47
Cost-Benefit Analysis of Transit Projects: Current Practice and Methodological Advances Elena Safirova Presented at New York University October 26, 2011

Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Cost-Benefit Analysis of Transit Projects: Current Practice and

Methodological Advances

Elena Safirova

Presented at New York University

October 26, 2011

Page 2: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Outline What is Cost-Benefit Analysis? Benefits of Transit Transit Infrastructure CBA: State of Practice Transit Benefits: Potential Drawbacks FTA LUSTRE Project Project Goals LUSTRE Framework Work Description

Concluding Remarks

Page 3: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

What is CBA?

A cost-benefit analysis is a systematic evaluation of the economic advantages (benefits) and disadvantages (costs) of a set of investment alternatives

A sum of discounted benefits is compared to a stream of discounted costs.

Benefit/cost ratio should be greater than 1 to justify the investment

Page 4: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Benefits of Transit (1)

Benefits to System’s Users Travel time reduction Travel cost reduction

Non-user Benefits Congestion reduction

Social Benefits Related to overall VMT reduction Environmental Benefits Accident Reductions

Page 5: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Benefits of Transit (2)

Benefits to vulnerable populations Significant reductions in costs to individuals Reduction in agency costs (e.g. paratransit)

Benefits of Transit-Oriented Development (TOD) Changes in travel patterns Changes in lifestyle (e.g. health benefits) Increase in land values

Page 6: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Costs of Transit Projects Not significantly different from other

infrastructure projects Cost escalation due to project delay and

initial cost underestimation Solution: cost management in a risk-

analytic framework

Page 7: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Transit CBA in Practice: Menu of Programs

FTA: New Starts DOT: TIGER I TIGER II TIGER III

State and MPO-level programs

Page 8: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Transit CBA: Methodology

Usually: a collection of disjoint categories of benefits

Inclusion of a particular benefit is largely data-driven

Due to the fragmentary approach, positive changes in benefits may be included while negative are omitted

Page 9: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Common Drawbacks of Practical Approach

High probability of double-counting E.g. travel-related benefits an TOD-related

benefits High probability of omitting large

categories of benefits Fragmentary nature of accounting Inconsistencies between benefit categories

Page 10: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Benefits of Travel and TOD

TOD and travel are interconnected TOD affects the demand for travel TOD changes spatial distribution of economic

activity in the entire region, and, as a result, changes the demand for travel

However, travel-related benefits are projected using regional travel demand model, and TOD benefits are estimated separately using different methods

Page 11: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

FTA LUSTRE Project

Objectives Develop “proof of a concept” framework that

demonstrates a relationship between transportation and “environment benefits” of transit projects

Investigate the ratio of transportation and “environment benefits”

Advance evaluation methodology of transit projects

Page 12: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

November 11

Land Use, Strategic Transport, Regional Economy (LUSTRE)

Literature Review Spatially Distributed Households Spatially Disaggregated Transportation Industry Modeling General Equilibrium Effects

LUSTRE Overview LUSTRE=START+RELU

Data and Calibration

Page 13: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

November 11

Washington-START Model

Transportation simulation model Developed by RFF researchers using

START modeling suite Designed for quick policy analysis Evaluation of policies using a consistent

economic framework Not politically constrained Calibrated for Washington, DC metro area

Page 14: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

November 11

RELU Model Features

Spatially disaggregated general equilibrium model of economic activity without predetermined location of residents and firms

Some extras 4 income classes Employed and unemployed Explicit modeling of housing Developers’ and landlords’ decisions Income and property taxes

Page 15: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

LUSTRE Model Overview Generalized Costs of Travel *Intermediate demand for finished goods and services, also referred as Input/Output (I/O) tables.

START

RELU

Generalized Costs of Travel

Wages & Trips

LUSTRE

Supply-Side Module

Route Network Rail Systems Bus System

Parking Facilities

Demand-Side Module

Logit Tree: Purpose/Origin (given)

Trip Generation

Destination

Mode

Time

Route

GCT Trips

Individuals Discrete Choices:

Choice of Work Status Choice of Work Location

Choice of Residence

Continuous Choices: Housing Consumption

Retail Goods & Services

Producers

Retail Agriculture

Manufacturing Business Services

Constr/Demo

Labor

Capital Space

I/O*

LandlordsDevelopers

Real Estate

Stock

Rent

Rent

Rent

I/O Freight

Labor Supply/ Wage

Price

Page 16: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

November 11

LUSTRE features

Consistent spatial disaggregation Non-monocentricity Agent heterogeneity Unemployment Frictions Income and real estate taxes Congestible alternative modes

Page 17: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

November 11

Data Sources

2000 Census SF1A & SF3A CTPP

BEA production data Consumer Expenditure Survey MWCOG transportation data Land use data

Page 18: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

November 11

Wage and Income Information for LUSTRE Baseline

*Net of taxes and commuting costs

Average Net Income*

(2000$/year)

Average Gross Wages Rates (2000$/hour)

Income Tax Rates

…………………..Quartile 1 15779 6.8 14.3%

Quartile 2 25815 14.1 16.6%

Quartile 3 43943 22.5 22.3%

Quartile 4 91805 47.0 31.5%

Page 19: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

November 11

Active Population Employed

1480873 830601(56.1%)

941310 738659(78.5%)

1244120 1144755(92.0%)

472832 461014(97.5%)

4139134 3175031(76.7%)

Quartile 3 (relative to active population)Quartile 4 (relative to active population)Total (relative to active population)

All Study Area

Quartile 1 (relative

to active population)Quartile 2 (relative

to active population)

Workers from All ZonesActive Population Employed Total per year

25265 13402 70323(53.0%)

14083 10528 85331(74.8%)

16139 14317 183792(88.7%)

7388 7152 104990(96.8%)

62874 45402 444437(72.2%)

Downtown CoreResidents

Quartile 1 (relative

to active population)Quartile 2 (relative

to active population)Quartile 3 (relative

to active population)Quartile 4 (relative

to active population)Total (relative to active population)

Population Distribution Over the Region

Population Distribution for the Downtown Core

Page 20: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

November 11

Commuting Trips

(Thousands/Day)

Shopping Trips

(Thousands/Day)

All Trips

(Thousands

/Day)

Commuting Trips

(Thousands/Day)

Shopping Trips

(Thousands/Day)

All Trips

(Thousands

/Day)AM Peak 1454 321 1775 226 11 238PMPeak 60 883 943 6 24 30Off Peak 908 1090 1998 108 31 139

Total 2423 2294 4716 341 66 407

All Study Area Ending at Downtown Core

AM Peak : From 6:30 am to 9:30 amPM Peak : From 3:30 pm to 6:30 pm

Commuting Trips

(Thousands/Day)

Shopping Trips

(Thousands/Day)

All Trips

(Thousands

/Day)

Commuting Trips

(Thousands/Day)

Shopping Trips

(Thousands/Day)

All Trips

(Thousands

/Day)Bus 86 32 118 29 15 45

Rail 234 13 246 163 7 169

SOV 1641 997 2638 91 10 101

HOV 291 1109 1401 40 14 54

Walking / Biking

171 142 313 18 21 39

HOV : High Occupancy Vehicle

All Study Area Ending at Downtown Core

SOV : Single Occupancy Vehicle

Distribution over Time Periods

Distribution over Mode of Transportation

Trips Distribution for LUSTRE Baseline

Page 21: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

November 11

Modeling area

Page 22: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Dulles Rail Project

23-mile extension of the existing Metrorail system

Will connect Downtown Washington DC with Dulles International Airport and surrounding area

The project will include 11 new stations

Page 23: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with
Page 24: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with
Page 25: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Zoom-in Tool

Zoom-in Land Use Module Zoom-in Transportation Module Approaches: “Little LUSTRE” “Little RELU” + Simplified transportation

module (STM) “Simplified RELU”+ “Little START” “Simplified RELU” + Simplified

transportation module (STM)

Page 26: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Simplified Transportation Module

3 suggested versions “Start Lite” Simple mode choice model Likely a Logit based mode choice, with a very

simple route structure. (No parking search, etc)

Econometric model We can calibrate this model by using START

model runs

Page 27: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Simplified RELU

Several features could be suppressed/simplified: Shopping modeling Features of “Closed Economy” Modified developers module

Goal: to retain consistency in welfare measurement while capturing key land use metrics

Page 28: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Integration between “Big LUSTRE” and zoom-in tool

Complete Integration (iteration until convergence on several aggregate parameters, e.g. residents, jobs, etc., trip times)

Partial integration Focusing on population movements and

transportation cost equivalency Post-processing (loose connection)

Page 29: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Assumed Unchanged

Big LUSTRE Calibration Area Population Initial Building Stocks Transportation Infrastructure Except for the Dulles rail project

Initial Income Levels Big LUSTRE Structure Long-term equilibrium framework

Page 30: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Resulting framework capabilities

Consistent (or largely consistent) welfare measurement

Account of population and job movement Changes in travel patterns in response to

infrastructure improvement/construction Changes in wages, rents, incomes, etc.

Page 31: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Mini-RELU Design

Focus on developers’ decisions New development Redevelopment

Focus on relocation of residents and businesses within the localized area

Don’t explicitly model variation in prices and wages in the zoom-in area

Page 32: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Mini-LUSTRE Data Work

Define zone structure Consistent with project goals Consistent with data availability

Obtain Data RELU data (population, housing, land use,

economic fundamentals) Transportation data

Calibrate the model

Page 33: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with
Page 34: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with
Page 35: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Zone # Description County Tracts

1 Tysons Fairfax 4802.02, 4802.03, 4605.01, 4604

2 Tysons East Fairfax 4712.01, 4712.02

3 Reston North Fairfax 4820.01, 4820.02, 4805.04, 4805.05, 4821, 4822.01, 4822.02, 4822.03, 4819

4 Reston South Fairfax 4812.01, 4812.02, 4823.01, 4823.02, 4823.03, 4814

5 Herndon North Fairfax 4808.01, 4808.02, 4809.01, 4809.02, 4809.03, 4810

6 Herndon South Fairfax 4811.01, 4811.02, 4811.03, 4811.04, 4825.01

7Sterling/Dulles Town Center Loudoun 6115.01, 6115.02, 6116.01, 6116.02, 6113, 6114, 6117

8 Ashburn Loudoun 6110.04, 6110.05, 6110.06, 6110.19, 6110.20, 6110.21, 6110.22, 6110.23,6110.24, 6110.25

910

CascadesBelmont/Landsdowne

LoudounLoudoun 6111, 6112

6110.02, 6110.09-6110.186105, 610611 Leesburg Loudoun

12 Dulles Airport Fairfax, Loudoun 9802, 9801

13 Great Falls Fairfax 4801, 4804

14 Northeast Fairfax Fairfax 4803, 4802.01

15 Dunn Loring Fairfax 4605.02, 4606

16 Vienna North Fairfax 4608, 4609

17 Vienna South Fairfax 4607.01, 4607.02, 4610

18 South of 66 Fairfax 4616.01, 4616.02, 4617, 4402.01

19 Woodburn Fairfax 4401, 4402.02, 4403

20 City of Fairfax Fairfax C of F + 4405.02+ 4405.01+ 4406

21 North of Oakton Fairfax 4611, 4615, 4612.01, 4618, 4619

22 Wolf Trap Fairfax 4602, 4603, 4824

23 Fairfax Northwest Fairfax 4805.01, 4805.02, 4805.03

24 East of Franklin Farm Fairfax 4815, 4816, 4817.01, 4817.02

25 Fair Oaks/Fair Lakes Fairfax 4612.02, 4917.01, 4917.02, 4917.03, 4917.04, 4918.01, 4918.02, 4918.03

26 Loudon/Prince William Fairfax 4910, 4911.01, 4911.02, 4911.03, 4912.01, 4912.02, 4915.01, 4915.02

27 Chantilly Fairfax 4826.01, 4901.01, 4901.03, 4916.01, 4916.02

28 Arcola/Stone Ridge Loudoun 6118.01, 6118.02, 6118.03, 6118.04, 6118.05, 6118.06

Page 36: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with
Page 37: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Table 2a: Average Weighted Travel Time Difference (Build - Baseline): Peak Walk to Transit

PKWKWTD 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1-DC Core 0 0 0 0 0 0 0 -37 -15 -68 -3 1 0 0 0 0

2-DC Other 0 0 0 0 0 0 0 -34 -15 -64 -5 1 0 0 0 0

3-VA Core 0 0 0 0 0 0 0 -35 -15 -66 -2 1 0 0 0 0

4-VA Arlington Orange Line 0 0 0 0 0 0 0 -32 -13 -63 0 1 -1 0 0 0

5-VA ARL Columbia Pike 0 0 0 0 0 0 0 -30 -12 -56 0 1 0 0 0 0

6-Alexandria/Springfield 0 0 0 0 0 0 0 -11 -17 -58 -9 0 0 0 0 0

7-Vienna Corr 0 0 0 0 0 0 0 -13 -6 -40 -3 0 0 0 0 0

8-Tysons -30 -27 -28 -22 -21 -17 -15 -11 -31 -94 -30 -12 -7 -29 -17 -26

9-Dulles Corr -14 -14 -12 -11 -10 -12 -5 -32 -18 -60 -6 -3 -15 -17 -4 -22

10-Ashburn/Sterling -34 -38 -35 -42 -37 -26 -27 -79 -45 -5 0 -9 -38 -33 -48

11-Rest of Loudoun -1 -2 -1 -14 -7 -5 -22 -62 -46 -8 0 -6 -8 -3 -4

12-PW County 0 0 0 0 0 0 0 -6 -12 -53 -12 0 0 0 0 0

13-MTG County 0 0 0 0 0 0 0 -14 -16 -60 -10 1 0 0 0 0

14-PG County 0 0 0 0 0 0 0 -38 -18 -57 -10 0 0 0 0 0

15-Outer VA 0 0 0 -1 0 0 1 -1 -24 -85 -36 0 0 0 0 0

16-Outer MD 0 0 0 0 0 0 0 -33 -19 -56 -11 0 0 0 0 0

Page 38: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Table 2b: Average Weighted Travel Time Difference (Build - Baseline): Peak Drive to Transit

PKDRWTD 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1-DC Core 0 0 0 0 0 0 0 -59 -28 -70 -6 1 0 0 0

2-DC Other 0 0 0 0 0 0 0 -44 -19 -61 -5 1 0 0 0 0

3-VA Core 0 0 0 0 0 0 0 -36 -15 -53 -5 0 0 0 0

4-VA Arlington Orange Line 0 0 0 0 0 0 0 -43 -16 -64 0 1 -1 0 0

5-VA ARL Columbia Pike 0 0 0 0 0 0 0 -42 -17 -58 -2 1 0 0 0

6-Alexandria/Springfield 0 0 0 0 0 0 0 -23 -18 -58 -9 0 0 0 0 0

7-Vienna Corr 0 -1 0 0 0 0 0 -31 -13 -48 -3 0 -2 -1 0 0

8-Tysons 1 1 1 1 2 1 0 0 -1 -47 -1 0 1 1 2

9-Dulles Corr -11 -12 -7 -10 -8 -9 -6 -43 -16 -62 -5 -3 -17 -14 0 -11

10-Ashburn/Sterling -32 -35 -30 -47 -35 -34 -46 -108 -78 -22 -3 -25 -43 -37 -31

11-Rest of Loudoun -18 -21 -18 -34 -24 -21 -47 -102 -92 -25 -3 -25 -28 -25 0 -15

12-PW County 0 0 -1 -4 0 0 -3 -39 -30 -72 -22 0 0 0 0 0

13-MTG County 0 0 0 0 0 0 -1 -24 -21 -65 -12 0 0 0 0 0

14-PG County 0 0 0 0 0 0 0 -43 -20 -60 -10 0 0 0 0 0

15-Outer VA 0 0 0 0 0 0 0 -24 -20 -77 -27 0 0 0 0 0

16-Outer MD 0 0 0 0 0 0 0 -42 -21 -57 -11 0 0 0 0 0

Page 39: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Zone # Description County Tracts

1 Tysons Fairfax 4802.02, 4802.03, 4605.01, 4604

2 Tysons East Fairfax 4712.01, 4712.02

3 Reston North Fairfax 4820.01, 4820.02, 4805.04, 4805.05, 4821, 4822.01, 4822.02, 4822.03, 4819

4 Reston South Fairfax 4812.01, 4812.02, 4823.01, 4823.02, 4823.03, 4814

5 Herndon North Fairfax 4808.01, 4808.02, 4809.01, 4809.02, 4809.03, 4810

6 Herndon South Fairfax 4811.01, 4811.02, 4811.03, 4811.04, 4825.01

7Sterling/Dulles Town Center Loudoun 6115.01, 6115.02, 6116.01, 6116.02, 6113, 6114, 6117

8 Ashburn Loudoun 6110.04, 6110.05, 6110.06, 6110.19, 6110.20, 6110.21, 6110.22, 6110.23,6110.24, 6110.25

910

CascadesBelmont/Landsdowne

LoudounLoudoun 6111, 6112

6110.02, 6110.09-6110.186105, 610611 Leesburg Loudoun

12 Dulles Airport Fairfax, Loudoun 9802, 9801

13 Great Falls Fairfax 4801, 4804

14 Northeast Fairfax Fairfax 4803, 4802.01

15 Dunn Loring Fairfax 4605.02, 4606

16 Vienna North Fairfax 4608, 4609

17 Vienna South Fairfax 4607.01, 4607.02, 4610

18 South of 66 Fairfax 4616.01, 4616.02, 4617, 4402.01

19 Woodburn Fairfax 4401, 4402.02, 4403

20 City of Fairfax Fairfax C of F + 4405.02+ 4405.01+ 4406

21 North of Oakton Fairfax 4611, 4615, 4612.01, 4618, 4619

22 Wolf Trap Fairfax 4602, 4603, 4824

23 Fairfax Northwest Fairfax 4805.01, 4805.02, 4805.03

24 East of Franklin Farm Fairfax 4815, 4816, 4817.01, 4817.02

25 Fair Oaks/Fair Lakes Fairfax 4612.02, 4917.01, 4917.02, 4917.03, 4917.04, 4918.01, 4918.02, 4918.03

26 Loudon/Prince William Fairfax 4910, 4911.01, 4911.02, 4911.03, 4912.01, 4912.02, 4915.01, 4915.02

27 Chantilly Fairfax 4826.01, 4901.01, 4901.03, 4916.01, 4916.02

28 Arcola/Stone Ridge Loudoun 6118.01, 6118.02, 6118.03, 6118.04, 6118.05, 6118.06

Page 40: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

0 200 400 600 800 1000 1200 1400

Change in number of Residents

1

5

9

13

17

21

25

Zone

#

Long-Term Growth in Residents

Page 41: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

0 200000 400000 600000 800000 1000000 1200000

Floor Space

1

6

11

16

21

26

Zone

#

Long-term Change in Single Family Housing

Page 42: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

0 20000 40000 60000 80000 100000 120000 140000 160000

Floor Space

1

5

9

13

17

21

25

Zone

#Long-term Change in Multi Family Housing

Page 43: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

0 200000 400000 600000 800000 10000001200000140000016000001800000

Floor Space

1

5

9

13

17

21

25

Zone

#

Long-Term Change in Commercial Building Space

Page 44: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Mini-LUSTRE Summary

Residential Growth: 10,791 (3.1%) Single Family Housing Growth: 8,300,000

sq. ft. (2.35%) Multi-Family Housing Growth: 876,000 sq.

ft. (2.31%) Commercial Building Floor Space Growth:

10,355,000 sq.ft. (1.73%)

Page 45: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Residential Movement in "Big" LUSTRE

-0.04

-0.03

-0.02

-0.01

0

0.01

0.02

0.03

0.04

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39

Zone #

Cha

nge

Page 46: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Caveats

Model is calibrated on 2000 data 2000 Census No new infrastructure included (e.g. ICC)

No natural population growth, economic growth, technological progress, etc.

The outcome is “static” long-term equilibrium

Only marginal effects are displayed; policy interactions are ignored

Page 47: Cost-Benefit Analysis of Transit Projects: Current Practice and ... · Dulles Rail Project 23-mile extension of the existing Metrorail system Will connect Downtown Washington DC with

Concluding Remarks

There is a wide gap between theory and practice of evaluating benefits of transit investments

Various categories of benefits are interconnected and should not be estimated separately from disconnected sources

Improvements in accuracy of demand estimates is likely to lead to more accurate CBAs in general