32
SEWERAGE SCHEME OF RAHIM YAR KHAN CITY WITH TREATMENT PLANT ZONE I Targets of Balance Work Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 A STP,Pattan Minara 1 Brick Lining 200 Sq.m/ day i) Arrangement of Material / Labour ii) 2 Interconnection of Ponds 36 Nos. i) Arrangement of Material / Labour ii) 21" i/d 63 Nos. 15 pipes/day 18" i/d 36 Nos. 15 pipes/day iii) Excavation / Lean Concrete 2 Structures/day iv) Steel Fabrication of Inlet / outlet slides 1 Structure/day v) Concrete laying of inlet / outlet slides 2 Structures/day vi) Laying of pipes and concrete pouring 2 Structures/day 3 Soling / Brick Pavement ( 8433 m) 100 m / day i) Arrangement of Material / Labour ii) Levelling / Dressing / Compaction of bed 150 m / day iii) 423 sq.m 4 Barbed Wire Fencing 2539 m i) ii) Casting of Concrete Poles (1036/15 = 70 days) iv) Installation of Concrete Poles 1036 /20 = 52 days 20 Poles / day v) Installation of Barbed Wire (2539 / 30 = 85 days) 30 m / day 5 Distribution Chamber 1 Job i) Arrangement of material ii) Excavation / Lean concrete Steel Fabrication for Base Slab iv) Concrete Laying in Base Slab Sr No. 677 m 3 Lining (daily consumption of Bricks (322807/30=10760 Nos /day) 01 Structure / day Supply of R.C.C pipes 21"i/d = 63 Nos,18" i/d = 36 Nos. 4035 m 3 Pavement (Cosumption of bricks 1923968/90 = 21377 / day) Arrangement of Material / Labour / Moulds for casting of R.C.C Posts Base Plate 15 Nos. iii ) Arangement of barbed wire (13 gauge) and eye bolts (10 mm) iii )

Construction Schedule for sewege treatment plant

Embed Size (px)

DESCRIPTION

here is a detail schedule for the construction of sewage treatment plant. abstract of a part of a project executed in pakistan.

Citation preview

SEWERAGE SCHEME OF RAHIM YAR KHAN CITY WITH TREATMENT PLANTZONE I

Targets of Balance Work

Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 Remarks

A STP,Pattan Minara

1 Brick Lining 200 Sq.m/ day

i) Arrangement of Material / Labour

ii)

2 Interconnection of Ponds 01 Structure / day 36 Nos.

i) Arrangement of Material / Labour

ii)

21" i/d 63 Nos. 15 pipes/day

18" i/d 36 Nos. 15 pipes/day

iii) Excavation / Lean Concrete 2 Structures/day

iv) Steel Fabrication of Inlet / outlet slides 1 Structure/day

v) Concrete laying of inlet / outlet slides 2 Structures/day

vi) Laying of pipes and concrete pouring 2 Structures/day

3 Soling / Brick Pavement ( 8433 m) 100 m / day

i) Arrangement of Material / Labour

ii) Levelling / Dressing / Compaction of bed 150 m / day

iii) 423 sq.m

4 Barbed Wire Fencing 2539 m

i)

ii) Casting of Concrete Poles (1036/15 = 70 days)

iii)

iv) Installation of Concrete Poles 1036 /20 = 52 days 20 Poles / day

v) Installation of Barbed Wire (2539 / 30 = 85 days) 30 m / day

5 Distribution Chamber 1 Job

i) Arrangement of material

ii) Excavation / Lean concrete

iii) Steel Fabrication for Base Slab

iv) Concrete Laying in Base Slab

Sr No.

677 m3

Lining (daily consumption of Bricks(322807/30=10760 Nos /day)

Supply of R.C.C pipes 21"i/d = 63 Nos,18" i/d = 36 Nos.

4035 m3

Pavement (Cosumption of bricks 1923968/90 = 21377 / day)

Arrangement of Material / Labour / Moulds for casting of R.C.C Posts

Moulds 5 Nos.Base Plate 15 Nos.

Arangement of barbed wire (13 gauge) and eye bolts (10 mm)

Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.

v) Steel Fabrication of Walls

vi) Concrete pouring in walls

6 Inlet Channel 15 m / day 535 m

i) Arrangement of material and labour (535/15 = 53 days)

ii) Excavation / Lean concrete

iii) Steel Fabrication in Base Slab

iv) Concrete laying in base Slab

v) Steel Fabrication for walls

vi) Concrete pouring in walls

7 Outlet channel 15 m / day 610 m

i) Arrangement of material and labour (610/15 = 40 days)

ii) Excavation / Lean concrete

iii) Steel Fabrication in Base Slab

iv) Concrete laying in base Slab

v) Steel Fabrication for walls

vi) Concrete pouring in walls

8 Area Lighting 1 pole/ 3 days 1 Job

i) Arrangement of poles

ii)

9 Plantation 3421 Nos.

i) Laying of Sweet soil

ii) Arrangement of plants

iii) Plantation 3421/60 = 57 /day

B Pattan Minara Disposal

1 Generator Room 1 Job

i) Arrangement of material and labour

ii) Excavation and Lean Concrete

iii) Steel Fabrication for Columns and Beams

iv) Concrete Pouring in columns and Beams

v) Brick Work / Foundation / Cable Trench / Flooring

vi) Fabrication for Roof slab

vii) Concrete laying in Roof slab

viii) Fixing of Windows / Ventilators / Door Shutter

Installation of poles with laying of wires (8 nos. x 3 days = 24 days)

Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.

ix) Plaster

x) Electrification

2 Staff Quarter 1 Job

i) Arrangement of material and labour

ii) Excavation and Lean Concrete

iii) Brick Work / Flooring / Plaster

iv) Fixing of Door / Window / Ventilators

v) Electrification

vi) Sanitary Works

3 Pluging 4 Jobs

i) Arrangement of material /labour / machinery

ii) First layer

iii) Second layer

iv) Third layer

v) Final Layer / Finishing

4 Dry Well 1 Job

i) Civil Work

ii) Intermediate Slab

iii) Stairs / Railing

iv) Brick Work

v) Fixing of Girder / Chain Pully

v) Roof Slab

5 Electrical works 1 Job

i) Manual Change Over

ii) Control pannel

iii) Motor control centre

6 Installation of Machinary & Yard Piping 1 Job

i) Construction of Foundation for Pumps

ii) M.S Sheet Installation under pumps

ii) Fixing of Machinery

iii) Yard Piping (suction, delivery with specials)

Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.

7 Boundary wall (182 / 40 = 05 m/ day) 5 m / day 182 m

i) North Side

ii) East Side

iii) West Side

iv) South Side

C Lift station Sadiq Branch

1 Generator Room 1 Job

i) Arrangement of material and labour

ii) Excavation and Lean Concrete

iii) Steel Fabrication for Columns and Beams

iv) Concrete Pouring in columns and Beams

v) Brick Work / Foundation / Cable Trench / Flooring

vi) Fabrication for Roof slab

vii) Concrete laying in Roof slab

viii) Fixing of Windows / Ventilators / Door Shutter

ix) Plaster

x) Electrification

2 Staff Quarter 1 Job

i) Arrangement of material and labour

ii) Excavation and Lean Concrete

iii) Brick Work / Flooring / Plaster

iv) Fixing of Door / Window / Ventilators

v) Electrification

vi) Sanitary Works

3 Sinking 4 Jobs

i) Arangement of machinery

ii) Dewatering set etc.

iii) Excavation under SSWL

Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.

4 Pluging 4 Jobs

i) Arrangement of material /labour / machinery

ii) First layer

iii) Second layer

iv) Third layer

v) Finishing

5 Dry Well 1 Job

i) Civil Work

ii) Intermediate Slab

iii) Stairs / Railing

iv) Brick Work

v) Fixing of Girder / Chain Pully

v) Roof Slab

6 Electrical works 1 Job

i) Manual Change Over

ii) Control pannel

iii) Motor control centre

7 Installation of Machinery 1 Job

i) Construction of Foundatio for Pumps

ii) M.S Sheet Installation under pumps

ii) Fixing of Machinery

iii) Yard Piping (suction, delivery with specials)

8 Screening Chamber 1 Job

i) Arrangement of Material (Screen / Pen Stock, etc)

ii)

iii) Fixing of Screen

iv) Fixing of Pen Stock

9 Boundary wall (182 / 40 = 05 m/ day) 5 m / day 180 m

i) North Side

ii) South Side

iii) East Side

Intermediate Slab (Shttering / Steel Fabrication / Concrete Pouring

Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.

iv) West Side

D Sewer Lines

1 Manufacturing of Pipe 72" dia 390 m / 160 Nos.

2 Laying of Pipe Line V - X 72" dia 1072 m

3 Manufacturing of Pipe 66" dia 512 m

4 Laying of Pipe Line R - V 66" dia 543 m

5 30 m

E Other works

1 Ittefaq colony disposal

2 Missing link to old disposal Line S -T 27" dia

i) Manufacturing of pipe 317 m / 130 Nos.

ii) Laying of pipe 318 m / 130 Nos.

3 G - I sewer line 48" dia

i) Manufacturing of pipe 543 m/ 223 Nos.

ii) Laying of pipe 543 m/ 223 Nos.

4 Line N-H City chowk crossing 21" dia 192 m / 79 Nos.

5 L-AW - 6a Abdu Zahbi road 21" dia

i) Manufacturing of pipe 287 m / 118 Nos.

ii) Laying of pipe 287 m / 118 Nos.

6 L-AW-6a Nazim Line 12", 15", 18" dia

i) Manufacturing of pipe 1636 m/ 670 Nos.

ii) Laying of pipe 1636 m / 670 Nos.

7 U1-V1 Niazi colony missing link, 24" dia

i) Manufacturing of pipe 390 m/ 160 Nos.

ii) Laying of pipe 390 m/ 160 Nos.

8 L-AW-2a Rescue/Hospital Road 21"dia

i) Manufacturing of pipe 852 m/ 350 Nos.

ii) Laying of pipe 852 m/ 350 Nos.

Laying of Pipe Line B - R 27" dia / M.H

Assumption-Stay order vacated in

January,11

Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.

9 A1-C Shahi road 12", 15" dia

i) Manufacturing of pipe 649 m/ 266 Nos.

ii) Laying of pipe 649 m/ 266 Nos.

10 A2-C-B Shahi road 15",18" dia

i) Manufacturing of pipe 791 m/ 324 Nos.

ii) Laying of pipe 791 m/ 324 Nos.

11 Collection Chamber Dari sangi "Q" Point 1 Job

12 Q-J Crossing of Fauji Chowk 24" dia 35 m

13 Collection Cahmber Ittefaq Town "U" Point 1 Job

14 Q-J Zarai College (additional) 18" dia

i) Manufacturing of pipe 65 m / 27 Nos.

ii) Laying of pipe 65 m / 27 Nos.

15 Syphon Line Y-Z 72" dia 1 Job

i) Arrangement of material / Labour

ii) Diversion of seepage drain

iii) Excavation / Lean Concrete

iv) Steel Fabrication for Base Slab

v) Concrete Laying in Base Slab

vi) Steel Fabrication / Shuttering of Walls

vii) Concrete Pouring

viii) Construction of Manholes

ix) Laying of pipe 72"i/d

x) Steel Fabrication & Shuttering for R.C.C Conduit

xi) Concrete Pouring

xii) Backfill / Dressing / Stone Pitching / Finishing

16 Ventilating Shaft 35 Nos.

i) Arrangement of material (Poles, etc) / labour

Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.

ii) Fixing of Poles

Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.

17 U-V Missing Link 33" dia 10 m

i) Manufacturing of pipe

ii) Laying of pipe

18 U-V Crossing 18" dia

i) Manufacturing of pipe

ii) Laying of pipe

19 D-E-F-H Missing link/M.H 21", 24" dia 44 m

20 Line I-R Missing Manhole 54" dia 1 No.

21 A.C Force main Dari Sangi 4" dia

i) Arrangement of A.C pipe 715 m

ii) Laying of pipe 715 m

iii) Testing of Pipe

22 Fixing of machinery Lift Station Dari Sangi 1 Job

23 Fixing of machinery Lift Station chak 111/P Gharbi. 1 Job

F G.R.P PIPE (Forcemain)

1 176 m

2 285 m

3 560 m

4 253 m

5 120 m

24 m / 9 Nos.

24 m / 9 Nos.

Ittefaq colony Arrangement of pipe 20" Ф

Laying of pipe 20" Ø

Basti Amanat Ali Arrangement of pipe 20" Ф

Laying of pipe 20" Ø

Basti Kahur Arrangement of pipe 36" Ф

Laying of pipe 36" Ø

Chak 111/East/West Arrangement of pipe 36" Ф

Laying of pipe 36" Ø

Pattan Minara Arrangement of pipe 36" Ф

Laying of pipe 36" Ø

SEWERAGE SCHEME OF RAHIM YAR KHAN CITY WITH TREATMENT PLANTZONE II

Targets of Balance Work

Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11

A Lift station Moye Mubark P.IV1 Sinking of well 4 Jobs

i) Arangement of machinery

ii) Dewatering set etc.

iii) Excavation under SSWL

2 Pluging 4 Jobs

i) Arrangement of material / labour / machinery

ii) First layer

iii) Second layer

iv) Third layer

v) Finishing

3 Dry well 1 Job

i) Civil Work

ii) Intermediate Slab

iii) Stairs / Railing

iv) Brick work

v) Fixing of Girder/ Chain Pully

vi) Roof Slab

4 Generator room 1 Job

i) Arrangement of material / labour / machinery

ii) Excavation and lean concrete

iii) Steel fabrication for columns and beams

iv) Concrete pouring in columns and beams

v) Brick work / Foundation / cable trench / flooring

vi) Fabricatio for Roof Slab

vii) Concrete laying in Roof Slab

viii) Fixing of Windows/ Ventilators/ Door Shutters

ix) Plaster

x) Electrification

5 Installation of Machinery & Yard Piping 1 Job

i) Constructio of foundations for pumps

ii) M.S Sheet Installation under pumps

Sr. No.

Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.

iii) Fixing of machinery

iv) Yard piping (suction / delivery with specials)

6 Screening Chamber 1 Job

i) Arrangement of material (Screen/Penstock.etc)

ii)

iii) Fixing of Screen

iv) Fixing of Pen Stock

7 Boundary wall 3 m / day 200 m

i) North Side

ii) East Side

iii) West Side

iv) South

8 GRP Pipe 40" dia 290 m

i) Arrangement of GRP Pipe

ii) Laying of Pipe

iii) Testing of pipe

9 Electrical works 1 Job

i) Manual Change Over

ii) Control Panel

iii) Motor control Centre

10 Ventilating Shaft 4 Nos

i) Arrangement of material (Poles, etc)

ii) Fixing of Poles

B Package III,V1 LAW6-b 18" i/d

i) Manufacturing of pipes

ii) Laying of pipes 219 m / 90 Nos.

2 Under water sewer(KLM 30") 15 m/ (4 MH)

i) Arrangement of material / labour / machinery

ii) Laying of pipe

3 L4a 21" i/d 2 MH

i) Arrangement of material / labour / machinery

Intermediate Slab (Shuttering/Steel Fabrication/Concrete Pouring)

Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.

ii) Laying of pipe

4 LAW1-b 15" i/d 112 Mtr

i) Arrangement of material / labour / machinery

ii) Laying of pipe

5 Under water sewer(KLM 36") 18 Mtr (1 MH)

i) Shifting of Poles

ii) Arrangement of material / labour / machinery

iii) Laying of pipe

6 L5a 12" i/di) Manufacturing of pipe 677 Mtr 279 Nos.

ii) Laying of pipe 677 Mtr 279 Nos.

7 LAW3-b 15" i/di) Manufacturing of pipe 60 Mtr/ 25 Nos

ii) Laying of pipe 60 Mtr 3 M.H

8 Forcemain 12" dia Basti Shahidan 901 Mtr

i) Arrangement of GRP Pipe

ii) Laying of pipe

iii) Testing of Pipe

9 L4b 12" i/d 115 Mtr

i) Arrangement of material / labour / machinery

ii) Laying of pipe

10 Remaining connections in Package III,V 50 Mtr

i) Arrangement of material/ labour/ machinery

ii) Laying of pipe

C Package IX Part I

Lift station Chak 111/P

1 Generator Room 1 Job

i) Arrangement of material/ labour/ machinery

ii) Excavation and lean concrete

iii) Steel Fabrication for columns and beams

iv) Concrete pouring in columns and beams

Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.

v) Brick work/ Foundation/ Cable Trench/ Flooring

vi) Fabrication for Roof slab

vii) Concrete laying in Roof slab

viii) Fixing of Windows/ Ventilators/ Door Shutter

ix) Plaster / Finishing

x) Electrification

2 Dry well 1 Job

i) Civil Work

ii) Intermediate Slab

iii) Stairs / Railing

iv) Brick work

v) Fixing of girder / Chain pully

vi) Roof slab

3 Installation of Machinery 1 Job

i) Construction of foundation for pumps

ii) M.S Sheet Installation under pumps

iii) Fixing of machinery

iv) Yar piping (Suction / Delivery with specials)

4 Electrical works 1 Job

i) Manual Change Over

ii) Control pannel

iii) Motor control centre

Lift station Nore wali/ Kacha sadiq abad road

1 Electrical works 1 Job

i) Manual Change Over

ii) Control pannel

iii) Motor control centre

2 yard piping (Suction / Delivery with specials) 15 Mtr

D Package IX Part II

Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.

Lift station J1 Point Water works

1 yard piping (Suction / Delivery with specials) 1 Job

2 Boundary wall 63 Mtr

i) North Side

ii) East Side

iii) West Side

iv) South Side

Lift station Basti Nayian

1 Forcemain(C.I) 32 Mtr

i) Arrangement of Pipe / Labour / machinery

ii) Laying of pipe

E STP,Moye Mubarak P.VIII

1 Earth Work 157805 Cum

i) Excavation / Filling for Ponds 1520 cu.m/day

2 Lining of Anaerobic ponds 220 Sq.m / Day 3521 Cum.

i) Arrangement of material / labour

ii)

3 Lining of Facultative Ponds 172 Sq.m / Day 3972 Cum

i) Arrangement of material / labour

ii)

4 Lining of Maturation ponds 61 Sq.m / Day 1361 Cum

i) Arrangement of material / labour

ii)

5 Distribution Chamber 1 Job

i) Arrangement of material

ii) Excavation / Lean concrete

iii) Steel Fabrication for Base Slab

iv) Concrete Laying in Base Slab

Lining (daily consumption of bricks 2537159 / 215 = 11800 Nos/ day)

Lining (daily consumption of bricks 1893929 / 205 = 9240 Nos/ day)

Lining (daily consumption of bricks 648952 / 200 = 3245 Nos/ day)

Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.

v) Steel Fabrication of Walls

vi) Concrete pouring in walls

6 Inlet Channel 7 m/ day 497 Mtr

i) Arrangement of material and labour

ii) Excavation / Lean concrete

iii) Steel Fabrication in Base Slab

iv) Concrete laying in base Slab

v) Steel Fabrication for walls

vi) Concrete pouring in walls

7 Interconnection 1 Job

i) Arrangement of Material / Labour

ii)

iii) Excavation / Lean Concrete 1 Structures/day

iv) Steel Fabrication of Inlet / outlet slides 1 Structure/day

v) Concrete laying of inlet / outlet slides 1 Structures/day

vi) Laying of pipes and concrete pouring 1 Structures/day

8 Outlet Channel 8 m / day 549 Mtr

i) Arrangement of material and labour

ii) Excavation / Lean concrete

iii) Steel Fabrication in Base Slab

iv) Concrete laying in base Slab

v) Steel Fabrication for walls

vi) Concrete pouring in walls

9 Soling / Brick Pavement ( 1204 m) 16 m / day 5098.67 Cu.m

i) Arrangement of Material / Labour

ii) Levelling / Dressing / Compaction of bed 50 m / day

iii)

10 Area Lighting 1 pole/ 3 days 1 Job

i) Arrangement of poles

ii)

11 Plantation 3090 Nos

i) Laying of Sweet soil

Casting of R.C.C pipes 21"i/d = 56 Nos,18" i/d = 32 Nos.

10 pipes/day10 pipes/day

Pavement (Cosumption of bricks 2431148/75 = 32415 Nos./ day)

Installation of poles with laying of wires (8 nos. x 3 days = 24 days)

Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.

ii) Arrangement of plants

iii) Plantation 3090/30 = 103 Plants /day

12 Barbed Wire Fence 2575 Mtr

i)

ii)

iii)

iv)20 Poles / day

v)150 m / day

Arrangement of Material / Labour / Moulds for casting of R.C.C Posts

Moulds 5 Nos.Base Plate 15 Nos.

Casting of Concrete Poles (1051/15 = 70 days)

Arangement of barbed wire (13 gauge) and eye bolts (10 mm)

Installation of Concrete Poles 1051 /20 = 53 days

Installation of Barbed Wire (2575 / 150 = 18 days)

SEWERAGE SCHEME OF RAHIM YAR KHAN CITY WITH TREATMENT PLANTZONE II

Targets of Balance Work

Remarks

M/S Friends Engineering Co.

Remarks

Azhar Construction Co.

Remarks

Nadeem Construction

Remarks

Sadaqat Builders

Remarks

work is in progress

M/S Nisar Ahmed & Company

work is in progress

Further time extention may be required after June 2011

Remarks

Further time extention may be required after June 2011

Remarks