CONSTRUCTION PROGRESS
UPDATE
Vol. 10September 2016
TO VALUED BUYERS OF
BODAIJU RESIDENCES
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
1
Dear valued buyers of Bodaiju Residences,
It is with great pleasure that I’m writing to you to share with you on the construction
progress for Bodaiju Residences.
Since the sales of Bodaiju Residences on 22nd August 2015, we had received over-
whelming support and much better than expected sales of Bodaiju Residences. With the
strong support, my construction team has been working endlessly to meet the construction
progress. After completing the UXO clearance and test piling works, we are currently
carrying out piling works in full force.
As part of our continuous engagement with you, I’m pleased to provide you with the
details of the construction in this report and endeavor to provide you with an update on
the construction every quarter.
Thank you for all the great support extended thus far.
Sincerely,
Toshihiko Muneyoshi
Founder/ Manager Director
Creed Group
©Torreya Asset Holdings Co., Ltd.
Construction Schedule Payment Schedule
Mar
Apr
May
Jun
Sep
Oct
Nov
Dec
2017
Jan
Feb
Jul
Aug
Mar
Nov.
2015
Oct.
Dec
2016
Jan
Feb
Vol. 10 September 2016
Bodaiju Site Progress Report - Building A and B -
2
GENERAL SCHEDULE (October 2015 – June 2017) CONSTRUCTION PROGRESS
We are completed the 2nd Floor Structure Work and
planning to complete the 7th Floor, Structure Work by
end of Oct.
Piling works
Architectural
works
Interior works
MEP
works
Completion of
7th floor structure
Completion of
RF floor structure
preliminary
works - Mine investigation
- Ultimate load test, etc.
RC
Superstructure
※Construction’s Schedule might vary to take weather conditions and other factors into account.
Building ABuilding B
※The diagram above only serves to illustrate the construction progress. Actual construction may not be
carried out as per the illustration.
P1
P2
1F
2F
3F
5F
6F
7F
8F
9F
10F
11F
12F
13F
RF
P1
P2
1F
2F
3F
5F
6F
7F
8F
9F
10F
11F
12F
13F
RF
FOUNDATION WORK
COMPLETED. MARCH-2016
Completion of
foundation
Parking 1
Parking 2
Garden Deck
1st FLOOR STRUCTURE
COMPLETED. JUNE-2016
Completion of
1st floor structure
NOW 5th FLOOR
STRUCTURE + MEP
©Torreya Asset Holdings Co., Ltd. Vol. 10 September 2016
Bodaiju Site Progress Report - Building A and B -
3
FOUNDATION COMPLETION – March 2016 PHOTOS OF PROGRESS COMPLETION
©Torreya Asset Holdings Co., Ltd. Vol. 10 September 2016
Bodaiju Site Progress Report - Building A and B -
4
1FL. SUPER-STRUCTURE COMPLETION-June 2016 PHOTOS OF PROGRESS COMPLETION
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
5
JULY 2016 SITE VIEW (BUILDING A & B)
In August 2016 we already complete the 5rd Floor Structure Work for Building A & B as we planned to compete 7th Floor Concreting Work byend of October 2016.
Vol. 10 September 2016
A1
A2
B1
B2
B1 View – Building B
B2 View – Building B
A1 View – Building A
A2 View – Building A
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
6
5FL-BEAM & SLAB FORM WORK (BUILDING A & B) 5FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)
Reinforcement Work site activities of Building A & B on 5th Floorwhich completed.
Slab and Beam Form Work installation activities in our constructionsite in August 2016.
Vol. 10 September 2016
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
7
5FL-RE-BAR CHECK & CLEANING (BUILDING A & B) 5FL-CONCRETE TEST AT SITEMixed-Concrete was tested at site before casting building A& B Structure, Slab and Beam.
Re-Bar Checking activates of Building A & B at construction site byour engineer.
Vol. 10 September 2016
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
8
5FL-MEP WORK (BUILDING A & B) 5F-CONCRETE WORK AT SITEConcrete Work for 5th Floor Level of Building A & B wascompleted in August 2016. This is level checking after castingconcrete.
Pipe for electricity in 5th Floor Slab was laid and our engineerchecking strictly on MEP works to be ready for concreting.
Vol. 10 September 2016
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
9
PLASTERING WORK (MOCK UP UNIT) MEP WORK (MOCK UP UNIT)
MEP work in our site for our mock up unit in building A alsostarted in this August.
Plastering work in our site for our mock up unit in building Aalready start in this August.
Vol. 10 September 2016