Upload
jaka-sembung-golok
View
11
Download
2
Tags:
Embed Size (px)
Citation preview
© ABB Group April 18, 2023 | Slide 1
Energizing SafetySite Safety Resource part 2 slide pack
GF-SA Sustainability Affairs, 29 January 2009
© ABB Group April 18, 2023 | Slide 2
4 Excavations – Traffic segregation
© ABB Group April 18, 2023 | Slide 3
4 Excavations – Safety barriers
© ABB Group April 18, 2023 | Slide 4
5 Vehicles & Mobile Plant
H&S plan should set out the access routes for all vehicles on site. One way system is preferable if feasible to ensure safe operation
and safe passage for pedestrians. Suitable signage to be provided and speed limit to be defined. All drivers and operators to be medically fit, competent, trained
and tested to a suitable level. Evidence to be provided. All drivers to be authorised and keys to vehicles controlled.
© ABB Group April 18, 2023 | Slide 5
5 Vehicles & Mobile Plant
Preventive measures to be taken to avoid the fall of vehicles into excavations or water.
All vehicles and earth moving equipment to be fitted with roll over protection and adequately protected against the weather
All cabs must be kept 1m from any face being excavated.
All earth moving equipment must have all equipment on which safety depends inspected daily e.g. motors, brake, steering gear, chassis, wire ropes etc.
© ABB Group April 18, 2023 | Slide 6
5 Vehicles & Mobile Plant
Adequate signalling or other control arrangements should be provided including reversing operations.
A trained and authorised signaller should be provided when the view of the driver is restricted.
When operating in close proximity to live overhead conductors, adequate precautions should be taken e.g. isolation or erection of OH barriers.
© ABB Group April 18, 2023 | Slide 7
6 Working at Height
Ensure that the work is properly planned, risk assessment based and that it is carried out safely
Where it is reasonably practicable avoid carrying out work at height
Where it cannot be avoided select the most appropriate equipment for work to prevent falls
Where possible use permanent access platforms rather than temporary access
Reduce the distance of and potential consequences of any fall
Ensure the work is carried out by trained and competent persons and the work is properly supervised
Ensure third parties are not put at risk
© ABB Group April 18, 2023 | Slide 8
6 Working at Height - Risk Reduction Hierarchy
Personal Protective Equipment (PPE) should be used as a last resort only after all other control options have been evaluated. Ensure that those who use safety harnesses, lanyards with fall arrestment systems are suitably trained and experienced. Those working at height must be trained in emergency recovery and have emergency rescue kits available
© ABB Group April 18, 2023 | Slide 9
6 Working at Height - Scaffolding
Close boarded to prevent fall of material.
Top rail to be 950mm and intermediate rail to be 470mm.
Toe boards also required
Competent supervision to be in place to ensure proper use.
Load to be evenly distributed and not subject to shock loads and never overloaded.
Workers not to use external scaffolds in weather conditions that might threaten their safety
© ABB Group April 18, 2023 | Slide 10
6 Working at Height - Scaffolding
Scaffolds to be inspected before being taken into use and thereafter e.g. every 7 days and a record kept.
Also after alteration, or if affected by weather or anything that could affect its stability.
Inspection should check on adequacy and fit for purpose and if the materials are of sufficient strength and that the scaffold is stable and the required safeguards are in place.
All scaffolds to be erected, altered or dismantled under the supervision of a competent person.
© ABB Group April 18, 2023 | Slide 11
6 Working at Height - Safety in Use of Ladders
Ladders to be erected with slope of 4:1
Should be placed on firm and level ground and not be displaced
Ladder should not be used as a place of work, it is a means of access.
It should extend 1m above landing level
If greater than 3m they should be secured or footed.
Intermediate landings to be provided where they exceed 9m
© ABB Group April 18, 2023 | Slide 12
6 Working at Height - Scaffold collapse
Investigation revealed:
Design didn’t show adequate information on ties
Contract manager and scaffolder changed this design without checking with design
300 ties were needed only 91 fitted
Ties were defective and scaffolders not trained on how to fix
Main contractor didn’t check design or installation
No scaffold register or weekly inspection
Since incident Main Contractor trained 40 engineers on scaffold inspection and scaffolder carried out company wide re-training
© ABB Group April 18, 2023 | Slide 13
6 Working at Height - Scaffolds
© ABB Group April 18, 2023 | Slide 14
6 Working at Height - Mobile Scaffolds
© ABB Group April 18, 2023 | Slide 15
6 Working at Height - Mobile Scaffolds
© ABB Group April 18, 2023 | Slide 16
6 Working at Height - Mobile ScaffoldsMobile Tower Safety checklist
Item Check
1 Check instructions for erection/dismantle and erect using competent resource
2 Erect on surface that is stable, sound and level
3 Ensure adjustable legs are fully engaged and brakes applied
4 Ensure frame braces are firmly in place
5 Ensure platform within maximum height as stated in the instructions and stabilisers added if required
6 If outdoor use tie to building or other structure where possible
7 Do not sheet towers this adds possible wind loading
8 Do not erect or use mobile towers near to exposed live electrical conductors
9 Do not lean ladders against towers access should be by ladder within the mobile or other suitable means
10 Guard rails and toe boards must be fitted
11 Do not exceed working load for mobile and keep platform tidy
12 Never use adjusting screw to gain extra platform height these are for levelling only
13 The tower should only be moved manually force should be applied to the base section. Ensure working platform clear of personnel and materials when moving
14 Store scaffold material tidily and ensure clean before reuse
© ABB Group April 18, 2023 | Slide 17
6 Working at Height – Mobile Elevated Working Platform (MEWP)
Check list Has the unit been inspected Has an exclusion zone been established Ensure operating conditions are not exceeded e.g. reach, load,
wind speed Ensure ground conditions adequate for use of MEWP To be used by trained operators only If unit to be moved ensure route is clear and ground conditions
safe to use. Beware of fragile covers, overhead power lines Ensure the outriggers safely deployed Do not stand on handrails or climb out of the unit Operator to wear full body harness and lanyard when operating Turn machine off immediately after use
© ABB Group April 18, 2023 | Slide 18
6 Working at Height - Stepladders
Check
Carry out risk assessment to determine suitability
Stepladder materials inspected and in sound condition
Must be stable when opened and standing on a level base
Must be fully opened, all four legs firmly and squarely on the ground
Positioned such that person is facing work
Unless design permits the persons knees should be kept below the top step
The user should not work from the top third unless the steps are designed for this purpose
© ABB Group April 18, 2023 | Slide 19
6 Working at Height - Roof Work
Plan and risk assess the roof work operation make appropriate steps to ensure the workers are safe
Ensure the work is properly supervised
Ensure safe access onto the roof
Ensure edge protection is provided to protect people and materials from falling
Ensure roof openings or fragile areas are securely covered or barriered off
Ensure tools and materials are secured at all times
Ensure people are kept away from the area below the roof
© ABB Group April 18, 2023 | Slide 20
6 Working at Height - Fall arresting
Includes safety nets, air bags etc
Workers to be trained including rescue.
Adequate strength and stability including anchor points.
Adequate clearance including any distortion in the safeguard.
To be provided where guard rails and toe boards are not practicable.
© ABB Group April 18, 2023 | Slide 21
7 Lifting Operations - Cranes
General All lifting equipment should be supplied with instructions for use
and with a test certificate regarding its max Safe Working Load (SWL),
SWL indicators should be fitted to cranes Consider the ground conditions on which the lifting appliance will
be operating. Special bases may be required where the ground is soft.
Outriggers and spreader plates to be deployed SWL load to be marked and for varying SWL then a SWL indicator to be fitted.
Safe working load indicators in use and working.
© ABB Group April 18, 2023 | Slide 22
7 Lifting Operations - Cranes
Safety Checklist General lifting Activities
Item Check
1 Ensure risk assessment and method statement available for lifting
2 Ensure competent people are available to plan, carry out and supervise the lifting work
3 Ensure records of each item involved in the lift have current and valid inspection records
4 Ensure these items are clearly marked with identification numbers and safe working load
5 Ensure method of communicating is agreed in advance
6 Ensure weight of item to be lifted is known
7 Ensure the ground is suitable for equipment and load to be lifted
8 Ensure sling charts , safe working radius charts are being used to plan the lift
9 Ensure correct techniques are being used for attachments and slinging to the item to be lifted
10 Ensure where possible that the angle of the slings does not exceed 90 degrees
11 Ensure slings are protected from sharp edges
12 Avoid doubling up slings
13 Ensure the hook is centrally above the item to be lifted
14 Ensure load is free before lifting
15 Ensure any defective slings are removed from site and responsible person is informed
© ABB Group April 18, 2023 | Slide 23
7 Lifting Operations – Examinations and Tests
All lifting equipment including machines and chains and ropes to be inspected and report issued before first use and after erection, alteration and subsequently at suitable intervals.
Test certificates and examination reports to be available (on site with the crane) specifying the SWL at different radii.
© ABB Group April 18, 2023 | Slide 24
7 Lifting Operations- Mobile Crane ChecklistItem Check
1 Check the crane selected crane has been supplied and it has the correct operating information along with a competent operator
2 Check that the correct and valid inspection paperwork is available for the crane and operator including daily and weekly inspections
3 Check the ground can take the crane outrigger loadings and is as level as possible
4 Ensure protection from live power cables
5 Ensure the area is adequately lit and free from obstruction
6 Ensure a no crush zone behind the crane
7 Ensure there is adequate access for craneage and delivery vehicles
8 Ensure crane operating from planned and agreed location
9 Ensure signaller is available for guiding lift
10 Ensure outriggers (if being used) are fully extended, locked and adequately supported
11 Check the crane is in good condition including tyres
12 Check crane is safe distance from any open excavations
13 Ensure that the lifting attachments on the item being lifted are adequate and have been tested
14 Ensure that the safe load indicator and alarm are working
15 Ensure the lift area is restricted to authorised personnel only. Nobody should be allowed to walk under the suspended load
© ABB Group April 18, 2023 | Slide 25
7 Lifting Operations - Ropes
Only lifting ropes with a known and adequate safe working capacity should be used.
Ropes must be installed, maintained and inspected as per manufacturer’s requirements.
Generally lifting ropes should be inspected at a frequency set down by country laws and regulations. (UK 12 months or if lifting people (man baskets) 6 months
Repaired steel ropes should not be used on hoists.
© ABB Group April 18, 2023 | Slide 26
8 Tools and Machinery
Ensure correct tools or machinery are being used for the job
Ensure all dangerous parts guarded
Ensure guards secured and in good repair
Ensure tools and machinery are in good repair and all safety devices operating correctly
Ensure all operatives are trained and competent
Are electrical tools operating at reduced voltage to reduce risk of death by electrocution
© ABB Group April 18, 2023 | Slide 27
8 Tools and Machinery – Saw benches
Ensure saw has proper guarding, riving and fence safety features
Ensure stop start local and easy to operate
Ensure Safety notices posted in area
Ensure appropriate PPE being worn
Ensure area tidy and segregated from other site operations
Ensure operatives trained in use of machine
© ABB Group April 18, 2023 | Slide 28
9 Electricity
Electrical accidents are caused
Because:
Persons are working on or near equipment which is thought to be dead but in fact is live; or
Because the equipment is known to be live, but those involved are without the requisite training and are not competent therefore, or
They do not have the right equipment and have not applied the appropriate precautions.
© ABB Group April 18, 2023 | Slide 29
H&S plan needs to consider the risk of electrocution in all foreseeable circumstances. This includes:
1. Contact with OH conductors or induced current from them.
2. Contact with buried services.
3. General risks with supplies on site and control.
4. Testing and commissioning activities.
Control of access to site to prevent unauthorised persons.
Suitable warning signs and notices.
9 Electricity
© ABB Group April 18, 2023 | Slide 30
Physical Controls
Disconnect equipment from supply and ensure that the isolator is locked in the OFF position. If a number of people are working on the system then a multiple locking hasp should be used so that each person can apply his personal lock
If isolation has been achieved by removing a fuse then ensure that the fuse is removed and held by the supervisor and that the fuse cabinet is locked and the key retained by the supervisor
A caution/danger notice should be posted on the isolator and also on the conductor to indicate that it is being worked on
All other live circuits in the area should be identified as such.
The circuits to be worked on should be proved as dead by testing. The testing device itself should tested immediately before and after testing
9 Electricity
© ABB Group April 18, 2023 | Slide 31
LOCKOUT & TAGOUT (LOTO) PROCEDURE REQUIREMENT
•Lock all work related switches•Lock all work related powered valves•Put tags on and sign•Test ensure energy isolated•Only the one who locked and tagged can remove it•Remove locks and tags after work
Lockout is a technique used to prevent the release of hazardous energy, or to prevent the hazardous energy from escaping.It is a procedure that protects you from equipment start-up
ELECTRICAL OPERATIONELECTRICAL OPERATION
© ABB Group April 18, 2023 | Slide 32
•Job Safety Analysis (JSA)Job Safety Analysis (JSA)•Permit – to- workPermit – to- work•Proper trainingProper training•Barricade and warning signsBarricade and warning signs•Post warden to ensure no un-Post warden to ensure no un-authorised accessauthorised access•Strictly follow LOTOStrictly follow LOTO
ELECTRICAL OPERATIONELECTRICAL OPERATION
ELECTRICAL WORK SAFETYELECTRICAL WORK SAFETY
© ABB Group April 18, 2023 | Slide 33
Physical Controls
In addition to the above proper designed earthing devices should be applied to the conductors being worked on.
Where there may be adjacent conductors that may be live then additional screening measures will be required to ensure that there is no contact possible.
In the case of HV work (>1000v) safe distances should be established to prevent the risk of arcing.
Risk of induced high voltage to be considered.
9 Electricity
© ABB Group April 18, 2023 | Slide 34
System Controls
The use of a written permit to work linked to the lock off device should be drawn up and issued by the supervisor who should witness the testing of the conductors to ensure that they are dead and that they cannot be made live once work has started, e.g. no possibility of back feed or induced voltages.
On transformers it is important that both sides of the transformer have been isolated and earthed.
Supervisor should check on the work periodically to ensure that there is total compliance with the safety requirements;
Permit must be closed out before conductors are re-energised and only on the orders of a competent person/supervisor after the earthing and short circuiting have been removed.
9 Electricity
© ABB Group April 18, 2023 | Slide 35
Human Controls
The persons who will work on the equipment must be briefed on what is to be done and the precautions to be taken.
They must also be trained for work on the voltage to which they will be exposed;
Workers should comply with ALL the requirements of the permit to work;
The supervisor should be competent in respect of electrical safety at the voltage being worked on.
Operators working on the equipment should also have been trained in appropriate first aid techniques to do with electric shock;
Always follow the ABB 7 Steps
9 Electricity
© ABB Group April 18, 2023 | Slide 36
10 Health - Hazardous Substances
Assess the risks arising to health from the substance to be used in the construction
Decide what precautions are required to carry out the work
You must first try to prevent exposure, where this is not practical adequate controls must be put in place to protect the worker
Ensure the control measures are used and maintained
Monitor the exposure of the worker if necessary
Carry out appropriate health monitoring where your assessment has decided this is necessary or where CoSHH sets specific requirements
Ensure employees are properly informed trained and supervised
© ABB Group April 18, 2023 | Slide 37
Hot processes generating airborne fume e.g. welding
Cold processes generating aerosols e.g. spraying
Dry processes generating airborne dust e.g. dust
Also physical/chemical character of the substance
10 Health – Dust and Fumes
© ABB Group April 18, 2023 | Slide 38
10 Health - Dangerous Atmospheres
Dangerous atmospheres or confined spaces are highly dangerous and are where toxic or harmful gas or fume, or oxygen deficiency may be present. SF6?
Special measures are required to protect against the danger.
Include a permit to enter and an alarm
Tests have been carried out on the atmosphere to ensure it is safe.
Adequate ventilation is provided.
Provision of suitable emergency equipment and procedures.
Presence of flammable liquids or gases introduces an additional hazard.
© ABB Group April 18, 2023 | Slide 39
Toxic &
V Toxic
Harmful Irritant
Corrosive
• Asbestos
• Lead & heavy metals
• PCB’s
• Acids & corrosives
• Contaminated land
• Gases
• Isocyanates
• Explosives
• Flammables
10 Health – Toxic Substances
© ABB Group April 18, 2023 | Slide 40
10 Health - Noise
Assess risk and advise workers
Reduce risk by using less noisy equipment or method
Use acoustic enclosures if practical e.g. site generators
Reduce exposure
Provide hearing protection in accordance with country laws and regulations
© ABB Group April 18, 2023 | Slide 41