    Construction Reform 101

    An Overview of Construction Reform in theCommonwealth of Massachusetts

    A New Approach for Public Sector Projects

    Division of Capital AssetManagement

    David B. Perini

    Commissioner

    New York City Bar AssociationJanuary 25, 2011

  • 7/31/2019 Construction Reform 101

    2/60

    BACKGROUND

    and

    OVERVIEW OF KEY PROVISIONS

  • 7/31/2019 Construction Reform 101

    3/60

    Construction Reform - What is it?

    The most comprehensive reform of state public

    construction laws since the Ward Commission (1981)

    Modified several fundamental areas in these laws:

    Provides for use ofAlternative Delivery Methodsfor vertical and horizontal construction projects.

    Changes thresholds governing general and filed sub-bids.

    Requires certification of filed sub-bid subcontractors.

    Makes owner prequalification of contractors widelyavailable/mandatory in certain instances (GCs, subs).

    Requires Owners Project Manager on certain projects.

    Extends MBE/WBE program requirements to statefunded municipal projects

  • 7/31/2019 Construction Reform 101

    4/60

    Construction Reform- Key Changes

    Chapter 193 of the Acts of 2004 instituted the following key changes:

    Alternative Delivery Methods (CM at Risk and Design-Build)

    General Bid & Filed Sub-Bid Threshold Changes

    Filed Sub-Bidder & General Bidder Certification

    General & Filed Sub-Bidder Prequalification

    Owners Project Manager Requirement

    Designer Selection Changes

    MBE/WBE Affirmative Marketing Program

  • 7/31/2019 Construction Reform 101

    5/60

    Construction Reform - How Did We Finally Get Here?

    After years of trying, every major interest group cametogether to hammer out needed legislative change.

    Public Owners (DCAM, Massport, Municipalities)

    Office of the Inspector General General and Subcontractor groups (AGC, ABC, ASM)

    Architect and Engineer groups

    Organized Labor

    MBE/WBE groups

    The Legislature and the Administration

  • 7/31/2019 Construction Reform 101

    6/60

    ALTERNATIVE DELIVERY METHODSCONSTRUCTION MANAGER AT RISK

    and

    DESIGN-BUILD

    (M.G.L. c 149A)

  • 7/31/2019 Construction Reform 101

    7/60

    Overview of CM at Risk - Background

    Construction Reform in the Commonwealth createdopportunity for use of alternative delivery methods onpublic projects.

    Per M.G.L. c. 149A, effective January 1, 2005, allows CM atRisk.

  • 7/31/2019 Construction Reform 101

    8/60

    Overview of CM at Risk - Background

    Delivery method is optional for DCAM (and other public agencies)for building projects $5 million or more.

    Inspector General approval required on a case by case basis---exceptions are DCAM, Mass Port, MWRA, and MSCBA (which mustannually submit procedures for projects they choose to procure CMat Risk).

    DCAMs procedures approved by IG.

    CM at Risk firm must be Certified by DCAM in the Category ofGeneral Building Construction.

    Laws governing prevailing wages, direct payment, prompt payment,unforeseen conditions, delays and contractor record keeping are allapplicable.

  • 7/31/2019 Construction Reform 101

    9/60

    Overview of CM at Risk - Why Use CM at Risk?

    Advantage - CM has broader scope (than General Contractor)from Pre-Construction to Construction Management Services,including but not limited to:

    CM provides cost estimation.

    CM provides design consultation.

    CM assists in preparation/coordination of bid packages.

    CM provides scheduling.

  • 7/31/2019 Construction Reform 101

    10/60

    Overview of CM at Risk - Why Use CM at Risk?

    CM assists with cost control - value engineering.

    CM assists with prequalification and evaluation of trade/othersubcontractors.

    CM acts as general contractor during construction (includesholding trade contracts and other subcontracts).

    CM provides management and construction services.

  • 7/31/2019 Construction Reform 101

    11/60

    Overview of CM at Risk - Procurement of CM Firm

    Two-phase competitive proposal selection process:

    Phase 1 - Prequalification of potential CM firms throughRFQ process.

    Phase 2 - RFP to prequalified CM firms.

  • 7/31/2019 Construction Reform 101

    12/60

    Overview of CM at Risk - Procurement of CM Firm

    Phase 1 - RFQ Process

    Prequalification Committee established (1 rep. from designer, theproject manager, and at least 2 rep. from awarding authority).

    RFQ developed by awarding authority.

    Public notice of RFQ.

    Interested CM firms submit Statement of Qualifications.

    Prequalification committee evaluates Statements ofQualifications based solely on criteria set forth in RFQ.

    Must prequalify a minimum of 3 CM firms to proceed to RFPPhase(if not, re-advertise or revert to c. 149).

  • 7/31/2019 Construction Reform 101

    13/60

    Overview of CM at Risk - Procurement of CM

    Phase 2 - RFP Process

    Selection Committee established - 1 rep. from designer, theproject manager, and at least 2 rep. from awarding authority(can be the same as prequalification committee).

    RFP sent to prequalified CM firms only.

    Fee/cost proposals and technical proposals submitted byprequalified CM firms.

    Selection Committee prepares non-price evaluations basedsolely on the criteria set forth in the RFP.

    The most advantageous proposal selected considering bothtechnical and price proposals.

  • 7/31/2019 Construction Reform 101

    14/60

    Overview of CM at Risk - Guaranteed Maximum Price (GMP)

    GMP is the guaranteed maximum price the awarding authority willpay for the project.

    GMP is comprised of the:

    Hard cost of the work;

    General conditions costs;

    Fee payable to the CM firm

    CM may benefit from incentive clause for various performanceobjectives of up to 1% of the estimated construction cost.

  • 7/31/2019 Construction Reform 101

    15/60

    Overview of CM at Risk - Guaranteed Maximum Price (GMP)

    GMP Shall:

    Be based on design documents (which

    are at least 60 percent complete).

    Be agreed to as written amendment to

    contract with awarding authority.

    Be executed before the commencement of major construction

    work.

  • 7/31/2019 Construction Reform 101

    16/60

    Overview of CM at Risk - Guaranteed Maximum Price (GMP)

    GMP Shall Include :

    Detailed line item cost breakdown by trade.

    CM firms contingency, general conditions, and fees.

    Listing of all the drawings, specifications and other information onwhich the GMP is based.

    Listing of any assumptions or clarifications on which the GMP is

    based.

    Detailed project schedule on which the GMP is based.

    Payment and performance bonds.

  • 7/31/2019 Construction Reform 101

    17/60

    Overview of CM at Risk - Subcontractors

    Prequalification of Trade Subcontractors:

    Prequalification process utilized to procure sub-bid classes ofwork subject to the filed sub-bid law (M.G.L. c. 149, 44F).

    Prequalification Committee established to evaluate TradeContractors (consists of 1 rep. from designer, 1 rep. from CMfirm and 2 reps. from awarding authority).

    Public Notice/RFQ issued for trades with ECC > $20,000.

    Trade Contractors respond to RFQ with Statement ofQualifications.

  • 7/31/2019 Construction Reform 101

    18/60

  • 7/31/2019 Construction Reform 101

    19/60

    Overview of CM at Risk - Subcontractors

    Prequalification of Other Subcontractors:

    Separate selection process for all classes of work > $20,000(which are not subject to the filed sub-bid law).

    CM provides awarding authority a minimum of 3subcontractors it believes to be qualified based onrelevant factors including, but not limited to, price, quality ofwork, and MBE and/or WBE participation.

    CM requests bids from qualified subcontractors and selectssubcontractor.

    Selection of subcontractors subject to approval of awardingauthority.

  • 7/31/2019 Construction Reform 101

    20/60

  • 7/31/2019 Construction Reform 101

    21/60

    Design Build (for Public Works Projects)

    Effective January 1, 2005

    Awarding authority contracts with one firm that provides bothdesign and construction

    Available to construct public works projects otherwise subject to

    G.L. c. 30, sec. 39M, estimated to cost $5 million or more (e.g.,roadwork, site work, site remediation) with prior approval of theInspector General.

    A 2 phase selection process is required:

    Prequalification via RFQ;

    Formal proposals, including separate technical and pricecomponents.

    Exempt Agencies procedures are subject to IG review andapproval on an annual basis. Exempt agencies are MHD,MassPort and MWRA.

  • 7/31/2019 Construction Reform 101

    22/60

    GENERAL BID & FILED SUB-BID THRESHOLDS

  • 7/31/2019 Construction Reform 101

    23/60

    Bidding Threshold Changes to Ch. 149Public Buildings

    Effective July 19, 2004

    General Bids Four categories based upon estimatedconstruction cost (ECC):

    3 Less than $10,000

    3 $10,000 - $25,000

    3 $25,000 - $100,000

    3 Over $100,000

    Sub-Bids - $20,000 or More

  • 7/31/2019 Construction Reform 101

    24/60

    Bidding Threshold Changes

    ECC Less than $10,000 Public Building Project

    Seek three or more written quotes from firms customarilyperforming type of work sought.*

    Award to responsible firm providing lowest quote.

    Agency must keep records of:

    Firms that were solicited for quotes;

    Quotes submitted; and

    Date and amount of each quote.

    Awarding Authorities can use Operational Services Division (OSD)Trade Contractor List to identify firms from which to seek quotes.

    Not Applicable: DCAM Certification, Filed Sub-Bids or bid deposit.

    (*Note this was recently amended by Chapter 188 of the Acts of 2010 to require only use of sound

    business practices where ECC

  • 7/31/2019 Construction Reform 101

    25/60

    Bidding Threshold Changes

    ECC $10,000 to $25,000 Public Building Project Public notification of scope, defining work and requirements and

    time period for completion of work.

    Posting two weeks on agency website and Comm-Pass or CentralRegister and conspicuous place in primary office of awarding

    authority. Written prices from firms customarily performing type of work

    sought.

    Award to responsible firm providing lowest price.

    Awarding authorities can supplement public notification bynotifying firms on OSD Trade Contractor List or other list of firmscustomarily providing work sought.

    Not Applicable DCAM Certification, Filed Sub-Bids or bid deposit.

  • 7/31/2019 Construction Reform 101

    26/60

    Bidding Threshold Changes

    ECC $25,000 to $100,000 Public Building Project (formerlyprojects $10,000 - $25,000) M.G.L. c. 30, 39M Process Applies

    Advertise two weeks in Central Register & newspaper of generalcirculation, Comm-Pass (recommended)

    Bid Deposit Required.

    Public Bid Opening.

    Award to lowest eligible and responsible bidder (eligible as definedin c. 30, 39M).

    Not Applicable: DCAM Certification or Filed Sub-Bids.

  • 7/31/2019 Construction Reform 101

    27/60

    Bidding Threshold Changes

    ECC over $100,000 Public Building Project (formerly over$25,000) M.G.L. c. 149, 44A-44H Process Applies

    Advertise two weeks in Central Register & newspaper of generalcirculation, Comm-Pass (recommended).

    DCAM Certification Required of General Bidders with UpdateStatement.

    DCAM Certification of Filed Sub-bidders required with UpdateStatement (effective 1/31/05 - C. 507).

    Filed Sub-bid applies for trades in 44F with ECC of $20,000 ormore.

  • 7/31/2019 Construction Reform 101

    28/60

    Bidding Threshold Changes

    ECC over $100,000 (continued)

    Bid Deposit Required.

    Public Bid Opening.

    Award to lowest eligible and responsible general bidder.

    Pre-qualification of prime and sub-bidders:

    Optional for projects with ECC of $100,000 - $10 million,

    Mandatory for non-exempt awarding authorities on projectswith ECC of $10 million or more. Certain state agenciesexempt.

  • 7/31/2019 Construction Reform 101

    29/60

    Bidding Threshold Changes

    Filed Sub-Bids (effective July 19, 2004)

    New filed sub-bid threshold: ECC $20,000 (formerly $10,000).

    Same 17 trades listed in M.G.L. c. 149, 44F apply.

    Effective December 31, 2005 Filed Sub-bidders must be DCAMcertified in specific trades.

  • 7/31/2019 Construction Reform 101

    30/60

    NEW SUBCONTRACTOR CERTIFICATION

    and

    UPDATES TO GENERAL CONTRACTOR CERTIFICATION

  • 7/31/2019 Construction Reform 101

    31/60

    Subcontractor Certification - Effective December 31, 2005

    Filed Sub-bidders must be certified by DCAM in order to bid onChapter 149 building contract work (Project ECC > $100,000,sub-bid ECC $20,000+).

    As of December 31, 2005 a DCAM Certificate of Eligibility &Update Statement will be required with every sub-bid

    submitted on a Chapter 149 building contract. (Chapter 507).

    DCAM has published an implementation schedule forapplication & certification of the 17+ sub-trades during 2005.

    See DCAM Website for up to date

    implementation and certification

    information and forms -

    www.mass.gov/cam

  • 7/31/2019 Construction Reform 101

    32/60

    Subcontractor Certification

    Effective December 31, 2005 (Chapter 507, Acts of 2004)

    DCAM reviews sub-bidder applications for certification in muchthe same way as prime contractors are certified, includingreview of applicants construction experience and financialcondition.

    As of December 31, 2005 every sub-bid for a building contractsubject to the filed sub-bid law (estimated cost of construction>$100,000) must include a copy of a Certificate of Eligibilityissued by DCAM & an Update Statement, containing updatedinformation since sub-bidders last application for certification

    including new projects and projects currently under contract.

    Sub-bidders must certify under penalties of perjury thetruthfulness and completeness of the information in their sub-bid.

  • 7/31/2019 Construction Reform 101

    33/60

    Subcontractor Certification

    Effective December 31, 2005 (Chapter 507, Acts of 2004)

    Sub-contractor certification is essentially the same as prime contractorcertification except:

    Projects evaluated over past 3 years compared to 5 years for

    prime contractors.

    Certificate of eligibility will not show single project andaggregate limits like the certificate for prime contractors.

    Certificate of eligibility will show the number of priorconstruction projects evaluated by DCAM, the averagenumerical value on those projects, and the number ofprojects given scores below the passing score established byDCAM (80%) over last 3 years.

  • 7/31/2019 Construction Reform 101

    34/60

    Subcontractor Certification

    Effective December 31, 2005 (Chapter 507, Acts of 2004) Subcontractor evaluations and responses to subcontractor

    evaluations are public records (this will apply to prime contractorevaluations as well).

    Public agencies that fail to submit to DCAM the sub-contractorevaluations forms together with any sub-contractor responses,within 90 days of project completion (certificate of occupancy) risknot being eligible for state funding.

    Indemnification of $1 million for representatives of public agenciesproviding sub-contractor evaluations with limited indemnification oflegal fees only, if the person is found to have acted in a willful,wanton or reckless manner in the evaluation (this is same as forprime contractors).

  • 7/31/2019 Construction Reform 101

    35/60

    Changes to General Contractor Certification

    Not specifically mandated in Construction Reform legislation.

    Making GC Certification regulations more user-friendly byseparating those directed at the contractor from those directed atthe awarding authority.

    DCAM has incorporated new factors into numerical rating systemincluding criteria such as: termination, amount of litigation, directpayment claims history, OSHA penalties.

    A contractors single project limit will be based on the average ofthe largest two projects, rather than on just the single largestproject.

    Single project and aggregate limits reduced to 130% of theaverage of the two largest projects - 180% if the contractor hasdemonstrated the capacity in the opinion of the Commissioner.

  • 7/31/2019 Construction Reform 101

    36/60

    PREQUALIFICATION OVERVIEW

    (FOR DESIGN-BID-BUILD PROJECTS)

  • 7/31/2019 Construction Reform 101

    37/60

    Prequalification Overview (Design-Bid-Build Projects)

    What is Prequalification?

    Prequalification is part of a new two-phased procurementprocess utilized by public awarding authorities (on design-bid-build projects) which enables public awarding authorities to limit

    the bidding pool to general bidders and sub-bidders who arequalified to do the work.

    The Two-Phase Process:

    RFQ Phase the awarding authority issues a RFQ and reviewsinformation submitted to determine qualified bidders.

    RFP Phase only prequalified bidders are invited to bid.

  • 7/31/2019 Construction Reform 101

    38/60

    Prequalification Overview

    Advantages of Prequalification

    Only prequalified contractors are in bidding pool.

    Raises the bar for quality of work.

    Price not the sole deciding factor.

  • 7/31/2019 Construction Reform 101

    39/60

    Prequalification Overview

    When is prequalification required by awarding authority? Mandatory for all non-exempt public awarding authorities to

    prequalifiy all general contractors and filed sub-bidders forpublic construction projects with estimated construction costs of$10 million or more.

    Discretionary for all non-exempt public awarding authoritiesto prequalify all general contractors and filed sub-bidders whereestimated construction costs are between $100,000 and

    $10,000,000.

    Discretionary for exempt agencies.

    Division of Capital Asset Management,Mass Port Authority, Mass Water ResourceAuthority, Mass State College Building Authority,U Mass Building Authority.

  • 7/31/2019 Construction Reform 101

    40/60

    Prequalification Overview

    Prequalification Steps: Prequalification Committee established.

    Public notice of RFQ.

    Statements of Qualifications submitted by GC and filed subs.

    Evaluation of Statements of Qualifications.

    Selection of prequalified bidders.

    RFP issued to prequalified bidders.

  • 7/31/2019 Construction Reform 101

    41/60

    Prequalification Overview

    Composition of Prequalification Committee: 1 representative from design group.

    3 representatives from public owner (OPM is 1 of the 3 if OPMrequired).

    RFQ Requirements

    Public Notice awarding authority must advertise RFQ in thenewspaper, central register and COMPASS system.

    Qualification Requirements/Points awarding authoritymust set forth the qualifications and evaluations points in the

    public notice.

  • 7/31/2019 Construction Reform 101

    42/60

    Prequalification Overview

    Public Notice of RFQ contains:

    Time and date for receipt of response; address to whichresponses should be sent; and timeframe that awarding authoritywill respond;

    General description of building project;

    Evaluation procedure and criteria for prequalification (includingthe point rating system and schedule for evaluation);

    Anticipated schedule and estimated cost for the building project;

  • 7/31/2019 Construction Reform 101

    43/60

  • 7/31/2019 Construction Reform 101

    44/60

    Prequalification Overview

    Evaluation Criteria:

    Mandatory Requirements

    Management Experience (25/50 points required)

    References (15/30 points required)

    Capacity to Complete Projects (10/20 points required)

  • 7/31/2019 Construction Reform 101

    45/60

    Prequalification Overview

    Mandatory Requirements

    Commitment letter from bonding company for payment andperformance bonds at 100% of estimated project value. (Onprojects with prequalification both general bidders and filed sub-bidders will be required to provide their own payment and

    performance bonds and must carry the cost of the bonds in theirown bid prices); and

    DCAM Certificate of Eligibility showing capacity rating sufficientfor project and an Update Statement.

  • 7/31/2019 Construction Reform 101

    46/60

    Prequalification Overview

    Management Experience - 25/50 points required Business owners experience

    Experience of management personnel

    Similar projects

    Terminations Legal proceedings

    Safety record

    MBE/WBE and Workforce compliance records

  • 7/31/2019 Construction Reform 101

    47/60

    Prequalification Overview

    References - (15/30 points required) Project references

    Credit references

    Public project record over last 3 years

    Capacity to Complete - (10/20 points required)

    Audited financial statements from general contractor for currentfiscal year (filed sub-bidders do not have to submit)

    Revenue under contract for next 3 years

  • 7/31/2019 Construction Reform 101

    48/60

    Prequalification Overview

    Evaluation Process Statements of Qualifications not opened publicly but opened in

    presence of 1 or more witnesses.

    Register of Responders prepared for public records.

    PQC evaluation based ONLY on criteria set forth in RFQ.

    minimum score of 70 required to be prequalified.

    minimum of 3 prequalified general contractors and filed sub-bidders in each trade required.

  • 7/31/2019 Construction Reform 101

    49/60

    Prequalification Overview

    What if there are less than 3 prequalified general contractorsor filed sub-bidders?

    If < 3 prequalified & prequalification is mandatory, thenawarding authority must solicit additional responses to RFQ byreadvertising. After second solicitation if still

  • 7/31/2019 Construction Reform 101

    50/60

    Prequalification Overview

    Review of Decision

    Upon inquiry, general contractors and filed sub-bidders areentitled to know their score.

    Decision of Prequalification Committee final and not subject toappeal (except where evidence of arbitrary, capricious, fraud or

    collusion).

  • 7/31/2019 Construction Reform 101

    51/60

    Prequalification Overview

    Resources: DCAM Website (www.mass.gov/cam)

    810 CMR 9.00 (General Contractor Prequalification Regulations)

    810 CMR 10.00 (Subcontractor Prequalification Regulations)

    DCAM Guidelines for Prequalification of General Contractors andSubcontractors to Work on Public Building Construction Projects

    Office of Inspector General Website (www.mass.gov/ig)

    Designing and Constructing Public Facilities (6th ed.)

  • 7/31/2019 Construction Reform 101

    52/60

    OWNERS PROJECT MANAGER

  • 7/31/2019 Construction Reform 101

    53/60

    Improved Project Oversight - Owners Project Manager

    Owners Project Manager

    Owners Project Manager (OPM) requiredon all projects with ECC of $1.5 millionor more.

    OPM Must be a registered Architect or Engineer with five yearsrelevant experience, or if not registered seven years relevantexperience.

    Hired before designer, serves as public agencies agent and

    consultant throughout planning, design, procurement andconstruction including advice on selection of designer, design,value engineering, scope, estimating, general and subcontractorpre-qualification and selection, scheduling and construction.

  • 7/31/2019 Construction Reform 101

    54/60

    Owners Project Manager (continued)

    Agency may assign an employee to serve as owners projectmanager if they meet qualification requirements.

    Owners Project Manager must be independent of designer,general contractor and sub-contractor.

    Qualifications based selection process required to procure OPM.

    Owners Project Manager Guidelines posted on DCAM website.

    www.mass.gov/cam

  • 7/31/2019 Construction Reform 101

    55/60

    DESIGNER SELECTION

  • 7/31/2019 Construction Reform 101

    56/60

    Designer Selection Changes

    Awarding Authorities may now utilize same designer thatconducted the feasibility study for the project final design withoutmandatory peer review.

    Municipalities must use standard designer selection form issued byDesigner Selection Board (DSB).

  • 7/31/2019 Construction Reform 101

    57/60

    AFFIRMATIVE MARKETING PROGRAM

    (MBE/WBE)

  • 7/31/2019 Construction Reform 101

    58/60

    MBE/WBE Participation-Affirmative Marketing Program(revision to M.G.L. c. 7, 40N and c. 23A, 44)

    MBE/WBE goals set by DCAM

    Published in Central Register, currentlyDesign - 8% MBE, 4% WBEConstruction 7.4% MBE, 4% WBE

    Apply to all state assisted building projects includes projects bymunicipalities and political subdivisions when costs paid in wholeor in part by Commonwealth.

    DCAM and Supplier Diversity Office (formerly SOMWBA) developprocedures for adjustment of goals by awarding authority onindividual projects.

  • 7/31/2019 Construction Reform 101

    59/60

    Affirmative Marketing Program (continued)

    DCAM and Supplier Diversity Office develop good faith effortswaiver procedure before award for use by awardingauthorities.

    Supplier Diversity Office monitors and reports for politicalsubdivisions Affirmative Marketing Program.

    DCAM monitors and reports for DCAMs Affirmative MarketingProgram.

    DCAM & MassHousing currently undertaking new disparitystudy.

  • 7/31/2019 Construction Reform 101

    60/60

    QUESTIONS AND ANSWERS