Upload
others
View
12
Download
0
Embed Size (px)
Citation preview
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-1
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
CONTENTS
10. HYDROLOGY, HYDROGEOLOGY, GEOLOGY AND SOILS 10-2 10.1 Introduction 10-2 10.2 Legislation and Guidance 10-2 10.3 Overall Approach 10-9 10.4 Baseline Conditions 10-12 10.5 Summary of Proposed Development 10-30 10.6 Good Practice and Embedded Mitigation by Design 10-34 10.7 Assessment of Potential Effects 10-35 10.8 Summary and Conclusion 10-39
Figures (Volume 3)
Figure 10.1: Local Hydrology
Figure 10.2: Soil Plan
Figure 10.3: Superficial Geology Plan
Figure 10.4: Peatland Classification
Figure 10.5: Bedrock Geology Plan
Figure 10.6: Peat Depth
Figure 10.7: Regional Hydrogeology
Figure 10.8: Groundwater Vulnerability
Appendices (Volume 4)
Appendix 10.1: Peat Management Plan (PMP)
Appendix 10.2: Peat Landslide Hazard Risk Assessment (PLHRA)
Appendix 10.3: Peat Investigation
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-2
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
10. HYDROLOGY, HYDROGEOLOGY, GEOLOGY AND SOILS
10.1 Introduction
10.1.1 This Chapter presents an assessment of the potential effects on soils, geology (including peat) and the water
environment as a result of the Proposed Development.
10.1.2 The assessment is supported by data provided by The Highland Council (THC), Forestry and Land Scotland
(FLS) and the Scottish Environment Protection Agency (SEPA) to characterise current baseline conditions. A
programme of site investigation, which has included peat depth and permeability assessment, has also been
completed and used to inform the design of the Proposed Development and to complete the assessment. The
Chapter discusses the baseline conditions and summarises relevant consultation responses. Industry standard
mitigation measures that would be used as part of the proposed works are detailed and the potential effects of
the Proposed Development on soils (including peat), geology, and the local groundwater and surface water
environments are then identified.
10.1.3 This assessment has considered a buffer of 500 m from the Proposed Development, which includes the
overhead lines (OHL), underground cable alignment, access spur roads, and horizontal directional drill
compounds.
10.1.4 The Proposed Development is located across open moorland and commercial forestry that has been partly
clear felled. Some of the clear felled forestry has been subject to peat restoration. Access is granted from the
A836 public road for much of the route while existing forestry and estate tracks are utilised where possible for
vehicular access.
10.1.5 This assessment has been informed by the following appendices, which should be read in conjunction with this
Chapter:
• Appendix 10.1: Peat Management Plan (PMP);
• Appendix 10.2: Peat Landslide Hazard Risk Assessment (PLHRA); and
• Appendix 10.3: Peat Investigation.
10.1.6 This Chapter has been prepared by SLR Consulting Ltd (SLR) under the supervision of a Technical Director
(FCIWEM). SLR have more than 25 years’ experience in the assessment of electrical transmission
infrastructure, soils, geology and the water environment. This experience includes many sites in Scotland in a
similar setting to this Proposed Development.
10.2 Legislation and Guidance
10.2.1 This assessment has been undertaken with regard to the following environmental legislation, planning policy
and general guidance.
Legislation
• The Water Environment (Controlled Activities) (Scotland) Regulations, 2011 (Controlled Activities
Regulations (CAR)) (as amended);
• EU Water Framework Directive (2000/60/EC);
• EU Drinking Water Directive (98/83/EC);
• The Public Water Supplies (Scotland) Regulations 2014;
• The Flood Risk Management (Scotland) Act 2009;
• Surface Waters (Fishlife) (Classification) (Scotland) Amendment Regulations 2003;
• Water Environment and Water Services (Scotland) Act 2003 (WEWS Act); and
• The Water Intended for Human Consumption (Private Supplies) (Scotland) Regulations 2017.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-3
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Planning Policy
10.2.2 In addition to Scottish Planning Policy (SPP) published by The Scottish Government (June 2014), THC
Highland-wide Development Plan (HwDP) (5th April 2012) provides planning guidance on the type and location
of development that can take place in the region. The HwDP presents policies of which the following are
relevant to this assessment:
• Policy 28 - Sustainable Design;
• Policy 30 - Physical Constraints;
• Policy 51 - Trees and Development;
• Policy 52 - Principle of Development in Woodland;
• Policy 53 – Minerals;
• Policy 55 - Peat and Soils;
• Policy 57 - Natural, Built and Cultural Heritage;
• Policy 58 - Protected Species;
• Policy 59 - Other Important Species;
• Policy 60 - Other Important Habitats;
• Policy 62 - Geo-diversity;
• Policy 63 - Water Environment;
• Policy 64 - Flood Risk;
• Policy 69 - Electricity Transmission Infrastructure; and
• Policy 72 – Pollution.
Guidance
10.2.3 The following guidance is also applicable to the assessment.
10.2.4 Planning Advice Notes (PANs) are published by the Scottish Government. Applicable PANs include:
• PAN 50 Controlling the Environmental Effects of Surface Mineral Workings;
• PAN 61 Planning and Sustainable Urban Drainage Systems (SUDS); and
• PAN 69 Planning and Building Standards Advice on Flooding.
10.2.5 SEPA and NetRegs Pollution Prevention Guidelines (PPG) and replacement Guidance for Pollution Prevention
(GPP):
• PPG 1: Understanding your environmental responsibilities - good environmental practices;
• GPP 2: Above ground oil storage tanks;
• GPP 5: Works and maintenance in or near water;
• PPG 6: Working at construction and demolition sites;
• PPG 7: Safe Storage - The safe operation of refuelling facilities;
• GPP 8: Safe storage and disposal of used oils;
• GPP 13: Vehicle washing and cleaning;
• GPP 21: Pollution incident response planning; and
• GPP 22: Dealing with spills.
10.2.6 Construction Industry Research and Information Association (CIRIA) publications:
• C532 Control of Water Pollution from Construction Sites (2001);
• C648 Control of Water Pollution from Linear Construction Projects – Technical Guidance (2006);
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-4
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
• C741 Environmental Good Practice on Site (2015); and
• C753 The SUDS Manual (2015).
10.2.7 SEPA Publications:
• Engineering in the Water Environment: Good Practice Guide – River Crossings (2010);
• Engineering in the Water Environment: Good Practice Guide – Sediment Management (2010);
• Engineering in the Water Environment: Good Practice Guide – Temporary Construction Methods (2009);
• Groundwater Protection Policy for Scotland, Version 3 (2009);
• Land Use Planning System SEPA Guidance Note 4, Issue 9 (September 2017);
• Land Use Planning System SEPA Guidance Note 31, Version 3 (September 2017); and
• Position Statement – Culverting of Watercourses (2015).
10.2.8 Other Guidance:
• Department of Environment, Food and Rural Affairs (DEFRA) Construction Code of Practice for the
Sustainable Use of Soils on Construction Sites (2011);
• DEFRA Good Practice Guide for Handling Soils (Ministry of Agriculture, Fisheries and Food (MAFF) (2000);
and
• Flood Risk and Drainage Impact Assessment: Supplementary Guidance (January 2013).
Information Sources
10.2.9 The following sources of information have been consulted to characterise the soils, geology, hydrogeology and
hydrology of the proposed works and adjacent area:
• Creag Riabhach Wind Farm Environmental Statement, Pegasus Group, January 2014;
• Dalchork 132kV Substation Environmental Appraisal, Ramboll, January 2019;
• Ordnance Survey (OS) 1:50,000 scale mapping data;
• British Geological Survey (BGS) 1:50,000 scale data - superficial deposits, bedrock and linear features
geology1;
• BGS Hydrogeological Map of Scotland, 1988;
• James Hutton Institute National Soil Map of Scotland (1:250,000)2;
• SEPA Groundwater Vulnerability Map of Scotland, SNIFFER, 2004;
• SEPA flood maps3;
• SEPA Water Environment Hub for water body classifications4;
• Scottish Natural Heritage (SNH) Sitelink Online Information Service5;
• SNH Carbon and Peatland 2016 Map6;
• Natural England Magic Map7;
• Joint Nature Conservation Committee The Geological Conservation Review8;
1 British Geological Survey GeoIndex Onshore, http://mapapps2.bgs.ac.uk/geoindex/home.html, accessed April 2019
2 Scotland’s Soils, http://soils.environment.gov.scot/maps/, accessed April 2019
3 Scottish Environment Protection Agency, https://www.sepa.org.uk/environment/water/flooding/flood-maps/ and
http://map.sepa.org.uk/reservoirsfloodmap/Map.htm, accessed April 2019 4 Scottish Environment Protection Agency, Water Classification Hub, https://www.sepa.org.uk/data-visualisation/water-classification-hub/, accessed April
2019 5 Scottish Natural Heritage, Sitelink Inline Information Service, https://gateway.snh.gov.uk/sitelink/searchmap.jsp, accessed April 2019
6 Scottish Natural Heritage, Natural Spaces, https://gateway.snh.gov.uk/natural-spaces/dataset.jsp?dsid=PEAT, accessed April 2019
7 Natural England, Magic Map Application, http://magic.defra.gov.uk/MagicMap.aspx, accessed April 2019
8 JNCC Geological Conservation Review, http://jncc.defra.gov.uk/page-2947, accessed April 2019
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-5
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
• data requests to SEPA regarding details of registered / licensed abstractions and discharges (April 2019);
and
• data requests to THC environmental health department regarding details of historic flooding records and
private water abstractions (April 2019).
Consultation
10.2.10 The consultation process is discussed in detail in Chapter 4 of this EIA Report. Table 10-1 summarises
responses to the consultation responses received that are relevant to soils, geology and the water environment.
Table 10-1: Consultation Responses of Relevance to Hydrology, Hydrogeology, Geology and Soils
Consultee Response Comment
Scoping
Response from
THC
6th June 2019
The proposed route crosses a number of
watercourses and careful consideration of the
siting, design and layout of the overhead line will
be required.
Supplementary Guidance will be important to take
account of within any assessment on development
impact, including the Flood Risk and Drainage
Impact Assessment: Supplementary Guidance
(January 2013).
The design and layout of the
OHL have been considered so
as to minimise impact on
watercourses. Details are set
out in this Chapter.
The noted Supplementary
Guidance has been utilised as
part of this assessment.
Scoping
Response from
SEPA
8th April 2019
The following should be incorporated in the design
of the overhead line, access routes, laydown
areas and construction compounds:
• No OHL poles or construction works should
be located on any watercourse bank;
• Details of groundwater abstractions to be
provided and design of the OHL route should
avoid buffer areas;
• Proposals for temporary watercourse
crossings to be provided; and
• Tree felling waste from works to be removed
from site;
• Proposals for borrow pits should be discussed
with SEPA.
Supporting maps should detail all proposed
upgraded, temporary and permanent site
infrastructure.
The submission must demonstrate how the layout
has been designed to minimise disturbance of
peat and outline the preventative / mitigation
measures to avoid significant drying or oxidation
of peat. The submission must include a detailed
map of peat depths and tabulated excavation
volumes.
Phase 1 habitat wetland areas also known as
Groundwater Dependent Terrestrial Ecosystems
(GWDTE) are protected under the Water
Framework Directive and therefore the layout and
design of the development must avoid impact on
With the exception of where
the proposed OHL crosses
watercourses a 50m buffer
would be applied to
watercourses.
Licensed and private water
abstractions near to the
Proposed Works have been
identified and avoided.
Plans show the location of
proposed upgraded tracks with
relation to watercourses, peat
and GWDTE habitat have
been prepared.
Subject to other development
constraints, areas of deep
peat, potential GWDTE,
flushes and peat instability
have been avoided.
Forestry is assessed in chapter
11.
No borrow pits are required.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-6
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Consultee Response Comment
such areas. A plan should be provided presenting
the locations of potential GWDTEs and buffer
areas.
A schedule of mitigation for the periods of
construction, operation, maintenance, demolition
and restoration should be prepared.
Gate Check
Response from
SEPA
16th December
2019
Following review of the gate check report and
meeting SEPA requested that:
• Permanent access roads (spurs) are shown
on development drawings and have the peat
depth information overlaid with this. If peat is
to be impacted appropriate proposals for peat
re-use should be made;
• Details of peat depths and any peat re-
use/storage proposals should be clearly
outlined, along with restoration proposals for
temporary infrastructure associated with site
compounds at the proposed Crask crossing;
• The route will cross areas of deep peat and
some of the most difficult ground conditions
have been avoided, but any sensitive wetland
habitats and deep peat areas should have
clear mitigation, outlining how impacts will be
minimised. It was noted that bog matting
might only be appropriate in some locations
depending on topography and that low ground
pressure vehicles are commonly used. We
would ask that a suite of measures be
considered by site contractors to ensure a
precautionary approach is taken to minimising
impacts on peat and wetlands;
• It is welcomed that no felled timber will be left
on site and that trees under a merchantable
size will be utilised for the biomass market.
• It is noted that there will be a Peat
Management Plan produced, and this should
address any re-use of excavated peat that will
not be directly used in backfilling. Due to the
peatland restoration works taking place, the
re-use proposals and working methods should
outline how they will compliment these works.
Methods / approach to ditch blocking should
be outlined etc.
• It is noted that the location of a site compound
/ laydown area will be left to discretion of the
principal contractor at a later stage. As
mentioned in the meeting, we would expect
an indicative location to be identified to ensure
that peat and GWDTE considerations have
been considered, and if the permission for
these is included within this proposed
consent, then we are likely to ask for a
condition to be applied.
The location of permanent
access tracks and recorded
peat depths are shown on the
Proposed Development
drawings.
See PMP (Appendix 10.1).
No peat is recorded at the
proposed compound locations
near the Crask River crossing.
See PMP (Appendix 10.1)
and PLHRA (Appendix 10.2).
Noted.
The PMP (Appendix 10.1)
outlines the general nature of
peat management works given
the information available at this
stage. The Applicant will liaise
directly with FLS and the SNH
Peatland Action Group during
the development of the Stage
2 PMP, and any requirement
for post construction
reinstatement and restoration.
As discussed within Section
3.8 of Chapter 3 of this EIA
Report, the locations of any
temporary site compounds
would be at the discretion of
the Principal Contractor.
Insufficient information is
available at this stage to
determine indicative locations,
and they may be located away
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-7
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Consultee Response Comment
from the site altogether;
however, all available
information relation to peat
soils and GWDTEs would be
made available to the Principal
Contractor in order to ensure
compounds are sited so as to
avoid peat and GWDTE.
Scoping
Response from
Scottish Water
3rd April 2019
No objection to proposals. N/A
Scoping
Response from
Scottish Natural
Heritage (SNH)
3rd May 2019
The EIA report should clearly detail what
mitigation will be implemented to prevent impacts
to the Caithness and Sutherland Peatlands
Special Protection Area (SPA) and Special Area of
Conservation (SAC).
Impacts to the River Naver SAC should be fully
considered within the hydrology section of the EIA
report.
A full NVC survey and peat depth survey should
be undertaken for the OHL section that lies within
the Ben Klibreck Site of Special Scientific Interest
(SSSI). SNH habitat data suggests there may be
pockets of blanket bog within the SSSI and these
should be avoided.
Low ground pressure machines should be used
for all construction within protected areas and
peatland habitats and in order to minimise ground
disturbance poles should not be dragged across
the site.
A detailed construction method statement should
be included as a supporting document within the
EIA.
A restoration plan should also accompany the EIA
detailing what restoration methods will be used
including detail what monitoring and subsequent
actions will be undertaken to ensure restoration is
successful.
A plan should be prepared indication the location
of construction compounds and pulling points,
both of which should avoid protected areas and
Class 1 and 2 priority peatland habitats and Class
5 habitats that have undergone restoration
(Dalchork forest).
The construction methodology should detail how
impacts would be minimised on nationally
important peat habitats.
Mitigation measures required
to safeguard Caithness and
Sutherland Peatlands SPA and
SAC, and the River Naver SAC
have been specified (see
Section 10.6).
A NVC survey has been
undertaken (see Chapter 7:
Ecology). A peat depth survey
has been undertake for the
whole route of the Proposed
Development.
Details of construction
methods are outlined in
Chapter 3 of this EIA Report.
This identifies that low ground
pressure vehicles and
temporary access panels
would be utilised to minimise
impacts on all protected areas
and peatland habitats.
Methods for reinstatement
would be detailed in
construction method
statements, as part of the
CEMP.
The locations of construction
compound(s) and pulling
points for the Proposed
Development would be
identified by the Principal
Contractor, who would seek
any permissions required for
such at the point of detailed
design and mitigation will be
provided via the CEMP.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-8
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Consultee Response Comment
Gate Check
Response from
SNH
4th December
2019
In response to the gate check report SNH
commented that:
• The proposed line will cross the River Naver
SAC and that impacts to this SAC should be
considered in full within the EIAR. The
qualifying features of the SAC are vulnerable
to pollution and the EIAR should detail what
mitigation will be implemented to avoid
impacts to this protected area.
• Some of the proposed line will pass through
Class 1 and Class 2 Carbon Rich Soils, Deep
Peat and Priority Peatland Habitat and
construction methodology should detail how
minimised on this habitat.
• The proposed line will pas through areas of
restored peat restored through Peatland
Action. These areas should be left in as good
or better condition on completion of
construction of the line. Pre and post
construction surveys should be completed by
a drone survey. Any required restoration
works should be agreed with SNH and FLS.
• The EIAR should detail what mitigation will be
provided to safeguard water quality in the
River Tirry during proposed Horizontal
Directional Drilling (HDD) beneath the river.
SNH advise that a geotechnical survey should
be undertaken prior to any HDD drilling to
ensure bentonite does not leak within the river
bed.
See Good Practice and
Embedded Mitigation by
Design.
See embedded mitigation and
PMP (Appendix 10.1).
See Good Practice and
Embedded Mitigation by
Design and the commitment to
undertaken pre and post
development surveys.
See Good Practice and
Embedded Mitigation by
Design which includes site
investigation to inform the
HDD programme.
Marine Scotland
Science (MSS)
Information on local fish populations and fisheries
should be sought from the Kyle of Sutherland and
the Brora District Salmon Fishery Boards (DSFB)
and the Kyle of Sutherland Fisheries Trust.
MSS ask that the ES includes the following:
• A description of which fish species are
present and their abundance in the
waterbodies and watercourses which could be
impacted by the development, and whether
they are important for conservation or
supporting fisheries;
• A description of the water quality of
waterbodies which could be impacted and
how the development may impact on these
pre-construction conditions;
• A description of what activities during
construction, post-construction and
decommissioning have the potential to impact
on fish or associated fisheries and what
mitigation measures will be put in place to
avoid and / or reduce this impact;
See Chapter 7 (Ecology) of
this EIA Report for information
on fisheries.
The existing quality of
watercourses and pressures
on these has been identified
(see Section 10.4: Baseline
Conditions).
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-9
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Consultee Response Comment
• Consideration of potential cumulative effects
with adjacent and other developments; and
• Proposals for monitoring during construction,
post-construction and decommissioning.
Kyle of
Sutherland
DSFB
26th April 2019
The Tirry catchment is subject to a salmon
restoration project involving the Kyle of Sutherland
DSFB, SSE and SEPA. Consideration of this
project must be given to protecting the aquatic and
riparian environment.
See Chapter 7 (Ecology) of
this EIA Report.
Safeguards to protect water
quality and flows of water in
the River Tirry have been
specified.
Gate Check
Response from
RSPB
12th December
2019
In response to the gate check report, RSPB
commented that the findings of site works and the
peat investigation work should be undertaken to
inform the new alignment should be included in
the EIA.
See Peat Investigation report
(Appendix 10.3).
10.3 Overall Approach
10.3.1 This assessment has involved the following:
• review of the Creag Riabhach Wind Farm Environmental Statement and Dalchork Substation
Environmental Appraisal;
• a desk study to establish existing soils, geology and hydrogeological and hydrological conditions beneath
and adjacent to the Proposed Development;
• site familiarisation visits by the technical team of this Chapter (14/05/2019 and 16-19/09/2019), which
included a peat investigation, assessing watercourse crossings and a Private Water Supply (PWS) survey;
• identification of the potential effects on the soils, geology and water environment and their significance; and
• identification of additional required mitigation measures and assessment of any residual effects.
Assessment Method
Assessing Significance
10.3.2 The significance of potential effects from the Proposed Development has been assessed by considering two
factors: the sensitivity of the receiving environment and the potential magnitude of effect, should that occur.
10.3.3 The assessment methodology has also been informed by experience of carrying out such assessments for a
range of electrical infrastructure developments, knowledge of the water environment characteristics in Scotland
and cognisance of good practice.
10.3.4 This approach provides a mechanism for identifying the areas where mitigation measures are required and for
identifying mitigation measures appropriate to the significance of potential effects presented by the Proposed
Development.
10.3.5 Criteria for determining the significance of effect are provided in Table 10-2, Table 10-3 and Table 10-4.
Sensitivity of Receptor
10.3.6 The sensitivity of the receiving environment (i.e. the baseline quality of the receiving environment) is defined as
its ability to absorb an effect without a detectable change. It can be considered through a combination of
professional judgement and a set of pre-defined criteria which are set out in Table 10-2. Receptors in the
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-10
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
receiving environment only need to meet one of the defined criteria to be categorised at that associated level of
sensitivity.
Table 10-2: Criteria for Assessing Sensitivity of Receptor
Sensitivity Example
High • SEPA Water Framework Directive Water Body Classification: High-Good or is
close to the boundary of a classification Moderate to Good or Good to High;
• receptor is of high ecological importance or national or international value (e.g.
SSSI, SAC, habitat for protected species or Geological Conservation Review
sites) which may be dependent upon soil, geology or the hydrology of the
development area;
• receptor is at high risk from flooding above 0.5% Annual Exceedance Probability
(AEP) and / or water body acts as an active floodplain or flood defence;
• receptor is used for public and / or private water supply (including Drinking Water
Protected Areas (DWPA);
• groundwater vulnerability is classified as high; and
• if a GWDTE is present and identified as being of high sensitivity.
Moderate • SEPA Water Framework Directive Water Body Classification Moderate or is
close to the boundary of a classification Low to Moderate;
• receptor is at moderate risk from flooding (0.1% AEP to 0.5% AEP) but does not
act as an active floodplain or flood defence; and
• moderate classification of groundwater aquifer vulnerability.
Low • SEPA Water Framework Directive Water Body Classification Poor or Bad;
• receptor is at low risk from flooding (less than 0.1% AEP); and
• receptor not used for water supplies (public or private).
Not Sensitive • receptor would not be affected by the Proposed Development, e.g. lies within a
different and unconnected hydrological or hydrogeological catchment.
Magnitude of Effect
10.3.7 The potential magnitude of an effect would depend upon whether the potential effect would cause a
fundamental, material or detectable change. In addition, the timing, scale, size and duration of the potential
change resulting from the Proposed Development are also determining factors. The criteria that have been
used to assess the magnitude of effect are defined in Table 10-3.
Table 10-3: Criteria for Assessing Magnitude of Effect
Magnitude Criteria Definition
Major Results in loss of
attribute
Fundamental (long term or permanent) changes to the
baseline hydrology, hydrogeology, soils and geology such as:
• wholesale changes to watercourse channel, route,
hydrology or hydrodynamics;
• changes to the site resulting in an increase in runoff with
flood potential and significant changes to erosion and
sedimentation patterns;
• major changes to the water chemistry; and
• major changes to groundwater levels, flow regime and risk
of groundwater flooding.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-11
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Magnitude Criteria Definition
Medium Results in effect on
integrity of attribute
or loss of part of
attribute
Material but non-fundamental and short to medium term
changes to baseline soils, geology, hydrology, hydrogeology
and water quality, such as:
• some fundamental changes to watercourses, hydrology or
hydrodynamics. Changes to site resulting in an increase
in runoff within system capacity;
• moderate changes to erosion and sedimentation patterns;
• moderate changes to the water chemistry of surface runoff
and groundwater; and
• moderate changes to groundwater levels, flow regime and
risk of groundwater flooding.
Low Results in minor
effect on attribute
Detectable but non-material and transitory changes to the
baseline soils, geology, hydrology, hydrogeology and water
quality, such as:
• minor or slight changes to the watercourse, hydrology or
hydrodynamics;
• changes to site resulting in slight increase in runoff well
within the drainage system capacity;
• minor changes to erosion and sedimentation patterns;
• minor changes to the water chemistry of surface runoff and
groundwater; and
• minor changes to groundwater levels, flow regime and risk
of groundwater flooding.
Negligible Results in an effect
on attribute but of
insufficient
magnitude to affect
the use / integrity
No perceptible changes to the baseline soils, geology,
hydrology, hydrogeology and water quality such as:
• no alteration or very minor changes with no effect to
watercourses, hydrology, hydrodynamics, erosion and
sedimentation patterns;
• no pollution or change in water chemistry to either
groundwater or surface water; and
• no alteration to groundwater recharge or flow mechanisms.
Potential Effects
10.3.8 The sensitivity of the receptor together with the magnitude of effect determines the significance of the effect,
which can be categorised into a level of significance as identified in Table 10-4. This also takes into account
good practice measures implemented and embedded as part of the design and construction of the Proposed
Development and use of professional judgement where appropriate. Good practice measures (i.e. embedded
mitigation) are discussed later in the Chapter.
10.3.9 The significance of a potential effect provides a guide to assist in decision making. However, it should not be
considered as a substitute for professional judgment and interpretation. In some cases, the potential sensitivity
of the receiving environment or the magnitude of potential effect cannot be quantified with certainty and
therefore, professional judgement remains the most robust method for identifying the predicted significance of a
potential effect.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-12
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Table 10-4: Significance of Effect
Magnitude of
Effect
Sensitivity of Receptor
High Moderate Low Not Sensitive
Major Major Major Moderate Negligible
Medium Major Moderate Minor Negligible
Low Moderate Minor Minor Negligible
Negligible Negligible Negligible Negligible Negligible
Mitigation
10.3.10 Potential effects of the Proposed Development on the water environment, soils or geology identified by the
assessment have been addressed and mitigated by the design and application of good practice guidance to be
implemented as standard during construction and operation. As such, a number of mitigation measures would
form an integral part of the construction process and these have been taken into account prior to assessing the
likely effect of the Proposed Development (embedded mitigation). Where appropriate, further tailored mitigation
measures have been identified prior to determining the likely significance of residual effects.
10.3.11 Good practice measures will be applied in relation to pollution risk, sediment management, soils management
and management of surface runoff rates and volumes. This would form part of the Construction and
Environmental Management Plan (CEMP) to be implemented for the Proposed Development and would be
prepared prior to construction.
10.3.12 The final CEMP would include details and responsibilities for environmental management and outline the
necessary surface water management, oil and chemical delivery and storage requirements, waste
management, traffic and transport management and would specify monitoring requirements for waste water,
water supply.
Residual Effects
10.3.13 A statement of residual effects, following consideration of any further specific mitigation measures where
identified, is then given where required.
Statement of Significance
10.3.14 The assessment provides a Statement of Significance associated with the Proposed Development. Effects of
major and moderate significance are considered to be significant in terms of the EIA Regulations.
Cumulative Effect Assessment
10.3.15 Due to the nature of the Proposed Development, in addition to the good practice and mitigation measures set
out at the end of this Chapter, significant cumulative effects on soils, geology or the water environment are not
anticipated, and thus an assessment of cumulative effects has not been included.
10.4 Baseline Conditions
10.4.1 This Section presents information gathered regarding existing soils, geological, hydrogeological and
hydrological conditions (including flood risk). Figure 10.1: Local Hydrology shows the hydrological setting.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-13
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Soils
10.4.2 An extract of 1:250,000 National Soil Map of Scotland is presented as Figure 10.2: Soil Plan, review of which
indicates that the route of the Proposed Development and access tracks are underlain by peaty gleys, blanket
peat and peaty podzols:
• peaty gleys have been recorded for much of the OHL route within the River Vagastie catchment (Photograph
10-1) and three sections of the route within the River Tirry catchment. Peaty gleys are described as drifts
derived from schists, gneisses, granulites and quartzites principally of the Moine Series. Landforms generally
associated with this soil type within the study area are undulating lowlands and uplands with gentle and
strong slopes with no-rocky exposures.
• blanket peat is the dominant soil type underlying the OHL route within the River Tirry catchment (Photograph
10-2.
• peaty podzols are recorded toward the south. Landforms associated with the peaty podzols have been
described as hummocky valleys and slope moraines with frequent boulders.
Photograph 10-1 River Vagastie, Looking Northeast towards WX06 and Meall nan Con
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-14
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Photograph 10-2 Exposure of Blanket Peat near Crask Inn
10.4.3 A comprehensive programme of peat depth probing has been completed and has been used to inform the
alignment of the proposed OHL. The peat depth data and observations gathered during the site surveys have
been used to prepare a peat management plan (PMP) (see Appendix 10.1) and a Peat Landslide Hazard Risk
Assessment (PLHRA) (see Appendix 10.2). Further water level monitoring wells have been advanced in the
peat, permeability data for the peat obtained and the characteristics of the peat recorded by site investigation
(see Peat Investigation, Appendix 10.3).
10.4.4 Much of the area of blanket peat has been used for commercial forestry with large areas having been recently
clear felled (Photograph 10-3) with some areas having undergone restoration work including reprofiling of peat
to remove forestry furrows and drains.
Photograph 10-3 Clear Felled Commercial Forestry With Brash Cover of Blanket Peat Soils
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-15
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Superficial Geology
10.4.5 An extract of BGS superficial deposits is mapping is presented as Figure 10.3: Superficial Geology Plan.
10.4.6 Till and morainic deposits of Glacial Till, sand and gravel along with large areas of peat have been recorded by
the BGS underlying the Proposed Development with discrete ribbons of alluvium, consisting of clay, silt, sand
and gravel along larger watercourse channels (Photograph 10-4).
Photograph 10-4 Alluvium Exposure along Banks of River Tirry at Crask Inn
10.4.7 It was noted during site visits that peat is typically underlain by low permeability Glacial Till of unsorted sub-
angular boulders, gravel, sand and silts with soil water seepage at the boundary between the peat and Till,
staining the Till orange with organic content and leached metals (Photograph 10-5).
Photograph 10-5 Cut Exposure of Glacial Till Underlying Thin Blanket Peat
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-16
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
10.4.8 Review of Peatland Classification mapping (SNH, 2016) (see Figure 10.4: Peatland Classification) shows
potential Class 1, 2 and 5 peatland across the Proposed Development route. The forested areas (including
areas of clear felling) within the River Tirry catchment are generally classified as Class 5, described as no
peatland habitat recorded and areas that may also include areas of bare soil where soil information has been
prioritised over vegetation data. Soils are carbon-rich and deep peat. Where peaty soils have not been used
for commercial forestry they are generally classified as Class 2, described as nationally important carbon-rich
soils, deep peat and priority peatland habitat. Class 2 peatlands are recorded as areas of potentially high
conservation value and restoration potential. Following the Proposed Development route, areas around the
watercourses Ferith Osdail, Abhainn Sgeamhaidh, the hills Cnoc na Doire and Croc a’ Ghiubhais and north of
the Crask Inn (PWS01) have been classified as Class 1 peatlands. Class 1 peatlands have been described as
nationally important carbon-rich soils, deep peat and priority peatland habitat that are likely to be of high
conservation value.
10.4.9 As part of this assessment peat depth surveys have been completed (Appendix 10.1 and 10.2). Figure 10.6:
Peat Depth shows the recorded peat depths and confirms that the OHL is underlain by peat.
10.4.10 With reference to Figure 10.6: Peat Depth it is evident that the proposed OHL alignment and access tracks
avoid many of the deeper areas of peat and only with the exception of small discrete sections are peat depths
recorded more than 2m. Typically the depth of peat is recorded at or less than 1 m.
10.4.11 The peat depth data has been combined with slope data and observations of underlying substrate condition to
complete an assessment of peat slide risk (Appendix 10.2) which shows that there are no areas of high peat
slide risk, and the proposed access tracks and much of the proposed OHL alignment is underlain by areas of
negligible and low peat slide risk.
10.4.12 As part of the baseline assessment a site investigation was completed to gather additional details of the
properties of the peat in areas at site that have been subject to peatland restoration (see Appendix 10.3). The
investigation included collecting data with regard to water levels in the peat, peat depth and peat permeability
and confirmed that peat deposits are saturated and have a very low bulk permeability typical of blanket peat.
Bedrock Geology
10.4.13 An extract of the BGS bedrock and linear features geology mapping is presented as Figure 10.5: Bedrock
Geology Plan.
10.4.14 The Proposed Development is underlain by metamorphic and metaphophic-igneous units of:
• Altnaharra Psammite Formation of psammites and micaceous psammites. This is the dominant bedrock
unit that underlies the OHL route;
• Lewisianoid Gneiss Complex of orthogneiss;
• Lewisianoid Gneiss Complex of mafic orthogneiss;
• Kilbreck Psammite Formation of migmatitic psammites and migmatitic-micaceous psammites;
• Kilbreck Psammite Formation of gneissose semipelite; and
• Loch Corie Formation of migmatitic pelites.
10.4.15 A number of Inferred faults have been recorded by the BGS, generally trending in a northeast to southwest
orientation.
Hydrogeology
10.4.16 An extract of the BGS 1:625,000 scale Hydrogeological Map of Scotland is presented in Figure 10.8:
Groundwater Vulnerability, review of which collaborates the bedrock and superficial geology records, and that
all of the Proposed Development is underlain by impermeable Precambrian rock. The BGS describe the
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-17
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Precambrian rock as a low productivity aquifer generally without groundwater except at shallow depth (in the
upper weather surface) with flow almost entirely through fractures and other discontinuities.
10.4.17 Groundwater quality within Scotland is monitored by SEPA and classified annually in accordance with the
requirements of the Water Framework Directive (WFD)9. SEPA record the Proposed Development as underlain
by one groundwater body: Northern Highlands (SEPA ID 150701).
10.4.18 The Northern Highlands groundwater body was classified in 2017 by SEPA as having an overall status of Good
with all sub-parameters also as Good. No pressures have been identified by SEPA for this groundwater
waterbody.
10.4.19 SEPA have confirmed that they do not hold any groundwater water quality data within 10 km of the Proposed
Development.
Groundwater Vulnerability
10.4.20 The SNIFFER groundwater vulnerability map (Figure 10.8: Groundwater Vulnerability) classifies the underlying
aquifer (superficial and bedrock) according to the predominant groundwater flow mechanism (fracture or
intergranular) and the estimated groundwater productivity. Groundwater vulnerability is divided into five classes
(1 to 5) with 1 being least vulnerable and 5 being most vulnerable.
10.4.21 Review of Figure 10.8: Groundwater Vulnerability indicates that the Proposed Development is underlain by
groundwater vulnerability Class 4(b-d) due to the upper weathered surface of the bedrock and thin superficial
cover. This highlights that groundwater is vulnerable to pollution, providing little to no attenuation in the event of
a pollution incident.
Hydrological Site Setting
10.4.22 An extract of Ordnance Survey (OS) mapping illustrating the hydrological setting of the Proposed Development
is presented in Figure 10.1: Local Hydrology and highlights that the Proposed Development straddles the
surface water catchments of the River Vagastie to the north (that sits within the River Naver greater catchment)
and the River Tirry to the south (that sits within the River Shin greater catchment) with a minor length of the
OHL in the very south drain via very small catchments that discharge directly to Loch Shin.
10.4.23 Topography along the Proposed Development route generally falls to the north in the River Vagastie catchment
and south-east within the River Tirry catchment. Elevations range between 115 – 280 m Above Ordnance
Datum (AOD) with the lowest elevations recorded in the south near Dalchork and highest recorded at the
catchment divide of River Vagastie and River Tirry (The Crask) and near the summit of the hill Cnoc na Doire
near the middle of the Proposed Development.
River Vagastie
10.4.24 The River Vagastie (SEPA ID 20609) serves the northern end of the Proposed Development and lies within the
wider River Naver catchment, which ultimately discharges to the North Sea at Bettyhill. The River Vagastie
within the Proposed Development study area is a moderately sized watercourse with a predominantly bedrock
channel with frequent large boulders (Photograph 10-6) and includes the headwater tributary Allt a’Chraisg.
9 SEPA Water Classification Hub available online at https://www.sepa.org.uk/data-visualisation/water-classification-hub. Last accessed 22/04/2019
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-18
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Photograph 10-6: River Vagastie
10.4.25 The River Naver and its headwater tributaries are recognised as a SAC statutory designated site for qualifying
features including Atlantic salmon (Salmo salar) and Freshwater pearl mussel (Margaritifera margaritifera), that
both are noted particularly sensitive to pollution, siltation and sedimentation. The River Vagastie has
recognised obstacles to fish migration and at the crossing of the A836 public road and the main River Vagastie
channel a weir has been reported by SEPA (fish barrier ID 2723). Two of the western headwater tributaries
have also been identified to include dams, which divert flow to Loch Shin that pose an obstacle to fish
migration. During the consultation period of the Creag Riabhach Wind Farm EIA the Northern DSFB
(07/02/2014) provided details that electric fishing data on the River Vagastie suggested that autumn flows are
not sufficient to support free access to spawners in every year, probably because of abstraction at the two
dams and diversion to Loch Shin.
River Tirry
10.4.26 The River Tirry (Photograph 10-7 and 10-8) sits within the greater River Shin catchment that ultimately
discharges to the Kyle of Sutherland at Inveran to the south from the Proposed Development.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-19
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Photograph 10-7: River Tirry at Crask Inn
Photograph 10-8: River Tirry at Fishery Hatchery and Trapping Site
10.4.27 The River Tirry catchment is large (approximately 161 km2) and includes many headwater sub-catchments:
• Allt Chaiseagail (Photograph 10-9) and its own headwater tributaries Feith Tharsuinn, Alltan Riabhach, Allt
Ruadh and Loch Tigh na Creige;
• Allt a’Bhreac-leathaid (Photograph 10-10) and loch Dubh and Loch Beannach;
• Feith Osdail (Photograph 10-11) and its headwater tributaries Allt a’ Mhadaidh-ruaidh, Allt Geal, Allt Coir’
an Torcain and waterbodies Loch Dail na Copaig, Loch na Fuaralachd and Loch Beag na Fuaralachd. The
Feith Osdail is also connected by canal to the Rover Brora at Strath Bora;
• Abhainn Sgeamhaidh (Photograph 10-12) and its headwater tributaries Feith Ra’fin, Feith Mhearanas,
Abhainn na Bruaiche Duibhe, Allt na Chloiche-muilinn, Allt Coir’ a’ Bheachdachaidh, Feith a’ Chaoruinn, Allt
Meall na Teanga, Allt a’ Mhill Mheadhonaich, Caichan Mor, and Feith a’ Chill;
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-20
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
• Alltan Dubh;
• Allt an Drochaidean Beaga;
• Allt an Fhuaran and Lochan Iain Bhuidhe;
• Feith Dhubh na Caorach;
• Shirink Burn;
• Allt Dubh an Daimh;
• Allt Domhain and its headwater tributaries Allt Leacach and Allt Briste;
• Allt Doir’ a’ Mheathais;
• Loch na Capulich;
• Loch Dubh Cul na Capulich; and
• Loch a’ Ghiubhais.
Photograph 10-9 Allt Chaiseagail
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-21
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Photograph 10-10 Allt a’Bhreac-leathaid
Photograph 10-11 Feith Osdail
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-22
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Photograph 10-12 Abhainn Sgeamhaidh
10.4.28 The River Tirry catchment is generally undulating land and steep gradients are absent along main watercourse
corridors.
10.4.29 As illustrated in Photograph 10-8, the River Tirry supports a hatchery (installed by SSE Generation as part of
the salmon fisheries work they undertake in consultation with SEPA and Kyle of Sutherland Fisheries) and
trapping site, which when the hatchery was in operation was restricted to limited stocking on the River Tirry
using fish captured from the River Shin.
10.4.30 The River Shin is dammed at Loch Shin that acts as an obstacle to fish migration (fish barrier ID 2727). Due to
the nature of the dam, Kyle of Sutherland DSFB and SSE operate a “trap and truck” operation on the tributaries
of Loch Shin and the River Shin downstream to maintain migration. Within the minutes of the 2016 Annual
Meeting of the Kyle of Sutherland DSFB10 it is reported that trap figures on the River Tirry were very low in
comparison to normal figures.
Surface Water Quality
10.4.31 SEPA monitor and classify three waterbodies immediately downgradient of the Proposed Development and the
most recent published classification details (2017) are summarised in Table 10-5.
Table 10-5 SEPA Waterbody Classification (2017)
Waterbody ID Overall Status Physico-Chem Biological
Elements
Hydromorphology
River Vagastie
(SEPA ID
20609)
Moderate ecological
potential Good Moderate Moderate
River Tirry –
whole catchment
above Rhian
(SEPA ID
20100)
Poor - Poor Good
10 Kyle of Sutherland DSFB 2016 Annual Meeting minutes, available online at https://kylefisheries.org/wp-content/uploads/2018/08/Mins-of-AMQP-
November-2016.pdf. Last accessed 22/05/2019
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-23
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Waterbody ID Overall Status Physico-Chem Biological
Elements
Hydromorphology
River Tirry –
Loch Shin to
Rhian
(SEPA ID
20099)
Poor High Poor Good
Allt Chaiseagail
(SEPA ID
20101)
Poor High Poor Good
Feith Osdail
(SEPA ID
20102)
Poor - Poor Good
Loch Beannach
(SEPA ID
100083)
Poor High Poor High
Loch Shin
(SEPA ID
100065)
Poor ecological
potential Moderate Poor Bad
10.4.32 SEPA identified the following pressures on the monitored waterbodies in 2014:
• River Vagastie (SEPA ID 20609): water abstraction and barrier to fish migration (fish barrier ID 3349 and
20074) for hydroelectricity generation;
• River Tirry: whole catchment above Rhian (SEPA ID 20100), River Tirry: Loch Shin to Rhian (SEPA ID
20099), Allt Chaiseagail (SEPA ID 20101), Feith Osdail (SEPA ID 20102), Loch Beannach (SEPA ID 100083)
and Loch Shin (SEPA ID 100065): barrier to fish migration (fish barrier ID 2727) for hydroelectricity
generation;
• Allt Chaiseagail (SEPA ID 20101): in addition to the fish barrier listed above this watercourse also has a
further legacy structure that is an obstacle to fish migration (fish barrier ID 20073); and
• Loch Shin (SEPA ID 100065): in addition to the fish barrier listed above, water quality pressures from elevated
concentrations of nutrients have been recorded however no adverse effects have been reported for plant and
animal communities.
10.4.33 It is noted that River Vagastie received a Good status for Physico-Chem classification due to water temperature
and pH remaining in the Good category while dissolved oxygen was classed as High.
Surface Water Flows
10.4.34 SEPA maintain a rain gauge at Rhian Bridge (ID: 115390) and review of the previous five years data (2014 –
2018) indicates an average annual rainfall of 1,087.84 mm.
10.4.35 SEPA confirmed they hold no recent flow data for the gauging stations downstream of the River Tirry (River
Shin downstream of Loch Shin). Flow data was retrieved from the National River Flow Archive11 for the
gauging station, Apigill, downstream of River Vagastie (River Naver downstream) and correlated with rainfall
data for the Rhian Bridge monitoring station (see Chart 10-1).
11 NRFA Apigill station flow data available online at https://nrfa.ceh.ac.uk/data/station/info/96002. Last accessed 22/05/2019
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-24
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Chart 10-1 River Naver Flow Data (2016)
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-25
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
10.4.36 Review of Chart 10-1 highlights that rainfall at the Proposed Development falls primarily across winter months
while summer is significantly drier. It is noted also that river flow responds quickly during rainfall events and
that the low permeability soils and geology beneath the Proposed Development result in a relatively rapid runoff
response to incident rainfall.
Designated Sites
10.4.37 Review of the Scottish Natural Heritage (SNH) Sitelink12 and Magic Map13 webpages and Joint Nature
Conservation Committee (JNCC) map of Geological Conservation Review (GCR) sites14 indicates that the
following sites are located within 1 km of the Proposed Development (see Figure 10.1: Local Hydrology):
• Ben Klibreck SSSI;
• Caithness and Sutherland Peatlands Ramsar, SAC and SPA;
• Cnoc an Alaskie SSSI; and
• River Naver SAC.
10.4.38 The Ben Kilbreck site has been designated as a SSSI for features including alpine heath, blanket bog, moines
and oligotrophic lochs. The high slopes and summits of Ben Klibreck support a range of alpine heath
communities. At higher elevations, heather is found alongside mountain azalea, a plant that is only found in
short vegetation on mountain tops in Britain while dense low-growing mats of the nationally scarce alpine
bearberry and lichens are also found in this habitat. Ben Klibreck contains one of the largest extents of this rare
dwarf shrub community in Britain. An uncommon combination of deergrass / cotton-sedge (western type) and
cotton-sedge / crowberry (eastern type) blanket-mire vegetation communities is found at this site. Calliergon
trifarium, a very local montane species of moss confined to the Highlands, occurs in a few base-rich flushes,
with lesser clubmoss Selaginella selaginoides. The rocks of the Ben Klibreck area mostly lie within the Moine
Supergroup that were altered by intense heat and pressure deep underground into hard pelites and psammites.
In places, partial melting of certain minerals formed banded rocks called migmatites that this site is particularly
valuable for both historical and current research into the origin of. Loch Choire and Loch a’ Bhealaich are
naturally nutrient-poor lochs, which contain a high diversity of aquatic plants, including the nationally scarce
awlwort. These lochs have clear water, low to moderate levels of nutrients and short underwater vegetation.
10.4.39 The Caithness and Sutherland Peatlands site has been designated as Ramsar, SAC and SPA for features
including acid peat-stained lakes and ponds, blanket bog, clear-water lakes or lochs with aquatic vegetation and
poor to moderate nutrient levels and depressions on peat substrates. The scale and diversity of the peatlands
of Caithness and Sutherland make them unique in Europe and they are three times larger than any other peat
mass in the UK. The site is important because of the considerable abundance of large (several square
kilometres) continuous areas of Sphagnum carpets and hummocks and while not only are these features
usually rare and localised on other bog systems in the UK, but a very high proportion of this ground remains
undisturbed. Caithness and Sutherland Peatlands supports a range of high-quality freshwater loch habitats that
include Oligotrophic to mesotrophic standing waters. The aquatic vegetation is dominated by a very narrow
range of species typical of northern, upland, lochs but there is much local variation in their abundance. The
margins of a few lochs support two nationally scarce plants; bog hair-grass Deschampsia setacea and marsh
clubmoss Lycopodiella inundata. Other notable species include awlwort Subularia aquatica and water sedge
Carex aquatilis. The range of aquatic invertebrates includes the nationally rare water beetle Oreodytes alpinus.
Depressions on peat substrates of the Rhynchosporion occur in complex mosaics with lowland wet heath and
valley mire vegetation, in transition mires, and on the margins of bog pools and hollows in both raised and
blanket bogs. The Nationally scarce species brown beak-sedge Rhynchospora fusca and marsh clubmoss
Lycopodiella inundata also occur in this habitat.
12 SNH SiteLink available online at https://sitelink.nature.scot/home. Last accessed 19/03/2019
13 MAGiC Magic Map available online at https://magic.defra.gov.uk/. Last accessed 19/03/2019
14 JNCC UK map of GCR sites available online at http://jncc.defra.gov.uk/page-4173. Last accessed 19/03/2019
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-26
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
10.4.40 The Cnoc an Alaskie site has been designated as a SSSI for features including blanket bog, breeding bird
assemblages and greenshank (Tringa nebularia). The site supports a range of bog types and associated pool
systems including ladder fens. Species of note include marsh clubmoss (Lycopodiella inundata) and the
nationally scarce dwarf birch (Betula nana). This site is notable for the local abundance of the nationally rare
olive bog-moss (Sphagnum majus) and nationally scarce golden bog-moss (Sphagnum pulchrum). The site
supports a nationally important range of breeding upland bird species including red-throated diver, teal, dunlin,
golden eagle, merlin and wood sandpiper. The population of greenshank is particularly important on this site as
this species occurs at a breeding density more than 1.5 times greater than the average in Caithness and
Sutherland.
10.4.41 The River Naver site has been designated as a SAC for features including Atlantic salmon (Salmo salar) and
Freshwater pearl mussel (Margaritifera margaritifera). The site supports a high-quality salmon population and,
along with the Rivers Borgie and Thurso, is representative of the northerly part of the species’ range in the UK.
With the River Borgie, this site in Sutherland represents the northern extreme for freshwater pearl mussels in
the UK while pearl mussels have been recorded throughout much of the length of River Naver.
Flood Risk
10.4.42 SEPA has developed national flood maps15 that present modelled flood extents for river, coastal, surface water
and groundwater flooding. The river, coastal, surface water and groundwater maps were developed using a
consistent methodology to produce outputs for the whole of Scotland, supplemented with more detailed, local
assessments where available and suitable for use. Flood extents are presented in three likelihoods:
• High likelihood: a flood event is likely to occur in the defined area on average more than once in every ten
years (1:10), or a 10% chance of happening in any one year;
• Medium likelihood: a flood event is likely to occur in the defined area on average more than once in every
two hundred years (1:200), or a 0.5% chance of happening in any one year; and
• Low likelihood: a flood event is likely to occur in the defined area on average more than once in every
thousand years (1:1000), or a 0.1% chance of happening in any one year.
10.4.43 A summary of the potential sources of flooding and a review of the potential risks posed by each source is
presented in Table 10-6.
15 SEPA Flood maps available online at http://map.sepa.org.uk/floodmap/map.htm . last accessed 19/03/2019
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-27
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Table 10-6 Potential Flooding Sources
Potential Source Potential Flood Risk
to Application Site
Justification
Coastal flooding No
Lowest elevations of the Proposed Development are
115 m AOD and therefore the site is not at risk from
tidal or coastal flooding.
River Flooding Yes
SEPA river flood mapping highlights that there is a
High Likelihood of flooding immediately adjacent to
larger watercourses including:
• River Vagastie and its upstream tributaries ;Allt a’
Chraisg and Allt Bealach an Fhuaraun;
• Lochan IIain Bhuidhe;
• River Tirry and its upstream tributaries Feith a’
Chaoruinn and Abhainn Sgeamhaidh;
• Loch Dubh Cul na Capulich;
• Feith Osdail;
• Allt a’ Bhreac-leathaid; and
• Allt Chaiseagail.
The OHL line directly crosses mapped flood extents of
the River Vagastie at watercourse crossing WX06, the
Abhainn Sgeamhaidh at WX04, the Feith Osdail at
WX03, the Allt a’ Bhreac-leathaid at WX02 and Allt
Chaiseagail at WX01 with the underground cable
crossing the River Tirry at WX05.
It is noted that the mapped potential flood extents are
all local to watercourses and never form large areas of
out of bank floodplains.
Small and discrete areas of river or stream flooding
might also be expected immediately adjacent to the
smaller watercourses.
Surface Water Flooding No
SEPA flood mapping does not suggest any
significant, large areas of surface water flooding
beneath the proposed OHL and cable alignment.
The flood maps do present very minor areas of
surface water flooding that have been mapped within
Shin Forest, generally along forestry rides, tracks and
along watercourses and loch bodies.
Groundwater Flooding No
Review of the SEPA mapping and site geology and
hydrogeology confirms that the solid and superficial
geology at and near to site do not contain significant
quantities of groundwater.
Flood Defence Breach
(Failure) No
The application site is remote from any formal flood
defences.
Flooding from artificial
drainage systems No
No drainage systems are present near to the site.
Flooding due to
infrastructure failure No
Review of the SEPA Reservoirs Map highlights that
there is no infrastructure upgradient of the Site.
Private Water Supplies and Licenced Sites (Abstractions / Discharges / Waste)
10.4.44 Consultation with THC and SEPA has been conducted regarding records of registered and licenced water
abstractions and discharges within 500 m of the Proposed Development. Recorded private water supplies
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-28
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
(PWS) and SEPA Controlled Activity Regulation (CAR) registrations / licences are illustrated in Figure 10.1:
Local Hydrology and are discussed below.
10.4.45 THC and review of OS data confirmed that there are four properties served by PWS within a 1 km of the
Proposed Development:
• The Crask Inn (PWS01);
• The Crask Inn House (PWS01);
• Rhian (PWS02); and
• New Log Cabin (PWS03).
10.4.46 During the site visit in April 2019, properties were visited and the source of the PWS confirmed with residents.
10.4.47 Both The Crask Inn and Crask Inn House (both PWS01) abstract surface water from a watercourse discharging
from Lochan Iain Bhuidhe to the north east of the properties (NGR NC 52868 25716). Both the PWS source of
these supplies and the pipeline connecting the properties to the supply are upgradient of the proposed cable
alignment and therefore not considered to be in hydrological connection to the Proposed Development. PWS01
is not considered to be at risk from the Proposed Development.
10.4.48 The property Rhian (PWS02) is supplied by a surface water abstraction from the watercourse Abhainn
Sgeamhaidh. The surface water us collected in a shallow well in adjacent to the watercourse (NGR NC 56295
16598) as illustrated in Photograph 10-13. The proposed OHL alignment lies over 2 km upstream east of the
PWS abstraction point.
Photograph 10-13 Rhian PWS Well
10.4.49 Review of the SEPA CAR authorisations indicated a further property (New Log Cabin, PWS03) that was not
shown on OS mapping also existed in the area to the east of the A836 public road near Rhian. During the site
visit, this property was visited and it was noted that the site has not been developed and that only temporary
structures exist. An intermediate bulk container (IBC) was witnessed that was full with water and it is assumed
that there is no PWS here and that visitors bring their own bottled drinking water and that the IBC is refilled by
tanker and not used for drinking purposes.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-29
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
10.4.50 SEPA has provided records of five CAR authorisations within 500 m of the Proposed Development. The
locations of the activities are shown on Figure 10.1: Local Hydrology and summary details are given below:
• CAR/R/1113227 & CAR/R/1113228 – Bridging culvert construction;
• CAR/S/1090938 - Croys / Groynes / Flow Deflectors;
• CAR/S/1156545 - Croys / Groynes / Flow Deflectors; and
• CAR/R/1054718 - Sewage (Private) Primary.
Groundwater Dependent Terrestrial Ecosystems (GWDTE)
10.4.51 Potential GWDTEs have been identified within Chapter 7 (Ecology) and discussed therein. National Vegetation
Classification (NVC) mapping has been used to screen for potential highly and moderately dependent GWDTE,
see Figure 7.3: GWDTE and Peatland Habitats, and which review shows that areas of potential GWDTE are
typically associated with stream corridors and forest rides.
10.4.52 It has been shown above that the site receives a high annual rainfall, and that the superficial and solid geology
has little capacity to store or allow the movement of groundwater. It is considered, therefore, that the areas of
potential GWDTE are not sustained by groundwater but rather rainfall and surface water runoff. Stand-offs or
buffers to these habitats specified in the SEPA guidance therefore need not apply.
Summary of Potential Receptors
10.4.53 Table 10-8 summarises the receptors identified as part of the baseline study, and their sensitivity based upon
the criteria contained in Table 10-2. These receptors form the basis of the assessment and are used in
conjunction with an estimate of the magnitude of an effect to determine significance.
Table 10.8: Sensitivity of Receptors
Receptors Sensitivity Reason for Sensitivity
Peat High Much of the Proposed Development crosses proven
deposits of peat and peaty soils of varying condition with
some areas considered to be of high conservation value.
Soils and Geology High The Ben Kilbreck SSSI has been designated for geological
features of the Moine Supergroup however it was noted that
during the site visit, there were no significant exposures of
bedrock along the OHL alingment.
Surface Water High Surface water quality is expected to be good near to and
downstream of the Proposed Development. SEPA
classifications of monitored watercourses show impacts
associaed with existing obstacles to fish migration. The
River Naver SAC that lies downstream on the River
Vagastie catchemtn is designated for species that are
particularly sensitve to pollution.
The Kyle of Sutherland DSFB operate a hatchery on the
River Tirry, downstream its confluce with Allt a’ Bhreac-
leathaid that the proposed OHL crosses the watercourse
(WX02).
Groundwater High Groundwater quality is recorded by SEPA to be good.
Groundwater is also present at relatively shallow depths and
been shown to be vulnerable to pollution.
Groundwater regionally is designated as a Drinking Water
Protection Zone in accordance with the WFD.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-30
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
Areas of Flood Risk High The OHL and cable alignment has been recorded to pass
over discrete areas of floodplain associated with larger
watercourses and isolated areas of surface water flooding.
Private Water Supplies High The surface water PWS at Rhian (PWS02) has been
identified to abstract from the Abhainn Sgeamhaidh
watercourse that lies approximately 2 km dowsntream from
the OHL crossing of this watercourse (Figure 10.1: Local
Hydrology).
Designated Sites with
Hydraulic Connectivity
to the Proposed
Development
High Designated sites within 1 km from the Proposed
Development are dependent on drainage shed from the site.
Nationally important species and habitats have been
recorded in both the River Vagastie and River Tirry
catchments.
GWDTE Low Potential GWDTE habitats are sustained by incident rainfall
and surface water runoff / ponding rather than by
groundwater.
10.5 Summary of Proposed Development
10.5.1 The construction practices and phasing are detailed within Chapter 3: Description of the Proposed
Development, which includes information on anticipated soil excavation works.
10.5.2 Consent is being sought for:
• approximately 22 km of 132 kV OHL, to be supported by double trident H wood poles, and underground cable
between a proposed on-site substation at Creag Riabhach Wind Farm (NGR NC 52993 27369) and the
proposed Dalchork substation (NGR NC 58204 09565); and
• associated works including tree felling and construction of new temporary and permanent access tracks.
10.5.3 Key tasks during construction of the project would relate to:
• establishment of suitable laydown areas for materials and installation of temporary track solutions (e.g.
Trackway), as necessary;
• upgrades to existing tracks (if required);
• new temporary access track bellmouths to the A836 public road;
• identification and formation (if required) of parking areas for construction workers to ensure safe parking
prior to transfer to tracked All-Terrain Vehicles (ATV);
• formation of Helicopter delivery sites;
• delivery of structures and materials to site;
• excavation of a suitable area for the poles, and backfilling after installation of the pole (backfilling would
generally be carried out the same day as excavation so that no open excavations are left overnight). The
exact area would depend on the ground conditions at each pole;
• in some pole locations, it may be necessary to add imported hardcore backfill around the pole foundations
to provide additional stability in areas where the natural sub soils have poor compaction qualities, this
hardcore will be inert;
• conductors would be installed on the poles using full tension stringing to prevent the conductor coming into
contact with the ground;
• construction of a 1.4 km trenched (0.9-1.6 m deep) section of 132 kV underground cables by the Crask Inn
with sealing end structures of the OHL at either end (details of this process are set out in Chapter 3 of this
EIA Report);
• provision of minor sections of permanent new stone access tracks to retain safe access to commercial
forestry blocks (identified on plans as spur roads); and
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-31
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
• remedial works would be carried out to reinstate the immediate vicinity of the structures, and any ground
disturbed, to pre-existing use. This would be undertaken using excavated material.
10.5.4 Access to the OHL and cable alignment would be afforded from existing tracks where possible and, where
necessary, new temporary access would be set out and removed upon completion of works.
10.5.5 Excavation, other than for the safeguarding of topsoil associated with placement of geo-textile fabric, for the
formation of access tracks is therefore not anticipated. The topsoil would be replaced following use of the
temporary access.
10.5.6 The Proposed Development would require a number of watercourse crossings of the OHL and cable route.
Details of the crossing locations on watercourses with upstream catchment areas greater than 5 km2 are
provided in Table 10-7.
10.5.7 The underground cable in the vicinity of the Crask Inn will require crossing the River Tirry (WX05) which would
be established by Horizontal Directional Drilling (HDD) techniques rather than an open cut technique to isolate
earthwork areas from the water environment. HDD will involve the establishment of temporary entry and exit
pits at either side of the River Tirry. From the entry pit a tracked drilling rig will drill at an angle to provide
enough clearance below the watercourse channel for the drill path. Drilling fluid will be added during operations
to purge cuttings, stabilise the bore hole, and lubricate and cool the drill head.
10.5.8 The entry and exit pits will be developed on temporary areas of ‘hardstanding’ that will constructed using inert
aggregate and be underlain by a low permeability HDPE liner (or similar). The drill rig, drilling fluids, oils and
fuel required to for the HDD technique will be stored on the hardstanding in bunded tanks. Following
completion of the drilling and insertion of the electrical cable all the equipment and hardstanding will be
removed.
10.5.9 Prior to establishment of the entry and exit pits a site investigation will be completed to confirm ground
conditions and the results of which will be used to design the HDD programme. Specifically, the site
investigation will be used to ensure that the HDD does not result in a loss of bentonite to the River Tirry.
10.5.10 Further, the HDD works will require authorisation from SEPA prior to the works being undertaken in accordance
with CAR. The CAR application will include a method statement and details the measures that will be taken to
safeguard the water environment and water quality and flows in the River Tirry.
10.5.11 A buffer of at least 20 m will be maintained at all times from proposed surface works to the River Tirry.
Table 10-7: Schedule of Watercourse Crossings
Crossing ID
Watercourse Name
Notes Photograhy
WX01 Allt Chaiseagail
NGR NC 57829 10777 Top Width: 3 m Channel Depth: 0.75 m Base Width: 2.5 m Water Depth: 0.1 m
View Upstream
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-32
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
View Downstream
WX02 Allt a’ Bhreac-leathaid
NGR NC 58030 12526 Top Width: 2 m Channel Depth: 1 m Base Width: 1.5 m Water Depth: 0.3 m
View Upstream
View Downstream
WX03 Feith Osdail
NGR NC 58308 14497 Top Width: 8 m Channel Depth: 1 m Base Width: 6.5 m Water Depth: 0.5 m
View Upstream
View Downstream
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-33
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
WX04 Abhainn Sgeamhaidh
NGR NC 57792 16833 Top Width: 5 m Channel Depth: 1 m Base Width: 4 m Water Depth: 0.3 m
View Upstream
View Downstream
WX05 River Tirry
NGR NC 52371 24530 (survey conducted approximately 200m downstream) Top Width: 5 m Channel Depth: 1 m Base Width: 4 m Water Depth: 0.2 m
View Upstream
View Downstream
WX06 River Vagastie
NGR NC 53281 27236 Top Width: 4 m Channel Depth: 1 m Base Width: 3 m Water Depth: 0.3 m
View Upstream
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-34
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
View Downstream
10.5.12 Following commissioning of the Proposed Development, all construction sites would be reinstated.
Reinstatement would form part of the contract obligations for the Principal Contractor and would include the
removal of all temporary access panels, all work sites around the pole locations and the re-vegetation of all
construction compounds and Helicopter delivery sites.
10.6 Good Practice and Embedded Mitigation by Design
10.6.1 The Applicant has established best practice construction techniques and procedures that have been agreed
with statutory consultees, including SEPA and SNH. These are set out within the Applicant’s General
Environmental Management Plans (GEMPs), included in Appendix 3.1.
10.6.2 The Proposed Development would be constructed in accordance with these plans.
10.6.3 A contractual management requirement of the successful Principal Contractor would be the development and
implementation of a comprehensive and site-specific CEMP. This document would detail how the successful
Principal Contractor would manage the works in accordance with all commitments and mitigation detailed in the
Environmental Impact Assessment, SSE’s GEMPs, statutory consents and authorisations, and industry best
practise and guidance.
10.6.4 The CEMP would also outline measures to ensure that the works minimise the risk to soils, peat, geology,
groundwater and surface water and licensed water uses.
10.6.5 It is expected that the following would be included within the CEMP and would ensure the works are undertaken
in accordance with good practice guidance, as detailed in Section 10.2:
• during construction there would be heavy plant and machinery required and as a result it is appropriate to
adopt best working practices and measures to protect the water environment, including those set out in
Pollution Prevention Guidance (PPG1);
• in accordance with PPG2 any above ground on-site fuel and chemical storage would be bunded;
• emergency spill response kits would be maintained during the construction works (GGP21);
• a vehicle management system would be put in place wherever possible to reduce the potential conflicts
between vehicles and thereby reduce the risk of collision (GPP21);
• suitable access routes would be chosen which minimise the potential requirement for either new temporary
access tracks or for tracking across open land which could contribute to the generation of suspended solids
and / or degradation of peat;
• bog matting and / or low load bearing machinery will be used when access is required over deposits of
peat;
• a speed limit would be used to reduce the likelihood and significance of any collisions;
• drip trays would be placed under stationary vehicles which could potentially leak fuel / oils;
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-35
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
• any temporary construction / storage compounds required would be located remote from any sensitive
surface water receptors and will be constructed to manage surface water run-off in accordance with best
practice;
• drilling fluid to be used during the HDD at watercourse crossing beneath the River Tirry will be inorganic
and details of the fluid including any necessary foaming agents will be maintained on site to inform correct
use, treatment and disposal;
• any water contaminated with silt or chemicals would not be discharged directly or indirectly to a
watercourse without prior treatment;
• water for temporary site welfare facilities would be brought to site, and foul water would be collected in a
tank and collected for offsite disposal at an appropriately licensed facility; and
• water quality monitoring requirements for sensitive receptors downstream of work areas.
10.6.6 The implementation of the CEMP would be managed on site by a suitably qualified and experienced
Environmental Clerk of Works (ECoW), with support from other environmental professionals as required. The
ECoW would have authority to stop any works that are or have potential to impair soils, geology or the water
environment.
10.7 Assessment of Potential Effects
10.7.1 The following have the potential to impair the soils, geology, local hydrology (surface water) and hydrogeology
(groundwater):
• the use of and tracking of machinery has the potential to damage soils and peat by compaction or indirectly
by draining water from the peat;
• soil compaction from vehicular movement may cause an increase of local flood risk;
• excavation of soils, peat and shallow geology has the potential to induce local ground instability;
• the use of and tracking of machinery has the potential to generate suspended solids in site runoff;
• the use of machinery has the potential to introduce oils or hydrocarbons;
• inappropriate use of drilling fluids has the potential to contaminate groundwater and without appropriate
controls there could be drilling fluid loss to surface water; and
• new temporary access tracks may change surface drainage paths which might increase flood risk and / or
impair water supplies.
Peat Resources and Peat Slide Risk
10.7.2 An extensive programme of peat depth probing has been completed it has been shown that the areas of
deepest peat have been avoided, where practicable and on balance with other environmental considerations
(see Figure 10.5: Bedrock Geology Plan).
10.7.3 No significant earthworks are required. Notwithstanding this, the following best practice measures would be
detailed in the site CEMP in order to safeguard peat:
• no peat would be excavated to form access tracks to the proposed OHL, low loading bearing access
vehicles would be used, and where required temporary portable tracking would be deployed, so to
safeguard peat below the access routes; and
• works would be undertaken with the Applicant’s GEMP (Working in Sensitive Habitats) which would ensure
peat stripping and excavation is kept to an absolute minimum.
10.7.4 The construction of the OHL does not require permanent excavation of peat, as most excavations to install the
poles and stays are undertaken over short periods of time and the excavated materials replaced generally the
same day. By adopting this approach the volume of peat excavated and stored is minimised.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-36
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
10.7.5 The method used for pole construction is to remove as large a section of turf to a depth of approximately 300
mm where possible. The turves are laid to the side for re-use and are only used on surface. The turves would
be handled carefully and replaced on the backfilled excavations to replicate the existing conditions. The
required excavation size is stripped in this way and the turves laid to one side.
10.7.6 The excavator operator would then commence excavating the pole foundations that are usually 2 m wide, 2.5 m
deep and 4 m long. The soil is removed in roughly even layers down the excavation depth with different soil
types stacked into separate piles.
10.7.7 With the pole erected or the stay installed, backfilling of the excavation would take place with the soils replaced
in reverse order whilst being compacted with the excavator bucket in approximately 300 mm layers. At this time
it may be necessary to add imported backfill around the pole foundation blocks to ensure stability.
10.7.8 Backfilling would continue until normal ground level is reached. The turfs would then be replaced – using the
excavator – around the structure and deliberately left slightly proud of the surrounding ground level. This is for
two reasons; the subsoils would naturally settle following excavation as a consequence of ‘bulking up’– despite
being compacted as they are replaced – and in time would form a ‘hollow’ around the structure. The second
reason is that with the replaced turf being kept slightly higher it would prevent the excavated materials
‘deteriorating and becoming very soft’ below the turf and aid quicker healing of the turf.
10.7.9 Generally within 12 months of reinstatement the excavated area would return to natural ground levels and no
evidence of the excavation itself visible.
10.7.10 There would be no storage of peat on site, and soils and turves would be handled sensitively to avoid cross
contamination between distinct horizons and to ensure re-use potential is maximised. It is not envisaged that
any excavation would be left open and excavations would be re-instated on the day they are excavated. Based
on experience from similar sites there would be no significant surplus peat generated from these construction
activities identified on site.
10.7.11 Notwithstanding this, a Stage 1 peat management plan (PMP) has been prepared (see Appendix 10.1) and
shows the volume of peat that will be excavated to establish the required poles and how the excavated peat will
be managed, how the integrity of the peat will be maintained how the peat will be reused. The PMP shows that
there will be no surplus peat generated as a consequence of the Proposed Development.
10.7.12 The Principal Contractor will be required to prepare a Stage 2 and Stage 3 peat management plan as part of
the detailed site design. The stage 2 PMP would be developed in consultation with FLS and SNH Peatland
Action, and this would form part of the CEMP agreed with SEPA and THC prior to construction commencing.
10.7.13 It has been shown that the proposed OHL and limit of deviation is mostly underlain by areas of negligible or low
peat slide risk (see Appendix 10.2). The peat slide risk assessment would be revised prior to construction and
incorporate the results of additional site investigation. The risk assessment would also consider the proposed
access routes and track design. Micro-siting would be used to locate the proposed infrastructure in areas of
least peat slide risk and mitigation measures to prevent a peat slide would be identified, if required. The
updated peat landslide risk assessment would form part of the CEMP that would be prepared by the Principal
Contractor and be agreed with SEPA and THC prior to construction commencing.
10.7.14 It is expected that the following controls would form part of the final peat slide risk assessment:
• careful micrositing of proposed pole supports to avoid drainage channels;
• development of detailed construction access plans, including siting of roads, pads and other associated
infrastructure;
• facilitating flow within existing watercourses and drainage features; and
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-37
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
• careful placement of excavation spoil and imported materials to avoid excess surcharging near excavations
or on slopes.
10.7.15 If required, a geotechnical risk register would form part of the updated peat slide risk assessment and part of
the CEMP.
10.7.16 Peat deposits are considered to have a high sensitivity. Given the safeguards detailed above the peat
resources at site would not be degraded nor is peat slide considered a risk. The magnitude of impact is
therefore considered negligible and the resultant significance of effect is likely to be negligible. No further
mitigation, other than monitoring and inspection, is therefore required.
10.7.17 Following pre-application consultation with SNH, the Applicant confirms that drone surveys would be
undertaken where the Proposed Development is within areas that have received grant funding from SNH
peatland action prior to and following construction. This would allow the Applicant, FLS and SNH Peatland
Action to undertake an assessment of the reinstatement and restoration works completed. The assessment
would determine whether works have been completed successfully, or if any further restoration works are
required at specific locations. If SNH determine the restoration works have been unsuccessful further
discussion would be undertaken regarding any requirement for compensation out with the construction area.
Soils and Geology
10.7.18 No significant earthworks are required. Notwithstanding this, the following best practice measures would be
detailed in the site CEMP in order to safeguard soils:
• any soils temporary stockpiled would be managed in accordance with best practice so that their value is not
degraded;
• works would be scheduled to avoid, when possible, periods of heavy rain and vehicular movement shall be
planned to avoid saturated ground conditions;
• soils would be protected from temporary heavy vehicular movement from placement of ground protection
mats or above ground tracks (underlain by a geotextile);
• stationary plant left for long periods would be parked on formal track / compounds so as to avoid potential
of soil compaction;
• all temporary tracks would be removed upon completion of works; and
• localised measures including silt fencing would be used to manage runoff shed from areas where soils are
disrupted so as not to locally impair water resources and protect sensitive receptors.
10.7.19 With careful management of soils and adoption of the above best practice, their value would not be impaired as
a result of the Proposed Development.
10.7.20 With the exception of the Ben Klibreck SSSI, which is considered to have a High sensitivity, the local geology is
considered to have a low sensitivity. The Proposed Development within Ben Klibreck SSSI is limited and not
significant when compared to its overall extent.
10.7.21 Given the safeguards detailed above neither the value of the soils or the geology would be impaired. The
magnitude of impact is therefore considered negligible and the resultant significance of effect is likely to be
negligible. No further mitigation is therefore required.
Surface Water and Groundwater Quality
10.7.22 As stated above, the works would be undertaken in accordance with the Applicant’s GEMPs and relevant
technical guidance, PPG / GPPs and other codes of best practice, to limit the potential for contamination of both
ground and surface waters. In addition, a site-specific CEMP would be prepared by the Principal Contractor
and include a surface and groundwater quality management plan.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-38
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
10.7.23 The above measures would significantly reduce the likelihood of pollutants, including suspended solids, being
discharged to nearby watercourses or groundwater (including River Naver SAC and the River Tirry).
10.7.24 It is proposed that water required for the site welfare facilities during the construction phase would be provided
by water bowser or tanker. Water from site welfare facilities would be discharged to a sealed tank which would
be routinely emptied and disposed of at an appropriately licensed off-site facility.
10.7.25 Should a need for water abstraction / discharge arise during works (e.g. vehicular / wheel washing), this would
be dealt with through a registration with SEPA as required under the Water Environment (Controlled Activities)
(Scotland) Regulations 2011 (as amended).
10.7.26 Groundwater and surface water is considered to have a high sensitivity. Given the safeguards detailed above
water quality would not be impaired. The magnitude of impact is therefore considered negligible and the
resultant significance of effect is likely to be negligible. No further mitigation is therefore required.
Flood Risk
10.7.27 As part of the detailed site design the Principal Contractor will identify locations for construction compounds and
access routes and prepare a detailed method statement, all of which will have regard to areas of known and
potential flood risk.
10.7.28 No permanent culverts are required. The design and capacity of any temporary watercourse crossings would
be agreed by the Principal Contractor in consultation with SEPA as part of the detailed site design. Any
temporary culverts would be authorised and regulated in accordance with the Controlled Activity Regulations.
10.7.29 The temporary compounds required to establish the entry and exit pits for the HDD would be located outside of
the modelled flood extents of the River Tirry and at least 20 m from the river.
10.7.30 A schedule of temporary watercourse crossings and construction method statements would be specified in the
CEMP.
10.7.31 Flood risk is considered to have a high sensitivity. Given the safeguards detailed above flood risk to the
development would be mitigated and flood risk downstream of the development would not be increased. The
magnitude of impact is therefore considered negligible and the resultant significance of effect is likely to be
negligible. No further mitigation is therefore required.
Surface and Groundwater Flow
10.7.32 The works and protection measures for soils would ensure no significant difference to the existing hydrological
characteristics at site. There would, therefore, be no effect on surface water flows or flood risk as there would
be no permanent change to ground conditions.
10.7.33 Surface water flow paths to areas identified as potential GWDTE would be maintained and thus these habitats
would be safeguarded.
10.7.34 The programme of site investigation has shown that the peat has a low bulk permeability (see Appendix 10.3)
and that the proposed foundations to the OHL and cable routes would not result in significant dewatering of the
peat. No permanent dewatering is required and following construction materials used to backfill the cable
trench and pole foundations will saturate and be the same as in the surrounding soils.
10.7.35 To prevent the cable trench forming a preferential flow path, impermeable barriers or ‘plugs’ will be installed in
the trench in accordance with best practice guidance.
Creag Riabhach Wind Farm Grid Connection: Environmental Statement Page 10-39
Chapter 10: Hydrology, Hydrogeology, Geology and Soils February 2020
10.7.36 As shown by the peat investigation (see Appendix 10.3) the Proposed Development would have no effect on
the quality or water levels within Loch Dubh Cul na Capulich, nor impair the bog pools or habitats present
therein.
10.7.37 Surface and groundwater flow is assessed to have a high sensitivity. Given the safeguards detailed above the
surface and groundwater flows would not be influenced or altered by the Proposed Development. The
magnitude of impact is therefore considered negligible and the resultant significance of effect is likely to be
negligible. No further mitigation is therefore required.
Private Water Supplies
10.7.38 PWS02 abstracts directly from the watercourse Abhainn Sgeamhaidh, which the OHL crosses the main channel
approximately 2 km upstream (WX04). The PWS source is considered to have a high sensitivity.
10.7.39 To ensure that the PWS is safeguarded it is proposed that a schedule of monitoring for the abstraction point is
agreed with THC and SEPA as part of the site CEMP.
10.7.40 With these safeguards and proposed monitoring the magnitude of impact is considered negligible and the
resultant significance of effect is likely to be negligible. No further mitigation is therefore required.
Designated Sites
10.7.41 Designated sites including Ben Klibreck SSSI, Caithness and Sutherland Peatlands Ramsar SAC and SPA,
Cnoc an Alaskie SSSI and River Naver SAC are all considered to have a high sensitivity. The safeguards and
embedded mitigation detailed above and used to protect soils, geology, water quality, groundwater and surface
flow detailed above would also afford protection to these sites and thus it is considered that the potential impact
on the designated sites is negligible. The significance of effect is therefore likely to be negligible, and no
further mitigation is required.
10.8 Summary and Conclusion
10.8.1 Existing soils, geological, hydrogeological and hydrological conditions have been identified and used to assess
the potential effects the Proposed Development may have on geology, soils and the water environment.
10.8.2 Best practice construction techniques that would safeguard soils, geology and the water environment and would
be incorporated in the detailed design of the works and during the construction works have been identified.
Subject to the adoption of the best practice peat resources, soils, geology or the water environment can be
safeguarded during and following development. No significant effects are considered likely to arise as a
result of the Proposed Development.