COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE Doug’s Corner ……………………..1–3 Traffic/Active Work ……………………...4-6 Construction Notices …………………….7-16 Project App ………………..………17 October 13, 2014 Volume 2, Issue 91 CONTRACTOR’S WEEKLY UPDATE DOUG’s CORNER NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP

CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

COURTEOUS

RESPONSIVE

DEPENDABLE

IN THIS ISSUE

Doug’s Corner ……………………..1–3

Traffic/Active Work ……………………...4-6

Construction Notices …………………….7-16

Project App

………………..………17

October 13, 2014 Volume 2, Issue 91

CONTRACTOR’S WEEKLY UPDATE

DOUG’s CORNER

NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP

Page 2: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

DOUG’s CORNER MY WEEK IN PICTURES

NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP

CONTRACTOR’S WEEKLY UPDATE

Page 3: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

DOUG’s CORNER MY WEEK IN PICTURES

Doug St. Stevens

NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP

CONTRACTOR’S WEEKLY UPDATE

Page 4: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

Dunlap - Dunlap / 19th Intersection Traffic signals, place station footings, set station steel

One (1) lane both east and westbound, left turn lanes will be maintained September 29 to October 17, 2014

Dunlap to Butler Track, double crossover, sig-comm, guideway curb

One (1) lane both north and southbound will be maintained

Butler, El Caminito, Las Palmaritas eastside closures thru Dec 31, 2014

Butler to Northern Storm, traffic signals, roadway widening

One (1) lane both north and southbound will be maintained

Turns at the signalized intersections will be maintained

Butler, El Caminito, Las Palmaritas eastside closures through Dec 31,

2014

Northern / 19th Intersection

One (1) lane east and west bound will be maintained October 20, thru December 31, 2014. Intermittent turn restrictions

Glendale and Northern to alternate restrictions. One or the other will have a minimum of 2 lanes and left turns maintained both east and westbound

Northern to Orangewood Century Link, storm drain, traffic signals, roadway widening

One (1) lane both north and south bound will be maintained

Turn lanes at the signalized intersections will be maintained

Augusta, Frier, Morten closures thru December 31, 2014

WEEK OF 10.13.2014

NORTH

NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP

CONTRACTOR’S WEEKLY UPDATE

DUNLAP — ORANGEWOOD

WORK ACTIVITIES AND TRAFFIC CONTROL

Page 5: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

WORK ACTIVITIES AND TRAFFIC CONTROL

Orangewood to Glendale Water, traffic signals

One (1) lane both north and south bound will be maintained

Turn lanes at the signalized intersections will be maintained

State and Myrtle closures October 13, 2014 to October 24, 2014

Gardenia and Northview closures October 20 to October 31, 2014

Glendale / 19th Intersection

One (1) lane east and west bound. Turns will be maintained October 10, 2014 thru October 18, 2014

Glendale and Northern to alternate restrictions. One or the other will have a minimum of 2 lanes and left turns maintained both east and westbound

Glendale paving notice October 13, 2014 to October 17, 2014

Glendale to Maryland Century Link, curb, gutter, sidewalk, driveways, roadway, form and pour

guideway curb

One (1) lane both north and south bound will be maintained

Turn lanes at the signalized intersections will be maintained

Ocotillo, Tuckey, Maryland closures to October 18, 2014

Maryland eastside closure October 2, 2014 to October 18, 2014

Maryland to Bethany Home Road Sidewalk, curb, gutter, driveways, traffic signals, roadway, Century Link

One (1) lane both north and south bound will be maintained

Turn lanes at the signalized intersections will be maintained

NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP

CONTRACTOR’S WEEKLY UPDATE

WEEK OF 10.13.2014

SOUTH ORANGEWOOD

-MONTEBELLO

Page 6: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

WORK ACTIVITIES AND TRAFFIC CONTROL

Bethany Home / 19th Intersection Century Link, grade and pave roadway, ductbank

Two (2) lanes east and west bound will be maintained beginning October 9, 2014.

Bethany Home Road to Montebello Century Link, curb, gutter, sidewalk, driveways and ductbank installation

One (1) lane both north and south bound will be maintained

Turn lanes at signalized intersections will be maintained

Mall entrance closure October 8, 2014 to October 31, 2015

NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP

CONTRACTOR’S WEEKLY UPDATE

WEEK OF 10.13.2014

SOUTH ORANGEWOOD

-MONTEBELLO

Page 7: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

CONSTRUCTION NOTICE

NORTHWEST EXTENSION

Dunlap Ave to Northern Ave

Roadway Widening & Track Install

Sept 1, 2014 – January 1, 2015

A new phase of construction is beginning with

roadway widening and track installation. This

new phase will modify traffic patterns along

19th Avenue including right-turn only

movements onto 19th Avenue.

Roadway widening

Track installation

Right turns only onto 19th Avenue

Temporary U-turn will located south of Alice Avenue

See map on following page

QUESTIONS?

VALLEY METRO

Community Outreach

Coordinators

Carla Kahn (623) 261-2605

Jessica Blazina(602)510-5491

SSWJV

Superintendent

Mike Howard

(602) 619-5813

STAY CONNECTED

Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest

facebook.com/valleymetro

24-Hour Project Hotline

602-254-RAIL (7245)

Page 8: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

CONSTRUCTION NOTICE

NORTHWEST EXTENSION

Roadway Widening & Track Install

Dunlap Ave to Northern Ave

QUESTIONS?

VALLEY METRO

Community Outreach

Coordinators

Carla Kahn (623) 261-2605

Jessica Blazina(602)510-5491

SSWJV

Superintendent

Mike Howard

(602) 619-5813

STAY CONNECTED

Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest

facebook.com/valleymetro

24-Hour Project Hotline

602-254-RAIL (7245)

Page 9: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

Pipe removal, roadway widening, and paving on east side of 19th Avenue

CONSTRUCTION NOTICE

NORTHWEST EXTENSION

Butler, El Caminito,

Las Palmaritas Eastside

Roadway Widening | Paving

Sept. 15 - Dec. 31, 2014

QUESTIONS?

VALLEY METRO

Community Outreach

Coordinators

Carla Kahn (623) 261-2605

Jessica Blazina (602)510-5491

SSWJV-Superintendent

Mike Howard

(602) 619-5813

STAY CONNECTED

Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest

facebook.com/valleymetro

24-Hour Project Hotline

602-254-RAIL (7245)

WORK DESCRIPTION

Intermittent road closure will take place between for Butler, El Caminito, and Las Palmaritas

El Caminito and Las Palmaritas will not close simultaneously

Use 15th Ave to access Butler Dr.

TRAFFIC RESTRICTION

19

th A

VE

LAS PALMARITAS

Work

EL CAMINITO

BUTLER DR.

19

th

LAS PALMARITAS

Work

EL CAMINITO

BUTLER DR.

Page 10: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

Pipe removal, roadway widening, and paving on the East side of 19th Ave

CONSTRUCTION NOTICE

NORTHWEST EXTENSION

Augusta, Frier, and Morten

Roadway Widening | Paving

Through December 31, 2014

WORK DESCRIPTION

Intermittent road closure will take place for Augusta, Frier and Morten

Frier will remain open if Augusta or Morten are closed

Augusta and Morten can close at the same time.

Use 18th Ave as alternate access to Augusta, Frier, and Morten

TRAFFIC RESTRICTION

QUESTIONS?

VALLEY METRO

Community Outreach

Coordinators

Carla Kahn (623) 261-2605

Jessica Blazina (602)510-5491

SSWJV-Superintendent

Mike Howard

(602) 619-5813

STAY CONNECTED

Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest

facebook.com/valleymetro

24-Hour Project Hotline

602-254-RAIL (7245)

Page 11: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

QUESTIONS?

VALLEY METRO

Community Outreach

Coordinators

Carla Kahn (623) 261-2605

Jessica Blazina(602)510-5491

SSWJV

Superintendent

Mike Howard

(602) 619-5813 Tie-in new waterlines and removal of existing

waterline.

CONSTRUCTION NOTICE

NORTHWEST EXTENSION

State Ave. & Myrtle Ave.

Waterline Tie-ins | Removals

October 13, 2014 to October 24, 2014

STAY CONNECTED

Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest

facebook.com/valleymetro

WORK DESCRIPTION

Intermittent road closure will take place between State Ave. & Myrtle Ave.

State and Myrtle will not close simultaneously.

Use Orangewood or Myrtle to 17th Ave. as alternate access to State.

Use Orangewood or State to 17th Ave. as alternate access to State and Northview

TRAFFIC RESTRICTION

Page 12: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

QUESTIONS?

VALLEY METRO

Community Outreach

Coordinators

Carla Kahn (623) 261-2605

Jessica Blazina(602)510-5491

SSWJV

Superintendent

Mike Howard

(602) 619-5813

Tie-in new waterlines and remove existing.

CONSTRUCTION NOTICE

NORTHWEST EXTENSION

Gardenia and Northview

Waterline Tie-Ins | Removals

October 20 to October 31, 2014

STAY CONNECTED

Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest

facebook.com/valleymetro

WORK DESCRIPTION

Intermittent road closure will take place between Gardenia and Northview.

Gardenia and Northview will not close simultaneously.

Use Gardenia to access Northview or Northview to access Gardenia,

Use Orangewood or Myrtle to access from 21st Ave.

TRAFFIC RESTRICTION

Page 13: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

QUESTIONS?

VALLEY METRO

Community Outreach

Coordinators

Carla Kahn (623) 261-2605

Jessica Blazina(602)510-5491

SSWJV

Superintendent

Mike Howard

(602) 619-5813

A new phase of construction is beginning with roadway widening and track installation. This new phase will modify traffic patterns along 19th Avenue including right-turn only movements onto 19th Avenue

CONSTRUCTION NOTICE

NORTHWEST EXTENSION

Roadway Widening

Glendale to Marlette Ave

October 13, 2014 to October 17, 2014

STAY CONNECTED

Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest

facebook.com/valleymetro

24-Hour Project Hotline

602-254-RAIL (7245)

Paving eastside of 19th Avenue

Access will be maintained onto 19th Avenue

Possibility of short delays as crews move through the area

Officers will be onsite to assist with access

Right turn only onto 19th Avenue

Page 14: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

QUESTIONS?

VALLEY METRO

Community Outreach

Coordinators

Carla Kahn (623) 261-2605

Jessica Blazina(602)510-5491

SSWJV

Superintendent

Mike Howard

(602) 619-5813

Paving of the eastside at Maryland

CONSTRUCTION NOTICE

NORTHWEST EXTENSION

STAY CONNECTED

Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest

facebook.com/valleymetro

24-Hour Project Hotline

602-254-RAIL (7245)

WORK DESCRIPTION

19th Ave & Maryland - East Side Closure Roadway Paving

October 2nd to October 18th

24 hour

No right turns from 19th Ave to Tuckey Rd

(Southbound to Westbound)

No left turns from 19th Ave to Tuckey Rd

(Northbound to Westbound)

No right turns from Tuckey Rd to 19th Ave

(Eastbound to Southbound)

No left turns from Tuckey Rd to 19th Ave

(Eastbound to Northbound)

TRAFFIC RESTRICTION

Page 15: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

QUESTIONS?

VALLEY METRO

Community Outreach

Coordinators

Carla Kahn (623) 261-2605

Jessica Blazina(602)510-5491

SSWJV

Superintendent

Mike Howard

(602) 619-5813 Remove and replace existing roadway, sidewalk,

curb and gutter

CONSTRUCTION NOTICE

NORTHWEST EXTENSION

Ocotillo, Tuckey, and Maryland

Roadway Widening - East Side

Through October 18, 2014

STAY CONNECTED

Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest

facebook.com/valleymetro

24-Hour Project Hotline

602-254-RAIL (7245)

WORK DESCRIPTION

Intermittent road closures—Tuckey or Maryland will be open throughout construction

Use 17th Ave for alternate access to Tuckey and Maryland

Use south alley or 17th Ave. apartment entrance for alternate access to Ocotillo

TRAFFIC RESTRICTION

Page 16: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

QUESTIONS?

VALLEY METRO

Community Outreach

Coordinators

Carla Kahn (623) 261-2605

Jessica Blazina(602)510-5491

SSWJV

Superintendent

Mike Howard

(602) 619-5813 Waterline tie-ins, roadway widening, and paving

CONSTRUCTION NOTICE

NORTHWEST EXTENSION

Christown Spectrum Mall Entrance

Waterline | Roadway Widening

October 8, 2014 to October 31, 2014

STAY CONNECTED

Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest

facebook.com/valleymetro

24-Hour Project Hotline

602-254-RAIL (7245)

WORK DESCRIPTION

Christown Spectrum Mall Entrance will be closed

Use Bethany Home Rd. or Montebello to access mall

TRAFFIC RESTRICTION

Page 17: CONTRACTOR’S WEEKLY UPDATECONTRACTOR’S WEEKLY UPDATE WEEK OF 10.13.2014 SOUTH ORANGEWOOD-MONTEBELLO. WORK ACTIVITIES AND TRAFFIC CONTROL Bethany Home / 19th Intersection Century

NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP

CONTRACTOR’S WEEKLY UPDATE

PROJECT APP

City of Phoenix