(SWL)or safety critical operating conditions. Regular servicing and maintenance will be carried out; anydefects arising will be rectified immediately. Only employees authorised and designated by A Buckler(Haulage) Ltd, and holding the appropriate CPCS (Construction Plant Competency Scheme) or similarqualification will be allowed to operate plant and machinery

  • 8/11/2019 Construction Phase Plan

    20/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 20

    Work on Excavations and Work where there are poor Ground Conditions

    A Buckler (Haulage) Ltd will take all practicable steps, where necessary to prevent danger to anyperson, including the provision of supports or battering, to ensure:-

    a) an excavation or part of an excavation does not collapse

    b) no material from the side, or adjacent to an excavation is dislodged or fallsc) no person is buried or trapped in an excavation by material which is dislodged or falls

    Suitable steps will be taken to prevent, any person, equipment, or material falling into an excavation andthe area around the excavation from being overloaded by equipment or material. A Buckler (Haulage)Ltd will not allow demolition work to be carried out in an excavation where any supports or battering isnot in place unless:-

    (a) The excavation, work equipment and materials which affect its safety, have been inspected by acompetent person:-

    (i) At the start of the shift in which the work is to be carried out.

    (ii) After an event likely to have affected the strength or stability of the excavation.(iii) After any material unintentionally falls or is dislodged.

    The person who carried out the inspection is satisfied that the work can be carried out there safely.

    When the person carrying out the inspection is not satisfied and informs A Buckler (Haulage) Ltdworkwill cease until the matter has been satisfactorily remedied.

    Work on or Near Water where there is a Risk of Drowning

    Where in the course of demolition work, persons are liable to fall into water (liquid) with a risk ofdrowning, A Buckler (Haulage) Ltd will ensure appropriate steps are taken, so far as is reasonablypracticable, to prevent persons falling. The risk of drowning in the event of a fall will be minimised andsuitable rescue equipment will be provided/maintained so that any person falling can be promptlyrescued.

  • 8/11/2019 Construction Phase Plan

    21/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 21

    Hot Work

    No hot work will be carried out unless the necessary permit to work has been completed and the controlsdetailed observed.

    Operatives will be fully trained and conversant with the techniques of Oxy Propane cutting of metals andwill be provided with suitable clothing, protective equipment and appropriate safety items. Where

    required, medical checks will be carried out at requisite intervals and the results recorded.

    All personnel engaged in flame cutting operations which are contaminated with lead will wear respiratoryprotective equipment of a type approved by the Health and Safety Executive (HSE), usually a NorthN7700 Twin Filter Respirator. All such work will comply with the Approved Code of Practice for theControl of Lead at Work Regulations.

    Whenever hot work is carried out on site, the operatives will have a fire extinguisher and/or charged uphose at hand and be trained in their use. At the end of each shift and before meal breaks, an inspectionof the area will take place to ensure there is no risk of fire. Following hot work, the area will be wetteddown before the end of each day if necessary.

    All hot work will cease half an hour before the end of a shift and a check of all hot work areas will becarried out prior to operatives leaving site.

    Asbestos

    In the event of any furthersuspect asbestos being encountered during the demolition work, all work willcease and the Client will be informed.

    Once the nature of the asbestos contaminated materials (ACM) has been verified an additional orreplacement Plan of Work will be issued by an Asbestos Removal Company covering all aspects of theasbestos removal work to conform to the necessary Asbestos Regulations and current Codes ofPractice.

    All reportable asbestos materials on site will be removed by the Licensed Contractor, notification of theremoval and Asbestos Plans of Work will be required before any work commences and approved by theClient/CDM Co-ordinator.

    All materials containing asbestos found in buildings, plant, pipe work or equipment will be handledaccording to the relevant safety legislation. All asbestos waste will be transported to a nominatedlicensed waste disposal site.

    The cost of any additional work due to the discovery of asbestos will be agreed between A Buckler(Haulage) Ltdand the Client.

    Dealing with Contaminated Land

    When working on land previously used (e.g. brown field sites) there may be a risk of contamination fromprevious processes carried out on the land. An assessment of the potential risk to health will be carriedout prior to commencement of the project. Protective measures required will be put in place to preventexposure.

    (If applicable any surveys will be included in the annex of this document.)

    Where a hazard is identified during the work in progress A Buckler (Haulage) Ltdwill put in place anyprotective measures required and inform the workforce of the risks involved and the controls to beimplemented. In addition A Buckler (Haulage) Ltdwill ensure any contractors or sub-contractors willalso provide the same assessment and controls required.

  • 8/11/2019 Construction Phase Plan

    22/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 22

    Manual Handling

    A Buckler (Haulage) Ltd willso far as is reasonably practicable, avoid the need for their employees toundertake any manual handling operations at work which involve a risk of them being injured. ABuckler (Haulage) Ltd will provide any equipment that it required as identified by the site specific riskassessment, assess any hazardous manual handling operations that cannot be avoided and put in place

    control measures to eliminate and reduce potential injury. Have equipment available for manualhandling purposes such as wheel barrows, sack barrows, bottle trolleys and bogies for example.

    Monitor manual handling operations and where required reassess the tasks and put in place anyadditional controls.

    (*See Manual Handling Assessment pro-forma is included in the appendix)

    Health Hazards

    Safety equipment that may be needed on site includes face masks and filters that conform to HSEapproval lists, respiratory equipment, protective clothing/overalls, gloves, footwear and full body safety

    harnesses. First aid and safety equipment will be available for use in an emergency.

    All A Buckler (Haulage) Ltd staff and contractors shall wear the appropriate protective clothing,identified in the Risk and COSHH Assessments, at all times. In the event of failure by a contractor toprovide or use the necessary protective clothing or equipment the Site Manager will stop the work untilthe problem has been remedied satisfactorily and safely.

    Operatives coming across any unknown substance will report the substance and its location to hissupervisor/site manager immediately who will inform A Buckler (Haulage) LtdPrincipal Contractor, whowill in turn arrange for the substance to be identified and dealt with accordingly.

    Storage of Materials

    Diesel or oil stored on site will be stored within a bund or specific bunded container to prevent spillagesfrom entering any water courses.

    Oxygen and Propane gas cylinders or packs will be stored safely within a secure, well ventilated areafitted with a lock. Propane will be stored separate from oxygen with a distance of at least three metresbetween them. Empty gas bottles will be stored separately.

    All flammable materials/substances held on site will be kept to minimum quantities and stored at leastfive metres away from any buildings; the location will be designated and clearly identified as a nosmoking area.

    Hazardous Materials

    All known hazardous materials will be covered by a current Material Safety Data Sheet (MSDS) andCoSHH assessment which will be made available for personnel to read. In addition personnel will beinstructed in the safe working procedures necessary before they come into contact with such materials.These procedures will be highlighted in the induction course or subsequent tool box talks. Any healthmonitoring required will be arranged in line with the requirements of the legislation concerned.

    Hazardous wastes will be stored in appropriate lockable containers, separate from other waste materialto prevent cross contamination.

  • 8/11/2019 Construction Phase Plan

    23/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 23

    Noise

    Under the Control of Pollution Act 1974, Part 3, Environmental Protection Act of 1990 and the Control ofNoise at Work Regulations 2005, noise is a recognised form of pollution and as such can be classified asa nuisance. The Control of Noise (Codes of Practice for Construction and Open Site) Order 1984 giveslegal approval for BS 5228, parts 1 & 2, 1997. This provides information on noise and noise control onconstruction and demolition sites.

    Every attempt shall be made to control/minimise noise at source.

    A Buckler (Haulage) Ltdoperatives working on demolition sites (particularly those near dwellings) willtake all reasonably practicable steps to minimise the noise generated on the site and thereby avoid aLocal Authority Notice (under Section 60 of the Control of Pollution Act 1974)being served.

    On site where construction or demolition works is in progress contractors have a responsibility to seethat activities are carried out in the quietest practicable manner. Where noisy activities are unavoidablethe disturbance will be minimised/attenuated by choice of technique, timing, shielding or protection asappropriate.

    On all moving plant, noise levels will be minimised by being vigilant on points such as:-

    Stopping rattles (e.g.: by tightening covers etc.).

    Throttling down engine when idling.

    Fitting engine covers and keeping them closed.

    Keeping tools sharp to lessen frictional noise.

    Not dropping items, e.g.: into skips, unnecessarily.

    If noise levels are still unacceptable high and no reasonably practicable alternative is available, ABuckler (Haulage) Ltdoperatives and contractors will use methods such as:-

    Screening, e.g.: by earth banks. Silencing, e.g.: by fitting silencers, mufflers, shield enclosures or barriers.

    Distancing the activity from occupied premises.

    Where any person is liable to be exposed to noise levels greater than 80-85 dB (A), they will be informedand provided with suitable ear protection. The most likely protection, in ascending order of attenuation isear plugs, ear muffs and noise attenuation helmets.

    Noise will be kept to a minimum at all times and any further restrictions imposed under the terms of thecontract will be strictly adhered to.

    (See Noise Exposure Levels Daily & Weekly included in the appendix)

    Vibration

    When the work involves use of vibratory equipment A Buckler (Haulage) Ltd will monitor their workforceto ensure the maximum exposure levels are not exceeded by any of their employees.

    Records of the expected levels of equipment will be kept along with times and durations of individualemployees exposures. (See section 12 vibration log sheet and appendix hand and arm vibrationcalculator)

    Equipment and tools will be selected, maintained and used in work scheduled and rotated to ensureeach employees exposure levels are kept within the legal requirements.

  • 8/11/2019 Construction Phase Plan

    24/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 24

    Exposure to UV Radiation (from the sun)

    A Buckler (Haulage) Ltd is aware of the dangers from the UV rays from the sun such as:-

    Skin damage

    Sunburn

    Blistering Skin Cancer

    A Buckler (Haulage) Ltd take the damage from the sun rays seriously andwill endeavour to provideinformation to site operatives which include sun protection advice through toolbox talks, communicationposters, encourage workers to cover up during the summer months, encourage workers to usesunscreen on parts of the body they cant cover up

    Lead

    Where the presence of lead has been identified, either in paint or other materials, the Control of Lead atWork Regulations 2002 and the associated Approved Code of Practice will apply. The principle risk is

    likely to arise from the burning and cutting of steelwork coated with lead based paints. Other areas ofrisk are the demolition of buildings or plant which have been used for processing lead or leadcompounds and the removal and dismantling of vessels which have been used for the storage of leadalkyls and leaded petrol.

    An assessment will be made to determine the nature and degree of exposure of the workforce to leadand the appropriate precautions required. The standards to be achieved are set out in the approvedcodes of practice.

    The precautions taken may include;-

    Prohibition of eating, drinking and smoking in contaminated areas. Provision of information and adequate washing facilities.

    Provision of protective clothing.

    Provision of local ventilation and respiratory protective equipment.

    Medical surveillance where necessary.

    Dust

    Demolition work, particularly the demolition of old buildings will generate dust especially during periodsof dry weather. This dust generation can be controlled by wetting of the surfaces being demolished. ABuckler (Haulage) Ltdoperatives will use hoses to spray water onto brickwork and debris, during thedemolition/loading operations when conditions demand.

    Siliceous dust occurs as a building material in natural stone, bricks or aggregates for concrete.Demolition processes involving breaking, crushing or grinding siliceous material will create dustscontaining Crystalline Silica. As with other dust and fume hazards for which there are no separate setsof regulations and where it is not possible to comply with the exposure limits, suitable respiratoryprotective equipment will be provided for and worn by employees at risk.

    All personnel working in dusty areas shall, when necessary, wear a dust mask deemed suitable by theHealth and Safety Executive (HSE). All operatives concerned will be instructed in the correct use of allRPE/PPE

    Dry areas of the works will be dampened down to prevent the spread of airborne dust.

  • 8/11/2019 Construction Phase Plan

    25/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 25

    Gases, Vapours and Fumes

    A Buckler (Haulage) Ltdshall monitor the works area at regular intervals for flammable gases/vapours.If at any time the acceptable gas levels are exceeded then work in the area shall be suspended untilinstructed otherwise.

    Unusual fumes, vapours or odours will be treated with caution, together with any excavated materials of

    unusual colour, and will be reported immediately to the Site Manager.

    Gases, vapours and fumes may be released from, for example:

    Residues and wastes left behind in premises previously used for chemical processes or storage. Demolition work involving excavations or access to sewage/ waste pipelines. The demolition of tanks, silos, bunds and pipe work. Hot cutting or welding processes. From fuels and byproducts introduced for the demolition process Natural processes such as organic decomposition.

    Dangerous atmospheres can also arise in pits, tunnels and confined spaces where oxygen has been

    removed from the air by chemical or biological action.

    Operations involving entry into storage vessels which have contained chemicals i.e. lead alkyls, or theremoval and handling of sludge and scale from tanks will be assessed even though the work may betransient. For work of this nature, the Confined Space Regulation 1997 and the duties imposed, for theavoidance of entry, safe systems of working and emergency arrangements will be addressed.

    When working inside tanks, air fed suits or air supplied respirators will be used alongside suitableprotective clothing. Particular care will be taken to avoid skin contact with contaminated clothing whetherduring removal, transit or decontamination.

    Drums or containers found in the area will be left in situ and the Site Manager informed immediately.Work will be suspended in the vicinity of the containers until they have been inspected and removed.

    Personnel will be made aware when they are working in a potentially hazardous environment andinstructed to report any unusual symptoms such as nausea, dizziness, rashes, inflammation of the eyes,nose, mouth etc. to the Site Manager.

    Personnel will be instructed if they get chemicals or tar like substances on their skin to wash it off with aproprietary cleaner or soap and water, change clothes and follow the recommendations of the MaterialSafety Data Sheets (MSDS) and CoSHH assessment.

    If any person working within a contaminated area has the slightest cut or scratch it shall be thoroughlycleaned and covered with a clean dressing from the first aid box.

    Possible Health Hazards Present

    Check List Comments

    Asbestos Possible

    Leptospirosis

    Contaminated Water

    Needlestick Injury Possible

    Aspergillus Infection

    Micro-Organisms (Sewage)

    Allergic Rhinitis (Dusts) Possible

    Extrinsic Allergic Alveolitis (Birds/dusts)

    Vibration During hand demolition and machine work

    Sun Exposure

  • 8/11/2019 Construction Phase Plan

    26/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 26

    SECTION 4 SITE SPECIFIC ARRANGEMENTS

    Location of Site Offices and Welfare Facilities

    The Principal Contractor site amenities are available within the confines of the site boundary

    Welfare Facilities (Site Cabins or other Suitable Rooms) will be available for breaks and when badweather stops work. They must be well lit, heated and ventilated and regularly cleaned.

    Project Site Plan refer to section 1.1.1

    Check List

    Toilets (Separate Male and Female where applicable)

    Wash basins with warm water, soap and towels

    Showers

    Changing area work clothes should be kept separate from workers own clothing

    Rest and eating facilities with a means to warm food and water

    Drinking Water

    Copy of F10 Notification on Site

    Copy of Section 81 on Site

    Copy of HSE Authorised ASB5 Application if required

    Copy of Asbestos Refurbishment or Demolition Survey on Site

    Copy of Health & Safety at Work Act (HASAWA) Poster on Site

    Copy of Employer Liability Insurance Certificate on Site

    Copy of all Termination of Services Certificates on Site

  • 8/11/2019 Construction Phase Plan

    27/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 27

    Site Waste Management Plans

    Introduction

    A Site Waste Management Plan (SWMP) is a report of the plans to reduce and manage the waste from aconstruction or demolition project. It provides a framework for waste minimisation as well as the actual

    management of waste types and quantities arising from a project.

    The SWMP Regulations 2008 apply to all construction, demolition and maintenance or refurbishmentprojects costing more than 300,000 (excluding VAT).

    A Basic SWMPmust be produced for projects costing above 300,000 up to 500,000 and a DetailedSWMPis required for projects in excess of 500,000.

    (This includes the cost of the WHOLE project and not just the individual phases e.g. the cost ofdemolishing and clearing an area for redevelopment may be 100,000; so long as the subsequentredevelopment exceeds 200,000, the project requires a SWMP)

    Although the Project Client has overall responsibility for ensuring a SWMP is produced, they candelegate the development and management of the SWMP to the Principle Contractor or other third party.

    Project subject to the above criteriaYes

    No

    Responsibilities of the Principle Contractor

    If the responsibility for the SWMP is delegated to a Principle Contractor, they have a legal duty to ensurethat:-

    All site waste is managed according to the Environmental Protection (Duty of Care) Regulations1991

    Sufficient site security to prevent illegal waste disposal

    The SWMP is updated whenever waste is removed from site

    Details are recorded on all SWMPs of the types of waste produced on site and how they aremanaged, as well as the quantities for Detailed SWMPs

    Waste is reused, recycled or recovered so far as is reasonably practicable

    Every site worker is inducted about the SWMP together with any further information and trainingto ensure waste is managed according to the plan this can be via Tool Box Talks, structuredtraining courses etc. There must also be arrangements to monitor personnel and ensurecompliance with the SWMP

    Maintain arrangements for effective cooperation among workers in relation to the SWMP and the

    effectiveness of such arrangements An up to date copy of the SWMP is kept on site and all contractors have access to it

    The SWMP is regularly reviewed to check it is accurate

    There is a facility to store a copy of the SWMP for 2 years after project completion

  • 8/11/2019 Construction Phase Plan

    28/175

  • 8/11/2019 Construction Phase Plan

    29/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 29

    Non-Hazardous Waste

    These are wastes that will break down or decompose when buried in landfill. This results in theproduction of landfill gases such as methane and carbon dioxide

    Examples include:

    Timber, paper and cardboard, green wastes, food, metal and biodegradable plastics

    Hazardous Waste

    These are wastes that are harmful to human health or the environment. They may be liable to causedeath, injury or impairment to living beings, pollution of waters or unacceptable environmental impact ifimproperly contained, handled, treated or disposed of.

    Examples include:*Will be removed for all average jobs less than 30K, but left in if building work to follow onimmediately after demolition

    Asbestos containing waste

    Contaminated soils

    Paints, solvents and adhesives

    Oily wastes

    Refrigerants and foams

    Wastes contaminated with various paints, solvents and oils

    Treated timber

    Waste electrical and electronic equipment with hazardous components

    Fluorescent tubes

    Batteries

    Concrete wash out water

    (A Site Waste Management Plan template is included in the appendix)

    Arisings

    Clean Materials of Commercial Value

    A Buckler (Haulage) Ltd aim to maintain a maximum demolition recovery index of approx 95% (weight)where possible by managing and sorting uncontaminated, clean materials into types for re-use/reprocessing (recovered aggregates on site), metals for re-use smelting, timber for re-use orchipping. These categories of materials will be transported to the nearest available recyclingestablishment.

    Clean Materials of No Commercial Value

    Uncontaminated clean materials, i.e. non-asbestos insulation will be placed in suitable containers which,when full, will be transported to and disposed of at a nominated licensed waste disposal site.

    Hazardous Waste

    Each demolition site where the hazardous waste is produced in excess of 200Kg in total will beregistered, prior to commencement of the demolition work. Due to the nature of the demolition industry itmay be necessary to register the Contractors mainoffice as the service premises under the mobileservice criteria especially where quantities produced from the site/premises are minimal/less than 200kg.

    Records of transfer notes will be kept for a minimum of three years, and the resulting waste will betransported to and disposed of at a nominated, licensed waste disposal site.

  • 8/11/2019 Construction Phase Plan

    30/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 30

    Debris

    Handling Debris:

    The handling of debris will be kept to a minimum. Operatives will not handle debris that can be movedwith a machine. When debris must be handled, the operatives will be issued with the appropriate typesafety gloves and will be reminded of the hazards associated with handling broken glass, nails etc.Broken glass will be swept up immediately and placed in a suitable container.

    Wood containing nails will be immediately loaded into wagons and removed from site; or stacked awayfrom personnel with protruding nails pointing down.

    Windblown Debris

    Debris will be cleared up as soon as possible. At no time will a vast amount be stockpiled awaitingremoval it will always be kept in a damp state and any material that could easily blow away will bebagged up or loaded onto wagons for removal from site before it causes problems

    Wagons and skips will be sheeted when containing materials that could be windblown.

    Falling Debris

    Operatives will not be allowed to work underneath or close to overhead work. At all times, the areadirectly below any overhead work will be cordoned off with the necessary signage to warn and prevententry.

  • 8/11/2019 Construction Phase Plan

    31/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 31

    SECTION 5 THE HEALTH AND SAFETY FILE

    A Buckler (Haulage) LtdsSite Manager/supervisor will gather and compile any relevant informationrequired for inclusion in the Health and Safety File, on an ongoing basis. The information will becompiled in an agreed format between the Client and the CDM co-ordinator at the start of the project.

    All contractors involved in the project will be advised by A Buckler (Haulage) Ltdas to the information

    required and to supply the required information for inclusion promptly.

    The information will be made available in the form of a final condition statement detailing how the sitewas left and the locations of any remaining service locations/terminations. At the completion of theproject the file will be handed over to the client at the appropriate time.

    The contents of the Health and Safety File may include some of the following information:

    A brief description of the work if any of the structure remains.

    Any residual hazards which remain and how they have been dealt with (for example surveys or otherinformation concerning asbestos; contaminated land; buried services etc)

    Key structural principles (for example, bracing, sources of substantial stored energy) The nature, location and markings of significant services, including underground cables; gas supply

    equipment; fire fighting services etc.

    Any voids left after removal of structures or parts of structures.

  • 8/11/2019 Construction Phase Plan

    32/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 32

    SECTION 6 SEQUENCE OF EVENTS

    To be checked off by the Supervisor/Manager on site

    1 Ensure that the site is secure

    2 All relevant demolition signs are in place

    3 Disconnect or identify existing services

    4 Establish that adequate welfare facilities are provided

    5 Establish Traffic Management Plan

    6 Remove Licensed Asbestos

    7 Remove Non-Licensed Asbestos

    8 Partial Soft-Strip of the Buildings

    9 Hand Demolition to Reduce in Height

    10 Demolish existing Buildings

    11 Grub up Slabs and Foundations

    12 Site works Cleared. Leveled and Landscaped

    13 Ensure area is left in safe state and address any housekeeping issues

  • 8/11/2019 Construction Phase Plan

    33/175

    NSL Ref 4237/4248

    NSL/PF/018 Demolition Method Statement Issue 6 33

    SECTION 7 METHOD STATEMENT

    Preliminary Work

    The Client will carry out this work:-

    Before any work commences all services must be physically isolated and written confirmation of the

    isolations received from the relevant authorities. Remaining services in the work areas to be clearly identified and protected before work commences. All structures for demolition or removal must be clearly identified. Safe means of emergency access and egress for work areas provided and clearly identified. Any underground and overhead services identified and protected before work commences. Any asbestos containing materials to have been identified (Refurbishment or Demolition Survey), all

    reportable asbestos materials removed and a clearance certificate obtained. Copy of the Refurbishment or Demolition Asbestos Survey to be on site and available during the full

    extent of the demolition works. Locations of any underground voids or unstable ground identified and adequately protected. All appropriate information regarding the stability of the structure to be made available prior to work

    commencing.

    Sequence of Events

    ProcedureNo.

    1 Erection of Heras Fencing/Hoarding 1

    2 Partial Soft Strip of the Buildings 2

    3 Hand Demolition to Reduce in Height 3

    4 Remote Demolition of the Buildings 4

    5 Lifting of Slabs and Foundations 5

    6 Crushing of Materials 6

    Standard Personal Protective Equipment Worn on this Site.

    Safety Helmets.

    Safety Boots or Shoes.

    Overalls or Suitable Clothing.

    Gloves

    Hi Visibility Jacket or Vest

    This method statement is a live document and may be subject to change during the course of theproject where unforeseen circumstances dictate and should be read as such. Any changes tothe Method Statement will be addressed and the Client informed.

  • 8/11/2019 Construction Phase Plan

    34/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 34

    Procedure Number 1

    Erection of Heras Fencing/Hoarding

    Personal Protective Equipment

    Gloves Eye Protection

    Tools and Equipment

    Spanners Plastic ties

    Description of Works

    Heras fencing will be erected around the demolition site, specific work areas and drop zones to preventunauthorised personnel gaining access

    In places Heras fencing will be changed to hoarding.

    NB: See attached drawing (Appendix 1)of unrecorded electric cables around the area, supplied by theClient

    Step Preparatory Work Key Points

    1.1 At least two operatives will unload the panelsand solid-block feet and position them aroundthe site or area boundary

    Care must be taken regarding manual handlingissues

    1.2 Ground must be solid and level Fencing must not be erected where unevenground is likely to lead to a collapse of the fence

    1.3 Erection and positioning must not interferewith public rights of way

    When erecting fencing close to roads orfootpaths, the thoroughfare should be closed toensure the safety of third parties and operatives

    Step Erection of Heras Fencing Key Points

    2.1 Two operatives will lift the panels and placethe uprights into the appropriate holes in thepositioned blocks

    Care must be taken regarding manual handlingissues

    2.2 If necessary a third operative will assist tomove the blocks into the correct position

    Solid block feet will be positioned at right angles tothe line of the fence to ensure stability

    2.3 After positioning the second panel, holdingclips will be fitted and tightened using thecorrect size spanner/socket

    At least three clips must be fitted to the fencing onall areas

    2.4 Repeat procedure around the full perimeterof the areas

  • 8/11/2019 Construction Phase Plan

    35/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 35

    Step Security and Stability Key Points

    3.1 Bracing may need to be fitted to add stability Bracing must only be fitted on the inside of thefence and must not cause a trip hazard

    Bracing will be fitted where there is a likelihood ofthe fence collapsing due to high winds or being

    pushed over

    3.2 A minimum amount of gates will be fitted andmust be able to be securely fastened andlocked

    Access must only be able to be gained via a propergate

    A secure lock must be fitted and access to the keycontrolled via a responsible person, the key mustbe readily available in case of emergencies

    3.3 Warning and information signs will be fittedusing nylon ties and not wire

    Signs must not be too large or numerous so as toact as a sail and de-stabilise the fencing in highwind

    Step Erection of Hoarding Key Points

    4.1 Where hoarding is required, the posts will beeither fixed to plates on the road. Footpath orholes dug to concrete them in

    If holes are to be dug for posts, the client orprincipal contractor will provide information on thewhereabouts of any live services underground.

    4.2 After the posts have been secured then railswill be fixed to the posts and suitable heighttimber panels fixed to the rails.

    The height of the panels is to be decided by theclient and reported to the demolition contractor.

    4.3 The colour of the panels will be decided by

    the client taking into account the adjacentGrenfell Club.

    Extreme care will be taken when working close to

    this club and the safety of the members will begiven full consideration

  • 8/11/2019 Construction Phase Plan

    36/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 36

    Hazards Controls Controls in place/ checked

    Manual Handling A minimum of two operatives must lift the panels

    Operatives must wear protective gloves at all times

    Operatives must not lift excessive quantities of materials

    Third party injury Fencing or block feet must not encroach upon a third partyright of way

    Fencing, block feet and bracing must be erected so as notto cause a trip hazard if necessary they should bemarked with a high-visibility paint

    Hand tools Check all hand tools are in good condition

    Wear gloves to protect hands against cuts and abrasions

    Collapse offencing

    The fencing will be erected with block feet at the end ofeach fence panel and bracing to prevent or minimisecollapse of fencing during high winds or vandalism

    Fencing will be erected on solid and stable ground and farenough away from any excavations or ground likely tocollapse

  • 8/11/2019 Construction Phase Plan

    37/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 37

    The documents referenced below are contained in the appendices for the individual titled sections andare applicable to the above procedure.

    Task Risk Assessments COSHH Assessments

    NS/DRA/014. Hand Tools

    NS/DRA/015. Heras Fencing

    NS/DRA/017. Live Services on Site

    NS/DRA/018. Manual HandlingNS/DRA/024. Slips Trips & Falls

    NS/DRA/026. Third Parties and General Public

    Erection of Heras Fencing and Hoarding

    All Operatives to sign this form after reading and understanding the Method Statement and RiskAssessments attached

    PRINT NAME CLEARLY SIGNATURE

    SUPERVISOR SIGNATURE

  • 8/11/2019 Construction Phase Plan

    38/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 38

    Procedure Number 2

    Partial Soft Strip of all Buildings

    Additional Personal Protective Equipment

    Gloves Dust Masks

    Access to Work at Height

    Tower Scaffold Step Ladders

    Tools and Equipment

    Iron Bars Wheel barrows, bins

    Hand Tools screw drivers, hammers , retractableknives etc

    Shovels, scrapers

    Description of Works

    A partial soft strip of fixtures and fittings will be carried out within the redundant buildings.

    A full soft strip of the buildings may not be required and it is up to the demolition contractors discretion howmuch waste materials he removes from the buildings.

    Step Preparatory Work Key Points

    1.1 No soft strip procedure will commence untilthe results of the asbestos survey are known,any asbestos products removed and thepremises certified as asbestos free

    Carrying out soft strip work prior to the removal ofasbestos may cause damage to the asbestosmaterials and contaminate the workers on site.

    1.2 Transit routes will be set up using the maindoors to the outside of the buildings Access to the buildings will be secured to preventunauthorised access

    Transit routes will be well lit and kept clearthroughout the procedure

    1.3 Designated drop zones will be fenced and astandby man employed if necessary

    Personnel will not be allowed to walk into the dropzone due to the possibility of tripping hazards andexposed nails from timbers

    1.4 Materials will be sorted into types wherepossible.

    Plasterboard will be kept separate from normalsoft strip materials and disposed of at anappropriate licensed waste disposal site or sent toan appropriate recycling station

    1.5 Certain materials may require damping downto prevent excessive dust becoming airborne

    Care must be taken not to leave work surfacesslippery through too much wetting

    1.6 Materials from the Library will be removedfrom the building on the South end doorway.

    Materials from the Council Offices will beremoved from the building into the small carpark area on the East side

    Materials from the single storey building will beremoved from the door on the East side

    Skips will be made available and all debris andrubbish loaded into them immediately.

  • 8/11/2019 Construction Phase Plan

    39/175

  • 8/11/2019 Construction Phase Plan

    40/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 40

    Step Disposal of Soft Strip Waste Key Points

    3.1 All waste materials will be separated intotypes for re-cycling where possible

    No burning of waste will be allowed on site

    Clean timbers may be sent for recycling

    Plasterboard may be sent for recycling

    3.2 Debris will be placed into wagons or skips forremoval to an appropriate waste disposalsite, or to an appropriate recycling station.

    Wagons entering and leaving the site will beassisted by a banksman to prevent anyinconvenience to road users or pedestrians

    Skips and wagons will be sheeted prior to leavingsite to prevent materials being windblown duringtransit.

    Hazards Controls Controls in place/ checked

    Manual Handling Operatives must not lift excessive amounts an ideal

    maximum should be no more than 25kg

    Hand tools All hand tools must be in good condition and checked on aregular basis and recorded

    Live services Loft areas, roof voids and floor voids may contain liveservices any live services should be isolated and certifiedby qualified personnel prior to any work commencing

    Needlestick injury Some areas of the properties or surrounding buildings mayhave been used for drug use any discarded needles or

    drug related paraphernalia will be removed by brush andshovel or suitable extended grabber, never by hand.Needles etc must be placed in sharp bins, NEVER inwaste bags

    Slips, trips andfalls

    Operatives carrying out soft strip work must take care inrespect of slips, trips and falls, work from a suitable safeplatform and wear appropriate footwear with good tread

    Hygiene No eating or drinking to take place in the properties

    Operatives will remove overalls etc after leaving the

    properties and dispose of them appropriately

    Operatives will make use of washing facilities beforeeating, drinking, smoking or going to the toilet.

    Any physical ill effects will be reported to a supervisor

    Working at Height Mobile scaffold towers must only be erected by trained andcompetent personnel

  • 8/11/2019 Construction Phase Plan

    41/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 41

    The documents referenced below are contained in the appendices for the individual titled sections and areapplicable to the above procedure.Task Risk Assessments COSHH Assessments

    NS/DRA/008. General Demolition NSL/DCA/062 Dusts

    NS/DRA/009. General Dust NSL/DCA/076 Fibre Glass

    NS/DRA/013. Hand Demolition NSL/DCA/108 Man Made Mineral Fibre

    NS/DRA/014. Hand Tools

    NS/DRA/017. Live Services on Site

    NS/DRA/018. Manual Handling

    NS/DRA/023. Work from Scaffold Towers

    NS/DRA/024. Slips Trips and Falls

    NS/DRA/025. General Soft Strip

    NS/DRA/026. Third Parties and General Public

    NS/DRA/031. Breaking Glass from Windows

    Partial Soft Strip of Buildings where requiredAll Operatives to sign this form after reading and understanding the Method Statement and Risk

    assessments attachedPRINT NAME CLEARLY SIGNATURE

    SUPERVISOR SIGNATURE

  • 8/11/2019 Construction Phase Plan

    42/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 42

    Procedure Number 3

    Hand Demolition of Building to Reduce in Height

    Additional Personal Protective Equipment

    Gloves Eye Protection

    Dust Masks Safety harness and lanyard

    Access to Work at Height

    MEWPs Mobile Tower Scaffold

    Tools and Equipment

    Electric/pneumatic Breakers Crowbar

    Hand Tools hammer and bolster Saws

    Description of Works

    Council OfficeHand demolition will take place to reduce the gable end in height, due to the proximity of the adjacentRedlands Day Nursery Building.Access to height will be by means of a MEWPs machine

    Single Storey BuildingHand demolition will take place to reduce the gable end in height, due to the proximity of the adjacent footpathand parking meterAccess will be by means of a tower scaffold

    View from the North looking South

    Area for handdemolition

  • 8/11/2019 Construction Phase Plan

    43/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 43

    View from South looking North

    View of the North end of the single storey building, this will be reduced almost down to ground level due to theclose proximity of the parking meter

    Step Preparatory Work Key Points

    1.1 The areas for hand demolition will be clearlyidentified to all operatives engaged in the task

    1.2 All debris will be removed away from theadjacent building and parking meter

    The single storey building, the debris may bedropped down inside of the building.

    The Council Office section the debris may beplaced directly into a skip via a chute or back intothe building and moved clear of the area.

    1.3 Banksmen will be on duty throughout the handdemolition period

    Reference the Council Office section, theadjacent building (Redlands Day Nursery) will beinformed of the day this work will take place toensure they are fully aware of what is happening

    and to ensure they will prevent any of the childrenbeing close to the works.

    Area for handdemolitionApproximateheight to bereduced to

  • 8/11/2019 Construction Phase Plan

    44/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 44

    Step Access to Height Key Points

    2.1 Access to the height work will be via acombination of mobile elevated workingplatform (MEWP) and mobile scaffoldingtower

    MEWP will only be used on solid and level groundand operated by trained and authorised personnel

    2.2 Operation of MEWP MEWP will be maintained according tomanufacturers instructions, inspected by acompetent person before use and properly testedas per manufacturers schedules written recordsof all inspections will be retained

    2.3 Malfunction of equipment Mobile scaffolding towers will be erected bycompetent persons, examined regularly andrecords kept

    The safe working load of any equipment mustnever be exceeded

    Hazards Controls Controls in place/ checked

    Falling fromHeights

    No person will be allowed to work alone

    Access to the work area will be restricted via fencing or astand-by operatives to keep out any unauthorisedpersonnel

    Safety harness and lanyards will be used; lanyards will beattached to a suitable structure

    Failure ofequipment

    Safety harnesses will be correctly stored, tested andinspected according to manufacturers specification andwritten records held

    Safety harnesses and lanyards will be checked before useby the site supervisor.

    Any damaged equipment will not be used and will beremoved from site for proper disposal

    Falling materials An exclusion zone will be set up at floor level using Heras

    fencing; consideration of materials disintegrating uponimpact will be taken into account

    Materials will never be thrown from a height

    No one will be allowed access to, or work beneath the workat height being carried out

  • 8/11/2019 Construction Phase Plan

    45/175

  • 8/11/2019 Construction Phase Plan

    46/175

  • 8/11/2019 Construction Phase Plan

    47/175

  • 8/11/2019 Construction Phase Plan

    48/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 48

    Procedure Number 4

    Remote Demolition of Buildings

    Tools and Equipment

    360 Demolition Machine Selector grab attachment

    Hydraulic Shear Attachment

    Description of Works

    The buildings will be demolished remotely using an Demolition Machine with fitted specialist attachmentsThe Council Offices and the single storey building will be demolished using the selector grab attachment, theLibrary will be demolished using the hydraulic shear attachment

    Step Preparatory Work Key Points

    2.1 A visual survey of the buildings will becarried out to highlight any areas of concern

    in respect of stability, stored energy etc

    This survey will be carried out by the sitesupervisor, if there is any cause for concern with

    regard to stability of the building a StructuralEngineer will be employed

    2.2 An exclusion zone will be in force and stand-by operatives used if considered necessary

    The exclusion zone will be the full extent of the siteor work area where possible

    2.3 The supervisor will perform a sweep of thebuildings and sound warnings to ensure nounauthorised persons remain on thebuildings

    The only personnel allowed within the exclusionzone will be the machine operator and the standbyman

    2.4 The machine operator will be made aware of

    any cellars and the location and nature ofany unstable ground

    Any cellar floors will be broken through

    2.5 Disposal skips will be placed at convenientplaces around the work area

  • 8/11/2019 Construction Phase Plan

    49/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 49

    Step Remote Demolition Key Points

    3.1 Remote demolition will be via a 360Demolition Machine fitted with a selectorgrab and hydraulic shear attachment

    Demolition Machine s will only be operated byqualified personnel

    The machine must be maintained in accordancewith manufacturers recommendations and checkeddaily records of inspections must be retained

    Machines will be fitted with falling object and rollover protection

    3.2 Roofing materials will be removed firstallowing access to walls without the hazardof collapse.

    3.3 This will be followed by the outer walls takingcare to ensure that the debris falls into theworking area

    Work will progress in a logical manner, working inone direction and sweeping across the open side ofthe buildings

    The machine must be sited in such a way that the

    slew movements are within the exclusion zone atall times.

    3.4 Debris will be sorted into types for furtherprocessing and appropriate disposal usingthe selector grab etc.

    Debris material will be cleared from the work areaon a regular basis

    Loading operations will be performed safely, nevercrossing the cab

    Wagons leaving the site with materials will besheeted to prevent lift off of materialsIf the Demolition Machine is used for lifting loads,the safe working load must never be exceeded

    only designated lifting points will be used3.5 The Library is constructed from acombination of brick, concrete and steelframe.

    The hydraulic shears will be used for the steelframe.

    3.6 The steel clad roof will be removed by theshears along with all steel frame-work in thebuilding.

    Scrap metal will be separated and loaded into skipsfor removal from site.

    3.7 Concrete and brick will be removed using thegrapple or the bucket attachment.

    All debris will be removed from the work areas andremoved from site via skips or wagons, or ifrequired to stay on site will be stockpiled forcrushing.

    Hazards Controls Controls in place/ checked

    Stability Walls reduced in a uniform and progressive manner nounsupported sections will remainSecure perimeter fencing to prevent unauthorised access

    Noise and dust Equipment with low noise level valuesNoise screen/enclosureDust suppressionOperatives to wear appropriate PPE

  • 8/11/2019 Construction Phase Plan

    50/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 50

    The documents referenced below are contained in the appendices for the individual titled sections and areapplicable to the above procedure.Task Risk Assessments COSHH Assessments

    NS/DRA/008. General Demolition Procedures NS/CA/062 Dusts

    NS/DRA/009. General Dust NS/CA/058 Diesel

    NS/DRA/010. 3600 Demolition Machines NS/CA/064 Diesel Fume

    NS/DRA/011. Fire Hazards (Demolition and Dismantling) NS/CA/083 Grease (Hi Temp)

    NS/DRA/021. General Noise NS/CA/122 Hydraulic Oil

    NS/DRA/022. Work Adjacent to Roads and Footpaths

    NS/DRA/026. Third Parties and General Public

    NS/DRA/029. Loading Wagons

    NS/DRA/036. Remote Demolition of Property

    Remote Demolition of Buildings

    All Operatives to sign this form after reading and understanding the Method Statement and Riskassessments attached

    PRINT NAME CLEARLY SIGNATURE

    SUPERVISOR SIGNATURE

  • 8/11/2019 Construction Phase Plan

    51/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 51

    Procedure Number 5

    Removal of Slabs and Foundations

    Tools and Equipment

    360 Demolition Machine with Bucket attachment

    Description of Works

    Upon completion of remote demolition, any remaining floor slabs and foundations will be lifted and removedfrom site.

    Step Preparatory Work Key Points

    1.1 The area will be visually surveyed to identifyany likely underground services or voids in theconcrete slab

    If the presence of underground services aredetected, they must be clearly marked andprotected

    Cat scans may be required to determine thewhereabouts of any live services

    Extreme care must be taken where there remainsa possibility of any unknown services

    Step Lifting of Slabs and Foundations Key Points

    2.1 The machine will be positioned where allslew movements will remain within theexclusion zone

    Demolition machines will only be operated byqualified personnel

    The machine must be maintained in accordance

    with manufacturers recommendations and checkeddaily records of inspections must be retained

    Machines will be fitted with falling object and rollover protection

    2.2 The machine will commence work at asuitable point on the floor slabs and lift theconcrete, breaking it into manageablesections

    The operator will be made aware of any unstableground or where there is a sudden change in levels

    Separation of adjoining structures, positioning oftemporary supports, capping of sewers etc will becompleted prior to removal work

    2.3 Work will continue in a progressive manner

    working in a single direction over theexpanse of the floor slabs on site

    The machine will stockpile the concrete ready for

    loading into wagons for removal from site.

    2.4 After the floor slabs have been removed, thefoundations will be lifted, the bucket havingto delve deeper into the ground to lift them,therefore more chance of coming intocontact with any unknown undergroundservices.

    The standby mans duties to include checking forany signs of any underground services during thelifting of the foundations, and to warn the machineoperator if anything unusual is seen.

    2.5 With the concrete slabs etc lifted clear andbroken into manageable sections, the wastewill be loaded into wagons for removal fromsite

    Suitable materials will be used to refill and level thesite after the removal of the foundations etc.

  • 8/11/2019 Construction Phase Plan

    52/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 52

    Hazards Controls Controls in place/ checked

    Noise and dust Equipment with low noise level values will be used wherepossible

    Noise screen/enclosures will be fitted where necessary

    Dust suppression may be necessary

    Operatives must wear appropriate PPE

    The documents referenced below are contained in the appendices for the individual titled sections and areapplicable to the above procedure.Task Risk Assessments COSHH Assessments

    NS/DRA/008. General Demolition NS/CA/062 Dusts

    NS/DRA/009. General Dusts NS/CA/058 Diesel

    NS/DRA/010. 360 Demolition Machines NS/CA/064 Diesel Fume

    NS/DRA/017. Live Services on Site NS/CA/083 Grease (Hi Temp)

    NS/DRA/022. Working Adjacent to Roads & Footpaths NS/CA/122 Hydraulic OilNS/DRA/026. Third parties & General Public

    NS/DRA/030. Loading Wagons

    NS/DRA/036. Excavations

    NS/DRA/037. Remote Demolition

    Lifting of Floor Slabs and FoundationsAll Operatives to sign this form after reading and understanding the Method Statement and Risk

    assessments attached

    PRINT NAME CLEARLY SIGNATURE

    SUPERVISOR SIGNATURE

  • 8/11/2019 Construction Phase Plan

    53/175

    NSL Ref No 4237

    NSL/PF/103 Demolition Phase Plan Issue 7 53

    Procedure Number 6

    Crushing on Site

    Additional Personal Protective Equipment

    Hearing Protection Dust Masks

    Gloves Eye Protection

    Tools and Equipment

    360 Degree Demolition Machine. Loading shovel.

    Crushing machine.

    Description of Works

    Upon completion of remote demolition all brick debris and concrete will be stockpiled and then cr