Upload
satishyadavalli
View
217
Download
0
Embed Size (px)
Citation preview
7/30/2019 Cost Monitoring System
1/18
1
Budgetary Cost Control
7/30/2019 Cost Monitoring System
2/18
2
OBJECTIVES
To enable control of cost of various items within the project
budget.
To continuously monitor cost of project and keep the
management informed of the expenditure incurred against
various commitments /orders.
To prepare necessary documentation and records for periodic
reference.
To forecast periodic plans, to phase out fund requirements as
per funds availability.
To prepare comparison of plan Vs actual expenditure
periodically.
7/30/2019 Cost Monitoring System
3/18
3
MAJOR AREAS OF
BUDGETARY COST CONTROL
Preparation of Annual Expenditure Plan (Yearly Budget).
Preparation of Monthly Expenditure Report.
Preparation of Revised Cost Estimate.
Preparation of various other reports for our internal use and alsoas per clients requirement.
7/30/2019 Cost Monitoring System
4/18
4
ANNUAL EXPENDITURE PLAN
(ANNUAL BUDGET)
The Annual budget is prepared for the year with monthly break-up.
The budget is prepared zone-wise, specifications wise under
following major heads:
(a) Civil work.
(b) Structural work.
(c) Equipment.
7/30/2019 Cost Monitoring System
5/18
5
Basis of Budget for Civil Work Monthly forecast for civil work is made based on plan of
concreting work.
Example:
SL
NOSPCIFICATION NO. DESCRIPTION TOTAL APR'08 MAY'08 JUN'08 JUL'08
RAW MATERIAL HANDLING SYSTEM (ZONE - 01)
Civil work Rs. in Cr. 64.12
Quantity (cum) 75000 4000 4000 3500 3500
Budget (Rs. in Cr.) 3.25 3.25 2.84
= 64.12 / 75000 * 4000 * 95%
95% is the progress payment
1 VSP-6.3-01-CVL-003
7/30/2019 Cost Monitoring System
6/18
6
Basis of Budget for Structural WorkMonthly forecast for structural work is made based on plan for
structural fabrication & erection. The weightage of fabrication &
erection depends on the scope of work of the contractor.
If steel is free issue then the weightage is normally considered as 60 40
i.e. 60% fabrication & 40% erection. Example:
SL
NO
SPCIFIC
ATIONDESCRIPTION TOTAL APR'08 MAY'08 JUN'08 JUL'08
RAW MATERIAL HANDLING SYSTEM (ZONE - 01)
Structural Work Rs. in Cr. 16.65
Fabrication Ton 12700 650 628 506 451
Erection Ton 12700 100 143 130 123
Structural Work (Weighted average
considering 60% for fabrication
& 40% for erection)
Ton 12700 430 434 356 320
Budget Rs. in Cr. 0.45 0.46 0.37
= 16.65 / 12700 * 430 * 80%
80% is the progress payment
= 650 * 60% + 100 * 40%
1
VSP-6.3-
01-STF-
001
7/30/2019 Cost Monitoring System
7/18
7
Basis of budget for equipmentMonthly forecast of equipment is based on terms of payment.
For progress payment of supply & erection monthly forecast is made
considering time schedule & using S curve formula which is as follows:
Y = [ 1 Sin {(X*180/Xn) + 90 } ] * 50 where Y = Percentage payment
(Cumulative) at a particular time (X) within the time schedule (Xn)
1 2 3 4 5
SL
NO
SPCIFICA
TION NO. DESCRIPTION
Rs. in
Cr.
Compl.
Time Start Finish Period APR'08 MAY'08 JUN'08 JUL'08 AUG'08
RAW MATERIAL HANDLING SYSTEM (ZONE - 01)
Supply & Erection of
electric Wagon Pusher &
Wagon Tippler
22.00 4
Equipment Supply 20.00 1 3 3 4.00 8.00 4.00Erection Testing &
Commissioning2.00 2 4 3 0.40 0.80 0.40
Budget (Rs. in Cr.) 4.00 8.40 4.80 0.40
80% is the progress payment
1 VSP-6.3-
01-PRH-
001
7/30/2019 Cost Monitoring System
8/18
8
Expenditure Report
Orders placed on the parties are considered as commitments
made against which expenditure is monitored.
Each order is assigned with job code, party code and
responsibility code in order to have proper monitoring of the
actual expenditure. The typical codification system at VSP is
explained below:
(A) Job Code : Job code is a 6 digit numeric.
X X X X X X
Expansion Zone Number Serial Number
Example - 601001
7/30/2019 Cost Monitoring System
9/18
9
(B) Party Code : Party code is a 6 digit numeric.
X X X X X X
1 for Public Sector First alphabet Serial Number
2 for Private Sector of the agency3 for Small Scale Ind. name
4 for Foreign Agency
5 for Consortium
6 for others
Example Flsmidth Minerals Pvt. Ltd.
Part Code - 206004
7/30/2019 Cost Monitoring System
10/18
10
(C) Responsibility Code : 6 digit alpha numeric.
X X X X X X
Expansion Zone Number Serial Number 0 for item rate
1 for turnkey supply
2 for turnkey erection
Example : E01041
7/30/2019 Cost Monitoring System
11/18
11
Actual expenditure is booked on regular basis based on the
Payment details. At the end of the month the expenditure reportis prepared based on the actual payments made.
Formats for expenditure report are given in the following pages.
7/30/2019 Cost Monitoring System
12/1812
Sl NoGovt. Approved Budget Heads
(PIB Heads)
Total
amount
sanctioned
(1)
Committm
ents made
till date
(2)
Exp. Upto
March '08
(3)
Jan.' 09
(4)
Expenditure
for the year
2008-09
(5)
Cumulative
expenditure
till date
(3+5)
(6)
A Plant Cost
1 Land & site development
2 Civil works
3 Structural works
4 Plant & Equipment
5 Erection charges incl.
Supervision & Training
6 DE, Consultancy services &
Project Management
B Other fixed investment
1 Spares
2 Start up expenses(Preliminary
pre- Operating expenses)
C Total fixed investment (A
+ B)
D Contingency
E Interest during
construction
F Development /
Expansion of Mine.
G Materials Received At
Stores
a) Reinforcement Steel
b) Structural Steel
H Total Capital Expenditure
VSP 6.3 MTPA - EXPANSION PROJECT
EXPENDITURE REPORT (Rs Crores)
SUMM OF COMMT & CAPITAL EXP FOR ORDERS RELEASED OF ALL ZONES FOR VSP EXPANSION PROJECT
7/30/2019 Cost Monitoring System
13/1813
REPORT NO : 01
MONTH :January 2009
ALL ZONES FINANCIAL YEAR 2008-2009
STATUS AS ON 25-01-2009 RS. IN CRS.
ZONE ITEM DESCRIPTION/ ACTIVITY DESCRIPTION
ESTIMATED
VALUE
(UPDATED)
ORDER VALUEEXP UPTO
MAR'2008
Exp for
Jan'09
EXP FOR THE
YEAR 08-09
CUM EXP TILL
DATE
ZONE -01 RAW MATERIAL HANDLING SYSTEM (ZONE -I)
ZONE -02 SINTER PLANT (ZONE -02)
ZONE -03 BLAST FURNACE # 3 (ZONE - 03)ZONE -04 STEELMELT SHOP # 2 (ZONE - 04)
ZONE -05 LIME CALCINING PLANT / CRMP (ZONE - 05)
ZONE -06 WIRE ROD MILL # 2 (ZONE - 06)
ZONE -07 SEAMLESS TUBE PLANT (ZONE - 07)
ZONE -08 STRUCTURAL MILL (ZONE - 08)
ZONE -09 SPECIAL BAR MILL (ZONE - 09)
ZONE -10 THERMAL POWER PLANT & BLOWER HOUSE (ZONE -
10)
ZONE -11-I MADHARAM DOLOMITE MINE (ZONE 11-I)ZONE -11-II LIMESTONE MINE (ZONE-11-II)
ZONE -11-III MANGANESE MINE (ZONE-11-III)
ZONE -11-IV QUARTZITE MINE (ZONE-11-IV)
ZONE -12 POWER DISTRIBUTION SYSTEM (ZONE-12)
ZONE -13 UTILITY (ZONE-13)
ZONE -14 WATER SYSTEM (ZONE-14)
ZONE -15 WORKS TRANSPORT & OTHERS (ZONE-15)
ZONE -16 AIR SEPARATION PLANT (ZONE-16)
ZONE -17 POWER PLANT (ZONE-17)ZONE -18 REINFORCEMENT STEEL (ZONE-18)
ZONE -19 STRUCTURAL STEEL NON FLAT (ZONE-19)
ZONE -20 STRUCTURAL STEEL FLAT (ZONE-20)
ZONE -21 PROJECT CONSULTANCY (ZONE-21)
ZONE -22 OTHERS (ZONE-22)
ZONE -23 SPARES (ZONE-23)
ZONE -00 PRELIMINARY CONSTRUCTION WORK OF VSP (ZONE-
00)
TOTAL (ALL ZONES)
TOTAL (ALL ZONES)( WITH OUT SERVICE TAX)
SUMM. OF COMMT. & CAPITAL EXP. FOR ORDERS RELEASED OF ALL ZONES FOR VSP EXPANSION PROJECT
7/30/2019 Cost Monitoring System
14/1814
RS. IN CRORE
BUDGET
2008-09 BUDGET ACTUAL BUDGET ACTUAL CUM. BUDGET CUM. ACTUAL
RMHS
I CIVIL
a VSP-6.3-01-CVL-003
b VSP-6.3-01-CVL-004
SUB TOTAL
II STRUCTURAL
a VSP-6.3-01-STF-001
b VSP-6.3-01-STF-002
SUB TOTAL
III EQUIPMENT SUPPLY
a VSP-6.3-01-PRH-005
b VSP-6.3-01-PRH-006
SUB TOTAL
TOTAL
ESTIMATED EXPENDITURE VS ACTUAL EXPENDITURE
For The Year 2008-09Jan-09 UPTO Jan-09
RS. IN CRORERS. IN CRORE RS. IN CRORE
SL. NO. DEPARTMENT PARTY NAME
7/30/2019 Cost Monitoring System
15/1815
REPO
MONTH :Jan
FINANCIAL YEAR
R
STATUS AS ON 25-01-2009
SL
NO
SPCIFICAT
ION NO.
PACKAGE
DESCRIPTION
ESTIMATE
D VALUE
(UPDATED)
RESP.
CODE
JOB
CODEORDER REF NO
ORDER
RELEASED
DATE
PARTY NAMEPARTY
CODE
ORDER
VALUE
EXP
UPTO
MAR'08
Exp
for
Jan'09
EXP
FOR
THE
YEAR
08-09
VSP-6.3-01-
PRH-001
WAGON TIPPLER AND
CAR PUSHER
DE, and Supply of all
eqpt. Incl. Comm. & Ins
Spares
17.28 E01041 601017 VSP/CONT/S(100)/104/EXPN/1840
8 VSP-157
27-Sep-07 McNally Bharat
Engg. Co. Ltd.
513006 21.72 2.17 2.17
SERVICE TAX AND E
CESS
0.02 0.02
ESCALATION
Storage, Handling, ETC
of all eqpt. Incl. Comm.
Spares & Ins Spares
1.31 E01042 601018 VSP/CONT/S(100)/104/EXPN/1840
9 VSP-157
27-Sep-07 McNally Bharat
Engg. Co. Ltd.
513006 1.87 0.19 0.19
SERVICE TAX AND E
CESS
0.02 0.02
ESCALATION
Sub-Total (With
Service Tax & E Cess
and Escalation)
2.40 2.40
Sub-Total (Without
Service Tax & E Cess
and Escalation)
18.59 2.36 2.36
PILING
VSP-6.3-01-
CVL-
001(R1)
Piling work for RMHS
(Part-Zone-1)
E01030 601001 VSP/CONT/EXPN
/57/2006-
07/17867 (DLOA)
23-Nov-06 VIJAY NIRMAN
CO.
222003 10.18 6.64
SERVICE TAX AND E
CESS
0.79
ESCALATION 0.12 0.05
SERVICE TAX AND E
CESS FOR
ESCALATION
0.02 0.01
Sub-Total (With
Service Tax & E Cess
and Escalation)
7.57 0.05
Sub-Total (Without
Service Tax & E Cess
and Escalation)
6.64
DETAILS OF COMMITMENT & CAPITAL EXPENDITURE FOR ORDERS RELEASED OF RMHS (ZONE-I) FOR VSP EXPANSION PROJ
R i d C t E ti t
7/30/2019 Cost Monitoring System
16/1816
Revised Cost Estimate
With the commitments made and commitments yet to be
made Revised Cost Estimate is prepared.
To prepare RCE following are considered
(a) Actual commitments made upto date.
(b) Balance commitment yet to be made.
Revised Cost Estimate is compared with the Original
Sanctioned Cost. The cost over run is explained under the
following heads:
(a) Escalation from the base date.(b) Additional items / change in scope.
(c) Exchange rate variation.
A typical format is given in the next page
7/30/2019 Cost Monitoring System
17/1817
(Rs. in Crore)
Sl.
No.
Item Description Original
Provision
Commit
ment
made
Order
No., Date
& Party
Change
Order to be
made
Fresh Order
to be placed
/ Sanctioned
under
process
Revised Cost
ZON
E-01
SPECIFICA
TION NO.
RAW MATERIAL
HANDLING SYSTEM
1 WAGON TIPPLER AND
CAR PUSHER
2 STOCK YARD
EQUIPMENT
3 CIVIL WORK
4 PILING
5 STRUCTURAL STEEL
WORK
6 PLANT ELECTRICS &
CONTROL SYSTEM
7 AUX. POWER WIRING
ETC.
8 WATER SYSTEM9 PLANT
TELECOMMUNICATION
SYSTEM
10 ADDITIONAL ITEMS
11 SCOPE CHANGE
12 QUANTITY CHANGE
13 EXCHANGE RATE
VARIATION
14 ESCALATIONTOTAL (RMHS)
Revised Cost Estimate
7/30/2019 Cost Monitoring System
18/18
THANK YOU