Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
COURTEOUS
RESPONSIVE
DEPENDABLE
IN THIS ISSUE
Doug’s Corner ……………………..1–3
Traffic/Active Work ……………………...4-6
Construction Notices …………………….7-16
Project App
………………..………17
October 13, 2014 Volume 2, Issue 91
CONTRACTOR’S WEEKLY UPDATE
DOUG’s CORNER
NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP
DOUG’s CORNER MY WEEK IN PICTURES
NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP
CONTRACTOR’S WEEKLY UPDATE
DOUG’s CORNER MY WEEK IN PICTURES
Doug St. Stevens
NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP
CONTRACTOR’S WEEKLY UPDATE
Dunlap - Dunlap / 19th Intersection Traffic signals, place station footings, set station steel
One (1) lane both east and westbound, left turn lanes will be maintained September 29 to October 17, 2014
Dunlap to Butler Track, double crossover, sig-comm, guideway curb
One (1) lane both north and southbound will be maintained
Butler, El Caminito, Las Palmaritas eastside closures thru Dec 31, 2014
Butler to Northern Storm, traffic signals, roadway widening
One (1) lane both north and southbound will be maintained
Turns at the signalized intersections will be maintained
Butler, El Caminito, Las Palmaritas eastside closures through Dec 31,
2014
Northern / 19th Intersection
One (1) lane east and west bound will be maintained October 20, thru December 31, 2014. Intermittent turn restrictions
Glendale and Northern to alternate restrictions. One or the other will have a minimum of 2 lanes and left turns maintained both east and westbound
Northern to Orangewood Century Link, storm drain, traffic signals, roadway widening
One (1) lane both north and south bound will be maintained
Turn lanes at the signalized intersections will be maintained
Augusta, Frier, Morten closures thru December 31, 2014
WEEK OF 10.13.2014
NORTH
NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP
CONTRACTOR’S WEEKLY UPDATE
DUNLAP — ORANGEWOOD
WORK ACTIVITIES AND TRAFFIC CONTROL
WORK ACTIVITIES AND TRAFFIC CONTROL
Orangewood to Glendale Water, traffic signals
One (1) lane both north and south bound will be maintained
Turn lanes at the signalized intersections will be maintained
State and Myrtle closures October 13, 2014 to October 24, 2014
Gardenia and Northview closures October 20 to October 31, 2014
Glendale / 19th Intersection
One (1) lane east and west bound. Turns will be maintained October 10, 2014 thru October 18, 2014
Glendale and Northern to alternate restrictions. One or the other will have a minimum of 2 lanes and left turns maintained both east and westbound
Glendale paving notice October 13, 2014 to October 17, 2014
Glendale to Maryland Century Link, curb, gutter, sidewalk, driveways, roadway, form and pour
guideway curb
One (1) lane both north and south bound will be maintained
Turn lanes at the signalized intersections will be maintained
Ocotillo, Tuckey, Maryland closures to October 18, 2014
Maryland eastside closure October 2, 2014 to October 18, 2014
Maryland to Bethany Home Road Sidewalk, curb, gutter, driveways, traffic signals, roadway, Century Link
One (1) lane both north and south bound will be maintained
Turn lanes at the signalized intersections will be maintained
NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP
CONTRACTOR’S WEEKLY UPDATE
WEEK OF 10.13.2014
SOUTH ORANGEWOOD
-MONTEBELLO
WORK ACTIVITIES AND TRAFFIC CONTROL
Bethany Home / 19th Intersection Century Link, grade and pave roadway, ductbank
Two (2) lanes east and west bound will be maintained beginning October 9, 2014.
Bethany Home Road to Montebello Century Link, curb, gutter, sidewalk, driveways and ductbank installation
One (1) lane both north and south bound will be maintained
Turn lanes at signalized intersections will be maintained
Mall entrance closure October 8, 2014 to October 31, 2015
NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP
CONTRACTOR’S WEEKLY UPDATE
WEEK OF 10.13.2014
SOUTH ORANGEWOOD
-MONTEBELLO
CONSTRUCTION NOTICE
NORTHWEST EXTENSION
Dunlap Ave to Northern Ave
Roadway Widening & Track Install
Sept 1, 2014 – January 1, 2015
A new phase of construction is beginning with
roadway widening and track installation. This
new phase will modify traffic patterns along
19th Avenue including right-turn only
movements onto 19th Avenue.
Roadway widening
Track installation
Right turns only onto 19th Avenue
Temporary U-turn will located south of Alice Avenue
See map on following page
QUESTIONS?
VALLEY METRO
Community Outreach
Coordinators
Carla Kahn (623) 261-2605
Jessica Blazina(602)510-5491
SSWJV
Superintendent
Mike Howard
(602) 619-5813
STAY CONNECTED
Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest
facebook.com/valleymetro
24-Hour Project Hotline
602-254-RAIL (7245)
CONSTRUCTION NOTICE
NORTHWEST EXTENSION
Roadway Widening & Track Install
Dunlap Ave to Northern Ave
QUESTIONS?
VALLEY METRO
Community Outreach
Coordinators
Carla Kahn (623) 261-2605
Jessica Blazina(602)510-5491
SSWJV
Superintendent
Mike Howard
(602) 619-5813
STAY CONNECTED
Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest
facebook.com/valleymetro
24-Hour Project Hotline
602-254-RAIL (7245)
Pipe removal, roadway widening, and paving on east side of 19th Avenue
CONSTRUCTION NOTICE
NORTHWEST EXTENSION
Butler, El Caminito,
Las Palmaritas Eastside
Roadway Widening | Paving
Sept. 15 - Dec. 31, 2014
QUESTIONS?
VALLEY METRO
Community Outreach
Coordinators
Carla Kahn (623) 261-2605
Jessica Blazina (602)510-5491
SSWJV-Superintendent
Mike Howard
(602) 619-5813
STAY CONNECTED
Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest
facebook.com/valleymetro
24-Hour Project Hotline
602-254-RAIL (7245)
WORK DESCRIPTION
Intermittent road closure will take place between for Butler, El Caminito, and Las Palmaritas
El Caminito and Las Palmaritas will not close simultaneously
Use 15th Ave to access Butler Dr.
TRAFFIC RESTRICTION
19
th A
VE
LAS PALMARITAS
Work
EL CAMINITO
BUTLER DR.
19
th
LAS PALMARITAS
Work
EL CAMINITO
BUTLER DR.
Pipe removal, roadway widening, and paving on the East side of 19th Ave
CONSTRUCTION NOTICE
NORTHWEST EXTENSION
Augusta, Frier, and Morten
Roadway Widening | Paving
Through December 31, 2014
WORK DESCRIPTION
Intermittent road closure will take place for Augusta, Frier and Morten
Frier will remain open if Augusta or Morten are closed
Augusta and Morten can close at the same time.
Use 18th Ave as alternate access to Augusta, Frier, and Morten
TRAFFIC RESTRICTION
QUESTIONS?
VALLEY METRO
Community Outreach
Coordinators
Carla Kahn (623) 261-2605
Jessica Blazina (602)510-5491
SSWJV-Superintendent
Mike Howard
(602) 619-5813
STAY CONNECTED
Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest
facebook.com/valleymetro
24-Hour Project Hotline
602-254-RAIL (7245)
QUESTIONS?
VALLEY METRO
Community Outreach
Coordinators
Carla Kahn (623) 261-2605
Jessica Blazina(602)510-5491
SSWJV
Superintendent
Mike Howard
(602) 619-5813 Tie-in new waterlines and removal of existing
waterline.
CONSTRUCTION NOTICE
NORTHWEST EXTENSION
State Ave. & Myrtle Ave.
Waterline Tie-ins | Removals
October 13, 2014 to October 24, 2014
STAY CONNECTED
Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest
facebook.com/valleymetro
WORK DESCRIPTION
Intermittent road closure will take place between State Ave. & Myrtle Ave.
State and Myrtle will not close simultaneously.
Use Orangewood or Myrtle to 17th Ave. as alternate access to State.
Use Orangewood or State to 17th Ave. as alternate access to State and Northview
TRAFFIC RESTRICTION
QUESTIONS?
VALLEY METRO
Community Outreach
Coordinators
Carla Kahn (623) 261-2605
Jessica Blazina(602)510-5491
SSWJV
Superintendent
Mike Howard
(602) 619-5813
Tie-in new waterlines and remove existing.
CONSTRUCTION NOTICE
NORTHWEST EXTENSION
Gardenia and Northview
Waterline Tie-Ins | Removals
October 20 to October 31, 2014
STAY CONNECTED
Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest
facebook.com/valleymetro
WORK DESCRIPTION
Intermittent road closure will take place between Gardenia and Northview.
Gardenia and Northview will not close simultaneously.
Use Gardenia to access Northview or Northview to access Gardenia,
Use Orangewood or Myrtle to access from 21st Ave.
TRAFFIC RESTRICTION
QUESTIONS?
VALLEY METRO
Community Outreach
Coordinators
Carla Kahn (623) 261-2605
Jessica Blazina(602)510-5491
SSWJV
Superintendent
Mike Howard
(602) 619-5813
A new phase of construction is beginning with roadway widening and track installation. This new phase will modify traffic patterns along 19th Avenue including right-turn only movements onto 19th Avenue
CONSTRUCTION NOTICE
NORTHWEST EXTENSION
Roadway Widening
Glendale to Marlette Ave
October 13, 2014 to October 17, 2014
STAY CONNECTED
Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest
facebook.com/valleymetro
24-Hour Project Hotline
602-254-RAIL (7245)
Paving eastside of 19th Avenue
Access will be maintained onto 19th Avenue
Possibility of short delays as crews move through the area
Officers will be onsite to assist with access
Right turn only onto 19th Avenue
QUESTIONS?
VALLEY METRO
Community Outreach
Coordinators
Carla Kahn (623) 261-2605
Jessica Blazina(602)510-5491
SSWJV
Superintendent
Mike Howard
(602) 619-5813
Paving of the eastside at Maryland
CONSTRUCTION NOTICE
NORTHWEST EXTENSION
STAY CONNECTED
Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest
facebook.com/valleymetro
24-Hour Project Hotline
602-254-RAIL (7245)
WORK DESCRIPTION
19th Ave & Maryland - East Side Closure Roadway Paving
October 2nd to October 18th
24 hour
No right turns from 19th Ave to Tuckey Rd
(Southbound to Westbound)
No left turns from 19th Ave to Tuckey Rd
(Northbound to Westbound)
No right turns from Tuckey Rd to 19th Ave
(Eastbound to Southbound)
No left turns from Tuckey Rd to 19th Ave
(Eastbound to Northbound)
TRAFFIC RESTRICTION
QUESTIONS?
VALLEY METRO
Community Outreach
Coordinators
Carla Kahn (623) 261-2605
Jessica Blazina(602)510-5491
SSWJV
Superintendent
Mike Howard
(602) 619-5813 Remove and replace existing roadway, sidewalk,
curb and gutter
CONSTRUCTION NOTICE
NORTHWEST EXTENSION
Ocotillo, Tuckey, and Maryland
Roadway Widening - East Side
Through October 18, 2014
STAY CONNECTED
Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest
facebook.com/valleymetro
24-Hour Project Hotline
602-254-RAIL (7245)
WORK DESCRIPTION
Intermittent road closures—Tuckey or Maryland will be open throughout construction
Use 17th Ave for alternate access to Tuckey and Maryland
Use south alley or 17th Ave. apartment entrance for alternate access to Ocotillo
TRAFFIC RESTRICTION
QUESTIONS?
VALLEY METRO
Community Outreach
Coordinators
Carla Kahn (623) 261-2605
Jessica Blazina(602)510-5491
SSWJV
Superintendent
Mike Howard
(602) 619-5813 Waterline tie-ins, roadway widening, and paving
CONSTRUCTION NOTICE
NORTHWEST EXTENSION
Christown Spectrum Mall Entrance
Waterline | Roadway Widening
October 8, 2014 to October 31, 2014
STAY CONNECTED
Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest
facebook.com/valleymetro
24-Hour Project Hotline
602-254-RAIL (7245)
WORK DESCRIPTION
Christown Spectrum Mall Entrance will be closed
Use Bethany Home Rd. or Montebello to access mall
TRAFFIC RESTRICTION
NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP
CONTRACTOR’S WEEKLY UPDATE
PROJECT APP
City of Phoenix