  • CONTRACTOR STATUS REPORT

    Project Title: Date Prepared:

    Vendor: Contract #:

    Scope Performance This Reporting Period

    Quality Performance This Reporting Period

    Schedule Performance This Reporting Period

    Page 1 of 3

  • Cost Performance This Reporting Period

    Forecast Performance for Future Reporting Periods

    Claims or Disputes

    Risks

    Page 2 of 3

    CONTRACTOR STATUS REPORT

  • Planned Corrective or Preventive Action

    Issues

    Comments

    CONTRACTOR STATUS REPORT

    Page 3 of 3

  • 196 Monitoring and Control Forms

    4.6 FORMAL ACCEPTANCE

    The Formal Acceptance form is used to document acceptance by the customer or other stakeholder. Formal

    Acceptance can be done periodically throughout the project, as with partial or interim deliverables, or for the proj-

    ect as a whole.

    There are two aspects regarding the deliverables formal acceptance:

    1. Verify the correctness of the deliverable; this is performed during the Control Quality process.

    2. Validate that the veri ed deliverable meets the acceptance criteria agreed upon with the customer; this is

    performed during Validate Scope.

    Deliverables that meet the acceptance criteria are formally signed off and approved by the customer or spon-

    sor. This formal documentation is forwarded to the Close Project or Phase process (Section 4.6).

    The Formal Acceptance form may include, but is not limited to:

    Requirements

    Method of validation

    Acceptance criteria

    Status of deliverable

    Signoff

    Use the information from your project to tailor the form to best meet your needs.

    The Formal Acceptance form can receive information from:

    Project Management Plan

    Requirements Documentation

    Requirements Traceability Matrix

    Work Performance Data

    It provides information to:

    Project Performance Reports

    Change Requests

    Project Closeout Report

    This form can be used in conjunction with processes 8.3 Control Quality and 5.5 Validate Scope in the

    PMBOK GuideFifth Edition.

    You can use the element descriptions in Table 4.6 to assist you in developing a Product Acceptance report.

    TABLE 4.6. Elements of Product Acceptance

    Document Elements Description

    ID Enter a unique requirement identi er from the requirements documentation.

    Requirement Enter the requirement description from the requirements documentation.

    Acceptance criteria Enter the criteria for acceptance from the requirements documentation.

    Validation method Describe the method of validating that the requirement meets the stakeholders needs.

    Status Document whether the requirement or deliverable was accepted or not.

    Comments Document why the requirement or deliverable was not accepted and the required changes for

    being accepted.

    Signoff Obtain the signature of the party accepting the product.