20
CONTRACTOR INSTALLATION INSTRUCTION FOR ELECTRICAL SUB-METERING REVISION V1.5 SEPTEMBER 2020

CONTRACTOR INSTALLATION INSTRUCTION FOR ELECTRICAL SUB

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

CONTRACTOR INSTALLATION INSTRUCTION

FOR

ELECTRICAL SUB-METERING

REVISION V1.5

SEPTEMBER 2020

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

DOCUMENT STATUS

Version No. Issue Date Amendment Details Amended by

0 November 2015

Draft version issued for inputs Defence

1.0 December 2016

Final version issued for upload to DEQMS. This document supersedes the ‘Electrical Sub-metering Manual for New Construction’ and the ‘Electrical Sub-metering Manual for Retrofits’.

Defence

1.1 March 2017 Contact details of NSP Program Manager changed and security requirements added

MWH

1.2 June 2017 Contact details of NSP Program Manager changed

Stantec

1.3 March 2018 Contact details of DEEERMS Assistant Director and of NSP Program Manager changed

Stantec

1.4 October 2019 Contact details of NSP Program Manager changed and 3G requirements changed to 4G where available.

Stantec

1.5 September 2020

Added requirements for remote sites Stantec

1.6 July 2021 Change of NSP Provider Defence

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

TABLE OF CONTENTS

1. PURPOSE ........................................................................................................................................... 1 2. LEGAL STATEMENT .......................................................................................................................... 1 3. NATIONAL SUB-METER PROGRAM DOCUMENTATION ..................................................................... 1 4. RELEVANT CONTACTS ..................................................................................................................... 2 SECTION 1 - PRE-SITE PLANNING AND PROCUREMENT ...................................................... 4 SECTION 2 – SITE INSTALLATION ............................................................................................... 7 SECTION 3 - COMMISSIONING & SIGN OFF ............................................................................ 10 APPENDIX A – SUB-METERING CHECKLIST .......................................................................... 13 APPENDIX B – STANDARDS AND LEGISLATION .................................................................... 14 1. STANDARDS AND CODES ................................................................................................................ 14 2. RELEVANT STATE BASED AGENCIES .............................................................................................. 14 APPENDIX C – ELECTRONIC FORM EXAMPLES ................................................................... 15 1. NEW METER FORM ......................................................................................................................... 15 2. METER HIERARCHY FORM ............................................................................................................. 16

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

GLOSSARY OF TERMS AND ABBREVIATIONS

AS Australian Standard

BMS Building Management System

CB Circuit Breaker

CT Current Transformer

DB Distribution Board

DERMS Directorate of Environmental Resource Management & Sustainability

DPM Defence Project Manager

Defence Commonwealth Department of Defence

Detailed

metering

schedule

Detailed instructions on appropriate sub-metering points at an existing Defence site,

as previously scoped up by the Defence Representative.

EEGO Energy Efficiency in Government Operations (Policy 2006, second edition 2007)

EMC Electromagnetic Compatibility

EMOS Estate Maintenance and Operations Services

ESAA Energy Supply Association Australia

GPRS General Packet Radio Service

GSM Global Systems for Mobile Communications

HRC High Rupture Capacity (fuse, usually filled with sand or similar)

HVAC Heating, Ventilating and Air-Conditioning

IP Internet Protocol

LCD Liquid Crystal Display

LED Light Emitting Diode

LVCT Low Voltage Current Transformer

MDA Meter Data Agent

MIEE Manual of Infrastructure Engineering – Electrical

MSB Main Switch Board

MSSB Mechanical Services Switch Board

MTB Meter Test Block

NCC National Construction Code

NMI National Meter Identifier

NSP National Sub-meter Program

NZS New Zealand Standard

RESO Regional Energy/Environmental and Sustainability Manager

RDMS Resource Data Management System

RMR Remote Meter Read

SIM Subscriber Identity Module

SIR Service Installation Rules

TWS Transformer Winding Services

VT Voltage Transformer

WHS Work Health and Safety

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 1 -

PRELIMINARIES

1. Purpose

The purpose of this document is to provide information and guidance to sub-metering contractors during

the planning, procurement, installation and commissioning for new and replacement electrical sub-

meters for the Commonwealth Department of Defence (‘Defence’) under the National Sub-meter

Program (NSP).

This document refers to the commissioning of sub-meters into Defence’s Resource Data Management

System (RDMS).

2. Legal Statement

Whilst this manual contains material relevant to electricity industry legislation, Codes of Practice and

Standards, it is not intended to provide legal advice on how contractors can meet their own statutory

obligations or comply with Legislation, Codes of Practice or industry Standards such as the SAA Wiring

Rules AS/NZS 3000.

This document provides guidelines for sub-meter installation and connection of these energy meters

and associated wireless telemetry. Where departures from these guidelines may be necessary, prior

consultation with Defence will be required.

Appendix B lists all relevant legislation, standards and codes that shall be adhered to as part of the

procurement, installation and commissioning of the sub-meters.

Note:

a) If there is any inconsistency between these guidelines and the relevant State, Territory and

Commonwealth legislation, then the hierarchy shall be that the requirements of the relevant

legislation shall prevail in the first instance.

b) This instruction is focusing on Delivery Phase only and you should always refer to Smart

Infrastructure Handbook: Planning, Design and Construction for overall program objective and

requirements

3. National Sub-meter Program Documentation

The relevant documentation associated with each project phase for the planning, design,

implementation and ongoing maintenance of sub-metering across the Defence estate are all available

on DEQMS

(https://www.defence.gov.au/estatemanagement/governance/policy/environment/energyefficiency/NS

P.asp).

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 2 -

4. Relevant Contacts

The relevant contacts for sub-metering installation projects are shown in Table 1.

Table 1 - Relevant Sub-metering Contacts

Role Organisation Role Description Contact Details (where applicable)

Authoritative

Defence Contact

DERMS The Authoritative Defence

Contact within DERMS is

responsible for overseeing and

approving the activities of the

Defence Representative and

assuring Defence achieves

value for money in all sub-meter

program activities.

Brenin Presswell

Assistant Director, Directorate of Energy

Efficiency, Environmental Resource

Management and Sustainability;

Infrastructure Division

DERMS

E: [email protected]

Defence Project

Manager

Project Delivery

Services Contractor

(Aurecon or Augility)

Estate Maintenance

and Operation Support

Where applicable to manage the

tendering and installation project

of electrical sub-metering

Contractor Varies for each contract To procure relevant hardware,

install and commission electrical

sub-metering on the Defence

estate

Meter Data Agent Metropolis To provide remote assistance

and facilitate the commissioning

of electrical sub-meters across

the Defence estate

Phone: 03 9024 7452

Hours of Operation: Monday – Friday

9:00am – 5:00pm

Melbourne local time excluding

Victorian Public Holidays

For escalations and form submission,

please email:

[email protected]

Estate Maintenance

and Operation

Support

Ventia

Spotless

BGIS

To provide assistance onsite

regarding the location of existing

and new sub-metering

requirements including access to

locations

NSP Program

Manager

WSP To facilitate the successful

installation and commissioning

of sub-meters, provision of SIM

cards and manage the RDMS

Phone: 03 9059 4058

Hours of Operation: Monday – Friday

9:00am – 5:00pm

Melbourne local time excluding

Victorian Public Holidays

For escalations and form submission, please email:

[email protected]

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 3 -

Role Organisation Role Description Contact Details (where applicable)

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 4 -

SECTION 1 - PRE-SITE PLANNING AND

PROCUREMENT

OH&S and regulatory documents

The Contractor must submit OH&S and regulatory documents to relevant Defence Project Manager for

approval. No site work will be undertaken without the approval of the Defence Project Manager to do

so.

Appendix B lists all relevant legislation, standards and codes that shall be adhered to as part of the

procurement, installation and commissioning of the sub-meters.

Project Contact

The Contractor should confirm all relevant project contacts at project commencement (refer Table 1)

Notification of Non-Compliance

If the Contractor is aware of a non-compliances prior to attending site they must refer to the Defence

Project Manager if changes are required on approved design due to site constraints or other issues.

Resource Data Management System

The Contractor shall confirm with Defence Project Manager prior to installation that the sub-meter being

installed will be connected to Defence’s RDMS.

If the sub-meter is being installed into a different data management system (i.e. a Building Management

System (BMS) or a Power and Control Management System (PCMS)) then they should confirm the

commissioning requirements with the Defence Project Manager including whether the BMS or PCMS

shall be connected to the RDMS (see BMS-RDMS Connection Protocol).

Sub-metering Installation Schedule

The Contractor must submit a detailed installation schedule to the Defence Project Manager and provide

the schedule to the Meter Data Agent (MDA) for reference. This schedule will allow the MDA to prepare

for remote commissioning at the commissioning phase.

This information should be provided together with:

the number of meters being installed

the meter type and serial number for each meter

the modem type and serial number for each modem

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 5 -

the SIM card IP address associated with each sub- meter (provided by the NSP Program

Manager when the SIM cards are issued)

the CT ratio

Network Signal

A Network Signal Analyser is to be used to ensure there is sufficient signal on site for the proposed

hardware.

The signal analyser must be compatible with the Telstra Cat-M1 (LTE-M) network if

available, the Telstra 4G communications network if Cat-M1 (LTE-M) is not available and

the Telstra 3G communications network if 4G is not available.

The signal analyser must display the network signal strength and frequency band

information for all available base stations.

The signal analyser must allow the connection of an external antenna to test the antenna

installed at meter installation position.

The signal analyser is used to test the antenna and cable installation at each meter

installation location.

At least 30% network signal strength must be available for the modem at each meter

installation location to ensure reliable communications. If the signal strength is below 30%,

then the antenna must be relocated to a position that provides sufficient signal strength.

If there is no signal strength greater than 30% on the 3G network, and the meter is to be

connected to the RDMS as deemed by the Authoritative Defence Contact, a Satellite

connection will be needed.

Procurement of Hardware

The Contractor is responsible for the procurement of approved hardware as per the Electrical Sub-meter Hardware Specification. It is recommended that the Contractor have either procured or have access to the following hardware and equipment for site installation and commissioning:

Electrical sub-meter and communications hardware configured for the Telstra Cat-M1 (LTE-M)

network if available, the Telstra 4G network if Cat-M1 (LTE-M) is not available, and the 3G

network if neither 4G or Cat-M1 (LTE-M) are available. The electrical sub-meter and

communications hardware shall also be configured for TCP/IP communications.

Note if no Cat-M1 (LTE-M), 4G or 3G coverage is available and the meter is l to be connected

to the RDMS as deemed by the Authoritative Defence Contact, a Satellite connection shall be

provided. In this case, the Contractor is to work with the Authoritative Defence Contact to

determine the most appropriate infrastructure to put in place.

Current transformers (if required)

Signal analyser to determine signal strength

Antenna (the contractor shall have standard and high gain antennas due to potential

communications issues)

SIM card/s (request from Stantec at no cost to the Contractor)

Laptop/tablet to complete electronic documentation onsite

Sub-metering Documentation

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 6 -

The Contractor must acquire the most up-to-date (on DEQMS) documents for the installation and

commissioning of electrical sub-meters. The following documents are to be pre-filled where possible

prior to site and then completed during meter installation.

Electricity New Meter Form

Meter Hierarchy Template

The Contractor must make contact with the Meter Data Agent at least two business days before the

scheduled installation to exchange the Electricity New Meter Form and provide other details as required

to prepare for meter provisioning. Refer to the Relevant Sub-metering Contacts section for contact

details.

Security Requirements and Site Notification

Prior to installation the contractor needs to confirm that the installation of the wireless meter/modem is

permitted at the design location, that all security requirements have been addressed, and that an

authorised building contact (e.g. Base Support Manager) has approved the installation and shut-down

process.

Site Access

To ensure that no delays occur due to site access issues the Contractor must confirm that:

All field technicians have appropriate site access and security credentials (access ID if required)

Contractor has obtained an authority/permit to work

Permission to bring laptop, electrical equipment and hardware onsite has been approved

through the Defence Project Manager

Permission to take photos has been approved through the Defence Project Manager

EMOS contractor is aware of works and can provide access (e.g. keys) to metering locations

If required the Electrical authority (Local) has been contacted

Defence Asset ID

The Contractor must ensure that a Defence asset registration number has been assigned and a sticker

obtained to be attached to the hardware installed onsite. This will be arranged through the Defence

Project Manager who may need to liaise with the EMOS for the site.

Shut Down

If required, the Contractor shall submit a site shutdown notification to the Defence Project Manager

prior to attending site. The Contractor will confirm with the Defence Project Manager the process

required for site shutdown.

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 7 -

SECTION 2 – SITE INSTALLATION

Notification of Non-Compliance

If the Contractor becomes aware of non-compliances while attending site and changes to

the approved design are required, the Contractor must refer to the Defence Project

Manager.

For retrofit projects, any alterations to existing infrastructure shall not compromise existing

protection measures (e.g. for switchboards fault withstands including arc fault current

protection, ingress protection or form of segregation. Refer to the requirements of AS/NZS

3000, AS/NZS 3439.1 and AS 4278).

Current Transformers (CTs) Installation

The following shall be considered by the Contractor if required to install new CTs or retrofitting sub-

meters to existing CTs:

Contractor shall ensure that new CTs meet the specification

Contractor shall install CTs of the correct physical size and with a CT ratio appropriate to the

application

Contractor shall confirm that any existing CTs are in good operating condition and appropriate

to the application. Where a CT is deemed to be not functioning, the Contractor must notify the

Defence Project Manager and replace with a new CT.

Any new CTs installed are not to compromise original switch design requirements

Contractor will ensure that CT wiring meets all relevant local and Australian Standards.

CT Ratio information must be correctly recorded and checked as part of the installation details.

Meter voltage connection

All active voltage conductors are to be coloured according to their phase (red, white or blue). The black meter neutral can be picked up from the neutral link. All wires are to be seven strands 2.5mm2 copper as per the Specification.

In general, smart meter and modem packages will be powered by a voltage connection and burden less than 10VA / 50mA per phase. Consult the hardware manufacturer’s data sheets for exact specifications.

If circuits are directly connected to the substation bus or main switchboard bus bars, HRC fuses are to be used because the fault currents in a bare-conductor short circuit can be extremely high.

Any voltage fuses installed beneath a fixed panel must be safely accessible without the need to disconnect power to the switchboard.

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 8 -

Meter Mounting Panel and Meter Test Blocks

The following shall be considered by the Contractor when installing the meter mounting panel and meter

test blocks:

AS3000 and Service Installation Rules (SIRs);

Sub-meters installed shall meet the Specification;

Contractor shall ensure that installations do not to intrude into passageways or present any

safety hazards;

Where Contractors are required to install meters in high security, prohibitive or sensitive areas

they must make note on the New Meter Form so future personnel wishing to access meters are

aware of potential impediment;

Meters shall remain accessible to be read, maintained or replaced without the need to

disconnect power from the switchboard;

Contractor shall ensure adequate shading and air circulation for any external installations;

Meter and modem are to remain clear of strong magnetic fields around heavy bus bars; and

Meter and modem shall be installed in a secure location to avoid the potential for vandalism

and/or theft of equipment.

Meter, modem and aerial

The installation steps to connect a standard electrical meter, modem and antenna package are:

1. Mounting of meter and modem (with installed SIM card) in the location designated by relevant

design documentation;

2. Connection of wiring between meter and meter test block (Note: wiring needs to ensure that

meter is reading usage or generation accurately and not reading generation when usage is

occurring or vice versa);

3. Connection of cabling between meter and modem;

o The radio modem is to be connected to the meter through the appropriate cable port,

noting that generally the meter supplies power and data to the modem through this

cable;

4. Mounting antenna at its nominated location;

o The antenna is to be placed in a location that produces signal strength of at least 30%,

but 60% signal strength or more is preferred

o Where the Contractor needs to undertake works for antenna installation (e.g. drilling for

wires) they must communicate with the Defence Project Manager and obtain the

required approvals.

5. Connection of antenna to modem; and

6. Removal of meter test block bridging links for CTs.

7. NOTE: Most radio modems have a maximum operating temperature around 55°C and will fail if

left exposed in full sun, similarly most meters have a maximum operating temperature around

70°C. Ensure adequate shading and air circulation for any external installations.

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 9 -

Antennas

Antennas are required at all sites to ensure adequate signal strength for reliable remote

communications.

The antenna must support the frequency bands used by the Telstra communication

network selected (preference is Cat-M1 (LTE-M) followed by 4G followed by 3G).

Low cost adhesive antennas must not be used unless there is no alternative due to

insufficient space to mount external omni-directional antennas with a gain of at least

2.0dBi.

Note that many high gain antennas only provide high gain in one frequency band that may

not be available at some installation locations. Please contact the Defence Representative

if unsure about a specific antenna type is suitable for the network and installation.

At least 30% network signal strength must be available for the modem at each meter

installation location to ensure reliable communications.

SIM Card

The SIM card is to be correctly inserted into the modem – consult the modem manual for additional

information and correct installation procedure.

Installation Documentation

The contractor shall ensure that the Electricity New Meter Form is completed at the end of each sub-

meter installation. This form is critical in the commissioning phase and ongoing maintenance of sub-

meters.

Where possible the Contractor shall take photos of the sub-meter, modem and current transformers for

reference and send to the Defence Project Manager with the Electricity New Meter Form as this provides

valuable information for meter rectification.

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 10 -

SECTION 3 - COMMISSIONING & SIGN OFF

Power up

The Contractor will perform a visual check of the installation to ensure all components have been

properly installed. This will be indicated by the LCD screen on the meter and correct sequence of status

indicators (such as LEDs) on the modem.

Network Signal Analyser

A Network Signal Analyser is to be used to ensure the modem and antenna installation are installed

correctly and allow for reliable remote meter reading operations.

The signal analyser must be compatible with the Telstra Cat-M1 (LTE-M) network if

available, the Telstra 4G network if Cat-M1 (LTE-M) is not available, and the 3G network if

neither 4G or Cat-M1 (LTE-M) are available..

The signal analyser must display the network signal strength and frequency band

information for all available base stations.

The signal analyser must allow the connection of an external antenna to test the antenna

installed at meter installation position.

The signal analyser is used to test the antenna and cable installation at each meter

installation location.

At least 30% network signal strength must be available for the modem at each meter

installation location to ensure reliable communications. If the signal strength is below 30%,

then the antenna must be relocated to a position that provides sufficient signal strength.

Verification of Installation

Verify that all elements of the installation are working correctly by viewing the following parameters on

the meter LCD display. If any of the following parameters are not available on the LCD display, the

Contractor will need to contact the MDA who will be able to perform a remote configuration, provided

wireless communications can be established.

Modem signal strength

o The modem signal strength is a sample taken at the moment when the modem starts

up. Minimum signal strength of at least 30% is required, but signal strength of 60% or

more is preferred.

Modem

o The modem status is normally shown by a sequence of LED indications. Contact the

MDA for assistance if required.

CT ratio

o In most cases, the CT ratio will not be set (basic CT ratio will be pre-programmed to

5/5) until the MDA configures the CT ratio remotely during the commissioning process.

GPS Location

o GPS location is required so that the physical location of the meter is known to parties

not involved in the physical installation of the meter. The Contractor should ensure that

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 11 -

the device used to obtain GPS co-ordinates is accurate within 10 meters of the actual

location.

Remote Commissioning and Verification

The Contractor shall contact and confirm the commissioning schedule with the MDA in advance so that

the final remote commissioning and verification can be performed efficiently. The Contractor shall remain

on site to make any required adjustments in real time.

The following information is required from the Contractor as a minimum to perform the remote

commissioning and verification (this information can be provided before the installations are complete if

known):

Meter model, type and serial number;

Modem model, type and serial number;

SIM serial number (ICCID), Phone Number (MSISDN) and IP address;

CT ratio for installed CTs;

Whether the meter is measuring usage, generation or both

Number of phases, voltage per phase, frequency; and

Photos for equipment installed.

The remote commissioning will be completed by the MDA which will include any additional meter configuration required. The remote commissioning will ensure the signal strength is satisfactory, end-to-end communications are working and that all components have been installed correctly. If any components are not working or have not been installed correctly, it is the responsibility of the Contractor to rectify the problem in consultation with the Defence Project Manager to perform the remote commissioning and verification.

Commissioning MDA: Metropolis Meter Transfers Team

03 9024 7453

Hours of Operation: Monday – Friday 8:00am – 4:00pm

Melbourne local time excluding Victorian Public Holidays

For escalations and form submission, please email:

[email protected]

The Contractor shall also advise the Defence Project Manager when commissioning will occur, and the

MDA shall advise the Defence Project Manager of commissioning outcomes.

Once satisfied, the Defence Project Manager, in consultation with the MDA and the NSP Program Manager, will acknowledge the installation as completed and ready for online data access.

Labelling

Permanent Traffolyte style labels shall be used, either screw fixed or glued. External labelling exposed

to the weather shall meet Defence Manual of Infrastructure Engineering – Electrical (MIEE)

requirements.

All new meters shall receive a Defence Asset identification number and associated sticker. This should

be co-ordinated through the Defence Project Manager.

Installation Documentation

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 12 -

The Contractor shall complete and submit Electricity New Meter Form, the Meter Hierarchy Form and

the Metering Strategy (part of the Smart Infrastructure Checklist) available on DEQMS to the Defence

Project Manager and the NSP Program Manager for each metering location. The project will not be

signed off until confirmation of completed project forms and fully commissioned sub-meters is received.

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 13 -

APPENDIX A – SUB-METERING CHECKLIST

Item Yes No Comments

PRE-SITE CHECKLIST

1. Have you provided the Defence Project Manager with

detailed metering installation schedule?

2. Have you provided the MDA with detailed metering

installation schedule (including meter numbers, SIM

numbers and IP addresses)?

3. Do you have an electronic new meter form and

electronic metering hierarchy form for each meter (from

DEQMS)?

4. Have you confirmed site access for technicians and

access to each metering location with EMOS

contractor?

5. Is the meter configured correctly for the modem being

installed and confirmed to be compatible with the MDA?

6. Has all equipment required been procured and is it

ready for installation (electricity meter, communications

hardware and cables, antenna and cables and SIM)?

SITE CHECKLIST

1. Has the new meter form and meter hierarchy form

been completed for each meter installed?

2. Has the MDA remotely commissioned each meter

and confirmed meter is reading?

3. Is the signal strength at the metering location greater

than 30%?

4. Have all meters been commissioned and

communications established and confirmed operational

prior to leaving site?

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 14 -

APPENDIX B – STANDARDS AND LEGISLATION

1. Standards and Codes

All local and National Electrical and Building Codes (Australian Standards) are applicable and must be

adhered to. Network standards are to be considered as a guide as the meters are to be installed on a

privately owned network.

Australian Standards, Legislation and Defence Guidelines:

Commonwealth Work Health and Safety Act, regulations and codes of practice;

Defence Manual of Infrastructure Engineering – Electrical (MIEE);

AS/NZS 3000 – ‘Electrical Installations’ (Wiring Rules);

AS/NZS 1939 – ‘Degrees of Protection Provided by Enclosures for Electrical Equipment’;

AS/NZS 3147 – Cable Manufacturing;

AS/NZS 61000 – ‘Electromagnetic Compatibility (EMC)’;

AS/NZS 60044.1-2003 – Current Transformers;

AS/NZS 60044.2-2003 – Voltage Transformers; and

All relevant State and Territory based legislation as governed by the agencies listed in Table

2.

2. Relevant state based agencies

Table 2: State and territory agencies governing electrical safety legislation

State Agency Contact

ACT ACT Planning and Land Authority, Worksafe ACT

www.actpla.act.gov.au www.worksafe.act.gov.au/health_safety

NSW NSW Fair Trading (Department of Finances and Services)

www.fairtrading.nsw.gov.auhttp://www.environmen

t.nsw.gov.au/

NT NT Worksafe www.worksafe.nt.gov.au

QLD Electrical Safety Office, Department of Justice

www.eso.qld.gov.au

SA

Office of the Technical Regulator, Office of Consumer and Business Affairs (licensing only)

www.technicalregulator.sa.gov.au www.ocba.sa.gov.au

Tas Workplace Standards Tasmania

www.wst.tas.gov.au/electricity

Vic Energy safe Victoria http://www.esv.vic.gov.au/

WA Department of Commerce www.energysafety.wa.gov.au

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 15 -

APPENDIX C – ELECTRONIC FORM EXAMPLES

1. New Meter Form

DEPARTMENT OF DEFENCE CONTRACTOR INSTALLATION INSTRUCTION – ELECTRICAL SUB-METERING

- 16 -

2. Meter Hierarchy Form

Meter Hierarchy TemplateThis template is used to describe the hierarchy of different meters to prevent double counting of usage data.

Site:

Project Name:

Project Stage:

Date:

Defence site name

E.g. For Tender, As-Constructed

Met

er ID

Ref

erence

HV c

onnec

tion

Sub-S

tatio

n

LV D

istrib

ution P

illar

Sub-L

V D

istrib

ution

Pill

ar

Build

ing M

SB

Dis

trib

ution B

oard

Dis

trib

ution

Ref

erence

Com

men

t

211111111 X Site HV Connection (existing)

211111112 X Sub-Station 5 (existing)

211111113 X Pillar 5A

211111114 X Pillar 5B

211111111 X Site HV Connection (existing)

211111115 X Sub-Station 6

211111116 X 0121/A104 - Base Offices

211111117 X 0121/A105 - Base Offices

211111111 X Site HV Connection (existing)

211111118 X Sub-Station 7

- X Pillar 7A

211111119 X 0121/D101 - Accommodation

211111120 X Floor 1

211111121 X Floor 2

211111122 X 0121/D102 - Accommodation

211111123 X Floor 1

211111124 X Floor 2

211111125 X 0121/D103 - Accommodation

211111126 X Floor 1

211111127 X Floor 2

Insert a break between different meter hierarchy groups.

Provide clarity on system hierarchy

Tie the hierarchy back to an existing connection point if possible (i.e. Site HV or existing sub-

station and note as such in comments).

Provide additional detail or note changes in hierarchy between

submissions, as required.