Kevin Dahm , DTE Energy Dal Vernon Reising , Human Centered Solutions. Control Room Modernization Using: Virtual Systems and High Performance Graphics . CR Redesign. HW Redesign. SW Redesign. HMI Redesign. Lessons. Topics Control Room Redesign Hardware Redesign Software Redesign - PowerPoint PPT Presentation

Citation preview

Page 1: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

Control Room Modernization Using: Virtual Systems and High Performance Graphics

Kevin Dahm, DTE EnergyDal Vernon Reising, Human Centered Solutions

Page 2: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

Topics

Control Room RedesignHardware RedesignSoftware Redesign

HMI RedesignLessons Learned: Facilitating Change

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 3: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Redesign

CR Modernization: Virtualization & High Performance Graphics

Topics

Control Room RedesignHardware RedesignSoftware Redesign

HMI RedesignLessons Learned: Facilitating Change

HW Redesign SW Redesign HMI Redesign Lessons

Page 4: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Redesign

CR Modernization: Virtualization & High Performance Graphics

DTE Energy brought in Human Factors control room specialists • Human Centered Solutions (HCS) • Operations requirements for control room • DCS workstations, Business network PC,

team meetings, protective tagging work process, handover, …

• Ergonomic best practices • Engineering support requirements • Collaboration requirements • Provided QA/QC for DTE with Console vendor

HW Redesign SW Redesign HMI Redesign Lessons

Page 5: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

Old vs. New: U shape or Sit/Stand

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 6: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

• Desk for protective tagging• P&IDs and pull out drawers

Page 7: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

Topics

Control Room RedesignHardware Redesign

Software RedesignHMI Redesign

Lessons Learned: Facilitating Change

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 8: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

• Virtual Servers• 1U clients w/Matrox

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 9: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

Topics

Control Room RedesignHardware Redesign

Software RedesignHMI Redesign

Lessons Learned: Facilitating Change

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 10: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

New software

• Eliminated “DTE Specials”

• Followed DCS manufacturers standards

• Easier to get assistance and upgrade

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 11: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

Topics

Control Room RedesignHardware RedesignSoftware RedesignHMI Redesign

Lessons Learned: Facilitating Change

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 12: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

HMI Design Project Work Flow

• HMI Design Workshop• Proper Attendance

• 2 days of Education & Best practices sharing

• 1 day of Hands-on Exercises

• Create a Style Guide

• Go to Work• Console screen configuration• Display hierarchy design

• 2nd 1-day hands-on

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 13: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 14: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 15: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 16: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 17: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 18: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

Redesigned: Control Room with High Performance Graphics

Hand outs

Color Blind vs

High Performance HMI and Gray Scale

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 19: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 20: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 21: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

ADVANTAGES:• Company Savings• Less DCS vendor work• Less rework• Corporate vs plant standards

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 22: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

Topics

Control Room RedesignHardware RedesignSoftware RedesignGraphics Redesign

Lessons Learned: Facilitating Change

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 23: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

Change: FGD CR Design Mock up Visualize ¼” = 1’

Change: HW Design Corporate Standard 2 vs quad and mouse

Change: SW Design Corporate Standard Modify libraries If you see it, change it

Change: Graphics Change in Operations Management Change in Liaisons Decision makers? Missed training Passive / Aggressive Style Guide signoff ** If things are going south of troublesome. STOP. Regroup/Comm

The HUMAN Factor

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 24: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

HMI Development - Common Failure Modes

1. Belief that up-front analysis methodologies are too expensive

2. Operators know what they want

3. P&IDs drive content & layout of operating displays

4. Developers lack training in effective display design

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons

Page 25: Control  Room Modernization Using:  Virtual  Systems and High Performance Graphics

CR Modernization: Virtualization & High Performance Graphics

QUESTIONS ???

Comments !!!

Thank You !!!

Kevin DahmDTE [email protected]

Dal Vernon ReisingHuman Centered [email protected]

CR Redesign HW Redesign SW Redesign HMI Redesign Lessons