Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
COST OPTIMISATION
‘CRASHING’
©Sheila Belayutham
LEARNING OUTCOME
Students will be able to:Understand the technique to obtain
the optimal duration at the lowest cost.
©Sheila Belayutham
COST OPTIMISATION
©Sheila Belayutham
Cost optimization is studied to consider the options available in balancing out the time savings against the cost of speeding up the work.
Client and contractor could assess the effect on direct and indirect costs of reducing the overall project period.
INTRODUCTION
©Sheila Belayutham
Important Terms
Direct Cost Indirect CostTotal Project CostOptimum Project Duration
©Sheila Belayutham
Direct Cost
Types of direct cost:– Labor– Plant– Materials– Overhead
Activity accelerated, direct cost increase. “Non linear” with time. Reason being, you need more worker, more
material (formwork), more supervisors, etc.
©Sheila Belayutham
Indirect cost
Time related cost, where it changes as the project duration changes.
Cost and time are ‘constant’. Examples:
– Project supervision– Site accommodation– Temporary services for site office– Site transportation
©Sheila Belayutham
When activity accelerated, indirect cost will decrease.
Reason being that contractor will be on site for a shorter period, therefore will be reduction in the site administration costs.
Indirect cost
©Sheila Belayutham
What will happen when a project is to be shorten?
Work overtimeWork following shiftAdditional equipment, machinery
required, which will increase the cost of mobilization and demobilization.
©Sheila Belayutham
When do we need to shorten the duration of project?
Over purchasing of material Political pressure Weather condition Having other new project in hand.
©Sheila Belayutham
Material being brought in bit by bit, therefore increase transportation cost and material cost because buying in bulk is cheaper.
Less worker, less productivity, affect the morale of workers.
What will happen when a project is to be lengthen?
©Sheila Belayutham
When do we need to lengthen the duration of project?
Happen that shortage of resources in the midst of progression.
Negative cash flow.Planning too fast.
©Sheila Belayutham
Total Project Cost
Summation of direct cost and Indirect Cost.
Optimum Project Duration
Optimum project duration occurs where the most beneficial least cost situation occurs, taking into consideration both direct and indirect costs.
©Sheila Belayutham
Relationship between direct cost, indirect cost and project duration.
Direct cost rises as project duration decreases.
Indirect costs rises as project duration increases.
There is a minimum duration for any project beyond which further reduction is not feasible.
©Sheila Belayutham
DETERMINING OPTIMUM PROJECT COST
Prepare a table of activities on the critical path showing normal activity duration and cost, and minimum (crash) activity duration and cost.
Calculate the cost slope of each activity in the table. List the activities in order of minimum cost slope. Omit activities which cannot be compressed (and those fully
crashed from previous compressions) Compress the activity (or activities if two are being
compressed) with the least cost slope, the maximum amount possible, or until some other activity becomes critical.
Calculate the new project duration and direct cost. When minimum duration is reached, calculate indirect costs for
each project duration. Add indirect costs to direct costs and calculate total costs for
each project duration. Determine optimum project cost.
©Sheila Belayutham
Network for Construction of a Bridge
000
153
4139 7
1610
374 4
85 11116 20
20816167 23
2312 242413
112011
10102
4151
4
10
1
2
3
11
53 4
1
3 1
3 4
3
©Sheila Belayutham
Activity reference
Normal Crash
Duration Cost Duration Cost0-1 4 3000 3 33000-2 10 9000 5 97500-3 1 100 1 1001-7 1 120 1 1202-6 1 100 1 1003-4 2 1500 2 15003-9 3 500 2 6004-5 1 500 1 5005-6 3 450 2 5256-7 5 1500 3 25007-8 4 1200 3 14008-12 3 750 3 7509-10 3 350 3 35010-11 4 550 3 60011-12 3 800 2 110012-13 1 500 1 500
©Sheila Belayutham
Given also:
Indirect costs are RM400.00 per week
Project duration is 24 weeks and the cost is RM20920
Determine optimum project cost
©Sheila Belayutham
Network for Construction of a Bridge
000
153
4139 7
1610
374 4
85 11116 20
20816167 23
2312 242413
112011
10102
4151
4
10
1
2
3
11
53 41
3 1
3 4
3
©Sheila Belayutham
Activity reference
Normal Crash
Duration Cost Duration Cost0-1 4 3000 3 33000-2 10 9000 5 97500-3 1 100 1 1001-7 1 120 1 1202-6 1 100 1 1003-4 2 1500 2 15003-9 3 500 2 6004-5 1 500 1 5005-6 3 450 2 5256-7 5 1500 3 25007-8 4 1200 3 14008-12 3 750 3 7509-10 3 350 3 35010-11 4 550 3 60011-12 3 800 2 110012-13 1 500 1 500
©Sheila Belayutham
Activity Maximum Compression
Cost per week
0-2 5 150
6-7 2 500
7-8 1 200
©Sheila Belayutham
Network for Construction of a Bridge
000
153
4139 7
1610
374 4
85 11116 20
20816167 23
2312 242413
112011
10102
4151
4
10
1
2
3
11
53 41
3 1
3 4
3
©Sheila Belayutham
Revised Network 1
000
113
499 7
1210
334 4
45 776 16
16812127 19
1912 202013
111611
662
4111
4
6
1
2
3
11
53 41
3 1
3 4
3
©Sheila Belayutham
First Compression: Project duration is now 20weeks and activities 0-3, 3-
4, 4-5 and 5-6 is also critical now
Activity Maximum Compression
Cost per week
0-2 5 150
Direct cost after first compression:RM20920 + (RM150 x 4) = RM21520
©Sheila Belayutham
Activity reference
Normal Crash
Duration Cost Duration Cost0-1 4 3000 3 33000-2 10 9000 5 97500-3 1 100 1 1001-7 1 120 1 1202-6 1 100 1 1003-4 2 1500 2 15003-9 3 500 2 6004-5 1 500 1 5005-6 3 450 2 5256-7 5 1500 3 25007-8 4 1200 3 14008-12 3 750 3 7509-10 3 350 3 35010-11 4 550 3 60011-12 3 800 2 110012-13 1 500 1 500
©Sheila Belayutham
Activity Maximum Compression
Cost per week
0-2 5 150
5-6 1 75
6-7 2 500
7-8 1 200
©Sheila Belayutham
Revised Network 1
000
113
499 7
1210
334 4
45 776 16
16812127 19
1912 202013
111611
662
4111
4
6
1
2
3
11
53 41
3 1
3 4
3
©Sheila Belayutham
Second Compression: To compress activity 5-6, you need to compress
activity 0-2 as well for the project time to be reduced 1week
It will cost RM75 + RM150 = RM225 Thus, it is cheaper to compress activity 7-8 at RM200 Project duration is now 19weeks
Direct cost after second compression:RM21520 + RM200 = RM21745
©Sheila Belayutham
Revised Network 2
000
113
489 7
1110
334 4
45 776 15
15812127 18
1812 191913
111511
662
4111
4
6
1
2
3
11
53 31
3 1
3 4
3
©Sheila Belayutham
Activity Maximum Compression
Cost per week
0-2 5 150
5-6 1 75
6-7 2 500
7-8 1 200
©Sheila Belayutham
Revised Network 3
000
113
479 7
1010
334 4
45 666 14
14811117 17
1712 18.1813
111411
552
4101
4
5
1
2
3
11
52 31
3 1
3 4
3
©Sheila Belayutham
Third Compression: Project duration is now 18weeks
Activity Maximum Compression
Cost per week
0-2 5 150
5-6 1 75
Direct cost after third compression:RM21720 + RM225 = RM21945
©Sheila Belayutham
Activity Maximum Compression
Cost per week
0-2 5 150
5-6 1 75
6-7 2 500
7-8 1 200
©Sheila Belayutham
Revised Network 4
000
113
459 7
810
334 4
45 666 12
128997 15
1512 161613
111211
552
481
4
5
1
2
3
11
32 31
3 1
3 4
3
©Sheila Belayutham
Fourth Compression: Project duration is now 16weeks
Activity Maximum Compression
Cost per week
6-7 2 500
Direct cost after third compression:RM21945 + (RM500 x 2) = RM22945
©Sheila Belayutham
To determine optimum cost, indirect cost must be added in.
Project Duration 16 18 19 20 24
Direct Cost 22945 21945 21720 21520 20920
Indirect Cost 6400 7200 7600 8000 9600Total Cost 29345 29145 29320 29520 30520
So, the optimum cost is RM29145 at a duration of 18weeks
©Sheila Belayutham
THE END…
©Sheila Belayutham