Cost Monitoring System

Embed Size (px)

Citation preview

  • 7/30/2019 Cost Monitoring System

    1/18

    1

    Budgetary Cost Control

  • 7/30/2019 Cost Monitoring System

    2/18

    2

    OBJECTIVES

    To enable control of cost of various items within the project

    budget.

    To continuously monitor cost of project and keep the

    management informed of the expenditure incurred against

    various commitments /orders.

    To prepare necessary documentation and records for periodic

    reference.

    To forecast periodic plans, to phase out fund requirements as

    per funds availability.

    To prepare comparison of plan Vs actual expenditure

    periodically.

  • 7/30/2019 Cost Monitoring System

    3/18

    3

    MAJOR AREAS OF

    BUDGETARY COST CONTROL

    Preparation of Annual Expenditure Plan (Yearly Budget).

    Preparation of Monthly Expenditure Report.

    Preparation of Revised Cost Estimate.

    Preparation of various other reports for our internal use and alsoas per clients requirement.

  • 7/30/2019 Cost Monitoring System

    4/18

    4

    ANNUAL EXPENDITURE PLAN

    (ANNUAL BUDGET)

    The Annual budget is prepared for the year with monthly break-up.

    The budget is prepared zone-wise, specifications wise under

    following major heads:

    (a) Civil work.

    (b) Structural work.

    (c) Equipment.

  • 7/30/2019 Cost Monitoring System

    5/18

    5

    Basis of Budget for Civil Work Monthly forecast for civil work is made based on plan of

    concreting work.

    Example:

    SL

    NOSPCIFICATION NO. DESCRIPTION TOTAL APR'08 MAY'08 JUN'08 JUL'08

    RAW MATERIAL HANDLING SYSTEM (ZONE - 01)

    Civil work Rs. in Cr. 64.12

    Quantity (cum) 75000 4000 4000 3500 3500

    Budget (Rs. in Cr.) 3.25 3.25 2.84

    = 64.12 / 75000 * 4000 * 95%

    95% is the progress payment

    1 VSP-6.3-01-CVL-003

  • 7/30/2019 Cost Monitoring System

    6/18

    6

    Basis of Budget for Structural WorkMonthly forecast for structural work is made based on plan for

    structural fabrication & erection. The weightage of fabrication &

    erection depends on the scope of work of the contractor.

    If steel is free issue then the weightage is normally considered as 60 40

    i.e. 60% fabrication & 40% erection. Example:

    SL

    NO

    SPCIFIC

    ATIONDESCRIPTION TOTAL APR'08 MAY'08 JUN'08 JUL'08

    RAW MATERIAL HANDLING SYSTEM (ZONE - 01)

    Structural Work Rs. in Cr. 16.65

    Fabrication Ton 12700 650 628 506 451

    Erection Ton 12700 100 143 130 123

    Structural Work (Weighted average

    considering 60% for fabrication

    & 40% for erection)

    Ton 12700 430 434 356 320

    Budget Rs. in Cr. 0.45 0.46 0.37

    = 16.65 / 12700 * 430 * 80%

    80% is the progress payment

    = 650 * 60% + 100 * 40%

    1

    VSP-6.3-

    01-STF-

    001

  • 7/30/2019 Cost Monitoring System

    7/18

    7

    Basis of budget for equipmentMonthly forecast of equipment is based on terms of payment.

    For progress payment of supply & erection monthly forecast is made

    considering time schedule & using S curve formula which is as follows:

    Y = [ 1 Sin {(X*180/Xn) + 90 } ] * 50 where Y = Percentage payment

    (Cumulative) at a particular time (X) within the time schedule (Xn)

    1 2 3 4 5

    SL

    NO

    SPCIFICA

    TION NO. DESCRIPTION

    Rs. in

    Cr.

    Compl.

    Time Start Finish Period APR'08 MAY'08 JUN'08 JUL'08 AUG'08

    RAW MATERIAL HANDLING SYSTEM (ZONE - 01)

    Supply & Erection of

    electric Wagon Pusher &

    Wagon Tippler

    22.00 4

    Equipment Supply 20.00 1 3 3 4.00 8.00 4.00Erection Testing &

    Commissioning2.00 2 4 3 0.40 0.80 0.40

    Budget (Rs. in Cr.) 4.00 8.40 4.80 0.40

    80% is the progress payment

    1 VSP-6.3-

    01-PRH-

    001

  • 7/30/2019 Cost Monitoring System

    8/18

    8

    Expenditure Report

    Orders placed on the parties are considered as commitments

    made against which expenditure is monitored.

    Each order is assigned with job code, party code and

    responsibility code in order to have proper monitoring of the

    actual expenditure. The typical codification system at VSP is

    explained below:

    (A) Job Code : Job code is a 6 digit numeric.

    X X X X X X

    Expansion Zone Number Serial Number

    Example - 601001

  • 7/30/2019 Cost Monitoring System

    9/18

    9

    (B) Party Code : Party code is a 6 digit numeric.

    X X X X X X

    1 for Public Sector First alphabet Serial Number

    2 for Private Sector of the agency3 for Small Scale Ind. name

    4 for Foreign Agency

    5 for Consortium

    6 for others

    Example Flsmidth Minerals Pvt. Ltd.

    Part Code - 206004

  • 7/30/2019 Cost Monitoring System

    10/18

    10

    (C) Responsibility Code : 6 digit alpha numeric.

    X X X X X X

    Expansion Zone Number Serial Number 0 for item rate

    1 for turnkey supply

    2 for turnkey erection

    Example : E01041

  • 7/30/2019 Cost Monitoring System

    11/18

    11

    Actual expenditure is booked on regular basis based on the

    Payment details. At the end of the month the expenditure reportis prepared based on the actual payments made.

    Formats for expenditure report are given in the following pages.

  • 7/30/2019 Cost Monitoring System

    12/1812

    Sl NoGovt. Approved Budget Heads

    (PIB Heads)

    Total

    amount

    sanctioned

    (1)

    Committm

    ents made

    till date

    (2)

    Exp. Upto

    March '08

    (3)

    Jan.' 09

    (4)

    Expenditure

    for the year

    2008-09

    (5)

    Cumulative

    expenditure

    till date

    (3+5)

    (6)

    A Plant Cost

    1 Land & site development

    2 Civil works

    3 Structural works

    4 Plant & Equipment

    5 Erection charges incl.

    Supervision & Training

    6 DE, Consultancy services &

    Project Management

    B Other fixed investment

    1 Spares

    2 Start up expenses(Preliminary

    pre- Operating expenses)

    C Total fixed investment (A

    + B)

    D Contingency

    E Interest during

    construction

    F Development /

    Expansion of Mine.

    G Materials Received At

    Stores

    a) Reinforcement Steel

    b) Structural Steel

    H Total Capital Expenditure

    VSP 6.3 MTPA - EXPANSION PROJECT

    EXPENDITURE REPORT (Rs Crores)

    SUMM OF COMMT & CAPITAL EXP FOR ORDERS RELEASED OF ALL ZONES FOR VSP EXPANSION PROJECT

  • 7/30/2019 Cost Monitoring System

    13/1813

    REPORT NO : 01

    MONTH :January 2009

    ALL ZONES FINANCIAL YEAR 2008-2009

    STATUS AS ON 25-01-2009 RS. IN CRS.

    ZONE ITEM DESCRIPTION/ ACTIVITY DESCRIPTION

    ESTIMATED

    VALUE

    (UPDATED)

    ORDER VALUEEXP UPTO

    MAR'2008

    Exp for

    Jan'09

    EXP FOR THE

    YEAR 08-09

    CUM EXP TILL

    DATE

    ZONE -01 RAW MATERIAL HANDLING SYSTEM (ZONE -I)

    ZONE -02 SINTER PLANT (ZONE -02)

    ZONE -03 BLAST FURNACE # 3 (ZONE - 03)ZONE -04 STEELMELT SHOP # 2 (ZONE - 04)

    ZONE -05 LIME CALCINING PLANT / CRMP (ZONE - 05)

    ZONE -06 WIRE ROD MILL # 2 (ZONE - 06)

    ZONE -07 SEAMLESS TUBE PLANT (ZONE - 07)

    ZONE -08 STRUCTURAL MILL (ZONE - 08)

    ZONE -09 SPECIAL BAR MILL (ZONE - 09)

    ZONE -10 THERMAL POWER PLANT & BLOWER HOUSE (ZONE -

    10)

    ZONE -11-I MADHARAM DOLOMITE MINE (ZONE 11-I)ZONE -11-II LIMESTONE MINE (ZONE-11-II)

    ZONE -11-III MANGANESE MINE (ZONE-11-III)

    ZONE -11-IV QUARTZITE MINE (ZONE-11-IV)

    ZONE -12 POWER DISTRIBUTION SYSTEM (ZONE-12)

    ZONE -13 UTILITY (ZONE-13)

    ZONE -14 WATER SYSTEM (ZONE-14)

    ZONE -15 WORKS TRANSPORT & OTHERS (ZONE-15)

    ZONE -16 AIR SEPARATION PLANT (ZONE-16)

    ZONE -17 POWER PLANT (ZONE-17)ZONE -18 REINFORCEMENT STEEL (ZONE-18)

    ZONE -19 STRUCTURAL STEEL NON FLAT (ZONE-19)

    ZONE -20 STRUCTURAL STEEL FLAT (ZONE-20)

    ZONE -21 PROJECT CONSULTANCY (ZONE-21)

    ZONE -22 OTHERS (ZONE-22)

    ZONE -23 SPARES (ZONE-23)

    ZONE -00 PRELIMINARY CONSTRUCTION WORK OF VSP (ZONE-

    00)

    TOTAL (ALL ZONES)

    TOTAL (ALL ZONES)( WITH OUT SERVICE TAX)

    SUMM. OF COMMT. & CAPITAL EXP. FOR ORDERS RELEASED OF ALL ZONES FOR VSP EXPANSION PROJECT

  • 7/30/2019 Cost Monitoring System

    14/1814

    RS. IN CRORE

    BUDGET

    2008-09 BUDGET ACTUAL BUDGET ACTUAL CUM. BUDGET CUM. ACTUAL

    RMHS

    I CIVIL

    a VSP-6.3-01-CVL-003

    b VSP-6.3-01-CVL-004

    SUB TOTAL

    II STRUCTURAL

    a VSP-6.3-01-STF-001

    b VSP-6.3-01-STF-002

    SUB TOTAL

    III EQUIPMENT SUPPLY

    a VSP-6.3-01-PRH-005

    b VSP-6.3-01-PRH-006

    SUB TOTAL

    TOTAL

    ESTIMATED EXPENDITURE VS ACTUAL EXPENDITURE

    For The Year 2008-09Jan-09 UPTO Jan-09

    RS. IN CRORERS. IN CRORE RS. IN CRORE

    SL. NO. DEPARTMENT PARTY NAME

  • 7/30/2019 Cost Monitoring System

    15/1815

    REPO

    MONTH :Jan

    FINANCIAL YEAR

    R

    STATUS AS ON 25-01-2009

    SL

    NO

    SPCIFICAT

    ION NO.

    PACKAGE

    DESCRIPTION

    ESTIMATE

    D VALUE

    (UPDATED)

    RESP.

    CODE

    JOB

    CODEORDER REF NO

    ORDER

    RELEASED

    DATE

    PARTY NAMEPARTY

    CODE

    ORDER

    VALUE

    EXP

    UPTO

    MAR'08

    Exp

    for

    Jan'09

    EXP

    FOR

    THE

    YEAR

    08-09

    VSP-6.3-01-

    PRH-001

    WAGON TIPPLER AND

    CAR PUSHER

    DE, and Supply of all

    eqpt. Incl. Comm. & Ins

    Spares

    17.28 E01041 601017 VSP/CONT/S(100)/104/EXPN/1840

    8 VSP-157

    27-Sep-07 McNally Bharat

    Engg. Co. Ltd.

    513006 21.72 2.17 2.17

    SERVICE TAX AND E

    CESS

    0.02 0.02

    ESCALATION

    Storage, Handling, ETC

    of all eqpt. Incl. Comm.

    Spares & Ins Spares

    1.31 E01042 601018 VSP/CONT/S(100)/104/EXPN/1840

    9 VSP-157

    27-Sep-07 McNally Bharat

    Engg. Co. Ltd.

    513006 1.87 0.19 0.19

    SERVICE TAX AND E

    CESS

    0.02 0.02

    ESCALATION

    Sub-Total (With

    Service Tax & E Cess

    and Escalation)

    2.40 2.40

    Sub-Total (Without

    Service Tax & E Cess

    and Escalation)

    18.59 2.36 2.36

    PILING

    VSP-6.3-01-

    CVL-

    001(R1)

    Piling work for RMHS

    (Part-Zone-1)

    E01030 601001 VSP/CONT/EXPN

    /57/2006-

    07/17867 (DLOA)

    23-Nov-06 VIJAY NIRMAN

    CO.

    222003 10.18 6.64

    SERVICE TAX AND E

    CESS

    0.79

    ESCALATION 0.12 0.05

    SERVICE TAX AND E

    CESS FOR

    ESCALATION

    0.02 0.01

    Sub-Total (With

    Service Tax & E Cess

    and Escalation)

    7.57 0.05

    Sub-Total (Without

    Service Tax & E Cess

    and Escalation)

    6.64

    DETAILS OF COMMITMENT & CAPITAL EXPENDITURE FOR ORDERS RELEASED OF RMHS (ZONE-I) FOR VSP EXPANSION PROJ

    R i d C t E ti t

  • 7/30/2019 Cost Monitoring System

    16/1816

    Revised Cost Estimate

    With the commitments made and commitments yet to be

    made Revised Cost Estimate is prepared.

    To prepare RCE following are considered

    (a) Actual commitments made upto date.

    (b) Balance commitment yet to be made.

    Revised Cost Estimate is compared with the Original

    Sanctioned Cost. The cost over run is explained under the

    following heads:

    (a) Escalation from the base date.(b) Additional items / change in scope.

    (c) Exchange rate variation.

    A typical format is given in the next page

  • 7/30/2019 Cost Monitoring System

    17/1817

    (Rs. in Crore)

    Sl.

    No.

    Item Description Original

    Provision

    Commit

    ment

    made

    Order

    No., Date

    & Party

    Change

    Order to be

    made

    Fresh Order

    to be placed

    / Sanctioned

    under

    process

    Revised Cost

    ZON

    E-01

    SPECIFICA

    TION NO.

    RAW MATERIAL

    HANDLING SYSTEM

    1 WAGON TIPPLER AND

    CAR PUSHER

    2 STOCK YARD

    EQUIPMENT

    3 CIVIL WORK

    4 PILING

    5 STRUCTURAL STEEL

    WORK

    6 PLANT ELECTRICS &

    CONTROL SYSTEM

    7 AUX. POWER WIRING

    ETC.

    8 WATER SYSTEM9 PLANT

    TELECOMMUNICATION

    SYSTEM

    10 ADDITIONAL ITEMS

    11 SCOPE CHANGE

    12 QUANTITY CHANGE

    13 EXCHANGE RATE

    VARIATION

    14 ESCALATIONTOTAL (RMHS)

    Revised Cost Estimate

  • 7/30/2019 Cost Monitoring System

    18/18

    THANK YOU